Full Judgment Text
1
[REPORTABLE]
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NO.7586 OF 2009
M/s. Larsen & Toubro Ltd. ….Appellant(s)
Vs.
M/s.Mohan Lal Harbans Lal Bhayana ….Respondent(s)
J U D G M E N T
A.K.SIKRI,J.
1. On an application preferred by the respondent herein
under Section 11(6) of the Arbitration and Conciliation Act,
1996 (hereinafter referred to as the Act), the High Court has
appointed/nominated an Arbitrator on behalf of the appellant
herein on the ground that in spite of notice by the respondent
JUDGMENT
in this behalf, the appellant had failed to nominate its
Arbitrator in terms of Clause 25 of the Agreement entered into
between the parties. Since the respondent had already
nominated its Arbitrator, further direction is given that the two
Arbitrators (one nominated by respondent and one appointed
by the Court for the appellant), shall appoint an Umpire in
Page 1
2
consonance with the said Clause 25. This order is impugned
by the appellant primarily on the ground that Clause 25 was
modified by three supplementary agreements whereby the
| said arbi | tration c |
|---|
on a conjoint reading of original Clause 25 with modification
effected by the supplementary agreements, there was no
question of arbitration between the appellant and the
respondent at this stage. To appreciate this contention, one
will have to traverse through the relevant clauses of the main
contract as well as supplementary agreements. Thus, we
would like to state along with the events, as they occurred, in
chorology. In fact, as we proceed to unfurl the events with our
comments thereon, there and then we shall be getting answer
JUDGMENT
as well to the issue involved.
2. An agreement dated 29.2.1988 was entered into between
the Standing Conference of Public Enterprises (SCOPE) and
the appellant namely Larsen & Toubro (L&T Ltd.). This
agreement was for construction of Twin Tower Office Complex
at Laxmi Nagar District Centre, Delhi which was awarded by
Page 2
3
the SCOPE to the appellant. Original contract value for this
work was stipulated at Rs.27.48 Crores. Works comprised of
the Civil Works and also subsidiary works, that could be
| e to ti | me by |
|---|
agreement also permitted the appellant to sub-contract.
Accordingly, the appellant entered into an agreement dated
3.3.1988 with the respondent. While retaining the civil works
with itself, the appellant awarded finishing works including
brickworks, wood works, flooring, furnishing, aluminum works
and other miscellaneous works including waterproofing etc. to
the respondent. It was a pass through contract on a back to
back basis. The value of sub contract was stated as Rs.12.08
crores. Clause 2 of this agreement dated 3.3.1988 pertains to
JUDGMENT
the payments which were to be made by the appellant to the
respondent. As can be seen from the reading of this Clause, as
reproduced below, amount under this sub contract was
payable to the respondent by the appellant only on receipt of
corresponding receipts from SCOPE:
“Clause 2 – L&T shall pay “MHB” the said contract
amount or such other sum as shall become payable
Page 3
4
only as and when the said payments are received by
“L&T” from SCOPE at the time and in the manner
hereinafter specified in the terms and conditions of
this Contract.”
| tant stip | ulation i |
|---|
Clause 6, as per which the respondent was to perform the
work awarded to it to the satisfaction of SCOPE, namely the
Principal. It reads as under:
“Clause 6 – All obligations in respect of ancillary
works undertaken by MHB shall be performed by
MHB itself and will not jeopardize the interest and
contract of L&T with SCOPE. Satisfaction of SCOPE,
their representatives and Architects shall form the
basis of this agreement.”
4. Clause 25 of the agreement between the appellant and
the respondent provides for arbitration for settlement of
JUDGMENT
disputes. Relevant part of this Clause reads as under:
“Clause 25 – Except where otherwise provided in the
contract, all questions, disputes, certificates
excluding “excepted matters” relating to this
contract shall be referred to a Sole Arbitrator in
case claims are upto and including Rs.10 lakhs to
be appointed by the General Manager (Civil), L&T
and for claiming over Rs.10 lakhs by panel of 3
Arbitrators of who one will be appointed by General
Manager (Civil), L&T the other by BHR and an
Page 4
5
umpire appointed in advance jointly by the two
Arbitrators….”
| nd only<br>SCOPE | upon<br>under th |
|---|
5. The position which prevailed up to this stage was that for
the works undertaken by the respondent, it could receive the
payments only when such payments were made by SCOPE to
the appellant. Further, all questions and disputes between the
appellant and the respondent were to be referred to a sole
arbitrator where the claim was up to Rs.10 lakhs and three
arbitrators for claims beyond 10 lakhs. The arbitrator(s) was
not supposed to deal with “excepted matters”, so stated in the
JUDGMENT
certificates. However, even if the award of the
arbitrator/umpire was in favour of the respondent, respondent
could not receive payment under the said award unless such a
payment was received by the appellant from SCOPE under the
award. In that event, the respondent was to provide an
opportunity to the appellant to raise those claims with SCOPE.
Page 5
6
On receiving the payments from SCOPE either under the
arbitration award between SCOPE and the appellant or
otherwise, the appellant was supposed to honour the award
| f the res | pondent. |
|---|
understood that as the Principal/Employer was SCOPE, for
whom the work was to be performed by virtue of main
agreement dated 29.2.1988 entered into between parties and
the sub contract between the appellant and respondent was
on back to back basis, any work done by the respondent was
for the benefit of SCOPE and ultimately liability for honoring
the claims of the respondents was that of SCOPE and the
appellant was not supposed to make any payment from its
coffers.
JUDGMENT
6. The parties even acted on the basis of aforesaid
understanding initially. There were certain claims of the
respondent and the appellant in turn raised those claims with
SCOPE. A settlement was reached between the appellant and
SCOPE with respect to those claims whereby the appellant
was given a sum of Rs.2.15 crores by SCOPE. The appellant
Page 6
7
and the respondent entered into an agreement dated
31.1.1990 for apportioning the aforesaid amount, whereby a
sum of RS.77.40 lacs was paid to the respondent towards full
| of claim | s/ price |
|---|
to hindrance caused in execution of work and to complete the
balance work. At the same time, another important
understanding was also reached between the parties. While
making this apportionment, the modalities of settling the
disputes between the parties through arbitrator also
underwent a significant change. This is clear from Clause (viii)
of the first supplementary agreement which reads as under:
“The Agreement provides that all disputes
between the parties shall be settled through
arbitration. It is now expressly agreed that any
dispute or difference which MHB might have with
L&T under the agreement or SCOPE might have
with L&T under the main contract between then
relating to the part of work that is to be executed
by MHB, shall be deemed disputes jointly between
MHB and L&T and SCOPE under the main contract
and L&T will refer all such disputes to SCOPE for
settlement by negotiation. If SCOPE does not settle
the same by negotiation, then L&T will refer the
said disputes for arbitration with SCOPE a/on with
any other disputes which L&T might have with
SCOPE in terms of the arbitration clause provided
in the main contract. MHB shall in such an event,
JUDGMENT
Page 7
8
| . The aw<br>in disput<br>e MHB’ | ard of t<br>e claims<br>s scope |
|---|
7. This clause acknowledges the fact that for the work done
by the respondent under the sub contract, there could be two
kinds of situations. There could be a situation where there
would be disputes and differences between the appellant and
the respondent for the works done by the respondent. This
could be regarding the workmanship or the amounts payable
JUDGMENT
for the work done etc. There could also be a situation where
SCOPE is not satisfied with the workmanship or may raise
dispute about the quantum of bills etc. resulting into denial of
payment or short payment to the appellant for the work
undertaken by the respondent under the sub contract. The
Clause (viii) in the first supplementary agreement provided
Page 8
9
that such disputes will be deemed to have been raised jointly
between the respondent and appellant on the one side and
SCOPE on the other side. For this reason, this Clause further
| lant was | to refer |
|---|
for settlement by negotiation failing which arbitration (as per
mechanism provided in the Clause between the appellant and
SCOPE). In order to lodge these claims suitably and properly,
the respondent was supposed to assist and cooperate the
appellant. Such an assistance was expected in successfully
pursuing arbitration as well. Reason for such a collaborative
effort, with synergy between the two parties synergize, was too
obvious. Since the respondent has undertaken the work, its
inputs could immensely help the appellant in prosecuting the
JUDGMENT
claims efficaciously and potently. Further, by participating the
respondent would have satisfaction that its interest is
appropriately taken care of. It was even supposed to bear
proportionate cost of arbitration. It was, thus, clear intention
that the claims of the respondent were to be taken up by the
appellant and raise with SCOPE and in the event SCOPE
disputing those claims, get those claims adjudicated through
Page 9
10
arbitration. In that sense, both the appellant and respondent
were on one side as co-claimants. However, since the
respondent is not a party to the main agreement dated
| entered | into be |
|---|
SCOPE, the respondent was supposed to give the assistance
and cooperate in the manner provided in this Clause. It is for
this reason that this Clause unambiguously further provided
that in view of the arbitration between the appellant and
SCOPE, pertaining to the claims of the respondent as well,
even if the disputes between the appellant and the respondent
were deemed to have been settled and were not referable to
arbitration again between these two parties.
8. On reading Clause 25 in the original agreement
JUDGMENT
pertaining to the process of arbitration along with the modified
mechanism agreed to between the parties in the aforesaid first
supplementary agreement, the parties for making the change
is clearly discernable. As per the original clause, the disputes
between the appellant and the respondent were to be referred
to the arbitral tribunal. After the rendition of award by the
Page 10
11
arbitral tribunal, money was still not payable under the award
to the respondent. Instead, in order to recover those moneys
from SCOPE, it was for the appellant to file a similar claim on
| iving the | paymen |
|---|
award, the appellant was to give the money to the respondent
as per the award between the appellant and the respondent. It
amounted to indulging in double exercise, viz. (1) an
arbitration between the parties herein and thereafter another
arbitration relating to subject matter between the appellant
and SCOPE. (2) In order to rationalize and eliminate the dual
exercise, the parties agreed that instead of resorting to
arbitration between themselves, both would join together and
prefer those claims with SCOPE. This modified process of
JUDGMENT
arbitration, as envisaged in the first supplementary
agreement, was much more rationale which appealed to
reason.
9. The next event which took place cemented the aforesaid
mechanism between the parties. It appears that there were
further claims of the respondent which were raised by the
Page 11
12
appellant with SCOPE. SCOPE agreed to make payments and
to apportion those payments between the appellant and the
respondent, these two parties entered into another
| ement da | ted 8.12 |
|---|
agreement is of paramount importance for our purposes. It
records:
“L&T has, therefore, invoked the arbitration clause
under L&T’s contract with SCOPE and referred all
the claims including those relating to MHB on
29.5.1992 to arbitration, which is now pending.”
10. The parties acted as per modified understanding. It was
further agreed whatever claims are received by the appellant
from the SCOPE, they shall be shared between the appellant
and respondent in the ratio of 67:33. The understanding
JUDGMENT
between the parties that for any claims of the respondent,
both the parties were to join together and raise claims against
SCOPE was reinforced by Clause 6 in the said agreement
which again provided an underlined message that in so far as
the appellant and the respondent are concerned, they shall
not resort to any arbitration between themselves on this
Page 12
13
account. For better appreciation, we reproduce Clause 6
herein below, of the second supplementary agreement, dated
8.12.1993:
| T and M | HB shall |
|---|
11. In the aforesaid arbitration, two Member Arbitral
Tribunal awarded a sum of Rs.15.02 crores approximately
(which was subsequently reduced to Rs.13.23 crores by
mutual negotiation) and as per the second supplementary
agreement, that amount was shared between the appellant
and the respondent whereby appellant paid a sum of Rs.4.58
JUDGMENT
crores to the respondent. So much so, when the amount of
Rs.15.02 crores, as awarded by the Arbitral Tribunal against
SCOPE and in favour of the appellant was reduced to 13.23
crores, this arrangement was endoresed by the respondent as
well by entering into third supplementary agreement dated
6.2.1995. The significance of this agreement, for the purpose
Page 13
14
of present case, is Clauses 5 and 16 thereof. Therefore, we
reproduce hereinunder both these Clauses:
| ard, sha<br>egotiatio | ll as far<br>n. It is |
|---|
Clause 16 – The parties further agrees amend and
modify clause 25 of the General Conditions of
Contract dated 3.3.1988 which deals with
settlement of Disputes by Arbitration to the limited
extent that in the event of any fresh reference of
disputes to arbitration, the Arbitrator or arbitrators
as the case may be shall be bound to give speaking
award. This Clause 25 is subject to the terms of the
first supplementary agreement dated 31.01.1990
which modified the agreement dated 03.03.1988.”
JUDGMENT
12. Following aspects emerge from the reading of these two
Clauses:
Page 14
15
(a) The parties herein agreed to settle the
claims between themselves through negotiations, in
the first instance.
| if there | were di |
|---|
appellant and the respondent they were only to be
identified but could not be referred to arbitration
with SCOPE until completion of the project.
(c) Even on the completion of the project, the
mechanism of raising the disputes had to remain
the same as was agreed to earlier in the first
supplementary agreement dated 31.1.1990 viz.
appellant had to raise the claims with SCOPE in
cooperation with the respondent and there was not
JUDGMENT
to be any inter-se arbitration between these parties.
(d) Clause 25 as contained in the original
agreement dated 3.3.1988 between the appellant
and the respondent pertaining to the arbitration
was specifically made subject to the logistic
provided in the first supplementary agreement
Page 15
16
dated 31.1.1990 making it abundantly clear that
Clause 25 stood modified by the supplementary
agreement.
| claims, o | ut of the |
|---|
and the appellant submitted those claims to SCOPE in
October, 2000 which were up to date in November 2000. These
were made jointly by these parties on SCOPE in August 2001.
They were up dated again in December 2002 and January
2003 in concert with each other.
14. Now the stage came which led to present proceedings.
While the things stood at the aforesaid level, the respondent
decided to close the contract sometime in the year 2002. We
are not required to go into the nitty gritty of this event viz. as
JUDGMENT
to whether the respondent abandoned the site or it had
completed the project. Suffice it is to note that the respondent
raised many claims with the appellant and also served legal
notice dated 31.1.2004 in this behalf. It nominated its
arbitrator and called upon the respondent to appoint its
arbitrator for settling the disputes between them. The
Page 16
17
appellant replied by denying the contents of the legal notice.
This denial of the appellant prompted the respondent to file
the application under Section 11 of the Act seeking a direction
| appoint | its arbi |
|---|
made in this application was as under:
“(a) Appoint an Arbitrator on behalf of the
Respondent in terms of Clause 25 of the
rd
Contract Agreement dated 3 of March 1988
between the parties as modified by
st
Supplementary Agreement dated 31 January
th
1990 and 6 February 1995.
(b) Direct the Arbitrators appointed by the
applicant and that appoint on behalf of the
respondent to appoint an umpire in terms of
rd
Clause 25 of the Contract Agreement dated 3
March, 1988.”
15. It is in this application, as mentioned above, impugned
orders are passed by the High Court holding that Clause 25
JUDGMENT
still survived and the arbitral tribunal can be constituted for
adjudication of the disputes between the appellant and the
respondent. The High Court has further held that though the
respondent had nominated its arbitrator, since the appellant
had failed to do so in spite of notice, the appellant lost its right
to nominate its own arbitrator. For this reason, it is the High
Page 17
18
Court which has appointed/nominated an arbitrator for the
appellant with direction that two arbitrators may appoint
presiding arbitrator.
| ng the | aforesaid |
|---|
commented on the effects of the three supplementary
agreements and impact thereof on Clause 25. It is too obvious,
from the reading of the relevant clause in the supplementary
agreements, that there could not have been any arbitration
between the appellant and respondent, at this stage. Clause
25 of the original agreement has undergone material change.
The modalities of raising arbitration are completely novated.
As per the modified understanding between the parties, which
is so eloquently recorded in writing, in the first instance, the
JUDGMENT
claims of the respondent are to be taken up by the appellant
with SCOPE. For pressing those claims and in order to ensure
their proper adjudication, the respondent is supposed to assist
and cooperate with the appellant in pursuing the arbitration.
In that sense, at this stage, the appellant and respondent are
on one side who have to put up a joint fight with SCOPE. It is
Page 18
19
only after the award is rendered in the arbitration between the
appellant and SCOPE and something remains, which may
qualify as a dispute between the appellant and the
| ere can | be an |
|---|
those disputes between these two parties. We are, therefore, of
the opinion that the High Court is not correct in holding that
Clause 25 of the original agreement in unamended form holds
the field. In fact, even the respondent knew fully well that said
clause had been drastically altered by supplementary
agreements. It is for this reason that in the prayer (a) of the
application under Section 11 of the Act filed by the
respondent, it has itself acknowledged this change by
mentioning that arbitrator be appointed in terms of Clause 25
JUDGMENT
rd
of the contract agreement dated 3 March 1988 “as modified
by supplementary agreements dated 31st January 1990 and
th
6 February 1995”. What, however, is lost sight of by the
respondent in the process, is that the modification in Clause
25 did not permit the respondent to move this kind of
application for appointment of arbitrator between the parties,
at that stage.
Page 19
20
17. Fully realizing the sequittor of the modified clause, Ms.
Priya Kumar, learned Advocate appearing for the respondent
tried to paint a different story alleging non-cooperation of the
| vociferou | s in her |
|---|
blameworthy conduct of the appellant in not raising the claims
preferred by the respondent, with SCOPE and submitted that
such a conduct of the appellant was reprehensible which
could not make the respondent wait for indefinite period. She
highlighted the fact that though the works were completed in
the year 2002, when even the constructed complex was
inaugurated and the respondent had preferred the claims with
the appellant with request to take up those claims with
SCOPE way back in October, 2002. But nothing has moved
JUDGMENT
forward. She further submitted that till date even the arbitral
tribunal has not been constituted and the respondent can not
be made to suffer by waiting endlessly.
18. This argument may be convincing in so far as equities
are concerned. However, merely thereby the legal position
which is contractually defined between the parties by way of
Page 20
21
written agreements does not alter. It would be necessary to
record here that when the High Court had passed the
impugned orders, the claim had not been made with SCOPE.
| the reaso | ns for th |
|---|
impugned order. However, the said position has undergone
substantial change thereafter. Even after the filing of the
Special Leave Petition against the impugned order and grant of
leave in the matter, in November 2009, there have been joint
meetings of the appellant and the respondent with the officials
of SCOPE. Few such meetings took place in April 2012.
Pursuant to those meetings, SCOPE had called upon the
appellant to complete the residual work rectification so that
SCOPE was in a position to settle the final bills, Thereafter in
JUDGMENT
June 2012, after detailed discussion on various issues
concerning the project, SCOPE asked the appellant to submit
th
revised final bill. Accordingly, bill dated 16 June, 2012 was
prepared by the appellant in consultation with the
representatives of the respondent and submitted to SCOPE.
Page 21
22
19. After the submission of the revised final bill, SCOPE has
been in the process of scrutinizing the same including the
claims. In this regard, several round of meetings held with
| ese meeti | ngs with |
|---|
after the submission of the revised final bill were attended by
the representative of the respondent along with the appellant.
In December 2013, again SCOPE called upon the appellant to
hold a meeting to discuss on the pending issues.
Meanwhile the appellant L&T has been continuing to
extend the Bank Guarantee which was submitted to SCOPE.
20. In such a scenario, when the final bill is almost at the
stage of finalization the only aspect that can be taken care of
at this stage is to hasten the process of arbitration, in case
JUDGMENT
after the passing of the final bill by SCOPE, some claims of the
respondent still survive.
21. Accordingly while allowing this appeal and setting aside
the order of the High Court, we would like to give the following
directions, in order to balance the equities:
(1) It shall be ensured by the appellant that
final bill is settled by SCOPE within two months
Page 22
23
from the date of receiving the copy of this order. For
this purpose, this order shall be brought to the
notice of SCOPE as well so that SCOPE acts swiftly
for settling the bill.
| ich are<br>and disp | not agree<br>utes re |
|---|
(3) In case the appellant is satisfied with the
final bill and chooses not to raise the claims with
SCOPE but the respondent feels that their claims
are legitimate then it would be treated as dispute
between the appellant and the respondent. In that
event, arbitral tribunal shall be constituted as per
Clause 25 of the agreement dated 3.3.1998 between
the parties within a period of two months of that
event.
JUDGMENT
(4) In either of the aforesaid arbitrations, the
arbitral tribunal shall endeavour to render its award
within six months from the date of the constitution
of the arbitral tribunal.
Page 23
24
22. The appeal is allowed and disposed of in the aforesaid
terms.
…………………………………….J.
(Surinder Singh Nijjar)
……………………………………..J.
(A.K.Sikri)
New Delhi,
Dt. February 25, 2014
JUDGMENT
Page 24