GARG BUILDERS vs. BHARAT HEAVY ELECTRICALS LIMITED

Case Type: Civil Appeal

Date of Judgment: 04-10-2021

Preview image for GARG BUILDERS vs. BHARAT HEAVY ELECTRICALS LIMITED

Full Judgment Text

REPORTABLE IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION CIVIL APPEAL NO.6216 OF 2021 (Arising out of S.L.P. (C.) No. 16320 of 2018) GARG BUILDERS      …APPELLANT(S)  VERSUS BHARAT HEAVY ELECTRICALS LIMITED       …RESPONDENT(S) J U D G M E N T S. ABDUL NAZEER, J. Leave granted. 2. This appeal is directed against the Order of the Division Bench of   the   High   Court   of   Delhi   dated   19.09.2017   in   FAO(OS) (COMM)No.120/2017 whereby it has upheld the judgment of the learned   Single   Judge   in   OMP   (COMM)   No.28   of   2017   dated Signature Not Verified 10.03.2017,   resulting   in   denial   of   interest   on   the pendente   lite   Digitally signed by Anita Malhotra Date: 2021.10.04 16:45:27 IST Reason: award amount to the appellant. 1 3. The respondent floated a tender for construction of boundary wall at its 2x750 MW Pragati III Combined Cycle Power at Bawana, Delhi   (hereinafter   referred   to   as   ‘the   project’).     The   appellant submitted   its   bid   for   the   project   which   was   accepted   by   the respondent.  Pursuant to which, the respondent issued a Letter of Intent (LOI) to the appellant dated 09.09.2008.   Subsequently, on 24.10.2008 the parties entered into a contract which,   inter alia, contained   the   interest   barring   clause   which   is   reproduced hereunder: “Clause 17: No interest shall be payable by BHEL on Earnest Money Deposit, Security Deposit or on any moneys due to the contractor.” 4. The disputes arose between the parties with respect to the aforesaid contract and subsequently the appellant filed a petition under Section 11 of the Arbitration and Conciliation Act, 1996 (for short, “the   1996  Act”)  before  the  Delhi  High  Court wherein the Court vide Order dated 16.09.2011 appointed Hon’ble Mr. Justice M.A. Khan (Retd.) as the sole Arbitrator to adjudicate the disputes. The appellant in the claim petition, apart from claiming various amounts   under   different   heads,   inter  alia   claimed   pre­reference, 2 pendente lite  and future interest at the rate of 24% on the value of the award.  Learned Arbitrator after hearing the contentions of both the parties concluded that there is no prohibition in the contract dated   24.10.2008   and   LOI   dated   09.09.2010   about   payment   of interest for the pre­suit,  pendente lite  and future period.  Therefore, he awarded  pendente lite  and future interest at the rate of 10% p.a. to the appellant on the award amount from the date of filing of the claim petition i.e. 02.12.2011 till the date of realization of the award amount. 5. The respondent challenged the said award under Section 34 of the   1996   Act   before   the   Delhi   High   Court   in   O.M.P.   (COMM.) 28/2017 on various grounds,   inter alia,   on the ground that the learned   Arbitrator   being   creature   of   the   arbitration   agreement travelled beyond the terms of the contract in awarding  pendente lite interest on the award amount as the same was expressly barred in terms of   the  contract.     The  learned   Single   Judge   vide   his   final judgment and order dated 10.03.2017 held as under: “The   Arbitrator   fell   in   error   in   holding   that   the aforesaid   clause   only   prescribed   pre­reference interest and  not pendente  lite  interest. As  stated earlier, in terms of Section 31(7)(a) of the Act, the 3 power of the arbitral tribunal to award pre award interest is contingent to the parties not agreeing to the contrary. Pre­award interest includes both pre­ reference interest as well as pendente lite interest. Thus, the conclusion of the Arbitrator that award of pendente lite interest was not prescribed by clause 17 of the Agreement is not sustainable. Accordingly, the impugned award to the extent of award of pendente lite interest is set aside.  The petition is disposed of. No orders as to costs.” 6. As noticed above, the Division Bench of the High Court has upheld the judgment and order of the Learned Single Judge in the impugned order.  7. On 03.07.2018, this Court issued notice observing as under: “Learned   counsel   for   the   petitioner   has   placed reliance   on   an   order   of   this   Court   in  Ambica Construction v. Union of India, (2017) 14 SCC 323.” 8. We have heard learned counsel for the parties and perused the materials on record.   Mr. Sanjay Bansal, learned counsel for the appellant,   contended   that   the   learned   Arbitrator   had   taken   a plausible view, in terms of the Clause 17 of the Contract and held that   the   said   clause   does   not   bar   the   payment   of   interest   for pendente   lite   period.     This   argument   was   advanced   in   view   of 4 judgment   of   this   Court   in   Ambica   Construction   v.   Union   of 1 India ,   wherein   the   appellant   was   entitled   for   the   payment   of interest for the  pendente lite  period.  He has also relied on another judgment of this Court in   Raveechee and Company v. Union of 2 India   in support of his contentions.  Further, it was argued by the learned counsel that the Clause 17 of the Contract barring payment of interest to the contractor on any sum due to the contractor, is and against the provisions of Section 28 of the Indian ultra vires   Contract Act, 1872. 9. On the other hand, Mr. Pallav Kumar, learned counsel for the respondent, submitted that Section 31(7)(a) of the 1996 Act gives paramount importance to the contract entered into between the parties   and   categorically   restricts   the   power   of   an   arbitrator   to award  pre­reference   and   pendente  lite   interest  when  the   parties themselves  have agreed  to the contrary.   He  argued that if the contract itself contains a specific clause which expressly bars the payment of interest, then it is not open for the arbitrator to grant pendente   lite   interest.     It   was   further   argued   that   Ambica 1 (2017) 14 SCC 323 2 (2018) 7 SCC 664 5 Construction  (supra) is not applicable to the instant case because it was decided under the Arbitration Act, 1940 whereas the instant case falls under the 1996 Act.  It was further argued that Section 3 of the Interest Act confers power on the Court to allow interest in the   proceedings   for   recovery   of   any   debt   or   damages   or   in proceedings in which a claim for interest in respect of any debt or damages already paid.   However, Section 3(3) of the Interest Act carves out an exception and recognizes the right of the parties to contract out of the payment of interest arising out of any debt or damages   and   sanctifies   contracts   which   bars   the   payment   of interest arising out of debt or damages.  Therefore, Clause 17 of the Contract is not violative of any the provisions of the Indian Contract Act, 1872.  In light of the arguments advanced, the learned counsel prays for dismissal of the appeal. 10. We have carefully considered the submissions of the learned counsel for both the parties made at the Bar.  The law relating to award of  pendente lite  interest by Arbitrator under the 1996 Act is no   longer   res   integra .     The   provisions   of   the   1996   Act   give paramount importance to the contract entered into between the 6 parties   and   categorically   restricts   the   power   of   an   arbitrator   to award  pre­reference   and   pendente  lite   interest  when  the   parties themselves have agreed to the contrary.   Section 31(7)(a) of the 1996 Act which deals with the payment of interest is as under :  “31(7)(a)   Unless otherwise agreed by the parties, where and insofar as an arbitral award is for the payment of money, the arbitral tribunal may include in the sum for which the award is made interest, at such rate as it deems reasonable, on the whole or any part of the money, for the whole or any part of the period between the date on which the cause of action arose and the date on which the award is made.” 11. It   is   clear   from   the   above   provision   that   if   the   contract prohibits   pre­reference   and   pendente   lite   interest,   the   arbitrator cannot award interest for the said period.   In the present case, clause barring interest is very clear and categorical.   It uses the expression “any moneys due to the contractor” by the employer which includes the amount awarded by the arbitrator.   12. In  Sayeed Ahmed and Company v. State of Uttar Pradesh & 3    this Court has held that a provision has been made under Ors. Section 31(7)(a) of the 1996 Act in relation to the power of the 3 (2009) 12 SCC 26 7 arbitrator to award interest.  As per this section, if the contract bars payment of interest, the arbitrator cannot award interest from the date of cause of action till the date of award.  13. In   Sree   Kamatchi   Amman   Constructions   v.   Divisional 4 Railway Manager (Works), Palghat & Ors.   it was held by this Court that where the parties had agreed that the interest shall not be payable, the Arbitral Tribunal cannot award interest between the date on which the cause of action arose to the date of the award. 5 14. Bharat Heavy Electricals Limited v. Globe Hi­Fabs Limited is an identical case where this Court has held as under : “16.  In the present case we noticed that the clause barring interest is very widely worded.  It uses the words “any amount due to the contractor by the employer”.   In our opinion, these words cannot be read as ejusdem generis along with the earlier words “earnest money” or “security deposit”.”   6 15. In   it   was Sri   Chittaranjan   Maity   v.   Union   of   India   categorically held that if a contract prohibits award of interest for pre­award period, the arbitrator cannot award interest for the said period.   4 (2010) 8 SCC 767 5 (2015) 5 SCC 718 6 (2017) 9 SCC 611 8 16. Therefore,   if   the   contract   contains   a   specific   clause   which expressly   bars   payment   of   interest,   then   it   is   not   open   for   the arbitrator to grant  pendente lite  interest.  The judgment on which reliance was placed by the learned counsel for the appellant in Ambica Construction   (supra) has  no application to the  instant case   because   Ambica   Construction   was   decided   under   the Arbitration Act 1940 whereas the instant case falls under the 1996 Act.  This has been clarified in  Sri Chittaranjan Maity  (supra) as under : “  Relying on a decision of this Court in  16. Ambica Construction   v.   Union of India,   (2017) 14 SCC 323, the   learned   Senior   Counsel   for   the   appellant submits   that   mere   bar   to   award   interest   on   the amounts payable under the contract would not be sufficient to deny payment on pendente lite interest. Therefore, the arbitrator was justified in awarding the pendente lite interest. However, it is not clear from   Ambica Construction   (supra) as to whether it was   decided   under   the   Arbitration  Act,   1940  (for short “the 1940 Act”) or under the 1996 Act. It has relied on a judgment of Constitution Bench in  State of   Orissa   v.   G.C.   Roy,   (1992)   1   SCC   508.   This judgment was with reference to the 1940 Act. In the 1940 Act, there was no provision which prohibited the arbitrator from awarding interest for the pre­ reference,   pendente   lite   or   post­award   period, whereas the 1996 Act contains a specific provision which says that if the agreement prohibits award of interest   for   the   pre­award   period,   the   arbitrator 9 cannot award interest for the said period. Therefore, the decision in   Ambica Construction (supra)   cannot .” be made applicable to the instant case 17. The decision in   (supra) relied on by Raveechee and Company the learned counsel for the appellant is again under the Arbitration Act 1940 which has no application to the facts of the present case. 18. Having regard to the above, we are of the view that the High Court was justified in rejecting the claim of the appellant seeking pendente lite  interest on the award amount. 19. This takes us to the next question as to whether Clause 17 of the Contract is   ultra vires   in terms of Section 28 of the Indian Contract Act, 1872.  According to Section 28, a contract is void to the extent it restricts absolutely a party from enforcing his rights by usual proceedings in ordinary courts or if it limits the time within which   he   may   enforce   his   rights.   Exception   I   to   this   section contains a rule that a contract by which two or more persons agree that any dispute which has arisen or which may arise between them in respect of any subject or class of subjects shall be referred to arbitration is not illegal. The question, therefore, is whether the 10 contracts barring payment of interest extinguish the rights of the parties.  Exception 1 to Section 28 reads as under : “ Exception   1:   Saving   of   contract   to   refer   to arbitration dispute that may arise. –  This section shall not render illegal a contract, by which two or more   persons   agree   that   any   dispute   which   may arise   between   them   in   respect   of   any   subject   or class of subjects shall be referred to arbitration, and that   only   the   amount   awarded   in   such arbitration shall be recoverable in respect of the dispute so referred .”  20. Exception I to Section 28 saves contracts where the right to move the Court for appropriate relief is restricted but where the parties have agreed to resolve their dispute through arbitration. Thus, a lawful agreement to refer the matter to arbitration can be made a condition precedent before going to courts and it does not violate   Section   28.     No   cause   of   action   then   accrues   until   the Arbitrator has made the award and the only amount awarded in such arbitration is recoverable in respect of the dispute so referred. Section 31(7)(a) of the 1996 Act which allows parties to waive any claim   to   interest   including   pendente   lite   and   the   power   of   the 11 Arbitrator   to   grant   interest   is   subject   to   the   agreement   of   the parties. 21. It is pertinent to note that interest payments are governed in general by the Interest Act, 1978 in addition to the specific statutes that govern an impugned matter.  Section 2 (a) of the Interest Act defines a “Court” which includes both a Tribunal and an Arbitrator. In turn, Section 3 allows a “Court” to grant interest at prevailing interest rates in various cases. The provisions of Section 3 (3) of the Interest Act, 1978 explicitly allows the parties to waive their claim to an interest by virtue of an agreement.   Section 3(3)(a)(ii) states that the Interest Act will not apply to situations where the payment of interest is “barred by virtue of an express agreement”. 22. Thus, when there is an express statutory permission for the parties to contract out of receiving interest and they have done so without any vitiation of free consent, it is not open for the Arbitrator to grant  pendent lite  interest. We are of the considered opinion that Clause 17 of the contract is not  ultra vires  in terms of Section 28 of the Indian Contract Act, 1872. 12 23. In the result, the appeal fails and is accordingly dismissed. Having regard to the facts and circumstances of the case, we direct the parties to bear their own costs. 24. Pending application, if any, shall also stand disposed of.         …………………………………J.     (S. ABDUL NAZEER)                                    …………………………………J.     (KRISHNA MURARI) New Delhi; October 4, 2021. 13