Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 20
PETITIONER:
RAJASTHAN STATE MINES & MINERALS LIMITED
Vs.
RESPONDENT:
EASTERN ENGINEERING ENTERPRISES & ANR.
DATE OF JUDGMENT: 20/09/1999
BENCH:
D.P.Wadhwa, M.B.Shah
JUDGMENT:
Shah, J.
By the impugned Judgment and Order dated 17th
December, 1991, the High Court of Judicature of Rajasthan at
Jodhpur, dismissed the S.B. Civil Miscellaneous Appeal No.
254 of 1991 filed by the appellant and confirmed the
Judgment and Order dated 1st August, 1989 passed by the
District Judge, Udaipur in Petition under Sections 30 and 33
of the Arbitration Act, 1940. The District Judge had passed
the decree in terms of the award.
The brief facts of the case are that on 14th May,
1981, appellant and respondent no. 1 entered into an
agreement on a turn-key basis for excavation, removal,
transportation including loading and unloading, disposal
dumping dozing, levelling etc. of over burden at the
specified dump yards including final dressing of the mine
benches, faces and sides etc. and incidental mining of rock
phosphate ore encountered during the excavation of
over-burden and its transportation to ore-stacks etc. from
the footwall, western portion and eastern portions of D
Block of the Jhamarkotra mines including drilling, blasting,
loading, transportation, unloading etc. with the leads and
lifts involved in connection therewith, more particularly
described in the said contract for the period of three years
and three months, that is, from 13.3.81 to 12.6.84 for the
quantity of 21.15 lacs cubic meter subject to plus minus 10%
at the fixed rate of Rs. 35.80 (Rupees Thirty Five and
eighty paise) all inclusive per cubic meter in respect of
over burden and/or ore actually excavated mined, removed
etc.
Respondent No. 1 vide its letter dated 7th September,
1983, raised certain disputes and claimed reimbursement
and/or additional payments and/or compensation on account of
escalation of cost of work and breach of contract by the
Appellant. The Appellant vide its letter dated 11th
September, 1984 refuted the claims of Respondent No. 1 by
stating that in no case the rates over and above Rs. 35.80
per cubic meter could be given. On 10th November, 1984,
respondent No. 1 invoking the arbitration clause, requested
the Managing Director of Appellant to appoint a sole
arbitrator to adjudicate the claims made by the Contractor.
Thereafter, on 5th February, 1985, Shri C.S. Jha,
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 20
Chairman-cum-Managing Director, Bihar State Mineral
Development Corporation Ltd. was appointed as a sole
arbitrator to decide all claims raised by the contractor,
M/s. Eastern Engineering Enterprises vide its letter dated
7th September, 1983.
On 20th September, 1985, the sole arbitrator made an
interim award in respect of three claims, namely, claim nos.
2, 3 & 5 and awarded Rs. 65 lacs to the claimants.
Paragraph 1 of the said award mentions that Mr. C.S. Jha
was appointed as the sole arbitrator to decide the disputes
between the parties arising out of the agreement dated 14th
May, 1981. It also recites that by the consent of the
parties, arguments were heard claim-wise and out of 7 claims
submitted by the claimants, hearing in respect of claim no.
2, 3 & 5 was completed. It is also stated that when final
award would be made in respect of the entire proceedings,
interim award would be integrated into and form part of the
final award. The Appellant challenged the interim award on
15th January, 1986 in the Court of District Judge, Udaipur.
Thereafter, on 18th February, 1986 the sole arbitrator
made final award. It, inter-alia, provides that after
considering the long drawn arguments and examination of
documentary evidence and having made detailed examination of
the calculations I have given due thought and weightage to
all that was placed/argued before me, as regards
admissibility as well as quantum of each claim by going
through details of work done under each item of claim as
filed before me. Thereafter, he awarded Rs. 1.07 crore for
the claims made by the respondent no. 1. The said amount
included the amount awarded against the claims 2, 3 & 5 for
which he had passed interim award. He further awarded
interest @ 12.5 % p.a. on the sum awarded from 5th
February, 1985 till the date of payment or decree whichever
is earlier.
That final award was also challenged before the
District Judge. The Court framed as many as 12 issues out
of which issues (5) to (8) are as under: - 5. Did the
Arbitrator fail correctly to consider Clauses 17 and 18 of
the Agreement and the Contract labour (Abolition and
Regulation) Act, 1970? 6. Did the Arbitrator fail to apply
his mind to consider pleadings, documents and evidence? 7.
Whether the award is bad as the learned sole Arbitrator
failed to apply his mind to documents and decide the dispute
on per unit basis? 8. Is the award perverse? Has it been
improperly procured and is it otherwise invalid as mentioned
in the Objection Petition?
Thereafter, the District Judge, rejected the
contentions raised by the appellant and declared the award
as the rule of court and passed the decree. That was
challenged by filing the appeal before the High Court.
Before the High Court, it was contended that the
District Judge erred in accepting the interim as well as the
final award and it was required to be set aside as the
arbitrator had ignored the fixed rate mentioned in clauses
17 & 18 of the agreement and thereby he has travelled beyond
his jurisdiction. It was also pointed out that by doing so
the arbitrator has legally misconducted himself. It was
also submitted that the arbitrator was influenced by Mr. K.
Sehgal, hence, the award was required to be set aside. The
High Court arrived at the conclusion that the point of
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 20
jurisdiction was not raised before the arbitrator.
Therefore, appellant cannot raise the same before the court.
The learned Judge held that the perusal of the letter dated
5th February, 1985 goes to show that there was nothing by
which the arbitrator was restricted with regard to rates, on
the contrary, he was asked to decide all the claims raised
by the contractor without any clarification. The High Court
further observed that the appellant raised objection in
view of clauses 17 and 18 of the Contract in his reply to
the claim petition but he has not raised this point before
the arbitrator and thus the arbitrator has not disclosed
it. The learned Judge further observed that the appellant
never asked the arbitrator to decide his objection at
initial stage or final stage and this conduct of the
appellant goes to show that he has waived the objection,
otherwise he ought to have asked the arbitrator to decide at
proper stage. The Court held that even before District
Judge, the point of jurisdiction was never raised and the
issues framed were with regard to clauses 17 & 18 which were
decided against the appellant.
Dr. A.M. Singhvi, the learned senior Counsel
appearing on behalf of the appellant contended that the
judgment and order passed by the High Court is, on the face
of it, illegal because all throughout the appellant has
contended that claims made by respondent no. 1 were not
entertainable in view of clauses 17 & 18 of the agreement.
He submitted that, on the face of it, claims made by the
respondent no. 1 were for prohibited or excepted items
under clauses 17 & 18 of the agreement between the parties.
Therefore, he submitted that the arbitrator travelled beyond
his jurisdiction in awarding the compensation for the said
claims. He referred to all claims and pointed out that
except the claim for release of additional security deposit
of Rs. 5 lacs furnished by way of bank guarantee, no claim
could be entertained and granted in view of stipulations in
clauses 17 & 18 of the agreement and also because the
contract is on a turn-key basis.
As against this, learned senior Counsel, Mr. Ashok H.
Desai, appearing on behalf of the Respondent No. 1
strenuously submitted that, in the present case, arbitration
clause is of widest amplitude and it provides that all
disputes and differences arising out of or in any way
touching or concerning the contract whatsoever shall be
referred to the sole arbitration. Hence, the award passed
by the arbitrator cannot be held to be without jurisdiction
or it cannot be held that arbitrator has travelled beyond
his jurisdiction. He also submitted that award is a
non-speaking one and, therefore, also the Court cannot go
behind the said award for finding out the mental process of
the arbitrator for awarding the said sum. He submitted that
the award only depends upon interpretation of the clauses of
the agreement between the parties. It is his further
contention that, in any case, jurisdictional question was
not raised properly before the arbitrator or before the
District Court and the appellant allowed the arbitrator to
proceed with the proceedings without raising its objection
of jurisdiction or competence. By the reference letter
dated 5th February, 1985, arbitrator was empowered to
decide all claims raised by the contractor vide its letter
dated 7th September, 1983. He also submitted that even the
committee appointed by the appellant-company to examine the
claims of the respondent, has recommended same payment to
the contractor by granting an escalation in contracted rate
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 4 of 20
and to pay compensation towards loss suffered on account of
non supply of explosives. Hence, the appellant should not
be permitted to raise the contention of jurisdiction and the
appeal be dismissed. For deciding the controversy, clauses
17 & 18 as well as clause 74 which provides for arbitration
is required to be referred. Clauses 17 & 18 reads thus: -
17. Blasting Operation
It is express term of this contract that while
carrying out the excavation/Mining operations from the
aforesaid areas, blasting wherever required, shall be
undertaken by the contractor at his cost. The remuneration
payable under this contract for the work aforesaid is
inclusive of this element which includes cost of explosives,
its accessories transportation, salary and wages of its
crew/blasters etc., or otherwise. In view of aforesaid, the
contractor shall obtain necessary permission/s from the
Director General of Mines Safety and/or other competent
authorities for undertaking the blasting operation
independently at the aforesaid areas covered by this
contract as also obtain necessary licence for the explosive
magazine etc. The contractor shall do all that are required
to be done to obtain the necessary permission etc., from the
competent authorities immediately without any further loss
of time and shall make regular and continuous efforts for
the same if for the present such permission is not granted
to him/her.
In the event of the contractor failing to obtain such
permission required from the competent authority for doing
blasting operation in the areas covered by this contract
after all genuine and effective efforts, the company may at
the request of the contractor and subject to its convenience
take up the blasting operation in the areas entrusted to the
contractor under this contract, at the cost and risk of the
contractor. Provided, however that the contractor shall be
bound to observe all terms and conditions of blasting
operation in the contract and other operations involved
therein shall be duly observed/undertaken by the contractor,
as if the blasting is being done by them. Drilling shall be
done by the contractor at places and as per the pattern
approved in writing by the Engineer-in-charge. The
Engineer-in-charge, may require drilling of additional holes
by the contractor before blasting is taken up. The holes
not drilled as per the approved drilling pattern shall not
be taken up for blasting. On receipt of written requisition
from the contractor in the prescribed proforma duly signed
by the authorised representative of the contractor to the
company not less than 2 days prior to intended date of
blasting, blasting will be done by the Company as and when
felt necessary and convenient by the Engineer-in-charge.
The company shall make available the blasting material, its
transportation, blasting accessories and blasting crews
including blaster/s. In case the company is not in a
position to arrange for the same, the contractor shall make
his own arrangements for the same without any liability and
obligation on the company. The company shall deduct the
actual landed cost of all explosives ex-Jhamarkotra as may
be used in the course of blasting plus five per cent value
of the landed cost of explosives as blasting charges from
the contractors running Bill/s or any amount that may be
found due and payable to the contractor or the security
amount. It is agreed and understood by the contractor that
in the event of company doing blasting as aforesaid, for and
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 5 of 20
on behalf of the contractor, the contractor shall not be
allowed and/or permitted to raise any dispute as to make,
type quantity of the explosives that will be used in
blasting by the company, fragmentation of rock, toes at the
mining face, landed cost of explosive, time and frequency of
blasting etc., and the contractor shall be bound to make
good the landed cost of explosives, cost of blasting
accessories etc., plus overheads @ 5% as may be certified by
the Engineer-in-charge from time to time. Provided also
that the contractor shall not be entitled and/or justified
to raise any claim or dispute on account of blasting or non
blasting or idling of his equipment or his labour or any
rise in the landed cost of explosives at any time or during
the currency of this agreement or on any ground or any
reason of any account, whatsoever.
At the time of blasting in the areas being worked by
the Company or by the contractor if the company is required
to carry out blasting operation, the contractor shall be
required to vacate the areas if the areas fall within
blasting zone, worked by him for which the contractor shall
not be entitled for any claim, additional payment
whatsoever.
18. Contractors remuneration for works under the
Contract:-
In consideration of the performance of the work,
fulfillment of all the obligations, terms and conditions of
this agreement by the contractor in execution of the work
covered by this contract in and from the aforesaid areas,
the contractor shall be paid remuneration calculated @ Rs.
35.80 (thirty five and eighty paise) all inclusive per cubic
meter in respect of over burden and/or Ore actually
excavated, mined, removed, transported, disposed off,
dumped, dozed, levelled and spreaded including drilling,
blasting, mucking, loading, and unloading, etc., with all
leads and lifts involved in connection with the
transportation and dumping of over-burden to the dump yards
or ore stacks, including all preparatory dressing, finishing
and other operational works etc., executed and approved by
the Engineer- in-charge. The rates aforesaid shall be
composite and inclusive of all services, activities and
operations involved in the execution of the work as per
terms and conditions of this agreement which constitute the
whole and inclusive remuneration that is payable by the
Company to the contractor under this contract. The
contractor shall be only entitled to the payment of
composite rate as aforesaid and no other or further payment
of any kind or item, whatsoever, shall be due and payable by
the Company to the contractor under this agreement except as
aforesaid.
The rates aforesaid shall remain firm, fixed and
binding during the currency of this agreement till the issue
of final certificate irrespective of any fall or rise in the
cost of Mining operations of the work covered by this
contract or for any other reason or any account or any
ground whatsoever.
Provided, however, that the company has agreed to
freeze the issue rate of Diesel as on 13th March, 1981, at
the rate of Rs. 2.78 (Rupees Two and seventy eight paise
only) per litre and the company shall issue the Diesel
subject to availability and its convenience to the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 6 of 20
contractor against the surrender of permit/s of the
equipment by him at the frozen rate of Rs. 2.78 per litre
during the currency of this contract even if there by any
rise in the cost of diesel after execution of this agreement
subject to a ceiling of 1.3 litres(one point three litre)
for one cubit meter of rock (in situ) actually handled and
work executed by the contractor and approved by the
Engineer-in-charge, as per provisions of this agreement. No
diesel at the frozen rate of Rs. 2.78 per litre shall be
supplied and/or issued to the contractor after the 12th day
of June, 1984, if the work is not finally completed by the
contractor as aforesaid. The company shall deduct the cost
of diesel @ Rs. 2.78 per litre actually issued to the
contractor from the contractors running bills or any amount
that may be due to him or the security amount. Save and
except as aforesaid the contractor shall not be entitled to
raise any claim and/or dispute on account of any rise in the
price of oil, lubricants, tyres, tubes, explosives, spares
etc. statutory or otherwise or increase in the wages or
Minimum wages or on any other ground or reason or account,
whatsoever.
Relevant part of arbitration clause 74 is as under:-
All disputes and differences arising out of or in any
way touching or concerning this contract whatsoever, except
as to any matter, the decision of which is expressly vested
in any authority in this contract, shall be referred to the
sole arbitration of the person appointed by the Managing
Director of Company who shall have status of a Mines Manager
having 1st Class Mines Managers Certificate and having
experience not less than five years in open cast mining as
Mines Manager.
At this stage, we would refer to the relevant portion
of letter dated 7- 9-1983 written by the Contractor to the
appellant as the dispute for the said claims made in the
letter are referred to for arbitration. 1. After stating
the reasons in delay in starting the work, it is mentioned:
- In view of above, we now request RSMML to consider our
case and condone the theoretical delay, which, in fact, was
not there and also give us necessary, relief as to
consequential damages thereof. Hence, we request you to
consider 1st August, 1981 as the date of start of work and
accordingly, extend the validity of the contract.
2. The demand is Release of additional security
deposit of Rs. 5 lakhs furnished by us in RSMMLs favour by
way of bank guarantee for the reasons stated therein. 3.
Request for Rescheduling of the existing excavation
schedule for the reasons mentioned therein. 4. Claim for
Escalation in the existing rate of excavation: We signed
the contract with a clear understanding that the rate under
this contract is firm and final and we shall get no
escalation in our rates, except in case of diesel, which
will be supplied to us by the Company at a frozen rate.
With the passage of time our cost calculations went hayway
for reasons which were beyond our control.
5 (i) From the beginning of the contract we had paid
wages equivalent to RSMML wages instead of Minimum wages.
The difference between the two on an average in the last 25
months works out to Rs.75,000/- per month, against an
average production of 40,000 cu.m. per month. Thus the
additional cost works out to Rs.1.80 per cu.m.
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 7 of 20
(ii) Unforeseen and difficult operating condition in
the footwall and its effect on the cost of operation: The
work in footwall area of D block is a major constituent of
the contract both quality and quantity wise. While the
contract is termed as a Turnkey contract, at least in the
footwall the work cannot, by any stretch of imagination, be
considered as Turnkey, as the operation in that area is
totally controlled by the Principal employer.
In fact, it was beyond our imagination that our
working in the footwall will be so much restricted,
resulting the cost of operation, which is virtually very
high than normal cost of operation. In view of above, we
feel that our request in this regard will be sympathetically
considered by the Management, who are also engaged in
similar work. Thus, for such poor utilisation of the
Shovel, the rate should be 35.80 = 61.20. 58.50x100 Thus,
an additional rate of Rs.25.40 per cu.m. for the entire
footwall operation has to be provided for. (iii)
Non-availability of explosive and use of costly explosive
for blasting :
Reimbursement of Rs.22.55 lakhs towards cash loss due
to non- supply of explosives in time plus Rs.1.82 per cu.m.
of rock handled so far. 6. Claim for Transportation of ore
: After stating reasons in detail, it is claimed thus:
Till 31st August, 1983 mined and transported 45,456
tonnes of ore and mixed ore from Eastern Saddle and
Footwall, the additional expenses involved in this operation
are: -
(i) Care being taken during mining to avoid as much as
possible admixture of ore and overburden, and
(ii) Additional transportation involved for taking it
to the crusher instead of the dumpyard. Towards this we
have to make claim of Rs.6/- towards this mining cost per
tonne and Rs.4/- towards transportation cost per tonne
making the total to Rs.4,05,660/- for 40,566 tonnes of ore
after allowing ½% of the total excavation volume of footwall
i.e. 3.36 lakhs cu/.m.
To sum up, claims under various heads are as under:
-
(i) Not to levy any damages for not starting work in
time and to treat 1st August, 1981 as the date of start of
work and thereafter calculate 3 years for completing this
work under this contract; (ii) To release performance bank
guarantee of 5 lakhs furnished in your favour by way of
additional security deposit; (iii) To re-schedule the
excavation schedule keeping in view the industrial climate
at Jhamarkotra @ 40,000/- cu.m. per month; (iv) To allow
us escalation of Rs.3.62 in our rates towards additional
cost that has been incurred by us with retrospective effect.
(v) To admit our claim of Rs.22.55 lakhs towards loss
suffered on account of non supply of explosives,
Rs.4,05,660/- towards additional cost of mining and
transportation of ore and Rs.52,53,650/- on account of loss
suffered by us for unforeseen and difficult operating
condition at footwall or in other words the present rate of
Rs.35.80 per cu.m. with retrospective effect. On the basis
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 8 of 20
of the claims made in the letter dated 7th September, 1983,
respondent filed claim statement for 8 items which is
tabulated by the High Court in its judgment. Claim
Description of Relief claimed No. claim
1. Claim for increase in rate Claimed reimbursement @
for excavation work at Rs.25.40 per cu.m. up to the
Footwall area demand Aug.83 thereafter @ 63.56 for
escalation in the per cu.m. Over and above existing rates
of the contract rate of Rs.35.80 excavation. Cu.m. In all
claim under this item quantified for Rs. 1,36,43,218/-.
2. Claim for increase in costs Claimed reimbursement
@ Rs. Of work due to use of high 1.80 per cu.m. for all
Explosives instead of use excavation done/to be done Of ANFO
mixture. Under the contract using high Explosives instead
of ANFO mixture.
3. Claim for reimbursement for Claim reimbursement of
Losses suffered due to non- Rs. 22.55 lacs by way of loss
Availability of explosive. During the period February, 1963
to May 1983.
4. Claim for reimbursement Claimed reimbursement of
of additional costs for mining additional costs at the rate
of and transport of ore. Rs. 6/- per ton Towards mining
and Rs.4/- per ton towards additional transportation to the
crusher. Total Rs.10/- per ton for 47856 tonnes of ore and
mixed ore upto 31st December, 1984 quantifying claim of
Rs.4,31,890/-.
5. Claim for reimbursement Claim reimbursement @ Rs.
of additional expenditure 1.82 per cu.m. for excavation
incurred on account of done/to be done on account Agreement
with RPMS.- Of respondent entering into For wages to
labourers. An agreement with RPMS Dated 26.5.81 Ex.C/I of
the Arbitration proceedings.
6. Claim for release of Claimed release of duly
discharged additional securities Bank guarantee of Rs.5
lacks on deposit. Account of Addl. Security deposit.
7. Claim for reimbursement Claim reimbursement of
Rs.0.90 of additional expenses on per cu.m. of excavation
done account of revised wage since 1.4.83 or to be done
structure w.e.f.1.4.83. thereafter as per Ex.C/58 and C/68.
8. Interest Claimed interest on the amount of Award @
Rs.18% per annum Or decree whichever is earlier.
As stated earlier by interim award, arbitrator has
awarded Rs. 65 lakhs for claims No. 2, 3 & 5. Thereafter,
by final award, he has awarded total sum Rs. 1.07 crores
with 12.5% interest w.e.f. 5.2.85.
Before discussing further, what emerges from the facts
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 9 of 20
stated above is: -
(1) in the award, no reasons are assigned for granting
various claims to that extent, it is non-speaking. For
claim Nos. 2,3 and 5, Rs. 65 lakhs were awarded by interim
award dated 20th September, 1985. (2) In the interim award,
the arbitrator has made it clear that he was appointed as
the sole arbitrator vide memo dated 5th February 1985 to
decide the dispute between the parties arising out of the
agreement dated 14th May, 1981. So, his authority or
jurisdiction to decide the claims raised by the contractor
was on the basis of the agreement between the parties. (3)
In the final award also, in the first paragraph itself,
arbitrator has stated that:-
The claimants have put in claims arising out of and
in relation to the work Excavation and removal of
overburden at the Jhamarkotra mines of RSMML executed
under agreement dated 14.5.1981, and have put in their
claims under 7 heads of claim and have further claimed
interest, pendentelite and future at 18% per annum.. It
further mentions that he has given due weightage to all the
documents placed and arguments submitted before him as
regards admissibility as well as quantum of each claim by
going through details of work done under each item of claims
as filed before me.
(4) In the letter dated 7th September, 1983, the
Contractor himself has clarified, admitted and stated thus:
We signed the contract with a clear understanding
that the rate under this contract is firm and final and we
shall get no escalation in our rates, except in case of
diesel, which will be supplied to us by the company at a
frozen rate. With the passage of time our cost calculations
went hay way for reasons which were beyond our control.
(5) The appellant in his detailed reply before the
arbitrator to the claims made by the contractor has pointed
out and relied upon clauses 17 & 18 for contending that
contractor was not entitled to any such claim under the
contract. (6) Before the District Judge also, the issues
pertaining to clauses 17 & 18 as stated above were raised.
(7) Before the High Court also, it was contended that
arbitrator made award against the stipulations of the
agreement between the parties and thereby travelled beyond
his jurisdiction.
From the facts stated above, learned Counsel for the
appellant has rightly pointed out that Claim No. 1 for
increase in rate of excavation work at footwall area and
claim no. 4 for reimbursement of additional costs for
mining and transport of ore is against the stipulation of
clause 18 as narrated above, which inter-alia, specifically
provides as under:-
(a) The contractor shall be paid remuneration
calculated @ Rs. 35.80(Rupees Thirty Five and Eighty Paise
only) all inclusive per cubic meter in respect of over
burden and/or Ore actually excavated transported (b)
The contractor shall be only entitled to payment of
composite rate as aforesaid and no other or further payment
of any kind of item, whatsoever, shall be due and payable by
the Company to the contractor under this agreement except as
aforesaid. (c) The rates shall remain in firm, fixed and
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 10 of 20
binding irrespective of any fall or rise in the cost of
Mining operations of the work covered by the contract or for
any other reason or any account or any ground whatsoever.
Similarly, claim no. 2 for increase in costs of work due to
use of high explosives instead of use of ANFO mixture and
claim no. 3 for reimbursement for losses suffered due to
non-availability of explosive is also against Clause 17,
which inter-alia, provides:- (a) It is express term of this
contract that while carrying out the excavation/Mining
operations from the aforesaid areas, blasting wherever
required, shall be undertaken by the contractor at his cost.
The remuneration payable under this contract for the work
aforesaid is inclusive of this element which includes cost
of explosives, its accessories transportation, salary and
wages of its crew/blasters etc., or otherwise. (b)
Provided also that the contractor shall not be entitled
and/or justified to raise any claim or dispute on account of
blasting or non blasting or idling of his equipment or his
labour or any rise in the landed cost of explosives at any
time or during the currency of this agreement or on any
ground or any reason of any account, whatsoever.
Similarly, claim no. 5 for reimbursement of
additional expenditure incurred on account of RPMS and claim
no. 7 for reimbursement of additional expenses on account
of revised wage structure w.e.f. 1.4.83 also cannot be
granted in view of aforesaid stipulations and also part of
Clause 18 which, inter-alia, provides as under: Save and
except as aforesaid the contractor shall not be entitled to
raise any claim and/or dispute on account of any rise in the
price of oil, lubricants, tyres, tubes, explosives, spares,
etc. statutory or otherwise or increase in the wages or
Minimum wages or on any other ground or reason or account,
whatsoever.
Apart from the aforesaid specific stipulations, even
the contractor has admitted in his letter dated 7th
September, 1983 that the contract was signed with clear
understanding that the rate under the contract was firm and
final and that no escalation in rates except in case of
diesel would be granted. Despite the admission by the
contractor, it is apparent that arbitrator has ignored the
aforesaid stipulations in the contract. In the award, the
arbitrator has specifically mentioned that he has given due
weightage to all the documents placed before him and has
also considered the admissibility of each claim. However,
while passing the award basic and fundamental terms of the
agreement between the parties are ignored. By doing so, it
is apparent that he has exceeded his jurisdiction. Further,
in the present case, there is no question of interpretation
of clauses 17 & 18 as the said clauses are so clear and
unambiguous that they do not require any interpretation. It
is both, in positive and negative terms by providing that
contractor shall be paid rates as fixed and that he shall
not be entitled to extra payment or further payment for any
ground whatsoever except as mentioned therein. The rates
agreed were firm, fixed and binding irrespective of any fall
or rise in the cost of the work covered by the contract or
for any other reason or any ground whatsoever. It is
specifically agreed that contractor will not be entitled or
justified in raising any claim or dispute because of
increase in cost of expenses on any ground whatsoever. By
ignoring the said terms, arbitrator has travelled beyond his
jurisdiction as his existence depends upon the agreement and
his function is to act within the limits of the said
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 11 of 20
agreement. This deliberate departure from the contract
amounts not only to manifests disregard of the authority or
misconduct on his part but it may tantamount to mala fide
action.
It is settled law that the arbitrator is the creature
of the contract between the parties and hence if he ignores
the specific terms of the contract, it would be a question
of jurisdictional error which could be corrected by the
Court for that limited purpose agreement is required to be
considered. For deciding whether the arbitrator has
exceeded his jurisdiction reference to the terms of the
contract is a must It is true that arbitration clause 74 is
very widely worded, therefore, the dispute was required to
be referred to the arbitrator. Hence, the award passed by
the arbitrator cannot be said to be without jurisdiction
but, at the same time, it is apparent that he has exceeded
his jurisdiction by ignoring the specific stipulations in
the agreement which prohibits entertaining of the claims
made by the contractor. In the letter dated 5th February,
1985 appointing the sole arbitrator, it has been
specifically mentioned that agreement dated 14th May, 1981
was executed by and between the parties and that contractor
has raised the claims as mentioned in the letter dated 7th
September, 1983 which was denied by the company and at the
request of the contractor, sole arbitrator was appointed to
adjudicate the claims made by the contractor vide his letter
dated 7th September, 1983. This reference to the arbitrator
also clearly provides that reference was with regard to the
dispute arising between the parties on the basis of the
agreement dated 14th May, 1981. It nowhere indicates that
the arbitrator was empowered to adjudicate any other claims
beyond the agreement between the parties. No such issue was
referred for adjudication. Even the arbitrator in his
interim award has specifically stated that he was appointed
to adjudicate the disputes between the parties arising out
of the agreement dated 14th May, 1981.
However, learned senior Counsel, Mr. Ashok H. Desai,
submitted that award is a non-speaking one and the
arbitration clause, in this case empowers the arbitrator not
only to decide all disputes arising out of the contract but
also to decide all disputes in any way touching the contract
whatsoever, hence the arbitrator is not required to confine
himself only to the terms of the contract but can pass
appropriate award so as to do justice between the parties
including awarding damages suffered by the contracting
parties. Therefore, award cannot be said to be without or
beyond jurisdiction. He further submitted that the award
passed by the arbitrator is on the basis of the
interpretation of clauses 17 & 18 and, therefore, the award
would be within his jurisdiction. Learned counsel for both
the parties submitted that law on this subject is well
settled. However, they referred to various decisions to
buttress their respective contentions. To do justice to
their contentions, we would refer to the various decisions
of this Court relied upon by them. In Jivarajbhai Ujamshi
Sheth and Others Vs. Chintamanrao Balaji and Others [(1964)
5 S.C.R. 481], the dispute arose between the partners of a
firm on retirement of partners which was referred to the
arbitrator. The arbitrator had passed non-speaking award.
While revoking the award, the High Court in concurrence with
the Court below upheld two objections: - (a) that the
arbitrator exceeded his jurisdiction; and (b) that he was
guilty of misconduct in receiving some evidence behind the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 12 of 20
back of one partner, Chintaman Rao. Before this Court, it
was contended that the deed of partnership as well as the
order of reference left the arbitrator a free hand and even
if the arbitrator wrongly interpreted the deed of
partnership and had included the depreciation and
appreciation while valuing partnership property, no question
of jurisdiction could arise. The partnership deed referred
to by the Court provided that in ascertaining the valuation
of the firm, the property was to be valued at the book value
of the firm and such stock and movables thus valued shall be
given to the remaining partners. After considering the
decision in Chempsey Bhara and Company Vs. Jivraj Balloo
Spinning and Weaving Company Ltd. [LR 50 I.A. 324],
Shah.J, observed that : (a) It is not open to the Court to
speculate, where no reasons are given by the arbitrator, as
to what impelled arbitrator to arrive at his conclusion (b)
It is not open to the Court to admit to probe the mental
process by which the arbitrator has reached his conclusion
where it is not disclosed by the terms of the award. (c)
The primary duty of the arbitrator under the deed of a
reference in which was incorporated the partnership
agreement, was to value the net assets of the firm and to
award to the retiring partners a share therein. In making
the valuation of the firm, his jurisdiction was restricted
in a manner provided by paragraph 13 of the partnership
agreement. As the arbitrator has expressly stated in his
award that in arriving at his valuation, he has included the
depreciation and appreciation of the property, the
arbitrator has travelled outside his jurisdiction and the
award was on that account liable to be set aside. This was
not a case in which the arbitrator has committed a mere
error of fact or law in reaching his conclusion on the
disputed question submitted for his adjudication. It is a
case of assumption of jurisdiction not possessed by him, and
that renders the award, to the extent to which it is beyond
the arbitrators jurisdiction, invalid. The award must fail
in its entirety as it was not possible to sever from the
valuation made by the arbitrator, the value of the
depreciation and appreciation included. In a concurring
judgment, Hidayatullah J, after considering the decision in
Chempsey Bhara and Companys case (supra) observed that the
first point is therefore to decide what were the limits of
the arbitrators action as disclosed by the reference and
the deed of partnership and then to see what the arbitrator
has actually done and not what he may have stated loosely in
his award. This is the only way in which the excess of
jurisdiction can be found. If the interpretation of the
deed of partnership lies with the arbitrator, then there is
no question of sitting in appeal over his interpretation, in
view of the passage quoted above from Champseys case but if
the parties set limits to action by the arbitrator, then the
arbitrator had to follow the limits set for him, and the
court can find that he has exceeded his jurisdiction on
proof of such action.
The next decision on which reliance is placed is
Continental Construction Co. Ltd. Vs. State of M.P.
[1988 (3) SCR 103]. In the said case, it was contended by
the contractor that contract could not be completed within
stipulated time because of alleged gross delay on the part
of the State in allotment of work and discharge of its
obligation under the contract. He had, therefore, incurred
unforeseen expenditure and claimed damages to the tune of
Rs. 5,29,812/-. The matter was referred to the retired
Engineer-in- Chief, PWD, Bhopal, who partly allowed the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 13 of 20
contractors claim. The award was set aside by the District
Judge. Appeal was also dismissed by the High Court and in
appeal before this Court, it was contended that the
contractor was not entitled to extra cost for material and
labour in terms of the contract. This Court held that
arbitrator misconducted himself in allowing the claim
without deciding the objection of the State that in view of
the specific clauses of the contract, the Contractor was not
legally entitled to claim extra cost. The Court observed:
If no specific question of law is referred, the decision of
the arbitrator on that question is not final however much it
may be within his jurisdiction and indeed essential for him
to decide the question incidentally. The arbitrator is not
a conciliator and cannot ignore the law or misapply it in
order to do what he thinks is just and reasonable. The
arbitrator is a tribunal selected by the parties to decide
their disputes according to law and so is bound to follow
and apply the law, and if he does not he can be set right by
the Court provided his error appears on the face of the
award. In this case, the contractor having contracted, he
cannot go back to the agreement simply because he does not
suit him to abide by it. The decision of this Court in M/s.
Alopi Parshad Vs. Union of India, [1960] 2 SCR 793 may be
examined. There it was observed that a contract is not
frustrated merely because the circumstances in which the
contract was made, altered. The Contract Act does not
enable a party to a contract to ignore the express covenants
thereof, and to claim payment of consideration for
performance of the contract at rates different from the
stipulated rates, on some vague plea of equity. The parties
to an executory contract are often faced, in the course of
carrying it out, with a turn of event which they did not at
all anticipate, a wholly abnormal rise or fall in prices, a
sudden depreciation of currency, an unexpected obstacle to
execution, or the like. There is no general liberty
reserved to the courts to absolve a party from liability to
perform his part of the contract merely because on account
of an uncontemplated turn of events, the performance of the
contract may become onerous.
Thereafter, the Court distinguished the decision in
Tarapore Company Vs. Cochin Shipyard Ltd. And another
[1984(2) SCC 680]. In the said case, there were no specific
clauses which barred consideration of extra claims in events
of price escalation. At this stage, we would mention that
in Tarapore Companys case, this Court after considering the
various decisions has held that a specific question as to
whether the claim of compensation made by the Contractor
demurred and disputed by the respondent would be covered
within the scope, ambit and width of the arbitration clause
was specifically referred by the parties for the decision of
the Arbitrator. In such cases, the award cannot be set
aside on the ground that there is an error of law on the
face of the award. Learned Sr. Counsel, Mr. Ashok H.
Desai has heavily relied upon this decision in support of
his contention that in the present case also, arbitration
clause 74 is very widely worded. Dealing with arbitration
clause, Court observed arbitration clause so widely worded,
as disputes arising out of the contract or in relation to
the contract or execution of the works, would comprehend
within its compass a claim for compensation related to
estimates and arising out of the contract. The test is
whether it is necessary to have recourse to the contract to
settle the dispute that has arisen. Further, while
interpreting such clause, the Court has held as under:- We
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 14 of 20
may now turn to some decisions to which our attention was
drawn. The first case we would like to refer to is A.M.
Mair & Co. Vs. Gordhandass Sagarmull [1950] SCR 792. The
Court was concerned with the arbitration clause drawn up as
: all matters, questions, disputes, differences and/or
claims, arising out of and/or concerning, and/or in
connection and/or in consequence of, or relating to, the
contract etc.. The question arose whether the due date
under the contract was extended within the time, earlier
reserved. The arbitrator held that the due date of the
contract has been extended by a mutual agreement and the
respondents were held liable to pay a sum of Rs. 4116
together with interest at the rates specified in the award.
It was contended that the dispute is not covered by the
arbitration clause. This clause while holding that the
dispute is covered by the arbitration clause observed that
looking to the rival contentions, such a dispute, the
determination of which turns on the true construction of the
contract, would also seem to be a dispute under or arising
out of or concerning the contract. The test formulated was
that if in settling a dispute, a reference to the contract
is necessary, such a dispute would be covered by the
arbitration clause.
It is true that arbitration clause in the present
case, is also very widely worded and that all disputes in
any way touching or concerning the contract whatsoever are
required to be referred to the arbitration. Therefore,
reference of the dispute to the arbitrator cannot be termed
as without jurisdiction. Still the question would be
whether arbitrator will have authority or jurisdiction to
grant damages or compensation in teeth of stipulation
providing that no escalation would be granted and that
contractor would only be entitled to payment of composite
rate as mentioned and no other or further payment of any
kind or item whatsoever, shall be due and payable by the
company to the contractor; the rates wherever fixed are
binding during the currency of the agreement irrespective of
any fall or rise in the cost of the work covered by the
contract or for any other reason or on any account or any
other ground whatsoever. In the said case, there was no
such specific agreement or stipulation. Further, the Court
has also given a finding that it was a case where a specific
question of law touching upon the jurisdiction of the
arbitrator was referred for the decision of the arbitrator
by the parties. Hence the Court held that in such a
situation, even if the view taken by the arbitrator may not
accord with the view of the Court, the award cannot be set
aside on the ground that there is an error of law apparent
on the face of the record. Facts and issues in the present
case are quite different as stated above.
In M/s. Sudarshan Trading Co. Vs. Government of
Kerala and Another [1989] 2 SCC 38, this Court posed the
following questions for its decision: - How should the
court examine an award to find out whether it was a speaking
award or not; and if it be a non-speaking award, how and to
what extent the court could go to determine whether there
was any error apparent on the face of the award to be liable
for the interference by the court. The other question that
arises in this case is, to what extent can the court examine
the contract in question though not incorporated or referred
to in the award.
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 15 of 20
In that case also, the arbitrator has passed the
non-speaking awards but with regard to each and every claim
it has separated and passed the order either accepting or
rejecting the claim or partly accepting the claim of the
contractor. After referring to the various decisions
including Jivarbhai Ujamshi Sheth case, the Court observed
as under: This was reiterated by Justice Hidayatullah that
if the parties set limits to action by the arbitrator, then
the arbitrator had to follow the limits set for him and the
court can find that he exceeded his jurisdiction on proof of
such excess. In that case the arbitrator in working out net
profits for four years took into account depreciation of
immovable property. For this reason he must be held to have
exceeded his jurisdiction and it is not a question of his
having merely interpreted the partnership agreement for
himself as to which the civil court could have had no say,
unless there was an error of law on the face of the award.
Therefore, it appears to us that there are two different and
distinct grounds involved in many of the cases. One is the
error apparent on the face of the award, and the other is
that the arbitrator exceeded his jurisdiction. In the
latter case, the courts can look into the arbitration
agreement but in the former, it cannot, unless the agreement
was incorporated or recited in the award.
This Court further observed:
An award may be remitted or set aside on the ground
that the arbitrator in making it, had exceeded his
jurisdiction and evidence of matters not appearing on the
face of it, will be admitted in order to establish whether
the jurisdiction had been exceeded or not, because the
nature of the dispute is something which has to be
determined outside the award whatever might be said about
it in the award or by the arbitrator... It has to be
reiterated that an arbitrator acting beyond his jurisdiction
-- is a different ground from the error apparent on the face
of the award.
Further, dealing with the non-speaking award and also
for the claims on the ground of escalation of price, due to
various reasons including payment of minimum rates of wages
payable to various categories of workers, this Court in
Associated Engineering Co. Vs. Government of Andhra
Pradesh and Another [1991] 4 SCC 93 referred to the contract
clauses and set aside the award by holding: - This
conclusion is reached not by construction of the contract
but by merely looking at the contract. The umpire travelled
totally outside the permissible territory and thus exceeded
his jurisdiction in making the award under those claims.
This is an error going to the root of his jurisdiction: See
Jivarajbhai Ujamshi Sheth Vs. Chintamanrao Balaji.
The Court further held as under: An arbitrator who
acts in manifest disregard of the contract acts without
jurisdiction. His authority is derived from the contract
and is governed by the Arbitration Act which embodies
principles derived from a specialised branch of the law of
agency(see Mustill and Boyds Commercial Arbitration, 2nd
edn., p. 641). He commits misconduct if by his award he
decides matters excluded by the agreement(see Halsburys
Laws of England, Volume II, 4th edn., para 622). A
deliberate departure from contract amounts to not only
manifest disregard of his authority or a misconduct on his
part, but it may tantamount to a mala fide action. A
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 16 of 20
conscious disregard of the law or the provisions of the
contract from which he has derived his authority vitiates
the award.
Learned Counsel for the Respondent relied upon the
case of Hindustan Construction Co. Ltd. Vs. State of
Jammu & Kashmir [1992] 4 SCC 217. In the said case, the
Court has observed that award was a non- speaking one and
contained no reasoning which could be declared to be faulty;
the scope of the Courts jurisdiction in interfering with
the non- speaking award is extremely limited. While
discussing the contention, the Court quoted the decision in
the case of Sudarshan Trading Co. case (which we have
earlier referred) and thereafter held that High Court has
not rested its decision on any question of the arbitrator
having exceeded his jurisdiction or travelled beyond the
contract; the Court has set aside the award on the ground
of error apparent on the face of it. The Court further held
that clauses of the contract referred to by the High Court
are not so clear or unambiguous as to warrant an inference
that the interpretation placed on them by the arbitrators is
totally unsustainable. In that view of the matter, the
Court held that it was difficult to say that the
arbitrators interpretation was erroneous on the face of it.
Hence, the aforesaid decision would have no bearing to the
facts and the law involved in this matter. Similarly, in
Managing Director, J&K Handicrafts, Jammu Vs. Good Luck
Carpets [1990] 4 SCC 740, dealing with the non-speaking
award, the Court negatived the contention that the agreement
containing the arbitration clause cannot be looked into even
to find out as to what was the nature of the dispute
contemplated by it with regard to which a reference to an
arbitrator was contemplated, nor so, when the award was
non-speaking one, by observing thus: Firstly, the award is
not a totally non-speaking one inasmuch as it gives a resume
of the incentive scheme and the agreement between the
parties as also the items of the claim made by the
respondent. Of course while fixing the amount found payable
by the appellant, no reasons are recorded. Secondly, if
there is any challenge to the award on the ground that the
arbitrator had no jurisdiction to make the award with regard
to a particular item inasmuch as it was beyond the scope of
reference, the only way to test the correctness of such a
challenge is to look into the agreement itself. In our
opinion, looking into the agreement for this limited purpose
is neither tantamount to going into the evidence produced by
the parties nor into the reasons which weighed with the
arbitrator in making the award.
In Tarapore & Co. Vs. State of M.P. 1994(3) SCC
521, this Court again considered whether the arbitrator has
exceeded his jurisdiction in awarding extra payment to the
contractor on account of payment of enhanced wages to labour
by the contractor pursuant to statutory revision of minimum
wages by Government or increase in rates of fair wages by
wage committee binding on the contractor under conditions of
tender notice. In the said case, Court considered the
distinction between the latent and patent jurisdiction of
the arbitrator in deciding the disputes and after referring
to the arbitration clause, observed that: - Any dispute
relating to or arising out of or in any way connected with
the contract has to be referred to arbitration. It cannot
be said that there was patent lack of jurisdiction on the
part of arbitrators in having gone into the question of
reimbursement; at the best it could be said that
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 17 of 20
arbitrators had no jurisdiction to entertain the claim and
hence a case of latent lack of jurisdiction.
After considering the decisions in Continental
Construction Co.(supra) and Tarapore and Co. (supra), this
Court held that as there was absence of escalation clause,
it was not a case where on the basis of the terms of the
agreement entered between the parties, it can be held that
arbitrator had no jurisdiction to make the award. The Court
observed that it cannot be held that arbitrator has no
jurisdiction to make the award because of lack of specific
provision permitting the claim at the hand. The Court
further observed:- It has to be seen whether the term of
the agreement permitted entertainment of the claim by
necessary implication. It may be stated that we do not
accept the broad contention of Shri Nariman that whatever is
not excluded specifically by the contract can be
subject-matter of claim by a contractor. Such a proposition
will mock at the terms agreed upon. Parties cannot be
allowed to depart from what they had agreed. Of course, if
something flows as a necessary concomitant to what was
agreed upon, courts can assume that too as a part of the
contract between the parties.
After referring to the facts as found from the record,
the Court held that the award cannot be said to be beyond
the jurisdiction of the arbitrator insofar as increased
payment on account of rise in rates of fair wages was
concerned. In our view, the said finding is based on
appreciation of evidence on record and the terms of the
contract. However, the Court made it clear that part of the
award which is relatable to increase in minimum wages cannot
be regarded as one within jurisdiction and observed
needless to say that if arbitrator goes beyond
jurisdiction, the same would amount to misconduct.
In T.N. Electricity Board Vs. Bridge Tunnel
Constructions and Others 1997(4) SCC 121, the contractor had
set up the claims raised at rates higher than the contracted
rates and twice the rate for the work done after the expiry
of the contract period. For those claims, dispute was
raised and the matter was referred to the arbitrator. The
Civil Court made the award rule of the Court. The High
Court confirmed the same. In appeal, this Court set aside
the award and while discussing various contentions, observed
as under: If the arbitrator decides a dispute which is
beyond the scope of his reference or beyond the
subject-matter of the reference or he makes the award
disregarding the terms of reference or the arbitration
agreement or terms of the contract, it would be a
jurisdictional error beyond the scope of reference; he
cannot clothe himself to decide conclusively that dispute as
it is an error of jurisdiction which requires to be
ultimately decided by the Court.
In New India Civil Erectors (P) Ltd. Vs. Oil &
Natural Gas Corporation [1997] 11 SCC 75, this Court again
considered the contention wherein the arbitrator has passed
award contrary to the specific stipulation/condition
contained in the agreement between the parties. The Court
observed thus:- It is axiomatic that the arbitrator being a
creature of the agreement, must operate within the four
corners of the agreement and cannot travel beyond it. More
particularly, he cannot award any amount which is ruled out
or prohibited by the terms of the agreement. In this case,
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 18 of 20
the agreement between the parties clearly says that in
measuring the built-up area, the balcony areas should be
excluded. The arbitrators could not have acted contrary to
the said stipulation and awarded any amount to the appellant
on that account.
The aforesaid judgment was considered in H.P. State
Electricity Board Vs. R.J. Shah and Company [1999(4) SCC
214] and in paragraph 26, the Court held as under:
In order to determine whether the arbitrator has
acted in excess of jurisdiction what has to be seen is
whether the claimant could raise a particular dispute or
claim before the arbitrator. If the answer is in
affirmative, then it is clear that arbitrator would have the
jurisdiction to deal with such a claim. On the other hand
if the arbitration clause or a specific term in the contract
or the law does not permit or give the arbitrator the power
to decide or to adjudicate on a dispute raised by the
claimant or there is a specific bar to the raising of a
particular dispute or claim, then any decision given by the
Arbitrator in respect thereof would clearly be in excess of
jurisdiction.
Learned Sr. Counsel, Mr. Ashok H. Desai relied upon
the case of P.V. Subba Naidu and Others Vs. Government of
A.P. and others 1998(9) SCC 407. In that case, the
non-speaking award was rendered by the arbitrator. The
Court held that the terms of the arbitration clause were
very wide, therefore, all the disputes which arise as a
result of the contract would be covered by the arbitration
clause and that all claims were expressly referred to the
arbitrator and were raised before the arbitrator. In that
set of circumstances, by purporting to construe the contract
the Court could not take upon itself the burden of saying
that it was contrary to the contract and as such beyond
jurisdiction. Thereafter, the Court referred to the
decision in Ch. Ramalinga Reddy Vs. Superintending
Engineer (1994) 5 Scale 67 and observed that in that case
arbitrator was required to decide the claims referred to him
having regard to the contract. Hence, his jurisdiction was
expressly limited to decide claims under the terms of the
contract but in the case which was considered by the Court,
there was no clause in the contract which prevented the
arbitrator from examining the claims put up before the
arbitrator. Considering the aforesaid aspect, in our view,
this judgment also would have no bearing in the present
case, as there are express prohibitions and stipulations in
the contract for non-payment of extra amount on any ground
whatsoever. In the present case, the rates were to remain
firm, fixed and binding irrespective of fall or rise in cost
of mining operation of the work covered by the contract or
for any other reason. The contract was for composite rate
and it stipulated that no other or further payment of any
kind of item whatsoever was payable by the company to the
Contractor. From the resume of the aforesaid decisions, it
can be stated that: (a) it is not open to the Court to
speculate, where no reasons are given by the arbitrator, as
to what impelled arbitrator to arrive at his conclusion.
(b) It is not open to the Court to admit to probe the mental
process by which the arbitrator has reached his conclusion
where it is not disclosed by the terms of the award. (c) If
the arbitrator has committed a mere error of fact or law in
reaching his conclusion on the disputed question submitted
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 19 of 20
for his adjudication then the Court cannot interfere. (d)
If no specific question of law is referred, the decision of
the Arbitrator on that question is not final, however much
it may be within his jurisdiction and indeed essential for
him to decide the question incidentally. In a case where
specific question of law touching upon the jurisdiction of
the arbitrator was referred for the decision of the
arbitrator by the parties, then the finding of the
arbitrator on the said question between the parties may be
binding. (e) In a case of non-speaking award, the
jurisdiction of the Court is limited. The award can be set
aside if the arbitrator acts beyond his jurisdiction. (f)
To find out whether the arbitrator has travelled beyond his
jurisdiction, it would be necessary to consider the
agreement between the parties containing the arbitration
clause. Arbitrator acting beyond his jurisdiction is a
different ground from the error apparent on the face of the
award. (g) In order to determine whether arbitrator has
acted in excess of his jurisdiction what has to be seen is
whether the claimant could raise a particular claim before
the arbitrator. If there is a specific term in the contract
or the law which does not permit or give the arbitrator the
power to decide the dispute raised by the claimant or there
is a specific bar in the contract to the raising of the
particular claim then the award passed by the arbitrator in
respect thereof would be in excess of jurisdiction. (h) The
award made by the Arbitrator disregarding the terms of the
reference or the arbitration agreement or the terms of the
contract would be a jurisdictional error which requires
ultimately to be decided by the Court. He cannot award an
amount which is ruled out or prohibited by the terms of the
agreement. Because of specific bar stipulated by the
parties in the agreement, that claim could not be raised.
Even if it is raised and referred to arbitration because of
wider arbitration clause such claim amount cannot be awarded
as agreement is binding between the parties and the
arbitrator has to adjudicate as per the agreement. This
aspect is absolutely made clear in Continental Construction
Co. Ltd.(supra) by relying upon the following passage from
M/s. Alopi Parshad Vs. Union of India [1960] 2 SCR 703
which is to the following effect: - There it was observed
that a contract is not frustrated merely because the
circumstances in which the contract was made, altered. The
Contract Act does not enable a party to a contract to ignore
the express covenants thereof, and to claim payment of
consideration for performance of the contract at rates
different from the stipulated rates, on some vague plea of
equity. The parties to an executory contract are often
faced, in the course of carrying it out, with a turn of
event which they did not at all anticipate, a wholly
abnormal rise or fall in prices, a sudden depreciation of
currency, an unexpected obstacle to execution, or the like.
There is no general liberty reserved to the courts to
absolve a party from liability to perform his part of the
contract merely because on account of an uncontemplated turn
of events, the performance of the contract may become
onerous.
(i) The arbitrator could not act arbitrarily,
irrationally, capriciously or independently of the contract.
A deliberate departure or conscious disregard of the
contract not only manifests the disregard of his authority
or misconduct on his part but it may tantamount to mala fide
action. (j) The arbitrator is not a conciliator and cannot
ignore the law or misapply it in order to do what he thinks
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 20 of 20
just and reasonable; the arbitrator is a tribunal selected
by the parties to decide the disputes according to law.
In view of the aforesaid law and the facts stated
above, it is apparent that the award passed by the
arbitrator is against the stipulations and prohibitions
contained in the contract between the parties. In the
present case, there is no question of interpretation of
clauses 17 & 18 as the language of the said clauses is
absolutely clear and unambiguous. Even the contractor has
admitted in his letter demanding such claims that the
contract was signed with clear understanding that the rate
under the contract was firm and final and no escalation in
rates except in case of diesel would be granted. Hence, by
ignoring the same, the arbitrator has travelled beyond his
jurisdiction. It amounts to deliberate departure from the
contract. Further, the reference to the arbitrator is
solely based upon the agreement between the parties and the
arbitrator has stated so in his interim award that he was
appointed to adjudicate the disputes between the parties
arising out of the agreement. No specific issue was
referred to the arbitrator which would confer jurisdiction
on the arbitrator to go beyond the terms of the contract.
Hence, the award passed by the arbitrator is, on the face of
it, illegal and in excess of his jurisdiction which requires
to be quashed and set aside.
Lastly, we would mention few other contentions raised
by the learned counsel for the respondent which are required
to be stated for rejection. His contention that arbitrator
has acted beyond his jurisdiction was not raised before the
District Court as well as before the Arbitrator, is without
any substance. Surprisingly, to say the least, the High
Court as well as the District Court observed that no
specific contention with regard to the jurisdiction was
raised before the arbitrator. It appears that the High
Court and the District Court had not considered the written
statement filed by the appellant before the arbitrator. The
District Court has also raised issue Nos. 5 to 8 quoted
above, which would cover the contention raised by the
appellant. The issue whether the award is perverse and that
the arbitrator failed to apply his mind to pleadings,
documents and evidence as well as the clauses 17 & 18 of the
agreement would cover the contention that the arbitrator
acted beyond his jurisdiction in ignoring stipulations of
the contract. With regard to the committees report on
which the learned Counsel for the respondent has relied
upon, it had been pointed out by the learned Counsel for the
appellant that the said report was specifically rejected by
the board of the appellant. Hence, it would have no bearing
on the award which was to be passed by the Arbitrator.
In the result, the appeal is allowed with costs. The
award passed by the arbitrator is quashed and set aside.
Consequently, the judgment and order dated 17th December,
1991 passed by the High Court in S.B. Civil Miscellaneous
Appeal No.254 of 1991confirming the judgment and order dated
1st August, 1989 passed by the District Judge, Udaipur in
Civil Miscellaneous Case No. 131 of 1985 and 45 of 1986 is
also quashed and set aside.