1
REPORTABLE
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NO. 6768 of 2021
M.P. HOUSING AND INFRASTRUCTURE DEVELOPMENT
BOARD & ANR. .. Appellants
Versus
K.P. DWIVEDI .. Respondent
WITH
CIVIL APPEAL NO.6769 Of 2021
M.P. HOUSING AND INFRASTRUCTURE DEVELOPMENT
BOARD & ANR. .. Appellants
Versus
K.P. DWIVEDI .. Respondent
WITH
CIVIL APPEAL NO.6770 OF 2021
M.P. HOUSING AND INFRASTRUCTURE DEVELOPMENT
BOARD & ANR. .. Appellants
Versus
Signature Not Verified
Digitally signed by
DEEPAK SINGH
Date: 2021.12.03
15:43:55 IST
Reason:
K.P. DWIVEDI .. Respondent
2
J U D G M E N T
M. R. Shah, J.
1. Feeling aggrieved and dissatisfied with the impugned
judgment and order dated 08.05.2018 passed by the High
Court of Madhya Pradesh in Arbitration Revision Nos.11, 12 &
13 of 2017 by which the High Court has quashed and set
aside the orders passed by the Madhya Pradesh Arbitration
Tribunal, Bhopal and has directed the said Tribunal to decide
the respective references on merits, Madhya Pradesh Housing
and Infrastructure Development Board and another have
preferred the present appeals.
2. As common question of law and facts arise in these group
of appeals, all these appeals are decided and disposed of
together by this common judgment and order.
For the sake of convenience Civil Appeal No.6768 of 2021
arising out of Special Leave Petition No.32557 of 2018 arising
out of the impugned judgment and order passed by the High
Court of Madhya Pradesh in Arbitration Revision No.13 of
3
2017 is treated and considered as the lead matter and the
facts in the said appeal are narrated which in nutshell are as
under:
2.1 Appellants floated a tender for construction of houses at
Riviera Town, Near MANIT Square, Bhopal. Contract was
awarded to the respondent herein. An agreement dated
15.07.2005 was executed between the appellants and the
respondent. In the year 2008, the disputes arose between the
parties. According to the appellants, the respondent was
supposed to complete the work within 18 months. However,
despite granting repeated extensions, the contractor failed to
complete the work, on account of which, appellants rescinded
the contract by invoking clause 3 of the contract agreement.
Aggrieved by the order dated 30.06.2008, rescinding the
contract, the respondent contractor by invoking clause 29 of
the contract agreement filed a claim petition along with
granting extension of time upto 31.03.2009 before the Deputy
Housing Commissioner, Bhopal. The respondent contractor
also filed a writ petition before the High Court seeking
4
direction to permit him to complete the work. High Court vide
Order dated 20.08.2008 disposed of the said petition on a joint
consensus of the parties that the dispute shall be decided by
the arbitrator i.e., Housing Commissioner, M.P. Housing
Board within the stipulated period. The respondent
contractor thereafter filed a modified claim before the Office of
the Housing Commissioner along with prayer for grant of
extension of time. Thus, the respondent contractor
participated in the arbitration proceedings before the Housing
Commissioner, M.P. Housing Board. That the learned
Arbitrator passed an award on 07.11.2008 rejecting the claim
of the respondent contractor and granting some relief in
favour of the appellants. Instead of challenging the said award
by way of an application under Section 34 of the Arbitration
and Conciliation Act, 1996 (hereinafter referred to as
‘Arbitration Act, 1996’), the respondent filed a fresh Reference
Petition before the Madhya Pradesh Arbitration Tribunal under
Section 7 of the Madhya Pradesh Madhyastham Adhikaran,
Vindhyachal, Bhopal, (hereinafter referred to as ‘the 1983
5
Act’). The appellants filed their written statements on various
grounds along with preliminary objections including that the
dispute has already been decided by the Arbitrator vide award
dated 07.11.2008 which was duly constituted by the High
Court and therefore, the fresh claim petition for the same
claim before the M.P. Arbitration Tribunal, Bhopal was not
maintainable. It was also submitted that the award passed by
the Arbitrator had already achieved finality and therefore, the
dispute for the said claim cannot be entertained by the
Tribunal subsequently. Vide order dated 27.02.2017 the
learned M.P. Arbitration Tribunal, Bhopal dismissed the said
claim/reference as not maintainable since claim made by the
respondent had already been decided by the Arbitrator
appointed by the High Court and the award passed by the
learned Arbitrator had achieved finality and so the dispute for
the said claim could not be entertained by the learned
Tribunal subsequently.
3. Having realized that the earlier order dated 20.08.2008
passed in W.P. No.9131 of 2008 by which the dispute was
6
referred for arbitration to the Housing Commissioner would
come in his way, as an afterthought, the respondent
contractor filed a review petition in the month of May, 2017
seeking clarification of the order dated 20.08.2008 passed in
W.P. No.9131 of 2008 to the extent that by directing the
adjudication of the dispute by the Housing Commissioner, it
did not take away the jurisdiction of learned Arbitral Tribunal
constituted under the 1983 Act. It appears that in the mean
time the full Bench of the High Court of Madhya Pradesh vide
judgment and order dated 05.05.2017 held that if an
agreement falls within the definition of ‘works contract’ then
the dispute arising from such an agreement shall be
adjudicated by the Tribunal under the 1983 Act. The review
application was opposed by the appellants. Vide order dated
07.09.2017, the High Court dismissed the review petition by
observing that the case did not fall within the review
jurisdiction of the Court under Order 47 Rule 1, CPC.
3.1 That after the dismissal of the review petition, the
respondent contractor filed the present Arbitration Revision
7
Petition before the High Court under Section 19 of the 1983
Act challenging the order passed by the learned Tribunal dated
27.02.2017 dismissing the claim/reference as not
maintainable. By the impugned judgment and order the High
Court has allowed the said revision and has quashed and set
aside the order passed by the learned Tribunal dated
27.02.2017 and has directed the learned Arbitral Tribunal
constituted under the 1983 Act to decide the reference/claim
on merits and in accordance with law.
4. Feeling aggrieved and dissatisfied with the impugned
judgment and order passed by the High Court, M.P. Housing
and Infrastructure Development Board has preferred the
present appeal.
5. Shri Bharat Singh, learned AAG has appeared for the
appellants and Shri Kavin Gulati, learned Senior Advocate has
appeared for the respondent contractor in the respective
appeals.
8
6. Shri Bharat Singh, learned counsel appearing on behalf
of the appellants has vehemently submitted that the impugned
judgment and order passed by the High Court quashing and
setting aside the order passed by the learned Arbitral Tribunal
dated 27.02.2017 by which the learned Arbitral Tribunal
dismissed the reference/claim petition filed by the respondent
contractor as not maintainable, in view of the earlier award
passed by the learned Arbitrator and directing the learned
Arbitral Tribunal to entertain the claim reference and to decide
the same on merits is unsustainable in law as well as on facts.
6.1 It is urged by learned counsel appearing on behalf of the
appellants that the High Court while passing the impugned
judgment and order has not at all appreciated and considered
the fact that earlier the dispute between the parties was
referred to the Arbitrator Housing Commissioner by the High
Court and that too in the petition filed by the respondent
contractor himself. It is submitted that the High Court has
not at all appreciated the fact that as such the learned
Arbitrator appointed pursuant to the order passed by the High
9
Court had passed an award which had attained finality
inasmuch as the said award had not been challenged by the
respondent – contractor by way of appeal under Section 34 of
the Arbitration Act, 1996.
6.2 It is contended that the learned Arbitrator had passed an
award and the only remedy available to the respondent
contractor was to challenge the same by way of an appeal
under Section 34 of the Arbitration Act, 1996, which remedy
the respondent contractor had failed to avail. It is submitted
that instead he filed a fresh claim petition before the learned
Arbitral Tribunal constituted under the 1983 Act which as
such and as rightly observed by the Arbitral Tribunal was not
maintainable.
6.3 It is further submitted that the order passed by the High
Court referring the dispute between the parties to the
Arbitrator Housing Commissioner was a consent order and
the same was as per the relevant arbitration clause in the
agreement entered into between the parties.
10
6.4 It is further urged that even subsequent to the order
passed by the Arbitral Tribunal dated 27.02.2017, with a mala
fide intention as an afterthought, the respondent contractor
filed a review application before the High Court challenging the
consent order dated 20.08.2008 i.e., after a period of 9 years
of the order and the said review petition had also came to be
dismissed by the High Court. It is submitted that even
dismissal of the review petition had also attained the finality
and the same was not carried further. It is urged that
therefore, it was not open for the respondent – contractor to
file a fresh claim petition for the same claim which was made
before the learned Arbitrator Housing Commissioner
constituted pursuant the order passed by the High Court.
6.5 It is submitted that in the case of Madhya Pradesh Rural
Road Development Authority and Another vs. L.G.
Chaudhary Engineers and Contractors , (2018) 10 SCC 826,
relating to the issue of jurisdiction of the M.P. Tribunal, this
Hon’ble Court has categorically held that if no objection to the
jurisdiction of the arbitration was taken at the relevant stage,
11
that award cannot be annulled only on that ground. It is
urged that in the present case no such objection was raised by
the respondent contractor at the relevant stage. It is urged
that in fact, the entire proceedings before the Arbitrator
Housing Commissioner was at the behest of the respondent
contractor, as it was he who filed the writ petition culminating
in the consent order appointing an arbitrator, and then filed a
claim.
6.6 It is contended that even a fresh reference petition by the
respondent contractor is also not maintainable in view of the
principle of Issue Estoppel. Reliance is placed on the
decisions of this Court in Hope Plantations Ltd. vs Taluk
(1999) 5 SCC 590 and
Land Board, Peermade and Another,
Bhanu Kumar Jain vs Archana Kumar and Another , (2005)
1 SCC 787.
6.7 It is further contended that the claim of the respondent
contractor that the judgment passed by the High Court in the
year 2008 was contrary to law and cannot confer jurisdiction
12
on the arbitrator is misconceived and erroneous for the reason
that the order was passed with consent and even if the order is
wrong, it will continue to bind the parties until and unless it is
set aside by a competent court. Reliance is placed on the
decisions of this Court in the case of Pushpa Devi Bhagat (D)
| Th. LR. Sadhna Rai (Smt.) vs. Rajinder Singh & Ors., | (2006) |
|---|
| 5 SCC 566 (para 17) and | Rafique Bibi (Dead) By Lrs. vs. |
|---|
| Sayed Waliuddin (Dead) by LRs and others, | (2004) 1 SCC |
|---|
287 (paras 7 and 8).
| 7. | | Making the above submissions and relying upon the |
|---|
above decisions, it is prayed to allow the present appeals and
set aside the impugned judgment and orders passed by the
High Court.
| 8. | | Present appeals are vehemently opposed by Shri Kavin |
|---|
Gulati, learned Senior Advocate appearing on behalf of
respondent – contractor. It is submitted that the 1983 Act is a
Special Act providing for statutory and compulsory arbitration
under the said Act for disputes pertaining to ‘works contract’.
13
It is submitted that Section 7 of the Act provides that either
party to a ‘works contract’…. shall irrespective of the fact
whether the agreement contains an arbitration clause or not,
refer in writing the dispute to the Tribunal. It is contended
that the term ‘dispute’ is defined in Section 2(d) to mean a
claim having a value of Rs.50,000/ or more. It is contended
that therefore the claims above Rs.50,000/ are to be
compulsorily brought before the Tribunal constituted under
Section 3 of the 1983 Act.
| 8.1 | | It is urged that even as per Section 7B of the 1983 Act no |
|---|
dispute can be referred to the Arbitration Tribunal unless the
dispute is first referred for decision of the final authority under
the scope of the term ‘works contract’. It is only once a
decision is made or if the authority fails to make a decision
can a claim be preferred before the Tribunal.
| 8.2 | | It is submitted that the 1983 Act is a Special Act insofar |
|---|
as the State of M.P. is concerned, and therefore it will prevail
over the provisions of the Arbitration Act, 1996. Reliance is
| placed on the decision of this Court in the case of | M.P. Rural |
|---|
14
Road Development Authority and Anr. vs. L.G. Chaudhary
| Engineers & Contractors | reported in (2012) 3 SCC 495 and |
|---|
| the subsequent decision in | M.P. Rural Road Development |
|---|
Authority and Anr. vs. L.G. Chaudhary Engineers &
| Contractors | reported in (2018) 10 SCC 826. |
|---|
| 8.3 | | It is submitted that the full Bench of the Madhya Pradesh |
|---|
| High Court has also taken the same view in the case of | Viva |
|---|
Highways Ltd. vs. MP Rural Road Development
| Corporation Ltd. in | AA No. 14 of 2017 and connected |
|---|
matters. It is submitted that the said judgment has been
| approved by this Hon’ble Court in the case of | M/s Essel Infra |
|---|
| Projects Ltd. vs. The State of MP | in Civil Appeal No.4250 of |
|---|
2018.
| 8.4 | | It is submitted that in the present case, arbitration |
|---|
clause contained in Clause 29 of the Agreement contemplates
a twostage adjudication. At the first stage a reference has to
be made to the Deputy Housing Commissioner for his
decision. If the amount is above Rs.25,000/ then the papers
15
have to be placed before the Housing Commissioner. This
constitutes the first stage. The second stage then contemplates
that, if the parties are aggrieved by the decision of the Deputy
Housing Commissioner, then the dispute will be referred to the
Additional Housing Commissioner subject to the jurisdiction
and limitations in accordance with the provisions of the 1983
Act. It is submitted that even the Additional Commissioner
can only deal with the disputes which are only below
Rs.50,000/ as disputes above that amount are statutorily
referable to the arbitration by the learned Tribunal as is clear
from Sections 3, 7, 2(d) and 7B of the 1983 Act.
| 8.5 | | It is submitted that in the present case, the contract in |
|---|
question was terminated on 30.06.2008 and a claim was
preferred before the Deputy Housing Commissioner on
11.07.2008. Since the contract was terminated and the
appellants herein were inviting fresh tenders and also seizing
the machinery and material of the respondent contractor, a
Writ Petition was filed bearing no.9131 of 2008 before the High
Court to expedite the conclusion of the first stage of
16
adjudication, under the threat of imminent monetary losses.
It is submitted that the Hon’ble High Court by its order dated
20.08.2008 after recording the submissions of the respondent
– contractor directed the Housing Commissioner to decide the
dispute within the period stipulated in the agreement. It is
submitted that as there was delay by the Deputy Housing
Commissioner in taking the decision, a direction was to the
Housing Commissioner to decide the issue, as the amount in
dispute was more than Rs.25,000/ and it is only the Housing
Commissioner who could take a decision as per Clause 29 of
the Contract. Liberty was also granted by the High Court to
both parties to seek a redressal of their grievances against the
final outcome by approaching the court of law. It is submitted
that thus it can be seen that the direction of the Hon’ble High
Court was consistent with Clause 29 as this represented a
decision which would be the first stage of resolution of dispute
as per Clause 29. It is submitted that the Housing
Commissioner by an order dated 07.11.2008 by an exparte
order dismissed the claims of the respondent – contractor.
17
Immediately thereafter, in line with Clause 29 of the
Agreement and Sections 7 and 7B of the 1983 Act, a reference
was preferred by the respondent – contractor herein under the
1983 Act. It is contended that the decision of the Housing
Commissioner dated 07.11.2008 cannot be said to be a
decision under the Arbitration Act, 1996. It is therefore urged
that the respondent was not required to file the objections
under Section 34 of the Arbitration Act, 1996 as contended on
behalf of the appellants.
It is submitted that a reference filed by the respondent –
contractor after the order of the Housing Commissioner was
maintainable only after the order of the Housing
Commissioner dated 07.11.2008 and not before that. It is
therefore submitted that the respondent – contractor has
acted strictly in accordance with Sections 7 and 7B of the
1983 Act read with Clause 29 of the Contract.
| 8.6 | | Alternatively, it is submitted assuming that even if the |
|---|
order of the Housing Commissioner dated 07.11.2008 is
considered to be under the Arbitration Act, 1996, the same
18
would be nonest as any arbitration relating to ‘works contract’
in M.P. could only be under the 1983 Act. The fact of the
respondent – contractor having consented to appear before the
Housing Commissioner would be immaterial as the
proceedings under the Arbitration Act, 1996 were without
jurisdiction and void abinitio. Reliance is placed on the
| decision of this Court in | Hindustan Zinc Ltd. vs. Ajmer |
|---|
| Vidyut Vitran Nigam Ltd. | , (2019) 17 SCC 82. |
|---|
Relying upon the above decisions it is prayed to dismiss
the present appeals.
| 9. | | Heard learned counsel for the respective parties at |
|---|
length.
| 10. | | The short question which is posed before this Court for |
|---|
consideration is, whether, in view of the award declared by the
Housing Commissioner, M.P. Housing Board, who was
appointed as an arbitrator pursuant to the order passed by
the High Court in Writ Petition No.9131 of 2008, was it open
for the respondent – contractor thereafter to file a reference
19
before M.P. Arbitration Tribunal with respect to the very
claim/claims which were the subject matter of arbitration
before the Arbitrator – Housing Commissioner.
It is the case on behalf of the respondent – contractor
that as the contract was a ‘works contract’ and therefore, the
dispute between the appellants and the respondent –
contractor could only be decided by the learned Arbitral
Tribunal constituted under the 1983 Act, therefore, the
Housing Commissioner had no authority to act as an
arbitrator and decide the dispute between the parties and the
award passed by the Arbitrator Housing Commissioner can
be said to be nonest and wholly without jurisdiction.
| 11. | | While considering the aforesaid issue and the |
|---|
submissions made by the learned counsel of the respective
parties, first of all the reliefs which were prayed by the
respondent – contractor in Writ Petition No.9131 of 2008 and
the respective claims made by the respondent – contractor
before the High Court in Writ Petition No. 9131 of 2008, before
20
the Arbitrator – Housing Commissioner and before the learned
Arbitral Tribunal are required to be referred to and considered.
| 11.1 | | In the Writ Petition No.9131 of 2008 the respondent – |
|---|
contractor prayed for the following reliefs:
(a) “To direct the Respondents to complete the
arbitration proceedings.
(b) To direct the Respondents not to cancel the
agreement and be permitted the Petitioner to
complete the work and quash the order of
tender dated 20.07.2008 (Annexure P/22) and
dated 27.07.2008 Annexure P/23).
(c) Set aside the order dated 30.06.2007 (Annexure
P/19) passed by the Executive Engineer.
(d) To direct the Respondents to pay the amount of
outstanding dues of Rs. 17835925.00 with
interest and compensation of ten crores.
(e) To direct the Respondents not to award the
contract to any other person and also direct the
Respondents to decide the arbitration, after
affording the proper opportunity to the
Petitioner.
(f) To call the relevant records
(g) Any other order/ orders, directions which this
Hon'ble Court deems fit and proper may kindly
be also granted.”
21
11.2 That thereafter the High Court passed the following order
dated 20.08.2008:
“Shri Sameer Seth, Counsel for the Petitioner.
Shri T.S. Ruprah, Sr. Counsel with Shri Harmeet
Singh, Counsel for Respondents/ M.P. Housing
Board.
Learned counsel for the Petitioner fairly stated
that the arbitration clause in the agreement has
been invoked by submitting reference vide
Annexure P20. He drew attention of this Court to
the prayer for interim relief regarding restraining
from inviting tender for the remaining work. He
stated at Bar that no order has been passed on
the prayer for interim relief.
This being so, this petition is disposed of with a
joint consensus of the learned Counsel for the
parties in the following manner:
(i) The arbitrator i.e. Housing Commissioner, M.P.
Housing Board would decide the dispute in
arbitration within the period stipulated in the
agreement.
(ii) A decision on the interim prayer made on the
interim page25 of the reference (Annexure P20)
would be taken within a period of one week from
today.
(iii) Till then no work order be issued pursuant to
the fresh tender.
(iv) Petitioner would also be at liberty to move a
separate application within three days with regard
to the relief granted vide interim order dated
07.08.2008. A decision on such application, if
filed, would be taken in an expeditious manner
22
preferably within a week. Interim order dated
07.08.2008 shall continue to operate till a decision
on such interim application is taken.
Petition, accordingly stands disposed of with
an observation that the aggrieved party, in case of
grievance against the final outcome, shall have a
right to approach the Court of law.”
| 11.3 | | Thereafter it was the respondent – contractor who himself |
|---|
submitted the claim before the Arbitrator – Housing
Commissioner. The Arbitrator Housing Commissioner issued
notice upon the respondent – contractor. However, after
submitting the claims, the respondent – contractor did not
appear before the learned Arbitrator – Housing Commissioner
and consequently on appreciation of evidence and considering
the submissions made on behalf of the appellant, the learned
Arbitrator – Housing Commissioner passed an award dated
07.11.2008. Subsequently, respondent – contractor filed a
reference before the learned Arbitral Tribunal constituted
under the provisions of 1983 Act making the very claims
which were made before the High Court in Writ Petition
No.9131 of 2008 as well as made before the learned Arbitrator
– Housing Commissioner.
23
At this stage, it is required to be noted that in the
Reference Petition there was no reference to the order passed
by the High Court in Writ Petition No.9131 of 2008 referring
the disputes between the parties to the Arbitrator – Housing
Commissioner and thereafter submitting the claims before the
Housing Commissioner and the award passed by the learned
Arbitrator – Housing Commissioner dated 07.11.2008. A
detailed written statement was filed. The relevant extracts of
the written statement are as under:
1. “The claim was also filed by the petitioner to
the Housing Commissioner of Respondents
which was duly decided complying with the
directions of the Hon'ble High Court of M.P.
2. The Hon'ble High Court by Order dated
20.08.2008 in Writ Petition No. 9131/2008
directed the Commissioner of M.P. Housing
Board to decide the application of interim stay
filed by the Contractor before retendering of
the works. The Directions were also issued for
final hearing under clause 29 of the agreement
with in the provision of agreement. The Hon'ble
Commissioner had fully complied with the
directions of the Hon'ble High Court and the
Contractor was duly notice but even than the
Contractor did not take any pains even to see
the order of Commissioner dt. 07.11.08, which
was passed by him in compliance with the
directions of the Hon'ble High Court.
24
3. The petitioner is not entitled to claim any relief
as he has not come before this Hon'ble M.P.
Arbitration Tribunal with clean hands and the
facts of paramount importance have been
deliberately suppressed by the petitioner in the
said petition.
4. That as per the directions order by Hon. High
Court, the matter has already been decided
and award has already been passed and duly
acknowledged by the petitioner hence the
petition filed before the Hon'ble MP Arbitration
Tribunal deserved to be dismissed, no relief
can be claimed.
5. That the petitioner has duly accepted the
award as it evident from his action that he has
accepted the payment so ordered by the
Arbitrator the Housing Commissioner in the
said award. In compliance with the award
dated 07.11.2008 passed by the Commissioner
the petitioner has already received the
payment as per award as is evident from the
letter dated 02.11.2009 the award so received
is Rs. 3,57,000/ in total through cheque
dated 02.01.2009.
6. That from the action and reactions of
petitioner it is evident that the petitioner has
accepted the award without challenging it
before the appropriate court prior to accepting
the payments awarded by the Arbitrator in the
light of orders of Hon'ble High Court has been
accepted and agreed by the Petitioner. Keeping
in view of this legal proceedings, this petition
of the Petitioner does not even deserves for
admission as the final adjudication was
complete by the Order of the Commissioner,
M.P. Housing Board, issued under the
directions of the Hon'ble High Court.”
25
| 11.4 | | That the appellants filed I.A. No.1 raising preliminary |
|---|
issues with respect to maintainability of the reference before
the learned Tribunal. The learned Arbitral Tribunal framed
the following preliminary issues:
“(i) Whether the Petitioner has complied with
provisions of clause 29 before approaching this
Tribunal?
(ii) Whether the Petitioner has no locus standi to
file the petition when the appointed arbitrator by
the Hon'ble High Court with consent passed the
award dated 07.11.2008 and acted upon?”
| 11.5 | | That by a detailed order and considering the order |
|---|
passed by the High Court dated 20.08.2008 referring the
disputes between the parties to the Arbitrator – Housing
Commissioner; the claims made before the High Court as well
as before the learned Tribunal dismissed the reference by
holding that the Reference Petition is not maintainable. While
dismissing the Reference Petition as not maintainable in para
18, the learned Arbitral Tribunal observed as under:
“On perusal of the order dated 20.08.2008 (Ex.
D/18) passed by the Hon'ble High Court it seems
that the said order was passed with the consent of
both the parties. The order indicates that the
Housing Commissioner was appointed as
26
arbitrator to decide the dispute between the
parties. The contention of the learned Counsel of
the Petitioner that the Housing Commissioner was
directed to decide the Petitioner's quantified claim
by invoking clause 29 as competent authority does
not appear to be acceptable because the Housing
Commissioner has been designated in the order as
the Arbitrator. Moreover, the Housing
Commissioner was not directed to decide the
dispute as competent authority. Apart from this,
under clause 29 there are only two competent
authorities, first, is Dy. Housing Commissioner
and if he fails to decide the dispute within 60 days
second is Additional Housing Commissioner.
There is no provision to decide the quantified
rd
claim by the 3 competent authority. Besides it,
Hon'ble High Court has no power to create/
appoint a third competent authority by invoking
the power clause 29 of the agreement, but Hon'ble
High Court has the power to appoint an arbitrator
under Section 11 (6) of the Act, 1996. Therefore,
keeping in view the aforesaid facts, it can only be
inferred that the Hon'ble High Court exercising the
power vested in it under Article 227 of the
Constitution of India appointed the Housing
Commissioner as Arbitrator to decide the dispute.
The submission of the learned Counsel for the
Petitioner that appointment of Arbitrator is
without jurisdiction and the said order dated
20.08.2008 does not have over riding effect on the
provisions of the Act, 1983 and the said order
being per incurium has no force appears to be
sound but this Tribunal has no power to say that
the order dated 20.08.2008 passed by the Hon'ble
High Court in writ jurisdiction is without
jurisdiction and has effect of nullity because this
Tribunal is subordinate of the Hon'ble High Court
which has supervisory power over it under Article
227 of Constitution of India. Moreover, the award
passed by this Tribunal is challengeable before the
Hon'ble High Court under Section 19 of the Act,
27
1983 by the Civil Revision. If the Petitioner was
not satisfied with the order dated 20.08.2008
passed by the Hon'ble High Court, the propriety
and the legality of the said order ought to have
been challenged by the Petitioner before the
competent forum but it was not done so.
Moreover, the said order was passed with the
consent of both the parties. In the said
circumstances, this Tribunal is bound to accept
the order passed by the Hon'ble High Court. On
the basis of the aforesaid facts and circumstances
of the case, it can be safely inferred that Housing
Commissioner was appointed by the Hon'ble High
Court to decide the dispute between the parties as
the Arbitrator who decided the same vide award
dated 07.11.2008. The legality and the propriety of
the said award could have been challenged by
filing appeal under Section 34 of the Act, 1996 but
the Petitioner failed to do so, consequently, the
said award had achieved finality before filing the
reference petition. Once the dispute between the
parties had already been decided by the competent
Arbitrator, the same dispute cannot be reagitated
before this Tribunal by the Petitioner. the Hon'ble
High Court in the case of Ditya (supra) elaborately
discussing in para 12 has held that even a wrong
decisions are taken which is contrary to the law is
binding upon the parties unless and until it is set
aside in the appeal or by the other remedy
provided under the clause.”
| 12. | | After the aforesaid order dated 27.02.2017 passed by the |
|---|
learned Tribunal holding that the reference petition was not
maintainable in view of the earlier order passed by the High
Court dated 20.08.2008 passed in Writ Petition No.9131 of
2008 directing the adjudication of the dispute by the
28
Arbitrator – Housing Commissioner, the respondent –
contractor filed a review petition before the High Court, having
realized that the order dated 20.08.2008 passed in the Writ
Petition No.9131 of 2008 will come in his way in pursuing the
reference petition before the learned Arbitral Tribunal, seeking
clarification of the order passed in W.P. No.9131 of 2008 to the
extent that by directing the adjudication of the dispute by the
Housing Commissioner, it does not take away the jurisdiction
of the learned Arbitral Tribunal constituted under the Act
1983. The said review petition was opposed by the appellants.
Vide order dated 07.09.2017 the High Court dismissed the
said review petition. Thereafter the respondent – contractor
filed the revision application before the High Court under
Section 19 of the 1983 Act being Arbitration Revision No.13 of
2017 challenging the order dated 27.02.2017 passed by the
learned Arbitral Tribunal dismissing the reference petition as
not maintainable. By the impugned judgment and order, the
High Court, relying upon the subsequent decision of the full
Bench has set aside the order passed by the learned Tribunal
29
on 27.02.2017 and has directed the learned Arbitral Tribunal
to decide the reference on merit. The impugned judgment and
order passed by the High Court in A.R. No.13 of 2017 is the
subject matter of present appeal.
| 13. | | At the outset, it is required to be noted that as such the |
|---|
earlier order passed by the High Court in Writ Petition
No.9131 of 2008, by which the dispute between the parties
was referred to the Arbitrator – Housing Commissioner was a
consent order. It was the respondent – contractor who filed
the Writ Petition No.9131 of 2008 submitting that he has
invoked the arbitration clause. Thereafter the respondent –
contractor submitted the claim before the Arbitrator – Housing
Commissioner who passed an award. The respondent –
contractor did not challenge the award passed by the
Arbitrator – Housing Commissioner and therefore, as such the
award passed by the Arbitrator – Housing Commissioner dated
07.11.2008 has attained finality.
30
| 14. | | The case of the respondent – contractor that the earlier |
|---|
order passed by the High Court dated 20.08.2008 passed in
Writ Petition No.9131 of 2008, referring the dispute between
the parties for adjudication to the Arbitrator – Housing
Commissioner and thereafter the award declared by the
Arbitrator – Housing Commissioner dated 07.11.2008 are non
est and void and therefore, it was open for the contractor to
file a fresh reference petition before the learned Arbitral
Tribunal under Section 7 of the 1983 Act, cannot be accepted
for the following reasons:
(i) It was the respondent – contractor who approached the
High Court by filing Writ Petition No.9131 of 2008
submitting that he has invoked the arbitration clause;
| The order passed by the High Court dated |
|---|
20.08.2008 passed in Writ Petition No.9131 of 2008
referring the dispute between the parties to the
Arbitrator – Housing Commissioner was a consent
order;
31
(iii) Thereafter the respondent – contractor submitted the
claims before the learned Arbitrator – Housing
Commissioner;
(iv) The learned Arbitrator – Housing Commissioner
passed an award which has attained the finality;
| That the review petition filed by the contractor for |
|---|
clarification of the order dated 20.08.2008 passed in
Writ Petition No.9131 of 2008 to clarify the aforesaid
order to the extent that it did not take away the right
of the contractor to file the reference petition before
the learned Arbitral Tribunal under the 1983 Act came
to be rejected and the same also attained finality;
(vi) The claims submitted before the Arbitrator – Housing
Commissioner; before the High Court in Writ Petition
No.9131 of 2008; and the claim submitted in
Reference Petition before the learned Arbitral Tribunal
under the 1983 Act are the same without any change;
32
(vii) In the subsequent reference petition before the learned
Arbitral Tribunal under the 1983 Act there was no
reference to the earlier order passed by the High Court
in Writ Petition No.9131 of 2008 referring the dispute
between the parties for adjudication to Arbitrator –
Housing Commissioner and the award passed by the
Arbitrator – Housing Commissioner. Thus, there was
a suppression on the part of the respondent –
contractor;
(viii) The order passed by the High Court dated 20.08.2008
passed in Writ Petition No.9131 of 2008 referring the
dispute between the parties for adjudication to the
Arbitrator – Housing Commissioner as such was a
consent order and thereafter the contractor
participated in the arbitration proceedings before the
Arbitrator – Housing Commissioner by submitting the
claim is binding between the parties on the ground of
‘issue estoppel’.
33
| 15. | | In the case of | Bhanu Kumar Jain | | (supra) | it is observed |
|---|
and held that a cause of action estoppel arises where in two
different proceedings identical issues are raised, in which
event, the latter proceedings between the same parties shall be
dealt with similarly as was done in the previous proceedings.
In such an event, the bar is absolute in relation to all points
decided save and except allegation of fraud and collusion.
| 16. | | Apart from the fact that the award declared by the |
|---|
Arbitrator – Housing Commissioner was not challenged by the
respondent – contractor, even, so long as the said award is not
challenged before the higher forum the same is binding
between the parties. Even the award or a nullity order has to
be challenged before the appropriate forum/higher forum. In
the present case it cannot be said that there was a total lack of
jurisdiction of the Arbitrator – Housing Commissioner in
passing the award as it was the High Court who passed the
order with consent referring the dispute between the parties
for the adjudication to the Arbitrator – Housing Commissioner.
Therefore, unless and until it was challenged by the contractor
34
before the higher forum, the respondent – contractor cannot
be permitted to ignore and/or to avoid the award passed by
the Arbitrator – Housing Commissioner dated 07.11.2008.
| 17. | | Even otherwise, it is required to be noted that what was |
|---|
filed before the High Court was the revision application filed by
the contractor under Section 19 of the 1983 Act rejecting the
reference petition as not maintainable. Section 19 of the 1983
Act reads as under:
| “ | 19. High Court's power of revision. – The High | | | | | |
|---|
| Court may | | suo motu | at any time or an application | | | |
| for revision made to it within three months of the | | | | | | |
| award by an aggrieved party, call for the record of | | | | | | |
| any case in which an award has been made under | | | | | | |
| this Act by issuing a requisition to the Tribunal | | | | | | |
| and upon receipt of such requisition, the Tribunal | | | | | | |
| shall send or cause to be sent to that Court the | | | | | | |
| concerned award and record thereof; | | | | | | |
| | | | | | |
| Provided that any application for revision may be | | | | | | |
| admitted after the prescribed period of three | | | | | | |
| months, if the applicant satisfied the High Court | | | | | | |
| that he had sufficient cause for not preferring the | | | | | | |
| revision with such period. | | | | | | |
| | | | | | |
| Explanation: The fact that the applicant was | | | | | | |
| misled by any order, practice or judgment or the | | | | | | |
| High Court in ascertaining or computing the | | | | | | |
| prescribed period may be sufficient cause within | | | | | | |
| the meaning of this subsection. | | | | | | |
35
| (2) If it appears to the High Court that the | | |
|---|
| Tribunal | | |
| (a) has exercised a jurisdiction not vested in it<br>by law; or | |
| (b) has failed to exercise a jurisdiction so vested;<br>or | |
| (c) has acted in exercise of its jurisdiction<br>illegally, or with material irregularity; or | |
| (d) has misconducted itself or the proceedings;<br>or | |
| (e) has made an award which is invalid or has<br>been improperly procured by any party to<br>the proceedings, | |
| the High Court may make such order in the case | |
| as it thinks fit. | |
| (3) The High Court shall in deciding any revision | |
|---|
| under this section exercise the same powers and | |
| follow the same procedure as far as may be, as it | |
| does in deciding a revision under Section 115 of | |
| the Code of Civil Procedure 1908 (No. 5 of 1908). | |
| (4) The High Court shall cause a copy of its order | |
|---|
| in revision to be certified to the Tribunal. | |
| Explanation. | | For the purposes of this section, an | |
|---|
| award shall include an 'interim' award.” | | | |
Therefore, as per Section 19 of the 1983 Act, Revision
Application to the High Court shall be maintainable only
against the award passed by the learned Arbitral Tribunal.
| Therefore, | prima facie | it appears that as such the order passed |
|---|
by the learned Arbitral Tribunal rejecting the reference petition
36
was not maintainable as by order dated 27.02.2017, no award
was passed by the Tribunal. However, as no such objection
was raised before the High Court and no submission has been
| made by the parties, we | | rest the | | matter there. |
|---|
| 18. | | Even otherwise it is required to be noted that while |
|---|
passing the impugned judgment and order, the High Court
has not set aside the award passed by the Arbitrator –
Housing Commissioner dated 07.11.2008. Therefore,
technically speaking the award passed by the Arbitrator –
Housing Commissioner dated 07.11.2008 stands even today.
It is binding between the parties. So long as the award passed
by the Arbitrator – Housing Commissioner dated 07.11.2008
s tands, there cannot be any subsequent fresh proceeding with
respect to the same claims which were considered and
adjudicated by the Arbitrator – Housing Commissioner while
passing the award dated 07.11.2008. S o long as the said
award stands it is binding between the parties.
| 19. | | Even otherwise it is required to be noted that no |
|---|
objection was raised by the respondent – contractor before the
37
Arbitrator – Housing Commissioner on the jurisdiction of the
Housing Commissioner to act as an Arbitrator. On the
contrary as observed hereinabove the order passed by the
High Court referring the dispute between the parties for
adjudication to the Arbitrator – Housing Commissioner was a
consent order and the respondent contractor conceded to
and accepted the said order and submitted his claim before
the Arbitrator – Housing Commissioner. The Arbitrator –
Housing Commissioner also passed an award on the said
claim. Therefore, as no objections were raised by the
respondent – contractor at the appropriate stage, the award
cannot be annulled subsequently. At the cost of repetition, it
is observed that at no point of time the respondent –
contractor had challenged the award passed by the Arbitrator
– Housing Commissioner and as observed and held
hereinabove even no court has set aside the award declared by
the Arbitrator – Housing Commissioner dated 07.11.2008 and
the same has attained finality. Therefore, the same is binding
between the parties. Hence, the subsequent fresh reference
38
petition before the learned Arbitral Tribunal under the 1983
Act for the very same claims which were raised before the
Arbitrator – Housing Commissioner would not be maintainable
at all. We agree with the view taken by the Arbitral Tribunal.
| 20. | | In view of the above and for the reasons stated above, the |
|---|
present appeals are allowed. The impugned judgment and
order dated 08.05.2018 passed by the High Court in A.R.
No.11, 12 & 13/2017 quashing and setting aside the order
passed by the learned Arbitral Tribunal constituted under the
1983 Act dated 27.02.2017 is hereby quashed and set aside
and the order passed by the Arbitral Tribunal dated
27.02.2017 stands restored.
All these appeals are allowed accordingly. In the facts
and circumstances of the case, there shall be no order as to
costs.
…………………………..J.
(M. R. SHAH)
…………………………...J.
(B.V. NAGARATHNA)
New Delhi;
December 03, 2021.