WAPCOS LTD. vs. SALMA DAM JOINT VENTURE

Case Type: Civil Appeal

Date of Judgment: 14-11-2019

Preview image for WAPCOS LTD. vs. SALMA DAM JOINT VENTURE

Full Judgment Text

REPORTABLE IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION   CIVIL APPEAL NO.                          OF 2019 (Arising out of SLP (C) No. 7979 of 2019) WAPCOS Ltd.          ...Appellant(s) Versus Salma Dam Joint Venture & Anr.      …Respondent(s) WITH CIVIL APPEAL  NO.            OF  2019 (Arising out of SLP (C) No……….. of 2019) (Diary No. 6975 of 2019) J U D G M E N T A.M. Khanwilkar, J. Leave granted.  These appeals take exception to the judgment and order 1. dated 25.01.2019 passed by the High Court of Delhi at New Delhi in Arbitration Petition No.810 of 2016, whereby the High Court allowed the Arbitration Petition purportedly filed by respondent Signature Not Verified Digitally signed by DEEPAK SINGH Date: 2019.11.14 13:06:12 IST Reason: No. 1 ­ Salma Dam Joint Venture, under Section 11(6) of the Page 1 of 27 Arbitration and Conciliation Act, 1996 (for short, “the Act”) and appointed a sole Arbitrator. 2. Briefly  stated,  the  Ministry  of  External  Affairs  (for short, “MEA”) and the appellant in the leading appeal, Water and Power Consultancy Services (India) Limited (for short, “WAPCOSL”),   a Public   Sector   Undertaking,   entered   into   an   agreement,   dated 29.11.2004,   for   the   implementation   of   the   work   on   “the Reconstruction,   Rehabilitation   and   completion   of   Salma   Dam Project   (3x14   MW),   Afghanistan,   Package   III:   Main   Civil   and Hydro­Mechanical   Works”   (for   short,   “project”).   The   appellant (WAPCOSL),   was   given   the   responsibility   to   provide   financial, administrative   and   contractual   management   services   for   the MEA. Even though MEA was to provide the finances, the same was   to   be   channeled   through   WAPCOSL   to   the   successful awardee of the tender. 3. The respondent No.1 in both the appeals, Salma Dam Joint Venture (for short, “SDJV”) was formed by the M/s SSJV Projects Private   Limited   (for   short,   “SSPPL”)   and   M/s   Angelique International   Ltd.   (for   short,   “AIL”)     under   a   Joint   Venture Agreement (for short,  “JVA”) dated 09.09.2005 to submit its bid for the said project. In accordance with the terms and clauses of Page 2 of 27 the JVA, SSPPL was nominated to be the ‘Lead Partner’ of SDJV with ninety­five percent (95%) share as compared to five percent (5%)   share   of   AIL.   SSPPL   was   also   authorized   to   invoke arbitration by appointing an arbitrator, make claims, et cetera, on behalf of AIL, by executing a Power of Attorney (for short, “PoA”) dated 09.09.2005 in favour of SSPPL, in accordance with Clause 3.3 of the JVA. 4. SDJV   was   successful   being   the   highest   bidder   and   was awarded tender for the said project on 17.01.2006. That was followed by a Contract Agreement dated 09.03.2006 (for short, “Contract Agreement”) for executing the stated contract between the   WAPCOSL   and   SDJV.   Along   with   the   said   agreement, WAPCOSL and SDJV signed certain documents to be read with the Contract Agreement and to form part and parcel thereof. Out of several such documents, Conditions of Particular Applications (for short “CoPA”) is the relevant one for the purpose of this case. Clause 20.1 thereof deals with Contractor’s claim and Clause 20.6 deals with Arbitration and it is under these clauses, the respondent No. 1 has rested its case, that is, arbitrability and the power to invoke arbitration.   5. Be   that   as   it   may,   the   consideration   of   the   Contract Page 3 of 27 Agreement was Rs. 253.84 Crores. However, the same was raised to Rs. 470.40 Crores, on a representation made by SDJV.  Once again, there was further change by way of revised rates, after a meeting between SDJV and a High­Power Committee (for short, “HPC”).   In the said meeting, SDJV cited reasons which were beyond its control for initiating timely construction of the project. That justification found favour with the HPC for which it had recommended revised rates with regard to eight items. A letter was sent by WAPCOSL, informing about the acceptance of revised rates of eight items and raising the total consideration to Rs. 872.67 Crores. Subsequent to this, SDJV and WAPCOSL signed a revised agreement for the rates, referred to as the Amendment of Agreement (for short, “AoA”), dated 09.06.2015. 6. Despite signing of AoA, SDJV raised certain claims before the Engineer of WAPCOSL. After rejection of said representation, SDJV   preferred   six   appeals   to   the   Technical   Committee constituted in terms of clause 2.1 of Section – 02 of AoA. Five of these   appeals   were   rejected/disposed   of   vide   report   of   the Technical Committee dated 28.10.2016.  7. In the meantime, on 04.06.2016, the Dam was inaugurated Page 4 of 27 by the Hon’ble Prime Minister of India and Hon’ble President of Afghanistan. Subsequent to which, a letter dated 02.08.2016 was issued by AIL addressed to WAPCOSL, informing that SDJV has started the process of dismantling the machinery and the work force from the project site with full awareness of WAPCOSL. Subsequent to the execution of AoA, dispute arose between 8. the JV partners which resulted in AIL filing a petition (bearing number   O.M.P.   (I)  (COMM.)  70/2016)  under   Section  9   of   the Arbitration Act, wherein the High Court of Delhi, vide order dated 05.09.2016, directed WAPCOSL to deposit the amount payable to SDJV with the Registrar of the High Court in order to secure the interests of both the JV entities. The High Court in a separate petition (bearing number Arb. P. 442/2016), filed by AIL against SSPPL, also appointed a sole arbitrator for their (AIL and SSPPL) inter se  disputes.  9. On 21.09.2016, the Board of Directors of AIL resolved to revoke the PoA executed in favour of SSPPL and in furtherance of the same, AIL, vide letters dated 19.10.2016 and 11.11.2016, wrote to the respective Banks and also to WAPCOSL informing them about the revocation of the authority of SSPPL. Thus, it was Page 5 of 27 duly   notified   through   these   letters   that   in   future,   only   those letters or communications which are signed or acknowledged by both   the   parties   (AIL   and   SSPPL)   shall   be   valid   and   be entertained by WAPCOSL. Notwithstanding   the   abovementioned   letters   sent   by   AIL, 10. upon rejection of the claims of SDJV by the Technical Committee, on 28.10.2016, SSPPL, unilaterally, espousing claims of SDJV proceeded to invoke the arbitration process, under clause 20.6 of CoPA and also appointed a nominee arbitrator, vide letter dated 12.11.2016.   WAPCOSL,   in   response,   vide   letter   dated 05.12.2016, recorded that since SDJV is a joint venture entity and the authority of SSPPL to represent AIL has been revoked, the appointment of arbitrator by SSPPL, unilaterally, is illegal in terms of clause 4.2 of the Contract Agreement and clause 3.2 of the JVA. Resultantly,   SSPPL   filed   a   petition   on   behalf   of   SDJV 11. against   WAPCOSL   under   Section   11(6)   of   the   Arbitration   Act (bearing   number   Arb.   P.   810/2016)   before   the   High   Court   of Delhi,   wherein   it   has   been   asserted   that   the   PoA   dated 15.07.2005 given by AIL in its favour is still in force and forms part of the Contract Agreement dated 09.03.2006. This assertion Page 6 of 27 is factually incorrect.  In that, the PoA was executed as a follow up document alongwith JVA on 09.09.2005 itself. Whereas, the Board of Directors of AIL vide resolution dated 15.07.2005 had authorised its officer to execute the JVA and PoA, which were so executed on 09.09.2005. 12. The said arbitration petition was contested by the appellant (WAPCOSL).   However,   the   High   Court   allowed   the   same   vide order   dated   15.03.2017   and   appointed   an   arbitrator   for WAPCOSL. Feeling   aggrieved,   WAPCOSL   preferred   a   Special   Leave 13. Petition   (bearing   number   SLP   (Civil)   26555/2017)   before   this Court.   This   Court,   vide   order   dated   03.11.2017,   directed impleadment   of   AIL   as   a   party   and   also   stayed   the   arbitral proceedings. AIL appeared before this Court and asserted that it did not give consent to SSPPL for appointment of an arbitrator or for filing petition under Section 11(6) of the Arbitration Act. Thus, it had urged that SSPPL had no authority to unilaterally appoint an arbitrator for SDJV or to file the subject petition on behalf of SDJV.  Further, the petition filed in the name of SDJV through SSPPL was not as per Delhi High Court Rules. This Court, vide order dated 11.12.2017, deemed it proper to set aside the order Page 7 of 27 passed   by   the   High   Court   of   Delhi   dated   15.03.2017   and   to relegate the parties before the High Court for reconsideration of all aspects, as would be raised by the parties including regarding the locus and competence of SSPPL to unilaterally appoint an arbitrator or file arbitration petition under Section 11 of the Act. 14. The High Court of Delhi, vide judgment dated 25.01.2019 (for short, “impugned judgment”), once again allowed the said arbitration petition and appointed a sole arbitrator, instead of three arbitrators envisaged in CoPA.  15. The   High   Court   opined   that   the   arbitration   agreement between SDJV and WAPCOSL was still in force on the date of filing   of   the   arbitration   petition   and   the   same   would   operate between the parties. That finding has been reached despite the AoA having been executed between the parties on 09.06.2015. The High Court also opined that SSPPL had authority under the JVA as well as the Contract Agreement to represent SDJV, as a leading partner thereof.   It held that SSPPL derived authority from clause 20.6 of CoPA read with the other enabling terms in the JVA and FIDIC Conditions of Contract for Construction (for short, ‘FIDIC’). The High Court was also impressed by the fact Page 8 of 27 that SSPPL had 95 per cent shareholding in SDJV as against only 5 per cent shareholding of AIL, the other partner. For that reason, it went on to observe that AIL cannot be permitted to derail the arbitration process commenced for and on behalf of SDJV through SSPPL. The High Court was also impressed by the fact that despite the execution of AoA, the Technical Committee entertained the appeals filed by SDJV in respect of certain items. That goes to show that even the Technical Committee was of the view that the dispensation regarding settlement of further claims of SDJV could be pursued and the arrangement arrived under AoA   between   the   parties   cannot   be   treated   as   full   and   final settlement.  Resultantly, SDJV was well within its rights to take recourse   to   arbitration   for   resolution   of   the   disputes   in   that regard. Further, the fact as to whether SDJV was entitled for the relief,   regarding   the   claims   raised,   was   a   matter   within   the exclusive   domain   of   the   Arbitral   Tribunal.     The   High   Court, therefore, allowed the Arbitration Petition and appointed a sole Arbitrator for resolution of the disputes between the parties.   16. Feeling aggrieved, WAPCOSL as well as AIL have assailed the decision of the High Court by filing separate Special Leave Petition(s). Page 9 of 27 17. We   have   heard   learned   Senior   Counsel   Mr.   Gaurav Panchnanda for WAPCOSL (appellant) and Mr. Shyam Divan for AIL (appellant), and Mr. Sachin Datta, learned Senior Counsel for SDJV (respondent No.1 in both the appeals). After cogitating over the erudite arguments of the counsel 18. appearing for the respective parties and perusing the relevant records,   including   Arbitration   Petition   and   the   written submissions filed by the learned counsel, in our opinion, two principal   issues   need   be   answered   in   this   judgment.   First, whether   on   the   date   of   presentation   of   Arbitration   Petition, purportedly   by   SDJV   through   SSPPL   on   15.12.2016,   the arbitration   agreement   posited   in   Contract   Agreement   dated 09.03.2006 was in existence or subsisting and in force? Second, whether   the   Arbitration   Petition   filed   in   the   name   of   SDJV through SSPPL, in law can be considered as having been properly and validly presented despite the express revocation of authority of SSPPL vide resolution passed by the Board of Directors of AIL on   21.09.2016   and   duly   communicated   to   SSPPL   as   well   as WAPCOSL before 15.12.2016, as was granted to SSPPL in terms Page 10 of 27 of JVA read with PoA including the Contract Agreement? 19. Reverting to the first question, we must immediately advert to   the   Arbitration   Agreement   incorporated   in   the   Contract Agreement.   That can be discerned from clause 4, which reads thus:­ “4. Settlement of Disputes 4.1 It is specifically agreed by and between the parties that   all   the   differences   or   disputes   arising   out   of   the Agreement shall be decided by process of settlement of disputes and arbitration as specified in Clause 20 of the Conditions of the Contract.  4.2 It is also agreed that the Salma Dam Joint Venture agreement dated 9th September 2005 shall be treated as part of this agreement and both the parties to the said joint venture namely M/s SSJV Projects Private Limited and M/s Angelique International Limited shall also be jointly and severally liable in the process of settlement of disputes in arbitration between WAPCOS and Salma Dam Joint Venture.” This clause must be read alongwith the terms specified in CoPA in particular clause 20 and clauses 1.14, 4.3 and 20.6 of FIDIC. Going by the Contract Agreement read with relevant clauses of CoPA and FIDIC, it is obvious that the parties had agreed for resolution of all their differences or disputes arising from the Contract   Agreement   by   process   of   settlement   of   disputes   and arbitration.  20. In  the  present case,  however,  in  due  course,  because  of fortuitous situation, the parties had to agree to amend certain Page 11 of 27 terms and conditions of the Contract Agreement and to provide for revised contract rates. That was done after due negotiations, as is evinced from the correspondence exchanged between SDJV and WAPCOSL vide letters dated 15.09.2011 and 17.09.2012 and the   recitals   of   the   AoA   itself.   Finally,   the   parties   (SDJV   and WAPCOSL   in   particular)   executed   a   formal   Amendment   of Agreement   (AoA)   on   09.06.2015.     The   same   records   the   new arrangement eventually agreed upon between the parties. It will be useful to first refer to the preamble of the AoA which reads thus: “1.0    Preamble          Consequent upon the modification of rates of certain Items   of   works   in   January   2013   which   is   subject   to special   terms   and   conditions,   the   Amendment   to   the Original   Agreement   between   WAPCOS   and   SDJV   (the Parties) was required to be entered upon thereafter. Nevertheless the work at site continued at very fast pace and   in   good   faith   and   trust   as   per   the   revised   rates agreed between the Parties. Despite several constraints the project completion progressed well during the years 2013 and 2014 and substantial part of the works (around st 97%) of the Dam and Spillway was completed by 31 December 2014. Remaining works are continuing at the project site.  Now, as the Amendment to Agreement is to be formalized for   proper   implementation   and   records,   therefore,   in continued good faith and trust the Parties have agreed to sign this Amendment of Agreement by incorporating the actual   site   conditions,   practical   difficulties   and subsequent developments that have taken place at site. ……. .”  21. In clause 1.1 of AoA, reference is made to the estimated cost Page 12 of 27 of works and the balance work to be completed in the revised estimated cost.  The note below the chart given in clause 1.1 and clauses 1.2 to 1.6 of the preamble are of some relevance. The same read thus:   “1.1 The balance work has to be completed in the revised estimated cost as given below.  Estimated Cost of Works ….   …..   …… Note:   If   due   to   site   conditions,   the   balance   quantities increases, the contractor will carry out the construction and complete the work 1.2 This Amendment of Agreement will form part of the Original   Agreement   no.   WAPCOS/SDP/AFG/Pkg.­III­05 dated 9th March 2006. 1.3 This Amendment of Agreement includes revised Bill of Quantity (BoQ) (containing executed & balance quantum of   works,   New   Items   of   work,   etc)   with   the   modified approved rates for eight major item of Civil works and modified   cost   of   Hydro­Mechanical   works   along   with additional terms and Conditions of Contract.  1.4   Any   Clauses/items   other   than   the   Amendment   of Agreement will be governed by Original Agreement and in case of any dispute the decision of CMD, WAPCOS will be final and binding to the Contractor. 1.5   In   case   of   any   inconsistency   between   Original Agreement and Amendment of Agreement, the content of Amendment of Agreement will succeed. 1.6 In case of any dispute on Technical Specification and interpretation   of   any   contract   clauses   the   decision   of CMD,   WAPCOS   will   be   final   and   binding   to   the Contractor. ……… .” 22. It may be useful to now advert to clauses 1.2 and 1.3 of Page 13 of 27 Section ­01 of the AoA, which read thus: “REVISED   COST   AND   RELATED   TERMS   AND CONDITIONS Clause 1.0  ….  …..  …..  The   revision   of   cost/modified   rates   of   above   item   are subject to the following:  1.1 ….   ….   …. 1.2 The balance pending claims of Contractor stands buried   and   it   was   agreed   by   the   Contractor   that,   no claims   will   be   raised   by   Contractor   on   any   of   the pending/settled claims/other claims resulting out of the correspondences   made   so   far   and   there   will   be   no arbitration for the settlement of claims. It is agreed that the Contractor shall not be paid any further amount on claim/additional   rate   for   new   item   of   work   settled   or pending over and above the payments already released to the contractor.  1.3 In future, no claim of Contractor on any account shall be entertained. However any claim arising out of force majeure shall be examined.”  Here, we may also take note of Section­02 of AoA concerning the amendment in general conditions of CoPA. Clause 2.1 of this section   predicates   that   sub­clause   1.1.2.16   of   CoPA   stands modified as Technical Committee means committee constituted by CMD, WAPCOSL.  It is pertinent to note that the execution of stated AoA has 23. not been disputed by SDJV or for that matter by SSPPL. More so, these entities have not even challenged the implementation of Page 14 of 27 AoA. On the other hand, it has come on record that all concerned gave effect to the terms set out in AoA by offering revised rates to SDJV in conformity with the agreed rates referred to in AoA and which   payment   was   received   and   availed   of   by   SDJV/SSPPL without any demur. We may hasten to add that even the subject Arbitration Petition does not question the execution of AoA or the applicability thereof.  Indeed, the asseveration in the Arbitration Petition is that the claim set up by SDJV is in reference to items and bills raised subsequent to the execution of AoA. 24. The moot question is: whether the AoA has the effect of undoing and abrogating the arbitration clause predicated in the Contract   Agreement?   According   to   SDJV   and   SSPPL,   the arbitration clause in the Contract Agreement remains intact and undisturbed.  The parties continue to be bound by the same.  25. For considering this plea we must appreciate the backdrop in which the AoA has been executed, to understand the true import of the terms and conditions set out therein. From the correspondence   exchanged   between   the   parties   preceding   the execution of AoA, being letters dated 15.09.2011 and 17.09.2012, it is amply clear that the parties were  ad idem  that substantial part of the works (around 97 per cent) of the “Dam and Spillway” Page 15 of 27 was   completed   by   31.12.2014.     This   fact   has   been   plainly restated in the preamble of the AoA. The AoA also records that if due   to   site   conditions,   the   balance   quantities   increase,   the contractor will carry out the construction and complete the work. Further,   the   AoA  would   form  part of   the   Contract Agreement dated 09.03.2006 and it includes revised Bill of Quantities (BoQ) (containing executed and balance quantum of works, new items of works, etc.) with the modified approved rates for eight major items of civil works and modified cost of Hydro­Mechanical works along with additional terms and conditions of Contract. Clause 1.4 of the AoA makes it amply clear that any other clauses/items other   than   the   AoA   will   be   governed   by   Original   Agreement (Contract Agreement) and in case of any dispute, the decision of CMD,  WAPCOSL   will   be   final   and   binding   on   the   contractor. Clause 1.5 of the AoA makes it further clear that in case of any inconsistency   between   the   Contract   Agreement   and   AoA,   the terms specified in AoA will prevail. Clause 1.6 of the preamble postulates that in case of any dispute on technical specifications and interpretation of any contract clauses, the decision of CMD, WAPCOSL will be final and binding on the contractor. Section­01 of   AoA   then   deals   with   revised   cost   and   related   terms   and Page 16 of 27 conditions.   Clause   1.0   thereof   provides   that   the   revision   of cost/modified rates of the items referred to therein will be subject to clauses 1.2 and 1.3, amongst others.  Clause 1.2 of Section­01 envisages that the balance pending claims of contractor “stands buried” and it has been agreed by the contractor, that no claims will be raised by the contractor on any of the pending/settled claims/other claims resulting out of correspondences made so far and there will be “no arbitration” for the settlement of claims. Clause 1.3 of Section­01 also makes it clear that in future no claim of contractor on any count shall be entertained except the claim arising out of force majeure.  26.  Despite such peremptory agreement and declaration by the parties,   SDJV   proceeded   on   an   erroneous   basis   that   the arbitration agreement in Contract Agreement still subsists and can be enforced by it.   As aforesaid, neither SDJV nor SSPPL have   disputed   the   execution   of   AoA   nor   it   is   even   remotely suggested in the Arbitration Petition that the AoA was executed by   them   under   duress   or   coercion.   From   the   indisputable circumstances, it becomes amply clear that the stated terms and conditions set out in the AoA were agreed upon by all concerned primarily due to revision of cost of the project upto Rs. 872.67 Page 17 of 27 crores   which   is   3.44   times   the   original   project   cost,   (i.e.   Rs. 253.84 crores) as the same was subject to clauses 1.2 and 1.3 of 1 Section­01 .  Notably,   this  AoA   was   executed  at   a  stage   when substantial part of the works (around 97%) had already been completed. In our opinion, the terms and conditions specified in AoA leave no manner of doubt that the arbitration agreement has been done away with – as is manifest from the unambiguous declaration   that   balance   pending   claims   of   Contractor   stand buried and that there will be no arbitration for the settlement of 2 claims .  27.     To   get   over   this   position,   SDJV   would   contend   that Section­02   of   AoA   specifically   deals   with   the   amendments   in general   conditions   of   CoPA   but   it   makes   no   reference   to amendment of clause 20 of CoPA.  That may be so, however, in our view, it will be of no avail.  We will deal with this aspect a little later. Suffice it to observe that the terms and conditions of AoA make it amply clear that the arbitration agreement stands overridden   in   view   of   the   express   declaration   in   AoA   in   that regard referred to earlier.  As   noticed   earlier,   AoA   was   executed   on   09.06.2015   by 28. 1  See – Clause 1.0 of Section­01 of AoA (in paragraph 22 above) 2  See – Clause 1.4 of Preamble (in paragraph 21 above) read with clauses 1.2 and 1.3 of Section ­01 of AoA (in paragraph 22 above). Page 18 of 27 which date, substantial part of the works (around 97 per cent) of the “Dam and Spillway” had been completed. The water filling in dam commenced on 26.07.2015 by closing diversion tunnel gate. That presupposes that the “Dam and Spillway” work was fully completed before that date. It is also not disputed that the project was inaugurated by the Prime Minister of India and the President of Afghanistan on 04.06.2016.  The terms agreed upon between the parties and as recorded in AoA dated 09.06.2015 was the outcome   of   steep   revision   of   rates.   These   circumstances   are germane whilst answering the question under consideration. We have no  manner  of   doubt  that  the   purport  of  the   terms  and conditions   incorporated   in   the   AoA   dated   09.06.2015   are unambiguous expression of intent to supersede the arbitration agreement incorporated in Contract Agreement dated 09.03.2006 and to resolve all the contentious issues regarding the claims of SDJV, in the manner specified therein.   The   High   Court,   however,   rejected   the   argument   of   the 29. appellant(s) herein on the following basis: “10.5 What is, however, not disputed is that as a matter of   fact,   the   J.V.   entity   had   lodged   its   claim   with   the Engineer   appointed   under   the   C.A.   and   upon   the Engineer repelling its claim, five appeals were lodged with the Technical Committee which rejected the same by way of a common order dated 28.10.2016. A perusal of the order of the Technical Committee would show that the Page 19 of 27 claims lodged by the J.V. entity have been examined on merits and also from the perspective of the plea raised before it with regard to their admissibility in view of the provisions of Clauses 1.2 and 1.3 of the AOA. 10.6 Therefore, if, as contended on behalf of WAPCOS, Clauses 1.2 and 1.3 of the AOA barred the J.V. entity from pressing any pending or future claims, then, to my mind, there was no need for the Technical Committee to deliberate upon the claims on merits. It is the stand of the   J.V.   entity   that   all   the   claims   lodged   by   it   with WAPCOS pertain to a period post the execution of the AOA. 10.7 The record shows that the AOA was executed on 09.06.2005, while the subject project was inaugurated post its completion only in 2016. Furthermore, it is the case of the J.V. entity that the AOA provided for revision of rates for eight major items concerning civil works and hydro   mechanical   works.   Therefore,   if   at   all,   the   bar would   apply   to   claims,   which   were   referable   to   pre­ existing claims, or claims pertaining to revision of rates relatable to eight major items of civil works and hydro mechanical works or those claims which overlapped with these claims. That being said, as to whether the position taken by  the J.V. entity is correct or not is a matter which   can   only   be   examined   by   the   Arbitral   Tribunal once  the matter   is  tried  as  based  on  mere  pleas  and counter pleas, this aspect cannot be decided in a Section 11 petition. Particularly, given the facts obtaining in this case, it is not possible to come to a definitive conclusion that   there   was   accord   and   satisfaction   upon   the execution of the AOA. 10.8 Therefore, the ground taken on behalf of WAPCOS that no claim could be lodged post execution of the AOA is untenable and hence cannot be accepted. There is, to my mind, much merit in the submission advanced on behalf  of  the  J.V.  entity   that   the AOA  cannot   impede adjudication of all future claims whether or not they have their   genesis   in   the   AOA.   If   that   was   the   intent,   as correctly argued on behalf of the J.V. entity, the AOA should have done away with Clause 20.6 of COPA, which contains the arbitration agreement.” 30. As regards the first reason weighed with the High Court that the Technical  Committee entertained  the  five appeals filed on Page 20 of 27 behalf of the SDJV, that in our view cannot undo the effect of terms and conditions of AoA which had annulled the arbitration clause in the Contract Agreement. There are at least two other tangible reasons to overturn the stated opinion of the High Court. First,   the   Technical   Committee   was,   as   a   matter   of   fact, constituted under clause 2.1 of Section – 02 of AoA by the CMD of   WAPCOSL,   as   is   evident   from   the   communication   dated 21.10.2015  sent  by  WAPCOSL  to  SDJV.     That  fact  has   been restated   in   the   subsequent   correspondence.     The   Technical Committee   was,   therefore,   not  constituted   in  terms   of   Clause 20.1 of  CoPA   as   has   been   erroneously   assumed   by   the   High Court. Second, the fact that the Technical Committee processed the appeals instituted by SDJV does not mean that WAPCOSL had   waived   the   terms   and   conditions   of   AoA,   in   particular clauses 1.2 and 1.3 of Section­01 thereof. No averment is found in the Arbitration Petition to even remotely suggest that it was a case of waiver express or tacit, by WAPCOSL  qua  the stipulation specified in clauses 1.2 and 1.3 of Section­01 of AoA.  Hence, this reason weighed  with the  High  Court is  manifestly  wrong  and cannot stand the test of judicial scrutiny.  31. The second reason weighed with the High Court is again Page 21 of 27 founded on incorrect assumption about the date of AoA.   The High Court in paragraph 10.7 proceeds on the basis that AoA was executed as back as on 09.06.2005 and having noted that date,   the   High   Court   then   observed   that   the   project   was inaugurated only in 2016.   On this erroneous assumption, the High Court rejected the claim of the appellant(s) herein.   As a matter of fact, the AoA was executed on 09.06.2015, at which point of time, 97 per cent of the project was completed and the same was rolled out by filling of the Dam from 26.07.2015 in less than one month, by closing diversion tunnel gate.  Not only that, the   project   was   dedicated   to   the   people   of   Afghanistan   soon thereafter on 04.06.2016. Thus understood, it becomes clear that the parties had agreed to give quietus to all the claims and adopt revised   rates   recommended   by   High   Power   Committee,   as recorded in AoA executed on 09.06.2015.  Suffice it to note that the basis for rejecting the argument of the appellant(s) is founded on erroneous assumption that AoA was executed on 09.06.2005. That is an error apparent on the face of the record.   32. The third reason weighed with the High Court is that clause 20.6 of CoPA, providing for resolution of disputes by arbitration has not been modified by AoA. Indeed, clause 4 of the Contract Page 22 of 27 Agreement makes reference to clause 20 of CoPA.  However, on a fair   reading   of   clause   4   of   the   Contract   Agreement   and   in particular 4.1 as reproduced hitherto, it would be crystal clear that the substance of the provision is to provide for process of settlement of disputes and arbitration. Reference to clause 20 of CoPA is only to indicate that the procedure specified therein may have   to   be   followed   whilst   taking   recourse   to   that   process. However,   as   the   substantive   provision   regarding   remedy   of arbitration itself has been done away with in terms of clauses 1.2 and 1.3 of Section­01 of AoA, there was no need to modify clause 20 in CoPA dealing with machinery provision.  Thus, the remedy of arbitration cannot be resurrected merely because clause 20 of CoPA has not been expressly modified in the AoA. Hence, even this reason does not commend us. 33. As these are the only reasons which had weighed with the High Court to reject the argument of the appellant(s) regarding non­existence   of   arbitration   agreement   and   the   same   being untenable in law, it must necessarily follow that the Arbitration Petition filed for and on behalf of SDJV through SSPPL was not maintainable.   In   other   words,   the   Arbitration   Petition   should have been rejected for lack of subsisting or existing arbitration Page 23 of 27 agreement between the parties on the date of filing of Arbitration Petition.  34. It   is   not   unknown   in   commercial   world   that   the   parties amend original contract and even give up their claims under the subsisting agreement.  The case on hand is one such case where the parties consciously and with full understanding executed AoA whereby the contractor gave up all his claims and consented to the new arrangement specified in AoA including that there will be no arbitration for the settlement of any claims by the contractor in future.  Having chosen to adopt that path, it is not open to the contractor   to   now   take   recourse   to   arbitration   process   or   to resurrect   the   claim   which   has   been   resolved   in   terms   of   the amended agreement, after availing of steep revision of rates being condition precedent.   We may usefully rely on the underlying principle   expounded   by   this   Court   in   Damodar   Valley 3 Corporation   vs.   K.   K.   Kar ,   wherein   the   Court   observed   as follows:­ “…..As   the   contract   is   an   outcome   of   the   agreement between   the   parties   it   is   equally   open   to   the   parties thereto to agree, to bring it to an end or to treat it as if it never   existed.   It   may   also   be   open   to   the   parties   to terminate   the   previous   contract   and   substitute   in   its place a new contract or alter the original contract in such 3  (1974) 2 SCR 240 @ 243­244 Page 24 of 27 a way that it cannot subsist. In all these cases, since the entire contract is put an end to, the arbitration clause, which is a part of it, also perishes along with it. Section 62 of the Contract Act incorporates this principle when it provides   that   if   the   parties   to   a   contract   agree   to substitute a new contract or to rescind or alter it, the original   contract   need   not   be   performed.   Where, therefore,   the   dispute   between   the   parties   is   that   the contract itself does not subsist either as a result of its being substituted by a new contract or by rescission or alteration,   that   dispute   cannot   be   referred   to   the arbitration as the arbitration clause itself would perish if the averment is found to be valid. As the very jurisdiction of the arbitrator is dependent upon the existence of the arbitration   clause   under   which   he   is   appointed,   the parties have no right to invoke a clause which perishes with the contract.” In   a   subsequent   decision   in   National   Insurance   Company 4 , in paragraph Limited vs. Boghara Polyfab Private Limited 52 this Court held as follows: “ 52.   Some   illustrations   (not   exhaustive)   as   to   when claims   are   arbitrable   and   when   they   are   not,   when discharge   of   contract   by   accord   and   satisfaction   are disputed, to round up the discussion on this subject are: (i) …. …. …. ( ii )   A   claimant   makes   several   claims.   The   admitted   or undisputed claims are paid. Thereafter negotiations are held for settlement of the disputed claims resulting in an agreement in writing settling all the pending claims and disputes. On such settlement, the amount agreed is paid and the contractor also issues a discharge voucher/no­ claim certificate/full and final receipt. After the contract is discharged by such accord and satisfaction, neither the contract   nor   any   dispute   survives   for   consideration. There   cannot   be   any   reference   of   any   dispute   to arbitration thereafter. ( iii ) …. …. …. ( iv ) …. …. …. ( v ) A claimant makes a claim for a huge sum, by way of damages.   The   respondent   disputes   the   claim.   The 4   (2009) 1 SCC 267 Page 25 of 27 claimant   who   is   keen   to   have   a   settlement   and   avoid litigation, voluntarily reduces the claim and requests for settlement. The respondent agrees and settles the claim and obtains a full and final discharge voucher. Here even if the claimant might have agreed for settlement due to financial   compulsions   and   commercial   pressure   or economic duress, the decision was his free choice. There was no threat, coercion or compulsion by the respondent. Therefore, the accord and satisfaction is binding and valid and there cannot be any subsequent claim or reference to arbitration.” 5 Further, in  , Nathani Steels Ltd. v. Associated Constructions this Court observed as follows:­ “3......Even otherwise we feel that once the parties have arrived   at   a   settlement   in   respect   of   any   dispute   or difference arising under a contract and that dispute or the   difference   is   amicably   settled   by   way   of   a   final settlement   by   and   between   the   parties,   unless   that settlement is set aside in proper proceedings, it cannot lie in the mouth of one of the parties to the settlement to spurn it on the ground that it was a mistake and proceed to invoke the Arbitration clause. If this is permitted the sanctity of contract, the settlement also being a contract, would be wholly lost and it would be open to one party to take   the   benefit   under   the   settlement   and   then   to question   the   same   on   the   ground   of   mistake   without having the settlement set aside. In the circumstances, we think   that   in   the   instant   case   since   the   dispute   or difference was finally settled and payments were made as per the settlement, it was not open to the respondent unilaterally   to   treat   the   settlement   as   non   est   and proceed   to   invoke   the   Arbitration   clause.   We   are, therefore, of the opinion that the High Court was wrong in the view that it took.” 35. Having said this, no other issue need be addressed in these appeals. As a result, these appeals must succeed.   Resultantly, the impugned judgment of the High Court is set aside and the 5  1995 Supp (3) SCC 324 Page 26 of 27 Arbitration Petition No. 810 of 2016 filed by the respondent No. 1 herein stands dismissed.   36. However, we must keep the option available to the parties to take recourse to other remedies,  inter se , which they are free to adopt in accordance with law; and the rejection of Arbitration Petition   will   be   no   impediment   for   them   to   pursue   those remedies.  We, accordingly, keep all other issues and contentions available to the parties open, to be determined in appropriate proceedings as and when occasion arises.  37. The appeals are allowed in the above terms with no order as to costs.  All pending applications are also disposed of.                                                               ….…………..................J.                 (A.M. KHANWILKAR)                           ………..……...................J.      (DINESH MAHESHWARI) New Delhi; November 14, 2019. Page 27 of 27