Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 5
PETITIONER:
BIHAR STATE ELECTRICITY BOARD
Vs.
RESPONDENT:
HOTEL SATKAR PVT. LTD. & ORS.
DATE OF JUDGMENT: 24/09/1996
BENCH:
G.B. PATTANAIK (J)
BENCH:
G.B. PATTANAIK (J)
RAMASWAMY, K.
ACT:
HEADNOTE:
JUDGMENT:
THE 24TH DAY OF SEPTEMBER, 1996
Present :
Hon’ble Mr.Justice K. Ramaswamy
Hon’ble Mr.Justice G.B.Pattanaik
Pramod Swarup and Praveen Swarup, Advs. for the appellant
S.B.Sanyal, Sr.Adv. Adn P.P. Singh, Adv. with him for the
respondents.
J U D G M E N T
The following Judgment of the Court was delivered:
Bihar State Electricity Board
V.
Hotel Satkar Pvt. Ltd. & Ors.
J U D G M E N T
PATTANAIK, J.
This appeal is directed against the judgment of the
Division Bench of the Patna High Court dated 7th September,
1979 in Civil Writ Jurisdiction Case No. 1710 of 1978.
The respondent filed the writ petition challenging the
legality of the notice served by the appellant issued in
exercise of power under Section 24(1) of the Indian
Electricity Act, 1910 (hereinafter referred to as ’the
Act.’) inter alia on the ground that a bona fide dispute
exists between the licensee and the consumer of electric
energy and as such the provisions of Section 24 (1) of the
Act will not apply. The case of the respondent consumer is
that the appellant has been supplying energy to the
respondent hotel but the said respondent has not entered
into any agreement. and therefore the appellant is entitled
to be charged on the basis of the actual consumption and not
on the basis of any contract demand. The appellant, however,
submitted bills in respect of the energy consumed on the
basis of the contract demand which the respondent did not
pay and for such default in payment of the amount charged
under the bills the appellant issued notice of
discontinuance under Section 24 of the Act. According to the
respondent’s case the bills submitted by the appellant being
disputed, no notice could have been issued by the appellant
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 5
under sub-section (1) of Section 24 and the matter can only
be referred to the Electrical Inspector for a decision as
provided under sub-section (2) of Section 24. The appellant
disputed the aforesaid stand of the respondent and submitted
that the respondent having failed to pay the bills raised by
the appellant in respect of the energy consumed, the
appellant was fully justified in issuing notice under
Section 24(1) of the Act and there is no illegality in the
same. The High Court by the impugned judgment came to the
conclusion that no agreement had been entered into between
the licensee, namely, the Bihar State Electricity Board and
the consumer, the respondent. It further came to the
conclusion that in the absence of any agreement between the
parties the Board seas not entitled to raise the bills on
the basis of the contract demand and can only charge on the
basis of the actual consumption o; energy. Finally, the High
Court came to the conclusion that there existed a bona fide
dispute between the licensee and the consumer, and
therefore, until that dispute is resolve by a determination
made by the Electrical Inspector under sub-section (2) of
Section 24, the licensee was not entitled to issue notice of
disconnection in exercise of power under sub-section (1) of
Section 24 of the Act. The High Court, therefore, quashed
the notice of demand and the threat of disconnection and
issued a mandamus to the licensee not to disconnect the
supply line so long as the dispute is not resolved in
accordance with law. The High Court also further held that
until the dispute is finally resolved, the consumer would be
liable to be charged on the basis of actual consumption of
energy. The amount of accumulated arrear which was indicated
in the notice of disconnection to the licensee was Rs.
3,01,449.30 upto March, 1979 which demand was quashed by the
High Court by the impugned judgment. This Court on 1st May,
1581 directed that the respondents shall pay the amount due
on the bills submitted to them by the appellant for the
actual consumption and future bills will be paid by The
respondents from time to time on the basis of actual and
such submission of bills and payments will be without
prejudice to the rights and contentions of the parties. By
another Order dated 5th may, 1982 this Court further
indicated that for the time being the Board will not collect
any energy charges by the application of the multiplier of
the two. Thereafter, as the respondent failed to pay the
bills issued by the Board, the supply of electricity to the
respondent was disconnected on 9th of May, 1984. The
respondent, therefore, approached this Court by filing an
application for necessary direction to the Board to restore
the connection of electricity supply and to injunct the
Board from disconnecting the supply without permission of
this Court during the pendency of the appeal, which was
registered as C.M.P. No. 23405 of 1984. In the said
application it was alleged that the appellant Board went
giving inflated bills based on erroneous conclusion on the
basis of 315 KVA of maximum contract demand which has
already been quashed by the Patna High Court and which is
contrary to the interim orders issued by this Court as
stated earlier. This application was disposed of by this
Court with the following direction:
"Counsel for both the parties have
jointly submitted before me that
the parties are agreeable that the
correct amount payable by the
respondent in the appeal by way of
charges for actual consumption of
electric energy as per tariff rates
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 5
applicable may be determined by any
officer not bellow the rank of
Chief Engineer nominated by the
Secretary, Department, of Energy,
Govt. of India. This suggestion
appears to me, just and fair which
is accordingly accepted and the
Secretary, Department of Energy
will forthwith nominate any one
officer under him of the rank
indicated above to go into the
question as to what amount, if any,
remains payable upto date by the
Hotel Satkar (P) Ltd. to the Bihar
State Electricity Board, Patna by
way of consumption charges taking
into account actual consumption.
Such determination will be made
after hearing both the parties of
their representatives at Delhi or
at Patna as will be convenient to
the officer nominated by the
Secretary, Department of Energy.
The entire process of determination
of the amount should be completed
within four weeks from today. The
Respondent shall file an
undertaking during the course of
the day today to pay to the Bihar
Electricity Board within one week
from the date of such determination
of the exact amount by the Officer
nominated by the Secretary,
Department of Energy. Subject to
the fulfillment of this condition
the Bihar State Electricity Board
is hereby directed to restore
forthwith the electric connection
to the respondent Hotel Satkar (P)
Ltd. If the respondent Hotel Satkar
fails or defaults in the payment
within one week of determination of
the amount due, it will be open to
the Bihar State Electricity Board
to disconnect electric connections.
The payment to be made by the
respondent in pursuance of this
order will be without prejudice to
the rights and contentions raised
in the appeal pending before this
Court."
Pursuant to the aforesaid order of this court the Chief
Engineer, Central Electricity Authority was nominated by the
Secretary, Department of Power, Ministry of Energy to go
into the question as to what amount, if any, remains payable
upto date by the respondent. The said Chief Engineer heard
the parties and gave opportunity to present their respective
case and after analyzing all the relevant papers and
documents produced before him, came to the conclusion that
for the period from April 1977 to February 1984 the
respondent is liable to pay the appellant a sum of
Rs.9,68,335.67 for the energy consumed on the basis of
actual consumption and out of the said amount the consumer
has paid a total of Rs. 5,83,776.34 and, therefore,
outstanding dues till February 1984 work out to Rs.
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 4 of 5
3,84,559.33. On behalf of the respondent an objection to the
aforesaid report of the Chief Engineer has also been filed
in this Court.
Mr. Pramod Swarup, learned counsel appearing for the
appellant contended that in view of the agreement between
the parties this Court having passed the order on 28th May
1984 requiring an officer not below the rank of Chief
Engineer be nominated by the Secretary, Department Energy,
Govt. of India to go into entire controversy and the said
Chief Engineer having gone into the controversy and having
determined the liability of the respondent, the parties are
bound by the same and it is no longer necessary to examine
the legality of the conclusion arrived at by the Patna High
Court. Mr. Sanyal, learned senior counsel appearing for the
respondent on the other hand contended that the report
submitted by the said Chief Engineer is patently erroneous,
and therefore could not bind the respondent for liability as
found and further the judgment of the Patna High Court is
unassailable. The learned counsel further contended that the
very order of this Court dated 28th May, 1984 indicates that
payment to be made by the respondent will be without
prejudice to the rights and contentions raised in appeal
pending before this Court. Mr. Sanyal, further contended
that the aforesaid order passed by this Court was in
relation to a fresh demand having been raised by the Board
during the pendency of the appeal and disconnection of the
electric supply for non-payment of the same and it would not
cover the demand for the period which was the subject matter
in the writ petition before the High Court and which is the
subject matter of appeal in this Court.
Having considered the rival submission and having
applied our mind to the relevant documents and several
orders passed by this Court we are of the considered opinion
that this Court was persuaded to pass tile order of 28th
May, 1984 on the agreement of the parties to get the
controversy examined by an officer not below the rank of
Chief Engineer to be nominated by the Secretary Department
of Energy, Govt. of India. The said Chief Engineer having
examined the documents produced before him by the parties
concerned and having determined the entire liability upto
February, 1984 the respondent cannot wriggle out of the said
order on the ground that the said order was without
prejudice to the contentions to be raised in the appeal. As
it appears, the controversy between the parties was, whether
the Board was justified in raising demands on the basis of
the contract demand in the absence of any agreement between
the parties and the High Court had ordered that demand can
be raised only as per the actual consumption of energy. It
further appears from the materials on record that the meters
which had been installed to record the consumption of energy
were only suitable to for 5 Amp. and had their dials
calibrated to register consumption corresponding to loads of
100 Amp. 200 Amp., 300 Amp. or 400 Amp. It further
transpires that though initially the dispute related to the
bills which had been, submitted upto the year 1979 but
during the pendency of the appeal in this Court when fresh
bills were also submitted by the Board and the respondent
did not pay the same, the appellant took action of
disconnection and respondent, therefore, approached this
Court for necessary direction for reconnection. It is on
consideration of all these materials and on the agreement
between the parties this Court passed the order on 28th May,
1984 requiring the entire controversy to he re-examined by
any officer not below the rank of Chief Engineer to be
nominated by the Secretary, Department of Energy, Govt. of
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 5 of 5
India. Thus on The date this Court passed the order on 28th
May, 1984 the controversy between the parties was in respect
of amount charged till February, 1984 and not the original
amount which was the subject matter of the writ petition.
This being the position and the matter having been duly
scrutinized by an officer of the Government of India and
amount having been arrived at and the parties having agreed
the controversy to be re-examined by such officer it is not
permissible for the respondents to contend that they are not
bound by the decision thus arrived at. So far as the merits
of the objections to the report of the Chief Engineer is
concerned we find that the said Chief Engineer has Act
determined the liability on the basis of contract demand but
on the basis of the actual consumption of energy. Mr.
Sanyal’s argument, however, was that in terms of sub-section
(2) of Section 24 of the Act when the matter has been
referred to the Electrical Inspector and the said Electrical
Inspector has determined the dispute in favour of the
respondent, such statutory determination cannot be given a
go-bye unless and until it is annulled by any superior
authority. He further contended that multiplying factor as
applied by the Chief Engineer is not at all applicable to
the facts and circumstances of the present case when there
was no defect with the meter at any point of time. We find
ourselves unable to accept these objections raised by Mr.
Sanyal appearing for the respondent. In respect of the
dispute with regard to the liability of the respondent to
make the payment as per the bills raised upto 1979 no doubt
had been referred to the Electrical Inspector under sub-
section (2) of Section 24 of the Act. But during the
pendency of the appeal in this Court when further hills were
raised by the appellant and for non-payment of the same the
electrical connection was disconnected and respondent
challenged the same and ultimately agreed before this Court
to get the entire controversy examined by an independent
officer of the Government of India and this Court ultimately
passed the order on 28th May, 1984, the entire controversy
with regard to the liability of the respondent to pay for
the energy consumed was before the Chief Engineer and
consequently any order passed by the Electrical Inspector
under sub-section (2) of Section 24 cannot override the
ultimate decision taken by the Chief Engineer in determining
the liability of the respondent. The objections of Mr.
Sanyal, therefore, cannot be sustained.
In the aforesaid premises the impugned judgment of the
Patna High Court stands reversed and the liability of the
respondent as determined by the Chief Engineer for the
energy consumed upto February 1984 becomes enforceable. The
respondent would be liable to pay in accordance with the
said determination after adjusting the amount already paid.
The appeal is disposed of with the aforesaid directions.
There will be no order as to costs.