THE MANAGING DIRECTOR (SHRI GRISH BATRA) M/S. PADMINI INFRASTRUCTURE DEVELOPERS (I) LTD. vs. THE GENERAL SECRETARY (SHRI AMOL MAHAPATRA) ROYAL GARDEN RESIDENTS WELFARE ASSOCIATION

Case Type: Civil Appeal

Date of Judgment: 28-09-2021

Preview image for THE MANAGING DIRECTOR (SHRI GRISH BATRA) M/S. PADMINI INFRASTRUCTURE DEVELOPERS (I) LTD. vs. THE GENERAL SECRETARY (SHRI AMOL MAHAPATRA) ROYAL GARDEN RESIDENTS WELFARE ASSOCIATION

Full Judgment Text

1 REPORTABLE IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION CIVIL APPEAL NO.2998 OF 2010 THE MANAGING DIRECTOR (SHRI GRISH BATRA)                        M/S.PADMINI INFRASTRUCTURE  DEVELOPERS (I) LTD.                               …       APPELLANT(S) VERSUS THE GENERAL SECRETARY  (SHRI AMOL MAHAPATRA) ROYAL  GARDEN RESDIENTS WELFARE  ASSOCIATION                                           …      RESPONDENT(S) WITH CIVIL APPEAL NO. 4085 OF 2010 J U D G M E N T V. Ramasubramanian, J. 1. Both the consumer (who was the complainant) as well as the   opposite   party   before   the   National   Consumer   Disputes Redressal Commission, have come up with these appeals, the Signature Not Verified Digitally signed by Jayant Kumar Arora Date: 2021.09.28 16:36:46 IST Reason: former aggrieved by the rejection of some of the reliefs sought and 2 the   latter,   challenging   the   reliefs   granted   in   favour   of   the consumer. 2. We have heard the learned counsel appearing on both sides. 3. A   residential   apartment   complex   was   promoted   by   M/s Padmini   Infrastructure   Developers   (India)   Ltd.   ( hereinafter referred to as ‘the opposite party’ ), on a land allotted by New Okhla Development Authority (‘ NOIDA’ for short ).  It appears that the opposite party constructed about 282 apartments and offered them for sale. The purchasers were put in possession during the period from 1998­2001, but the completion certificate itself was issued only in December, 2001. 4. The   purchasers   of   flats   formed   themselves   into   an association   known   as   Royale   Garden   Residents   Welfare Association   and   got   it   registered   on   30.09.2003   under   the Societies Registration Act, 1860. 5. The   Residents   Welfare   Association   entered   into   an agreement on 15.11.2003 with the opposite party for taking over the   maintenance   of   the   apartment   complex.   Thereafter,   the Residents   Welfare   Association   ( (hereinafter   referred   to   as   the 3 ‘complainant’ ), filed a consumer complaint in Complaint No.9 of 2007   before   the   National   Consumer   Disputes   Redressal Commission. 6. The reliefs sought by the complainant before the National Commission were as follows:­ “1.to pay the monthly maintenance charges for unsold flats amounting to Rs. 9,05,810/­ 2. to   complete   the   water   softening   plant   and   make   it operational. 3. to complete fire fighting equipments and make the same operational and to obtain safe working certificate from Fire Safety Department of NOIDA and handover the same to the Complainant. 4. to furnish and equip a second health club for which space is   available   in   half   portion   of   basement   of   Tower   Blue Heaven­2. 5. to   complete   a   second   swimming   pool   and   get   cement plastered and white washed the stilts. 6. to   provide   furnished   space   for   a,   Club   House   in   the basement of Eden Tower which is existing but locked. 7. to get the rented portion of the terrace (roof) vacated meant for the resident of Tower Eden of the Complainant rented out   by   the   Opposite   Party   to   HUTCH   (P)   Limited   and earned rent after on 15.11.2003 to be returned to RWA with 24% interest. 8. not to sell or rent out the remaining flats about 45 till the facilities   mentioned   above   are   provided   to   the Complainant. 9. to direct the OP not be sell stilt and open car parking to future or present purchasers. 4 10. to   pay   the   cost   to   the   Complaint   and   damages   for harassment   mental   torture,   agony   etc.   caused   to   the Complainant by the OP. 11. to pass any other or further orders which this August Commission deems fit in the circumstances of the case to meet the ends of justice.” 7. The complaint was resisted by the opposite party both on merits and on the ground of limitation. The opposite party also claimed that the Agreement dated 15.11.2003, entered into with the   complainant   contained   an   arbitration   clause   and   that whatever   facilities/amenities   were   promised   at   the   time   of promotion of the complex, have been put in place. 8. The   National   Commission   by   its   interim   order   dated 04.06.2008,   appointed   a   local   Commissioner,   to   inspect   the systems/facilities relatable to the reliefs claimed in prayer clause nos. 2 to 6 of the complaint and to submit a report. The said Commissioner submitted a report on 08.07.2008 after making a local inspection, in the presence of the representatives of both the parties. 9. Accepting   the   report   of   the   local   Commissioner   and overruling   the   contention   of   the   opposite   party   regarding limitation, the National Commission allowed the complaint partly 5 by an order dated 05.01.2010. The operative part of the order of the Consumer Commission reads as follows: “Consequently, complaint is partly allowed with cost of         Rs. 25,000/­ with direction to the opposite party to make the systems/facilities as at Sl. Nos. 2,3,4,5 and 6 of the prayer clause  of   the  complaint   operational/complete   and  to  obtain and   supply   fire   safety   certificate   of   the   complex   to   the complainant   association   within   ten   weeks   from   today.   The opposite party will submit a report within two weeks thereafter from   an   independent   Architect   certifying   that   the systems/facilities   in   question   have   been   fully   made operational/complete by the opposite party. In the event of not making operational/complete the systems/facilities referred to above within the time allowed, the opposite party will pay through a demand  draft the costs thereof  as  mentioned in aforesaid report dated 8.07.2008 within two weeks from after the expiry of 12 weeks time to the complainant association.” 10. Aggrieved   by   the   order   of   the   National   Commission,   the opposite   party   (builder) ,   has   come   up   with   one   appeal   in C.A.No.2998 of 2010. Aggrieved by the refusal of the National Commission to grant the reliefs as per prayer clause nos. 1, 7, 8, 9 & 10, the consumer­complainant has come up with another appeal in C.A.No.4085 of 2010. 11. As observed earlier, the consumer complaint was contested by   the   opposite   party   both   on   merits   and   on   the   ground   of limitation.  Since it is easy to deal with the objection relating to limitation without much ado, we shall take it up first. 6 12. Section   24A(1)   of   the   Consumer   Protection   Act,   1986 prescribes a period of limitation of two years from the date on which  the   cause   of   action   has   arisen   for   the   admission   of   a complaint,   by   the   District   Forum,   State   Commission   or   the National Commission. In the case on hand, the opposite party handed   over   the   work   of   maintenance   of   the   complex   to   the complainant,   under   an   Agreement   dated   15.11.2003.   As   seen from   the   preamble   to   the   Agreement,   the   Agreement   covered common essential services such as generators, lifts, tube­well, water softening plant, electric substation, cabling, fire fighting system,   pipelines,   swimming   pool,   health   and   fitness   centre, parking, club­house,  water  supply,  drainage/sewerage system, horticulture, water tanks/pumps and lawns/parks. 13. But   different   timelines   were   prescribed   under   the   said Agreement   for   different   obligations   still   remaining   to   be performed by the opposite party, towards the purchasers of flats. The last of such timeline was indicated to be 31.03.2004. 14. There   were   specific   obligations   to   be   performed   by   the opposite party under the said Agreement, in relation to certain 7 services. It may be useful in this regard to extract clauses 13, 14 and 19 of the Agreement as follows:­ “ 13. The   FIRST   PARTY   shall   bear   the   contractual obligations of lift, generator, health club and equipments fitted at   swimming   pool.   FIRST   PARTY   shall   also   bear   the maintenance   of   these   equipments   till   these   contracts   are concluded.   FIRST   PARTY   shall   bear   any/all   expenses   on maintenance/repair/replacement of these equipments. 14. To FIRST PARTY shall make the softening plant and tube will in working condition and hand it over to SECOND PARTY separately on or before 31.1.2004.  The FIRST PARTY shall   also   bring   the   fire   fighting   Equipments/generators   in working condition and hand it over to the SECOND PARTY separately on or before 31.12.2003. …                      …                             … 19. The FIRST PARTY shall construct the second Health Club and second swimming pool on or before 31.3.2004 and provide space for Club house in one of the basements for the residents as promised and assured at the time of selling the apartments on or before 31.12.2003.” 15. Therefore, the cause of action for the complaint, as per the above clauses continued even after the date of the Agreement namely 15.11.2003. 16. In the affidavit filed by the local Manager of the opposite party by way of evidence, it was admitted that certain works in relation to fire­fighting equipment continued up to the year 2005. In fact, the opposite party filed certain bills, which were dated 27.02.2005,   22.04.2005,   01.05.2005,   19.07.2005,   29.10.2005 8 and 12.12.2005, to show that the opposite party was honest and diligent in carrying out their obligations. 17. The affidavit in evidence filed by the opposite party and the aforesaid bills establish that the cause of action continued at least   till   December,   2005.   The   complaint   before   the   National Commission was filed in February, 2007. Therefore, the National Commission   was   right   in   rejecting   the   objection   relating   to limitation. 18. Coming to the merits, let us first take up the challenge to correctness of the reliefs granted by the National Commission in favour of the complainant, as the appeal filed by the opposite party appears to be first in point of time. 19. The reliefs granted by the National Consumer Commission related to water softening plant, fire­fighting, second health club equipment, second swimming pool and space for club house in Eden   Tower.   These   reliefs   were   granted   by   the   National Commission   on   the   basis   of   the   Report   of   the   local Commissioner. 9 20. It appears that opposite party filed objections to the report of the local Commissioner, contending  inter alia(i)  that the water softening plant was fully functional when the complex was taken over by the complainant association;   (ii)   that any deficiency or defect   relating   to   the   fire­fighting   equipment   is   wholly attributable to the lack of maintenance and wrongful practices adopted by the complainant association;      that they are not (iii) contractually   liable   to   provide   a   second   health   club   and   the finding of the local Commissioner that one of the health clubs is fully functional and in good condition has to be accepted; and  (iv) that   the   second   swimming   pool   was   completed   and   made operational by the opposite party, but what remained was the filling   up   of   water   after   filtration,   which   was   the   job   of   the maintenance agency. 21. Interestingly the affidavit of objections to the Report of the local   Commissioner,   filed   on   behalf   of   the   opposite   party   on 06.08.2008,   covered   only   the   findings   relating   to,     water (i) softening plant;   (ii)   fire­fighting  equipment;   (iii)   second  health club;   and     second   swimming   pool,   but   did   not   cover   the (iv) finding relating to the liability of the opposite party to provide 10 furnished space for a club house in the basement of Eden Tower (relatable to relief no.6 of the complaint) . However, the affidavit covered the claim of the complainant for maintenance charges, though the local Commissioner had nothing to do with the same. 22. The Commissioner appointed by the National Commission was an architect by name Amit Bahl. When he carried out the inspection,   4   persons   representing   the   opposite   party,   which included the advocate of the opposite party and the deponent to the affidavit of objections were present. The architect examined each one of the items and not only found that they were not operational on date but also found,  (i)  that the equipment for the water softening plant was incomplete, ineffective and inadequate;  that the fire­fighting equipments were not in operation due to (ii) incomplete commissioning of the system as a whole and that even the fire safety certificate dated 05.11.2001 noted down the same;   that while the first health club in the basement of the (iii) Tower  Blue   Heaven­2   was   fully   furnished   and   functional,   the second health club was not adequately furnished though the civil works are complete;  (iv)  that the second swimming pool was not complete   and   operational,   as   the   filtration   plant   was   non­ 11 functional and the pump was removed after installation and that even the change rooms and showers have not been provided for; and   that in so far as the club house in the basement of Eden (v) tower   is   concerned   it   was   kept   under   lock   and   key   by   the opposite   party   and   found   to   have   been   used   as   a   store   for keeping various building materials. 23. In  the   light   of   the   aforesaid   findings   by   an   independent architect appointed by the National Commission it is not open to the   opposite   party   to   create   a   façade   as   though   all   essential services and amenities were handed over in a fully functional state.  If all the aforesaid services had been handed over in a fully functional   state,   the   opposite   party   should   have   taken   an acknowledgment   in   writing   from   the   complainant.   In   the alternative,   the   opposite   party   should   have   insisted   upon   an appropriate provision in the Agreement dated 15.11.2003. 24. As   noted   by   the   Commissioner,   even   the   fire   safety certificate dated 05.11.2001 states that though the majority of the equipment have been satisfactorily installed, some equipment have been removed and stored for security purposes and that the inference therefore is that the system never got commissioned. 12 25. It is not impossible for an experienced architect to find out whether   the   condition   in   which   the   aforesaid   amenities   and services were found on the date of the inspection, was entirely due   to   lack   of   maintenance   or   due   to   non­commissioning   or incomplete commissioning. 26. As   noted   by   the   National   Commission,   the   affidavit   of objections filed on behalf of the opposite party to the Report of the local Commissioner does not deal with the cost of estimates indicated by the Commissioner in his Report. In addition, the affidavit of objections does not even deal with the finding relating to the club house at Eden Tower, said to have been kept under lock and key by the opposite party for storing building materials. The   very   fact   that   at   the   time   of   inspection   by   the   local Commissioner, the possession of the club house in Eden Tower was with the opposite party, goes to show that the opposite party was still retaining control of at least some part or certain services in the complex, perhaps due to the fact that there were about 45 unsold flats. 27. In view of the above, we are not convinced that the reliefs granted by the National commission in favour of the complainant 13 warrant any interference. Therefore, the appeal in C.A. No.2998 of 2010 is liable to be dismissed. 28. But before we do that, we should take note of the fact that as   per   the   operative   portion   of   the   order   of   the   National Commission (which we have extracted elsewhere) the opposite party is obliged to make the systems/facilities at prayer clauses 2, 3, 4, 5 & 6 of the complaint, fully operational/complete and they are also obliged to obtain a certificate of completion from an independent architect.  If the opposite party failed to do so within the time stipulated by the National Commission, the opposite party   was   obliged   to   pay   the   cost   as   estimated   by   the Commissioner in his Report dated 08.07.2008. 29. The costs estimated by the local Commissioner in his Report dated 08.07.2008 are as follows :­
1<br>.Water softening plantRs. 20,29,962
2<br>.Fire fighting equipmentRs. 83,00,000
3<br>.Second health clubRs. 7,60,000
4<br>.Second swimming poolRs. 2,70,000
5<br>.Furnishing the club house in Eden<br>TowerRs. 2,75,000
TotalRs.1,16,34,962
14 30. While   ordering   notice   in   C.A.No.2998   of   2010,   on 29.03.2010, this Court granted stay of operation of the impugned order   on   condition   that   the   opposite   party–builder   deposit Rs.60,00,000/­   within   8   weeks.   Subsequently,   the   order   was modified on 14.05.2010, permitting the opposite party to deposit the sum in two equal instalments, the first instalment before nd 22.05.2010 and 2  instalment before 15.07.2010. It appears that the amount has been accordingly deposited and the amount has been invested in a Fixed Deposit which is renewed from time to time by the orders of this Court. 31. In   view   of   the   fact   that   the   possession   of   the   common amenities   were   handed   over   by   the   opposite   party   to   the complainant   Association   18   years   ago   (under   the   Agreement dated 15.11.2003), it may not be possible at this distance of time to compel the opposite party to make those facilities/systems at relief clauses 2, 3, 4, 5 and 6, fully operational now.  The cost of estimate   which   works   out   to   approximately   Rs.1.16   crores, includes within itself the cost of fire fighting equipment and this constitutes the major component (it works out to Rs. 83 lakhs). As seen from the Commissioner’s Report, the mistake committed 15 by the opposite party was in removing a part of the equipment but not putting them back.  This finding is as per the fire safety certificate.   Therefore,   it   may   not   be   appropriate   to   ask   the opposite party to bear the entire burden. 32. Therefore, taking into account the overall picture, we are of the considered view that interests of justice will be met if the order of the National Commission is modified in such a manner (i)  that the complainant Association shall receive in full and final settlement, the deposit now lying in the Registry of this court, towards adequate compensation for the reliefs that they are held entitled to by the National Commission; and  (ii)  that the opposite party is directed to remove all building material stored in the club   house   in   the   basement   of   Tower   Eden   and   hand   over possession of the club house to the complainant. 33. Now coming to the appeal CA No.4085 of 2010 filed by the complainant against the refusal of the reliefs in prayer clause nos.1, 7, 8, 9 and 10, we think that the National Commission was justified  in  rejecting those reliefs. The  claim  for  monthly maintenance   charges   for   the   unsold   flats,   amounting   to Rs.9,05,810/­ sought as per prayer clause no.1, was made by 16 the complainant on the basis of clause 10 of the Agreement dated 15.11.2003 which reads as follows: “10. The FIRST PARTY agrees to pay to the SECOND PARTY the   monthly   maintenance   charges   @   50   paise   per square   feet   for   the   unsold   flats   w.e.f.   16.11.2003. FIRST PARTY shall make the advance payment for 6 months   within   7   days   of   signing   of   the   agreement. Subsequently   these   charges   will   be   paid   yearly   in advance.” 34. The averments relating to the relief claimed at prayer clause no.1 are found in paragraph 16 of the complaint which reads as follows:­ “16. That   the   amount   of   such   advance   payment   upto 31.12.2006 is Rs.619568/­ approx. an advance for the year 2007 comes to Rs.286242/­.  Thus the OP has to make   the   total   payment   amounting   to   Rs.  905810/­ approx. with interest @ 24% for the delayed period for which   OP   had   agreed   vide   agreement   dated 15.11.2003 Clause No.6 last two lines.” 35. Though the National Commission did not deal with the relief claimed   at   prayer   clause   No.1   in   sufficient   detail   and   the National   Commission   did   not   also   provide   cogent   reasons   for rejecting the relief, we find that the complainant may not be entitled to the said relief. There are two reasons as to why we say so.   The   first   reason   is   that   the   complainant   did   not   provide detailed calculations about the plinth area of the unsold flats, the 17 period during which they remained unsold and the manner in which the amount indicated in para 16 of the complaint was arrived at. In any case the payments were to be made under clause   10   of   the   agreement,   first   within   seven   days   of   the agreement in respect of the advance payment for six months and thereafter by way of annual payments in advance.  Therefore, a major portion of the claim for money was obviously barred by limitation when the complaint was filed. Moreover, the opposite party raised a dispute about the quantum and asserted in para 16 of their reply before the National Commission that what was due   was   only   Rs.232750/­.   Thus,   the   question   became   a disputed question of  fact on  which  both parties  did  not lead sufficient evidence.  Therefore, the rejection of the claim at prayer clause No.1 was legally correct. 36. The  relief claimed  at prayer clause no.8 is to direct the opposite party not to sell or rent out the unsold flats till the facilities mentioned in prayer clause nos.2 to 6 are provided. By its very nature, this relief is in the nature of an interim relief and, hence, was rightly rejected by the National Commission in the final judgment. 18 37. The relief claimed in prayer clause no.9 relates to stilt and open car parking. There was  no evidence  before the National Commission to grant such a relief and, hence, the refusal to grant the relief mentioned in prayer clause no.9 is in order.    38. The claim for costs and damages for harassment, mental torture, agony etc., made in prayer clause no.10 was not granted by the National Commission, and rightly so, in view of the fact that   after   handing   over   the   common   amenities   under   the Agreement dated 15.11.2003, the opposite party continued to carry out at least some works. This is why the complaint was lodged in 2007. Therefore, we find no reason to grant the relief prayed for in prayer clause no.10. 39. That leaves us with the relief claimed in prayer clause no.7. This was for a direction to the opposite party to vacate the tenant occupying   the   terrace   of   Tower   Eden.   According   to   the complainant,   the   terrace   of   Tower   Eden   was   let   out   by   the opposite party to a company, leaving the residents of Tower Eden without   a   terrace   for   common   use.   But   the   relief   of   eviction involves a third party and hence the National commission rightly 19 left it to the complainant to pursue the remedy in an appropriate Forum. 40. Thus, we find that the refusal of the National Commission to grant the reliefs mentioned in prayer clause nos.1, 7, 8, 9 and 10   warrant   no   interference.   Therefore,   the   appeal   of   the complainant in CA No.4085 of 2010 is liable to be dismissed. 41. Accordingly the appeal of the consumer­complainant in C.A. No. 4085 of 2010 is dismissed. The appeal of the builder­opposite party in C.A. No. 2998 of 2010 is partly allowed, modifying and substituting the judgment of the National Consumer Disputes Redressal Commission dated 05.01.2010 in Consumer Complaint No. 9 of 2007, to the following effect:  The   complainant   shall   be   entitled   to   all   told   monetary compensation in a sum of Rs. 60 lakhs, now lying in deposit with the   Registry   of   this   court,   together   with   the   interest   accrued thereon, in lieu of the reliefs sought in prayer clauses 2, 3, 4, 5 and   6   of   the   complaint.   The   opposite   party   shall,   within   two weeks, remove all building material stored by them in the club house in the basement of Tower Eden and hand over possession of the club house to the complainant. The complaint shall stand dismissed in all other respects. No costs.  42. The   parties   are   to   bear   their   respective   costs   in   these appeals. The Registry shall liquidate the fixed deposit standing to the credit of the above appeal and make payment of the proceeds 20 to   the   complainant   namely,   Royal   Garden   Residents   welfare Association. All interlocutory applications if any are closed.    ...................................J. (Hemant Gupta) ...................................J. (V. Ramasubramanian) New Delhi September  28, 2021