Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 8
CASE NO.:
Appeal (civil) 3615 of 1996
PETITIONER:
Bombay Electric Supply & Transport Undertaking
RESPONDENT:
Laffans (India) Pvt. Ltd. & Anr.
DATE OF JUDGMENT: 21/04/2005
BENCH:
CJI R.C. Lahoti, Dr. AR. Lakshmanan & G.P. Mathur
JUDGMENT:
J U D G M E N T
R.C. Lahoti, CJI
This appeal, by special leave, has been preferred against
the judgment dated 10.3.1995 of the Division Bench of Bombay
High Court, by which the Letters Patent Appeal filed by first
respondent, Laffans (India) Pvt. Ltd. was allowed, the judgment
dated 17.3.1993 of the learned Single Judge dismissing the writ
petition was set aside and the notice of disconnection of
electricity supply issued by the appellant was quashed.
The appellant, Bombay Electricity Supply and Transport
Undertaking is an undertaking of Municipal Corporation of
Greater Bombay (second respondent) and is a licensee under the
Indian Electricity Act, 1910 (hereinafter referred to as "the
Act"). The appellant was supplying electricity to the first
respondent, Laffans (India) Pvt. Ltd. who had a showroom at
Veer Nariman Road, Bombay, for carrying on business of retail
trade in textiles. The appellant had installed two meters at the
premises of the first respondent, for measuring the quantity of
electricity consumed : one __ by lights, fans and other small
fixtures, and, the other __ by the air-conditioning unit. The
dispute here relates to the meter measuring the quantity of
electricity consumed by the air-conditioning unit. Initially, meter
No. 850050 had been installed but the same got burnt and a
new meter bearing No. 860154 was installed on 2.5.1988.
According to the appellant, in a routine checking the said meter
was found to be running slow and accordingly the first
respondent was informed on 14.6.1989 that the meter would be
replaced and revised bills would be issued. Thereafter, a new
meter bearing No. 890324 was installed on 30.6.1989. This
meter was also found to be running slow and accordingly the
first respondent was informed on 25.9.1989 that the meter
would be replaced and revised bills would be issued. On
18.12.1989, a new meter bearing No. 880272 was installed.
This also got burnt and was replaced by meter No. 890272 on
30.12.1989. The appellant then taking the preceding one year’s
period i.e. from 2.2.1987 to 1.2.1988 as the base period and on
the pattern of consumption recorded therein, revised the bills
and sent a demand notice dated 5.9.1990 for Rs. 2,19,602/73
paise for the period 1.2.1988 to 30.12.1989 on the footing that
the first respondent had been undercharged by 1,13,212 units.
A perusal of the contents of the demand letter shows that for the
period for which the meter is alleged to have recorded incorrect
readings, bills were sent month by month on the basis of
readings as recorded by the meter. As, according to the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 8
appellant, the first respondent had been undercharged due to
the meter not accurately recording the readings, a revised bill,
based on the average consumption of the respondent for the
period 2.2.1987 to 1.2.1988 i.e. for such period for which the
meters had recorded incorrect readings was raised. As the first
respondent did not pay the amount, a notice of disconnection
was sent to it on 25.10.1990 calling upon it to pay the amount
within a week, failing which the electricity supply would be
disconnected. The first respondent then challenged the notice of
demand and disconnection by filing a writ petition which was
dismissed by a learned Single Judge of the High Court on
17.8.1993. The Letters Patent Appeal preferred by the first
respondent was allowed by the Division Bench and the demand
notice was quashed.
The learned Single Judge held that it was for the consumer
(first respondent) to raise a dispute before the Electrical
Inspector under Section 26(6) of the Indian Electricity Act in
case he challenged or disputed the assertion of the appellant
that the meter was not recording correctly and was running
slow. Since the consumer did not raise any such dispute, the
appellant was entitled to replace the meter if the same was
defective and to raise a demand on the basis of average
consumption in the past period. The Division Bench has reversed
this view and has held that if the appellant disputed the
correctness of the meter, it should have referred the dispute to
the Electrical Inspector as provided in Section 26(6) of the Act
and it was for the Electrical Inspector to estimate the amount of
energy supplied to the consumer. The appellant having not
referred any such dispute to the Electrical Inspector and
consequently no estimate of the energy supplied by it to the first
respondent (consumer) having been made, it was not open to
the appellant to raise a bill on the basis of average of past one
year’s consumption. The Division Bench further held that the
demand notice was for a period exceeding six months
immediately preceding the date thereof and, therefore also, the
same was illegal.
The main question, which requires consideration, centres
around sub-section (6) of Section 26 of the Indian Electricity Act,
1910 __ whether the applicability of said provision is attracted to
the facts and circumstances of the present case and, if so, to
what extent?
The relevant parts of Section 26 of the Indian Electricity
Act, 1910 and Rule 57 of the Indian Electricity Rules, relevant for
the purpose of this judgment, are reproduced hereunder:-
The Indian Electricity Act, 1910
"26. Meters.- (1) In the absence of an agreement to
the contrary, the amount of energy supplied to a
consumer or the electrical quantity contained in the
supply shall be ascertained by means of a correct
meter, and the licensee shall, if required by the
consumer, cause the consumer to be supplied with
such a meter:
Provided that the licensee may require the
consumer to give him security for the price of a
meter and enter into an agreement for the hire
thereof, unless the consumer elects to purchase a
meter.
(2) xxx xxx xxx
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 8
(3) xxx xxx xxx
(4) The licensee or any person duly authorized by
the licensee shall, at any reasonable time and on
informing the consumer of his intention, have access
to, and be at liberty to inspect and test, and for that
purpose, if he thinks fit, take off and remove, any
meter referred to in sub-section (1); and, except
where the meter is so hired as aforesaid, all
reasonable expenses of, and incidental to, such
inspecting, testing, taking off and removing shall, if
the meter is found to be otherwise than correct, be
recovered from the consumer; and, where any
difference or dispute arises as to the amount of such
reasonable expenses, the matter shall be referred to
an Electrical Inspector, and the decision of such
Inspector shall be final:
Provided that the licensee shall not be at
liberty to take off or remove any such meter if any
difference or dispute of the nature described in sub-
section (6) has arisen until the matter has been
determined as therein provided.
(5) xxx xxx xxx
(6) Where any difference or dispute arises as to
whether any meter referred to in sub-section (1) is
or is not correct, the matter shall be decided, upon
the application of either party, by an Electrical
Inspect; and where the meter has, in the opinion of
such Inspector ceased to be correct, such Inspector
shall estimate the amount of the energy supplied to
the consumer or the electrical quantity contained in
the supply, during such time, not exceeding six
months, as the meter shall not, in the opinion of
such Inspect, have been correct; but save as
aforesaid, the register of the meter shall, in the
absence of fraud, be conclusive proof of such amount
or quantity:
Provided that before either a licensee or a
consumer applies to the Electrical Inspect under this
sub-section, he shall give to the other party not less
than seven days’ notice of his intention so to do.
(7) xxx xxx xxx
Explanation. __ A meter shall be deemed to be
"correct" if it registers the amount of energy
supplied, or the electrical quantity contained in the
supply, within the prescribed limits of error, and a
maximum demand indicator or other apparatus
referred to in sub-section (7) shall be deemed to be
"correct" if it complies with such conditions as may
be prescribed in the case of any such indicator or
other apparatus."
Indian Electricity Rules, 1956
"57. Meters, maximum demand indicators and
other apparatus on consumer’s premises. \026 (1)
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 4 of 8
Any meter or maximum demand indicator or other
apparatus, placed upon a consumer’s premises in
accordance with Section 26 shall be of appropriate
capacity and shall be deemed to be correct if its
limits of error are within the limits specified in the
relevant Indian Standard Specifications and where
no such specification exits, the limits of error do not
exceed 3 per cent, above or below absolute accuracy
at all loads in excess of one-tenth of full loads and
up to full load.
Provided that for extra high voltage consumers
the limit or error shall be 1 1 per cent.
(2) No meter shall register at no load.
(3) Every supplier shall provide and maintain in
proper condition such suitable apparatus as may be
prescribed or approved by the Inspector for the
examination, testing and regulation of meters used
or intended to be used in connection with the supply
of energy:
Provided that the supplier may with the approval
of the Inspector and shall, if required by the
Inspector, enter into a joint arrangement with any
other supplier for the purpose aforesaid.
(4) Every supplier shall examine, test and regulate
all meters, maximum demand indicators and other
apparatus for ascertaining the amount of energy
supplied before their first installation at the
consumer’s premises and at such other intervals as
may be directed by the State Government in this
behalf.
(5) Every supplier shall maintain a register of
meters showing the date of the last test, the error
recorded at the time of the test, the limit of accuracy
after adjustment and final test, the date of
installation, withdrawal, re-installation, etc. for the
examination of the Inspector or his authorized
representative.
(6) Where the supplier has failed to examine, test
and regulate the meters and keep records thereof as
aforesaid, the Inspector may cause such meters to
be tested and sealed at the cost of the owner of the
meters in case these are found defective."
The abovesaid provisions have been the subject-matter of
consideration by this Court in three cases which have been
brought to our notice. They are M.P. Electricity Board v.
Basantibai __ (1988) 1 SCC 23, Belwal Spinning Mills Ltd. &
Ors. v. U.P. State Electricity Board & Anr. __ (1997) 6 SCC
740 and J.M.D. Alloys Ltd. v. Bihar State Electricity Board __
(2003) 5 SCC 226. The first and the last of the cases are
decisions by three learned Judges and the second one is a
decision by two learned Judges. We have carefully perused the
three decisions and we find ourselves in entire agreement with
the view of the law taken in these cases. In particular, in
Belwal Spinning Mills’s case, this Court has examined the
provisions of Section 26, specially sub-section (6) thereof, in
very many details, also taking into consideration the legislative
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 5 of 8
intention and the object sought to be achieved by substituting
sub-section (6) by Act 32 of 1959 in its present form over the
predecessor provision. We would be referring to the relevant
findings of law recorded in these cases. However, at the outset
and here itself, we would like to mention that the applicability of
sub-section (6) of Section 26 is attracted only when the meter is
not correct. Section 26(6) will have no applicability (i) if the
consumer is found to have committed a fraud with the licensee
and thereby illegally extracted the supply of energy preventing
or avoiding its recording, or (ii) has resorted to a trick or device
whereby also the electricity is consumed by the consumer
without being recorded by the meter. In effect the latter class of
cases would also be one of fraud. Tampering with the meter or
manipulating the supply line or breaking the body seal of the
meter resulting in non-registering of the amount of energy
supplied to the consumer or the electrical quantity contained in
the supply - are the cases which were held to be not covered by
Section 26(6) in the case of Basantibai (supra), while the
provision was held applicable to any case of meter being faulty
due to some defect and not registering the actual consumption
of electrical energy. Similar is the view taken in the case of
J.M.D. Alloys Ltd. (supra).
What is a correct meter? The language of sub-section (6)
of Section 26 starts with __ "where any difference or dispute
arises as to whether any meter referred to in sub-section (1) is
or is not correct\005". The dictionary meaning of the word
"correct" is: Adhering or conforming to an approved or
conventional standard; Conforming to or agreeing with fact;
Accurate.
As to what would be a "correct" meter, there is sufficient
indication in the Act and the Indian Electricity Rules, 1956 in
the explanation given at the end of sub-section (7) of Section 26
of the Act and sub-rules (1) and (2) of Rule 57, quoted
hereinabove. Where the meter is completely non-functional on
account of any fault or having been burnt, it will not register the
supply of energy at all. Since a burnt meter does not record any
supply of energy, it virtually means "no meter".
What is contemplated by Section 26(6) is a running meter,
but which on account of some technical defect registers the
amount of energy supplied or the electrical quantity contained in
the supply beyond the prescribed limits of error. It contemplates
a meter which is either running slow or fast with the result that
it does not register the correct amount of energy supplied.
There is an additional reason for coming to such a conclusion.
Section 26(6) confers power upon the Electrical Inspector to
estimate the amount of energy supplied to the consumer or the
electrical quantity contained in the supply, during such time, not
exceeding six months, as the meter shall not, in the opinion of
such Inspector, have been correct. Where the meter is running
slow or fast, it will be possible for the Electrical Inspector to
estimate the amount of energy supplied to the consumer by
determining the extent or percentage of error in recording the
supply, whether plus or minus. However, where the meter is
burnt or is completely non-functional, such an exercise is not at
all possible. Therefore, Section 26(6) can have no application in
a case where a meter has become completely non-functional on
account of any reason whatsoever.
In Belwal Spinning Mills’s case, this Court has held inter
alia:-
(1) Any difference or dispute arising between the
licensee and the consumer, as to whether any meter
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 6 of 8
has recorded or is recording correct reading or not,
can be raised by either party and referred, upon the
application of either party, for decision by an
Electrical Inspector.
(2) If the Electrical Inspector comes to the finding that
the meter has ceased to be ’correct’, he has to
determine the quantum of electricity consumed for
the statutory period of six months, referred to in
sub-section (6). The determination made by the
Electrical Inspector on twin questions (i) whether
meter was correct or not, and (ii) if the meter was
not correct then the estimate of supply of electricity
to the consumer for the statutory period of six
months, is binding on the licensee and the consumer
(subject only to judicial review by a competent
Court).
(3) For any other period anterior to the statutory period,
the legislature has in no uncertain terms indicated in
the latter part of sub-section (6) that reading
registered in the disputed meter will not only be
presumed to be correct but such reading shall be
conclusive proof of the quantity of electricity
consumed or the amount of electricity supplied to
the consumer. For any period other than the
statutory period of six months, referred to in sub-
section (6), the legislature has intended by the
amendment of sub-section (6) of Section 26 (as
made by Act 32 of 1959) to put an end to such
contest between the licensee and the consumer and
has set at rest any dispute relating to any period
anterior to the statutory period on estimation by
providing that in a case of dispute as to functioning
of meter, the reading in the meter for the period
beyond the period of statutory estimation, will be
final.
(4) Any unilateral decision of either of the parties about
the correct status of the meter is not to be accepted
by the other party if the other party raises objection
as to the status of the meter.
(5) The estimate to be prepared by the Electrical
Inspector, on the dispute being referred to him, may
go only up to six months prior to the date of raising
the dispute and reference but such estimate will only
cover that period prior to raising the dispute during
which, according to the Electrical Inspector, the
meter had ceased to be correct.
(6) The estimate of supply of energy by the Electrical
Inspector is to be made for a period not exceeding
six months calculated backwards from the date of
reference to the Electrical Inspector. Thus, it is the
date of reference to Electrical Inspector which is
conclusive of the period of six months; the date of
inspection, the date of raising dispute and the date
of adjudication are immaterial. (Here, we may add,
that such period of six months shall apply).
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 7 of 8
The above said deductions, drawn in the case of Belwal
Spinning Mills, are accompanied by in-depth analysis of several
provisions of the Act, the historical background and practical
aspects of supply and consumption of electricity. As we find
ourselves in entire agreement with the abovesaid statement of
law, it is not necessary for us to make a detailed independent
discussion of our own of the reasons as the same is available in
the case of Belwal Spinning Mills.
In the present case, the demand raised by the appellant
against the first respondent can be divided into two parts: (i) for
the period during which the meter was burnt, and (ii) for the
period for which the meter was not correct. For the period for
which the readings could not be recorded or retrieved because
the meter was burnt there is nothing wrong in the licensee
having raised the demand based on the average consumption for
the similar period during the previous year. It is a reasonable
basis. Nothing has been brought on record by respondent No.1
to show or even suggest that any basis other than the one
adopted by the appellant could have been more reasonable and
more appropriate for calculating the quantity of electricity
consumed during the period of no-meter or no-meter-reading.
For the period for which, according to the appellant, the
meter was not correct, none of the parties has referred the
dispute to the Electrical Inspector. The meter though it is alleged
by the appellant to have remained not correct, readings have
been regularly recorded, bills raised and also paid by the
consumer-respondent No. 1. According to Section 26(6), the
readings would bind the appellant and respondent No. 1 both. It
has never been the case of the appellant at any stage that the
meter was not correctly recording the consumption of electricity
on account of being non-functional due to any fraud committed
or device or trick adopted by the consumer-respondent No. 1 or
that the body seal of the meter was found broken or tampered
with. The respondent No. 1 was accepting and honouring the
demands raised by the appellant and, therefore, respondent No.
1 cannot be expected to have raised a dispute and sought for a
reference for determination by Electrical Inspector. The appellant
could not have, therefore, revised the demand for such period
based on average consumption during the previous year. There
is yet another reason why the entitlement of the appellant to
recover charges from the respondent No. 1 may have to be
denied. According to the proviso appended to sub-section (4) of
Section 26, the licensee cannot take off or remove any such
meter as to which difference or dispute of the nature described
in sub-section (6) has arisen until the matter has been
determined by the Electrical Inspector. The purpose is to
preserve the evidence. The dispute shall be expeditiously
disposed of by the Electrical Inspector by applying scientific
method of investigation to find out if the meter was incorrect
and if so then what was the extent of error. In the present case,
the meters said to be incorrect have been removed and replaced
by the appellant. Admittedly, no dispute has been raised and
referred to the Electrical Inspector. The most material evidence
being the meter itself has been lost by the act of the appellant in
removing the incorrect meter. The appellant cannot be permitted
to take advantage of its own act and omission \026 the act of
removing the meter and the omission to make a reference to the
Electrical Inspector.
The material available on record before us does not enable
the separation of the impugned demand by bifurcating the same
into two on the criterion discussed hereinabove. The appellant
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 8 of 8
shall have to be left free to examine its records and then revise
its demand. We may clarify that the demand raised by the
appellant based on the average consumption during the similar
period in the last year is justified, in the facts and circumstances
of the present case, for the period for which the reading was lost
on account of the meter having been found burnt. Accordingly,
the calculation based on the record of consumption for the
corresponding period from the previous year shall hold good.
The appellant shall raise a demand accordingly and the first
respondent shall be bound to honour the same. So far as the
period for which the meter is said to be incorrect, the demand
has not been revised by basing it on the finding arrived at by the
Electrical Inspector and hence is not available to be revised.
The meter is alleged by the appellant to be not correct and yet
the appellant has not made a reference to the Electrical
Inspector under Section 26(6). The appellant cannot now be
allowed to raise an additional demand over and above the
demand raised through the bills which were issued for that
period and paid by the first respondent. The right to raise
additional bills stands lost by the appellant for its failure to
proceed in accordance with Section 26(6) of the Electricity Act,
1910.
We direct accordingly and dispose of the appeal in the
above terms with no order as to the costs.