Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 3
CASE NO.:
Appeal (civil) 7333 of 2004
PETITIONER:
State of Kerala & Anr
RESPONDENT:
M.A. Mathai
DATE OF JUDGMENT: 09/04/2007
BENCH:
Dr. ARIJIT PASAYAT & LOKESHWAR SINGH PANTA
JUDGMENT:
J U D G M E N T
Dr. ARIJIT PASAYAT, J.
Challenge in this appeal is to the judgment rendered by a
Division Bench of the Kerala High Court dismissing the appeal
filed by the appellant-State and its functionary questioning
legality of the judgment and decree in O.S. No.859 of 1988 on
the file of the Sub Court, Trichur. The suit was filed for
recovery of money in connection with the award of work
undertaken by the respondent-plaintiff who is the contractor.
The High Court was of the view that the court below had
fixed award of damage of Rs.9,53,669/- and found that the
plaintiff was entitled to damage under other head and,
therefore, restricted the decretal amount to Rs.10,00,000/-
The appeal was accordingly dismissed.
In support of the appeal learned counsel for the appellant
submitted that the letters on which reliance had been placed
show that the contractor was not doing the work within
stipulated period and had been asked for to apply for
extension. The basic stand of the plaintiff\026respondent was
that the extensions had been sought for and supplemental
agreements were executed not on the free will and free consent
of the plaintiff but it was due to circumstances which
prevailed at that time which necessitated the plaintiff to agree
to the commands of the defendants. To put it differently as
noted above the plaintiff had contented that it was due to
coercion that these supplemental agreements were executed.
The trial court concluded that on the threat of forfeiture, re-
allocation and re-arrangement at the cost of the plaintiff the
execution of supplemental agreement was done. It is pointed
out that there was no clause for any escalation. It was wrongly
assumed by the trial court that the supplemental agreements
and declarations made by the plaintiff were not binding on
him as it was not obtained by free consent and free will and in
the normal course of events.
In response, learned counsel for the respondent
submitted that the amounts awarded were not for damages
and it was only in respect of extra work done that the amounts
has been awarded. It was submitted that the department itself
had recommended for payment for the extra work done and as
per rates under the contracts the amounts have been
awarded. Though the Government did not agree to the
proposal, that itself shows about the genuineness of the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 3
respondent’s claim. In respect of another contract the extra
amounts have been paid.
The trial court and the High Court appear to have been
totally confused about the nature of the suit. The plaint itself
indicated that it was a "suit for recovery of money for
damages". In fact the High Court itself observed at para 8 that
the primary issue related to assessment of damages. It also
found that the plaintiff was entitled to damages under various
heads.
Additionally, the trial court concluded that the
supplemental agreements (Ex. B-2 to Ex. B-6) and
Declarations (B-10 to B-14) were not at all binding on the
plaintiff. If that was really so, there could not have been any
extension. The finding that these documents were not
obtained by free will and free consent and in the normal
course of events, to say the least, is an inferential conclusion
not supported by any evidence.
As noted above, the trial court proceeded on the basis as
to whether plaintiff was entitled to damages and if so what is
the amount and quantum is to be fixed. It was noted that
being a suit for damages, the plaintiff was claiming so many
items of damages in terms of money involving many
calculations. This is contrary to respondent’s plea before us.
Their stand is that the amount was not for damages but for
extra work done. As noted above it was only a suit for
damages. In General Manager, Northern Railway and another
v. Sarvesh Chopra [2002 (4) SCC 45] it was inter alia observed
as follows:
"In our country question of delay in
performance of the contract is governed by
Sections 55 and 56 of the Indian Contract Act,
1872. If there is an abnormal rise in prices of
material and labour, it may frustrate the
contract and then the innocent party need not
perform the contract. So also, if time is of the
essence of the contract, failure of the employer
to perform a mutual obligation would enable
the contractor to avoid the contract as the
contract becomes voidable at his option. Where
time is "of the essence" of an obligation, Chitty
on Contracts (28th Edn., 1999, at p. 1106,
para 22-015) states
"a failure to perform by the
stipulated time will entitle the innocent
party to (a) terminate performance of the
contract and thereby put an end to all the
primary obligations of both parties
remaining unperformed; and (b) claim
damages from the contract-breaker on
the basis that he has committed a
fundamental breach of the contract (’a
breach going to the root of the contract’)
depriving the innocent party of the
benefit of the contract (’damages for loss
of the whole transaction’)".
If, instead of avoiding the contract, the contractor accepts
the belated performance of reciprocal obligation on the part of
the employer, the innocent party i.e. the contractor, cannot
claim compensation for any loss occasioned by the non-
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 3
performance of the reciprocal promise by the employer at the
time agreed, "unless, at the time of such acceptance, he gives
notice to the promisor of his intention to do so". Thus, it
appears that under the Indian law, in spite of there being a
contract between the parties whereunder the contractor has
undertaken not to make any claim for delay in performance of
the contract occasioned by an act of the employer, still a claim
would be entertainable in one of the following situations: (1) if
the contractor repudiates the contract exercising his right to
do so under Section 55 of the Contract Act, (ii) the employer
gives an extension of time either by entering into supplemental
agreement or by making it clear that escalation of rates or
compensation for delay would be permissible, (iii) if the
contractor makes it clear that escalation of rates or
compensation for delay shall have to be made by the employer
and the employer accepts performance by the contractor in
spite of delay and such notice by the contractor putting the
employer on terms."
In the instant case both the trial court and the High
Court have without any basis come to hold that the
supplemental agreement was due to coercion etc. For coming
to such conclusion, material had to be placed, evidence had to
be led. Mere assertion by the plaintiff without any material to
support the said stand should not have been accepted by the
trial court and the High Court.
Looked at from any angle the impugned judgment of the
High Court is without any basis and is set aside. The appeal
is allowed but in the circumstances without any order as to
costs.