ANUJ JOSHI & ANR vs. CHIEF CONSERVATOR OF FORESTS

Case Type: Contempt Petition Civil

Date of Judgment: 15-01-2016

Preview image for ANUJ JOSHI & ANR vs. CHIEF CONSERVATOR OF FORESTS

Full Judgment Text

1 Non-Reportable
E SUPREME COUR
CONTEMPT PETITION NO 245 OF 2014 IN CIVIL APPEAL NO.6736 OF 2013 Anuj Joshi & Anr. ……Petitioners Versus Chief Conservator of Forests & Others …. Respondents O R D E R JUDGMENT Uday Umesh Lalit J. 1. This contempt petition under Sections 2(3) and 15 of the Contempt of Court Act, 1971 read with Article 129 of the Constitution of India alleges violation of directions contained in judgment and order dated 13.08.2013 passed by this Court 1 in Alaknanda Hydro Power Company Limited vs. Anuj Joshi and others (C.A. 1 (2014)1 SCC 769 Page 1 2 No.6736/2013 with Civil Appeal No.6746-6747/2013 and Transferred Case No.55 to 57 of 2013). Four persons are arrayed as alleged contemnors in this petition.
Nos.3 and4. We are
out against them and as such the proceedings against them are dropped. We therefore, confine ourselves in respect of alleged act of contempt on part of alleged contemnor Nos.1 and 2. 2. In the judgment and order dated 13.08.2013 this Court had passed certain directions in paragraph 51. We may quote said paragraph 51 : “51. We are also deeply concerned with the recent tragedy, which has affected the Char Dham Area of Uttarakhand. Wadia Institute of Himalayan Geology (WIG) recorded 350mm of rain on June 15-16, 2013. Snowfall ahead of the cloudburst also has contributed to the floods resulting in the burst on the banks of Chorabari lake near Kedarnath, leading to large scale calamity leading to loss of human lives and property. The adverse effect of the existing projects, projects under construction and proposed, on the environment and ecology calls for a detailed scientific study. Proper Disaster Management Plan, it is seen, is also not in place, resulting in loss of lives and property. In view of the above mentioned circumstances, we are inclined to give following directions: JUDGMENT (1) We direct the MoEF as well as State of Uttarakhand not to grant any further environmental clearance or forest clearance for any hydroelectric power project in the State of Uttarakhand, until further orders. Page 2 3
dation, if s<br>e present tro, to what<br>agedy occ
(3) MoEF is directed to examine, as noticed by WII in its report, as to whether the proposed 24 projects are causing significant impact on the biodiversity of Alaknanda and Bhagirath River basins. (4) The Disaster Management Authority, Uttrarakhand would submit a Report to this Court as to whether they had any Disaster Management Plan is in place in the State of Uttarakhand and how effective that plan was for combating the present unprecedented tragedy at Uttarakhand.” 3. It is alleged in the present petition as under: “That it has come to petitioners’ knowledge that forest land for Vishnugad-Pipalkoti Project has been transferred to Tehri Hydro Development Corporation (THDC). The current status of the project as displayed on website of THDC states that “G.O. by GoUK for transfer of 80.507 ha of forest land has been issued vide letter th dated 6 December, 2013.” According to news report dated 23.12.2013 work contract for the construction of Vishnugad- Pipalkoti projects has been awarded recently. These activities can be undertaken only after Government of Uttarakahand issues Forest Clearance. The petitioner has sent Right to Information request for copies of Forest Clearance regarding Vishnugad-Pipalkoti and Kotlibhel 1A to Respondents Nos 1,2 and 3 on 26.2.2013 which remain unreplied on the date of filing this petition. Though Stage 1 and Stage 2 Forest clearances were issued to the Vishnugad- Pipalkoti project before 13.08.2013, however, State Government appears to have issued Forest Clearance after 13.08.2013 which is in contempt of the judgment of this Hon’ble Court.” JUDGMENT Page 3 4 4. Insofar as the aforesaid alleged violations are concerned, the following persons are arrayed as alleged contemnor Nos. 1 and 2:
2. R.S.T.Sai, Managing Director, Tehri Hydro Development Corporation, Pragatipuram, Rishikesh, Uttarakhand. 5. The respondent no.1 in his affidavit in reply submitted that the concerned Vishnugad-Pipalkoti Project was cleared as far back as on 02.06.2006, that the documents annexed to the contempt petition themselves show that Stage 1 clearance in respect of 80.507 Hectare of forest land (‘forest land’ for short) was accorded by MoEF on 03.06.2011 subject to fulfillment of certain conditions and that upon compliance of the conditions, final approval for transfer of forest JUDGMENT land was accorded by MoEF on 25.04.2013. It was further stated that vide letter dated 06.12.2013, the approval of diversion of forest land was communicated by Additional Secretary, Uttarakhand to Additional Chief Conservator of Forests, Uttarakhand and that actual approval was accorded much before the pronouncement of the judgment and order dated 13.08.2013. It was submitted as under: Page 4 5
totally m<br>o prejudiceisleading<br>this Hon’
6. We have perused the record and heard Shri Bharat Jhunjhunwala, Applicant No. 2 in support of the petition and Mr. Mohan Parasaran and Ms. Rachana Srivastava, learned counsel for the respondents. The letter dated 06.12.2013 from Additional Secretary, Uttarakhand has simply communicated the conditions stipulated in the approval dated 28.05.2013. The approval was well before the judgment and order dated 13.08.2013. Plainly, the letter dated 06.12.2013 has not JUDGMENT taken any decision after 13.08.2013 but has merely communicated the decision taken well before 13.08.2013. There is thus no violation of any of the directions contained in para 51 of the judgment and order dated 13.08.2013. Further, the alleged contemnor no.1 has simply received the communication dated 06.12.2013, while copy of that communication was marked to General Manager, Tehri Hydro Development Corporation Ltd. In our view, the alleged contemnors Nos.1 and 2 could not be said to have committed any violation of the directions contained in Page 5 6 judgment and order dated 13.08.2013. 7. We, therefore, dismiss this contempt petition. ………………………….J (Dipak Misra) …..………………………J (Uday Umesh Lalit) New Delhi January 15, 2016 JUDGMENT Page 6 7 1A-For Order COURT NO.09 SECTION X S U P R E M E C O U R T O F I N D I A RECORD OF PROCEEDINGS
4 In C.A.No. 673
VERSUS CHIEF CONSERVATOR OF FORESTS & ORS Respondent(s) Date : 15/01/2016 This petition was called on for pronouncement of ORDER today. For Petitioner(s) Mrs. Santosh Singh,Adv. For Respondent(s) Mr. Amit Anand Tiwari, Adv. Mr. Abhinav Raghuvanshi, Adv. Mr. Abhinandan Banerjee, Adv. Hon'ble Mr. Justice Uday Umesh Lalit pronounced the order of the Bench comprising Hon'ble Mr. Justice Dipak Misra and His Lordship. JUDGMENT Contempt petition is dismissed in terms of the signed non-reportable order. (VINOD KUMAR) (MALA KUMARI SHARMA) COURT MASTER COURT MASTER (Signed Non-Reportable order is placed on the file) Page 7