Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 19
CASE NO.:
Appeal (civil) 5188 of 2001
PETITIONER:
Ganga Retreat & Towers Ltd. & Anr.
RESPONDENT:
State of Rajasthan & Ors.
DATE OF JUDGMENT: 19/12/2003
BENCH:
R.C. Lahoti & Ashok Bhan
JUDGMENT:
J U D G M E N T
With
CA No. 5189 and CA No. 5190 of 2001
BHAN, J.
Aggrieved by the judgment and order of the Division Bench of
Rajasthan at Jaipur in setting side the order of the Single Judge, thereby,
dismissing the writ petition filed by the appellants, the present appeals have
been filed. All the three appeals have been filed by the same set of
appellants and against the same judgment. As three separate appeals were
filed by the respondents before the Division Bench against the order of the
Single Judge the appellants have filed three separate appeals. They are taken
up for disposal by a common order.
The State of Rajasthan (hereinafter referred to as "the Respondent No.
1") decided to dispose of by public auction two prime properties situated in
the heart of Jaipur City. One of the properties was known as Dr. Helligs
Bungalow, near Khasa Kothi State Hotel, M.I. Road, Jaipur and the other
was a plot of land situated near Khasa Kothi known as the site of Food Craft
Institute building on M.I. Road, Jaipur. In the present case we are
concerned with the first property only. Respondent No. 1 issued
advertisement for auction of Dr. Helligs Bungalow, which was scheduled to
be held, according to the auction notification on 21.12.1994. In the
advertisement the property was described as free hold, ceiling free, vacant,
crest jewel property known as Dr. Helligs Bungalow (10,400 sq. yards). The
permitted use of the property was shown as hotel/commercial complex/hotel
cum-commercial complex. The terms and conditions for the auction were
also provided in the advertisement. Condition Nos. 7,8,9,10,12 and 13 relate
to the controversies involved in this litigation and are reproduced hereunder:
"7. Land measuring 1,400 sq. mtr. shall be
auctioned with the condition that the successful
bidder shall have to surrender a strip of land
measuring 6.2 sq. mtr. for the road
widening/parking of commercial vehicle free of
charges. He will be given the benefit in terms of
FAR, which is calculated on the basis of original
plot size.
8. Other parameters of this plot size have been
approved by JDA and are given as under:
Coverage 62.5% F.A.R.
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 19
F.A.R. 2.0
No of floors B + G + 4
Maximum permissible 16.76 Mtrs.
Height
Parking provision IPCU per 200 sq. mtr. of
built up area
Set backs
Front towards 15 mtrs. Station Front
towards roads.
Front towards 15 mtrs. Circuit House
7.5 mtr. Atal Ban (After
leaving 6.2 Mtrs. for
future road widening/
parking commercial
vehicle.
Rear 6 Mtrs. as indicated in
the plan.
9. The construction work on the plot should be
commenced with in one year from the date of
handing over of possession of the land and the
building. Building construction should be done
within 3 years. If the party wants further extension
beyond three years that shall be given against the
penalty of Rs. 20,000/- (Rupees twenty thousand)
p.m. but in no case the period shall be extended
more than 2 years.
10. After the full amount due against the plot as
deposited by the purchaser the Patta of the plot
will be issued in favour of the purchaser which
would enable him to start construction on the plot
in accordance to the approved plan and under
architectural control as per specifications given by
JDA.
12. The land shall be used for construction of
Hotel/Commercial Complex/Hotel cum
commercial complex only. If he uses this property
for other than this purpose, he would have to seek
prior permission from the Government of
Rajasthan against payment of charges as the
Government may fix thereof.
13. The purchaser shall have to strictly abide by
the parameters and set backs as laid down in
condition No. 8. Any violation of these terms and
conditions shall lead to the forfeiture of his right
on this property and hence the property shall stand
reverted to the Government without payment of
any compensation for the land and the building
thereupon."
M/s Ganga Retreat and Towers Ltd., a company registered under the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 19
Indian Companies Act, 1956 (formerly known as M/s Lok Hotels and
Resorts Limited), the appellants herein were declared as the successful
bidder in the auction held. The appellants’ bid of Rs. 19,56,76,000/- being
the highest was accepted and the property was knocked down in their favour.
The successful bidder, as per term No. 5, was required to pay the sale
consideration, as per the following schedule:-
"i) 10% of the final bid on the spot in cash or
through Demand Draft in favour of Director
of Estate, Rajsthan, Jaipur (the amount of
Rs. 20.00 lacs deposited as earnest money
shall be allowed to be adjusted against this
deposit of 10%).
ii) 15% amount of the final bid will have to be
deposited within 15 days from the date of
acceptance, letter sent to the successful
bidder by the Government of Rajathan.
iii) 75% amount of the final bid will have to be
deposited by successful bidder within 60
days of the notice for deposition of the full
and final amount of the bid amount which
the party shall be informed by the
Government of Rajasthan.
Failure to deposit it the aforesaid amount at any
state, i.e., (I), (ii) and (iii) above will result in
forfeiture of the amount already deposited by the
successful bidder and hence cancellation of the
bid."
The payment was not made as per schedule given above. The entire
sale consideration amounting to Rs. 19,56,76,000/- was paid on 16.5.1995.
As there was a delay in making the payment as per schedule the appellants
accepted their liability to pay interest for the delayed payment. A sum of Rs.
30,01,273/- towards interest for delayed payment was made. Last installment
of Rs. 83,562.72 P. towards the amount of interest was paid by demand draft
dated 21.08.1995. Total amount paid was Rs. 19,86,77,273/-. The cost and
expenses for registration of patta, stamp duty and all other incidental
expenses were also to be borne by the purchaser. Sale deed could not be
executed in favour of the appellants as the appellants did not furnish the
stamp papers. After repeated letters including the letter dated 21.05.1996
the appellants submitted the requisite stamp duty and registration charges
amounting to Rs. 1,19,25,720/- for execution of the sale deed on 18.12.1996.
Thereafter, the sale deed was executed and registered on 7.01.1997 and
immediately thereafter possession was delivered to the appellants. Term of
the auction notice that Floor Area Ratio (for short "FAR") would be 2.00
was also repeated in the sale deed.
The appellants thereafter applied for sanction of plans for putting up
construction on the property and the Planning Cell of the Jaipur Municipal
Corporation (for short "the JMC") demanded a deposit of Rs. 1,48,79,887/-
towards map approval charges. These charges were deposited under protest
by the appellants. According to the appellants the JMC had not framed any
Rules in this regard and that the charges were exorbitant and without
authority of law. The appellants also handed over 6.2 meters width of strip
land to the JMC of old Dr. Helligs bungalow as per their letter dated
2.5.1997 (Annexure IV).
On 11.4.1997, the Additional Director and Competent authority under
the Urban Land Ceiling and Regulation Act, 1976 (for short "the Ceiling
Act") issued a notice to the appellants under Section 38 of the Ceiling Act,
alleging that the appellants were holding land in excess of ceiling limits and
had not filed the return as required under Section 6 (1) read with Section 15
of the Act. The appellants replied to the aforesaid notice on 17.4.1997
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 4 of 19
pointing out that the Respondent No. 1 had sold the property as free from
ceiling limit and therefore, there was no need to file a return. As the
explanation was not accepted by the competent authority, the appellants
applied for exemption under Section 20 of the Act. The appellants also
submitted the return in the prescribed form with a covering letter dated
19.4.1997. On 3.5.1997 the Competent Authority issued a notice under
Section 8(3) of the Ceiling Act enclosing a draft statement as to vacant land.
Simultaneously, application filed under Section 20 of the Act for exemption
was processed. On 11.8.1997, the competent authority granted exemption to
the appellants on certain conditions. It was stipulated that the exemption
was being granted subject to the terms and conditions stated in the
conveyance deed dated 7.1.1997 and that it could be used only for the
purposes set out in the conveyance deed. It was also stipulated that for any
construction on the land, plans will have to be submitted for sanction to the
JMC and all the standards regarding construction shall be applicable as per
the norms of the JMC. Another condition put was that the land would not be
transferred or conveyed in any manner to any one without prior permission
of the State Government except offering it as security to the financial
institutions for raising loan. As this clause has given rise to the controversy
on which lengthy arguments have been addressed, the same is reproduced
below for reference:
"5) That the sale, gift or any transfer of the plot
will not be closed without prior approval of the
State Government. But mortgaging the property to
financial institution for taking loan without parting
with the possession the State Government will
have objection."
On 24.6.1996 the Jaipur Development Authority (for short "the JDA")
revised its bye-laws. The revised building Bye-laws came into force w.e.f.
24.6.1996 in which parameters in respect of commercial hotels and
commercial plots were amended. Vide Regulation No. 9.3.3 of the 1996
Regulations the FAR was reduced to 1.75 instead of 2.00 as provided by the
Bye-laws of 1989.
Appellants submitted their building plans as per FAR 2.00. JMC on
22.2.1997 approved the building plans subject to FAR 1.75 only as per 1996
Bye-laws as against FAR 2.0 permitted by the auction notice and the
conveyance deed. On 10.10.97, after getting the land exempted from
ceiling, the Company wrote to the JMC to re-examine the case and allow
FAR 2.0 on the appellants’ re-submitting the plans for approval or in the
alternative to advise the General Administration Department to refund the
proportionate amount consequent upon the reduction in the FAR.
On 28.10.1997, the appellants wrote a letter to the Minister for Urban
Development, Government of Rajasthan, for intervening in the appellants’
favour in their dispute with the JMC which was not allowing FAR 2.0 as
promised in the terms of auction and the sale deed. Appellants also wrote a
letter to the Chief Minister on 17.11.1997 for intervention in the matter and
for ordering the Secretary, Urban Development and Housing to clear the
plans with FAR 2.0 as a special case urgently. On 18.12.1997 again, a
communication was addressed by the appellants to the Chief Secretary
giving the following three proposals:
"(A) to instruct Jaipur Nagar Nigam to allow
F.A.R. 2 as per Auction conditions. As F.A.R. 2
existed before the new Byelaws came into force in
September, 1996. Plus to pay interest at 18% p.a.
for delayed period to clear our plans as
compensation. The delayed period may be
calculated from the day we deposited our plans for
approval to the day the plans are approved. We
have paid interest on account of delay from our
side.
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 5 of 19
(B) To refund the whole amount with interest,
the registration cost, the maps approval charges,
the L.B.T. charges etc.
(C) To refund proportionate charges on all
above for the reduced F.A.R. from 2 to 1.75 i.e.
12.5% all above charges."
It was also stated in this letter that if no response was received to the
proposals in writing within fifteen days, the appellants shall go to the court
of law for redressal of their grievances. On 22.10.1997 the Chief Secretary
wrote to the Urban Development and Housing Department recommending
the case of the appellants for grant of FAR 2.0 instead of FAR 1.75 in
compliance with the conditions of the auction. As no decision was taken,
the appellants filed S.B.Civil Writ Petition No. 195/98 against the State of
Rajasthan, Jaipur Development Authority, Jaipur Municipal Corporation
amongst others, who were officers of the State Government, claiming the
following reliefs.
"In the premises aforesaid the writ petition of the
petitioner may kindly be allowed with costs and by
an appropriate writ, order or direction, the Hon’ble
Court may be pleased to:
(a) declare that on account of the reasons set out
herein and the order dated 9th September,
1997 passed by the Municipal Corporation,
referring to approve maps upto 2.0 FAR the
contract of sale of the property described in
this petition vide sale deed dated 7th Jan.,
1997 stands frustrated or has become
impossible of performance or invalid
rendering the sale deed dated 7th Jan., 1997
void.
(b) declare that the Regulations of 1996 were
not applicable to the petitioner and the same
cannot be enforced against the petitioner by
the Municipal Corporation, Jaipur or JDA in
view of the sale deed dated 7th Jan., 1997.
(c) declare that the sale deed being a
government grant was not required to be
registered and no stamp duty was required to
be paid and consequently the petitioner is
entitled to the refund of the stamp duty and
the registration charges.
(d) direct the respondents jointly and severally
to pay to the petitioner a sum of Rs.5102.94
lakhs alongwith future interest @ 18.5% per
annum.
Any other appropriate writ order or direction
which may be considered just and proper in the
facts and circumstances of the case may kindly
also be issued in favour of the Petitioners."
On issuance of notice the respondents put in appearance and filed
their replies. Apart from contesting on merits, preliminary objections were
raised regarding maintainability of the petition on the ground that
declaratory relief claimed could not be granted in the writ jurisdiction. It was
also contended that the reliefs claimed pertained to the concluded contract
with regard to the sale of property culminated by execution of the sale deed.
That the relief being claimed was based on breach of contract and the writ
petition was not the appropriate remedy for redressal of such grievances. No
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 6 of 19
petition could be entertained for either specifically enforcing the contract
or/and for compensation for breach of contract. That the highly disputed
questions of fact were involved which could not be adjudicated without
adducing evidence. Such disputed questions of fact could not be adjudicated
by the High Court in exercise of its extra-ordinary jurisdiction under Article
226 of the Constitution of India.
Learned Single Judge rejected the preliminary objections regarding
the maintainability of the petition and declared that the sale deed was
statutory in nature. It was a grant as well. The rights and the obligations as
incorporated in the sale deed were statutory in character as regards the rights
and obligation of the parties. No change could be effected thereafter on any
pretext whatsoever in regard to the reducing the FAR from 2.0 to 1.75. In
the auction notice property was described as free hold and ceiling free. The
action of the State in not acting upon the assurance given amounted to a
fraud, which invalidated the sale. Consequently, the learned Single Judge
declared that the auction sale held on 21.12.1994 and the consequent sale
deed dated 7.1.1997 were null and void having no legal sanctity. The
contract was frustrated. All consequent actions taken by either of the parties
pursuant to the auction and the sale deed were invalidated and the appellants
were declared entitled to be restituted to the original position as it existed
prior to the date of auction and execution of the sale deed. Consequently,
the respondents were directed to refund to the appellants, the payments
received by the respective respondents, pursuant to any term of the auction
dated 21.12.1994 which included the entire sale considerations as mentioned
in the sale deed dated 7.1.1997 along with all other payments made to the
respondents by the appellants towards stamp duty, registration charges, land
and building taxes etc. with interest @ 18% per annum calculated from the
date of receipt of such amount by the respective respondents till the date of
actual refund to the appellants. It was also directed that the JMC shall
refund all payments made by the appellants towards building map approval
charges, additional constructed area charges, licence fee, inspection charges,
etc. along with interest @ 18% per annum from the date of receipt of said
payments by the appellants till the date of actual refund to the appellants. As
regards the damages claimed by the appellants for the incomplete
construction which by that time had been raised upto 9 stories (which was
held to be under compulsion), it was directed that it would be advisable that
the State of Rajasthan constitutes an expert Committee consisting of the
Chief Engineer PWD and Director, Town Planning Department or any other
officer having expertise to assess the value at the PWD rates and value the
construction on the site and after such valuation made by the Committee, the
amount assessed be refunded to the appellants within forty five days of the
assessment.
As directed by the learned Single Judge, a Valuation Committee was
constituted by the State Government and the value of the construction as per
PWD rates was assessed at Rs. 9,97,51,003/-. From this amount, 10% was
deducted by the Committee as contractor’s profit, which was included in the
analysis of BSR rates. After deducting 10% amount, i.e., Rs. 99,75,100/-
amount payable to the appellants representing the construction on the land
was worked out by the Committee at 8,97,75,903/-.
Aggrieved by the aforesaid order of the learned Single Judge, appeals
were preferred before the Division Bench which were accepted. It was held
that the sale of land by way of auction was neither statutory nor by way of
grant. Consequently, it was held that the rights and obligations incorporated
in the sale deed were not statutory in character. That it was a completed
contract in which highly disputed questions of fact were involved which
could not be adjudicated upon by the High Court in exercise of its writ
jurisdiction. It was left open to the appellants to seek their remedy in the
Civil Court, if so advised.
At the outset, we may state that Shri Shanti Bhushan, learned senior
counsel appearing for the appellants fairly conceded that he would not be
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 7 of 19
able to support the findings recorded by the Single Judge to the effect that
the rights and obligations incorporated in the sale deed were statutory in
character or that the sale of land by Respondent No. 1 to the appellants were
by way of grant. He accepted the findings to the contrary recorded by the
Division Bench in this regard.
Before taking up the contentions raised on the merits by the counsel
for the parties we would like to briefly refer to the question regarding the
maintainability of the writ petition in contractual matters. Challenging the
finding recorded by the Division Bench regarding the maintainability of the
writ petition it was contended on behalf of the appellants that there is no
absolute bar to the maintainability of the writ petition in contractual matters.
Maintainability or otherwise in contractual matters is but an aspect of the
existence of equally efficacious alternative remedy. The power to entertain
a writ petition under Article 226 even in contractual matters is plenary but
actual exercise of jurisdiction in a particular case would be discretionary and
such discretion in turn is exercisable on sound judicial principles. This
Court in appropriate cases has entertained the writ petitions in contractual
matters and interfered to grant the relief deemed fit keeping in view the
facts of the case. No cause can be adjudicated without reference to some
facts and mere enquiry into facts, as those emerging from a limited set of
admitted facts does not in any manner act as a bar to the exercise of writ
jurisdiction. In the present case the entire case centers around roughly 25
undisputed documents. The question of leading oral evidence does not arise
and no intricate interpretation of documents or complicated inquiry into facts
is warranted. So far as the issue as to assessment of value of the structure
standing on the property is concerned the same stands covered by a detailed
factual report quantifying the precise valuation. Based on the inferences to
be drawn from documents, the questions of what relief, if any, this Court
considers fit to grant, and how, if at all, such relief is to be tailored to suit the
facts and circumstances of the case, are to be answered.
As against this, Mr. Harish Salve, learned senior counsel appearing
for the respondent-State submitted that the contention that contractual
disputes can be raised in proceedings under Article 226 is misconceived.
The remedy under Article 226 is a remedy in public law, and, therefore in a
remedy by way of judicial review, what is amenable to challenge is the
decision making process and not the decision itself. According to him, the
actions of the Government in contractual field, in rare cases, may be
questioned as being arbitrary or unreasonable being violative of Article 14 of
the Constitution but that does not mean that the Court is required to examine
a completed contract of sale of property being void or otherwise. That the
points involved in the writ petition are highly disputed questions of fact
which cannot be decided without taking evidence and therefore the Division
Bench was right in non-suiting the appellants on the ground of non-
maintainability of the writ petition and leaving it open to the appellants to
work out their remedy in the Civil Court.
Although prima facie we are in agreement with the view taken by the
High Court that the petition involves disputed questions of fact in relation to
a completed contract of sale of land which cannot be adequately adjudicated
upon in exercise of writ jurisdiction, but, despite holding that the disputed
questions of fact are not be adjudicated in exercise of writ jurisdiction, yet
we are not inclined, in the exercise of power under Article 136 of the
Constitution to dismiss the appeal on this account at this stage because that
is likely to result in the miscarriage of justice on account of lapse of time
which may now result in the foreclosure of all other remedies which could
be availed of by the appellants in the ordinary course. At the present stage
of the proceedings the alternative remedy of filing the suit would not be
efficacious. This Court in a number of cases, even after recording a finding
that the writ petition was not maintainable and that the High Court ought
not to have entertained it, has declined to interfere on the ground of non-
maintainability where it is found, that the matter has been pending for long
and/or the High Court has already entertained the writ petition [albeit
wrongly] and/or when to send the writ petitioner back would cause grave
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 8 of 19
delay or harassment. In such cases this Court has proceeded to decide the
dispute on merits. For this, we may refer to a recent decision of this Court in
Kerala State Electricity Board & Anr. Vs. Kurien E. Kalathil & Ors.,
2000 (6) SCC 293, in which this Court observed:
"12. Ordinarily, in view of the aforesaid
conclusions on the first contention, we would have
allowed the appeal and directed dismissal of the
writ petition (OP No. 283 of 1995) without
examining the second contention. However,
despite holding that the disputes in question could
not be agitated in a writ petition and thus the High
Court wrongly assumed jurisdiction in the facts of
the case, yet we are not inclined in the exercise of
our power under Article 136 of the Constitution, to
dismiss the writ petition of the contractor at this
stage because that is likely to result in the
miscarriage of justice on account of lapse of time
which may now result in the foreclosure of all
other remedies which could otherwise be availed
of by the contractor in the ordinary course. Those
remedies are not efficacious at the present stage
and, therefore, in view of the peculiar
circumstances of the case, we have examined the
second contention and the factors which weighed
with the High Court in granting relief. "
Keeping in view the peculiar facts of the case and the fact that it will
not be a sound exercise of judicial discretion to relegate the petitioners to
recourse to the alternate remedy of civil suit belatedly at the present stage,
we proceed to examine the dispute on merits .
The case of the appellants are that the conveyance deed is liable to be
cancelled and set aside on the ground that it is vitiated by misrepresentations
made on behalf of the Respondent, on account of which the appellants were
wrongly induced to enter into the contract and that the conveyance was
entered into by mistake. The misrepresentation alleged is on account of :
(a) the FAR of the property being 1.75 whereas it was described
as 2.00 in the auction notice as well as conveyance deed;
and
(b) the property was, in the auction notice, described as "free
hold and ceiling free" whereas the appellants were
compelled to apply for exemption from land ceiling which
procedure involved some delay. While giving exemption
from the provisions of Chapter III of the Ceiling Act a
condition was put that the plot would not be "sold, gifted or
transferred" without prior approval of the State Government
which was onerous as well as contrary to the auction notice.
The land in dispute was not ceiling free as was represented
in the auction notice and that the condition put in the
exemption letter that the property would not be alienated
without prior permission of the Government made the
property not to be free hold as well.
Elaborating the first point, it was submitted that the appellants
purchased the property on a representation made to them, that the FAR was
2.0 and the property was free hold as well as ceiling free. The appellants
were persuaded to make the bid as a result of such misrepresentation by the
Government in the auction notice. The contract could not be said to have
been made by the consent of the parties under Section 10 and became
voidable at the option of the appellants under Section 19 of the Indian
Contract Act. That the contract was frustrated and incapable of being
performed in terms of Section 56 of the Indian Contract Act. That the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 9 of 19
appellants have almost come to ruination because of the action of the
respondents in as much as they have invested huge sums of money after
borrowing from the Bank at high rates of interest without any return for the
last so many years. As against this the case put forth on behalf of the
respondents is that there was no misrepresentation as alleged. On the date
on which the contract was entered into, i.e., the date on which auction went
in favour of the appellantss there was no misrepresentation even as alleged
by the appellants since the FAR on that date was 2.0. The FAR was
changed by virtue of change in law, which could not have been envisaged at
the time the contract was entered into. The delay in the execution of the
conveyance deed was pre-dominantly on account of causes attributable to
the appellants. That the appellants having got executed and accepted the
conveyance even after the reduction of the FAR voluntarily or without
demur and having raised construction clearly declared their intention to
proceed with the contract which is inconsistent with the plea that they had
the intention to rescind the contract. Having declared their intention to
proceed with the contract the appellants were bound by their affirmation.
Having affirmed the contract they cannot go back on their affirmation and
seek rescission of the contract. That the contention in relation to frustration
is misconceived as Section 56 of the Indian Contract Act does not apply to
the cases of completed transfer.
From the pleadings of the parties it is clear that the appellants gave
their bid in the auction for sale of the property on the terms and conditions as
contained in the auction notice which included the parameters approved by
the JDA for construction of building complex set out in Clause (8)
providing for FAR 2.0. Appellants paid the price inclusive of interest for the
delayed payment amounting to Rs. 19,86,77,273/- and got the sale deed after
paying the requisite stamp duty and registration charges, executed on
7.1.1997 and got the physical possession of the auction property vide
possession letter dated 7.1.1997. After receiving the possession the
appellants submitted the plans for construction of Hotel-cum-Commercial
Complex to the JMC on 27.1.1997 for approval. The Building Plans
Committee of the JMC on 20.2.1997 approved the plans with the
modification of FAR from specified FAR 2.0 in the sale deed to 1.75 only.
It was stated that this modification of FAR by the JMC was because of the
Buildings Regulations/Bye Laws of 1996 which came into force w.e.f.
28.6.1996. Even after approval the JMC did not release the plans till
charges for approval of plans were paid. The appellants deposited a sum of
Rs. 1,48,78,887/- for the approval of the plans with the JMC on 21.4.1997
and after receiving the approved plans the appellants commenced the
construction activities which according to the appellants were without
prejudice to their rights and the belief that the remaining FAR would be
approved.
From these facts what emerges is that on 21.12.1994, the date on
which the auction went in favour of the appellants there was no
misrepresentation even as alleged by the appellants since the FAR on that
date was 2.0. The FAR was changed by virtue of change in the law. As per
term No. 5 of the auction notice the successful bidder was required to
deposit 10% of the final bid on the spot in cash or through Demand Draft in
favour of the Director of Estate, Rajsthan. 15% of the amount of the final
bid was required to be deposited within 15 days from the date of acceptance
and the remaining 75% of the amount of the final bid was to be deposited by
successful bidder within 60 days of the notice for deposit of the said bid
amount on being informed by the Respondent. Failure to deposit the amount
as per the above stipulation could result in forfeiture of the amount already
deposited by the successful bidder and result in cancellation of the bid. The
appellants did not deposit the amount as per schedule of payment set out in
the auction notice. The entire sale consideration amounting to Rs.
19,56,76,000/- was paid on 16.5.1995. A sum of Rs. 30,01,273/- towards
interest for delayed payment (to the payment of which the appellants agreed)
was also paid. The last payment of Rs. 83,562.72 P. towards amount of
interest was made by demand draft dated 26.09.1995. The cost and expenses
for registration of patta, stamp duty and all other incidental expenses were to
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 10 of 19
be borne by the purchaser. The sale deed could not be executed in favour of
the appellants as the appellants did not furnish the stamp paper on which the
sale deed was to be executed. After repeated letters including the letter
dated 21.05.1996 the appellants submitted the requisite stamp duty and
registration charges amounting to Rs. 1,19,25,720/- for execution of the sale
deed on 18.12.1996. Thereafter, the sale deed was executed and registered
on 7.01.1997 and immediately thereafter the possession was delivered.
These facts demonstrate that delay in the execution of the conveyance was
principally on account of the reasons attributable to the appellants. In the
meantime the FAR was changed by virtue of a change in the law. The 1989
Bye-laws were changed by Bye-laws of 1996 which came into force w.e.f.
28.6.1996. As per these bye-laws FAR was changed from 2.0 to 1.75. Had
the appellants made the payments as per schedule of the payment given in
the auction notice and submitted the requisite stamp duty the conveyance
deed would have been executed prior to the amendment in law. The
appellants by their letter dated 18.12.1996, i.e., after the reduction of the
FAR requested the respondent to execute the conveyance. This was done
despite knowledge of reduction of FAR. Request made to the respondent
on 18.12.1996 for execution of the conveyance deed despite having
knowledge of the reduction of the FAR clearly shows that the plea of
misrepresentation or mistake on account of change of FAR is not made out
on the admitted facts.
It was then contended on behalf of the appellants that in the
conveyance deed the FAR was again mentioned as 2.0 and at that stage
there was a clear misrepresentation by the respondent. To establish
misrepresentation on this count the reliance was placed on the provisions of
the Indian Contract Act. There is no force in this submission. Statement
about the existing state of the law innocently made cannot constitute
misrepresentation if it is later found that the statement was erroneous. This
would be particularly so where the other party to whom the statement is
made is aware of or has the ability to conveniently apprise itself of the
correct state of the facts and the law applicable. Assuming (but without
holding) that there was some misrepresentation the appellants had a couple
of remedies, i.e., to either rescind the contract or seek restitution or to affirm
the contract without prejudice to their right to seek damages by way of
restitution for the loss caused by the misrepresentation. It is apparent that
the appellants did not rescind the contract or seek restitution by way of
damages. Instead they affirmed the contract which is clear from the fact
that they immediately commenced construction on the land even though the
building plans were on FAR 1.75. Affirmation of the contract and
proceeding with the construction clearly indicates that the appellants did not
rescind the contract nor reserved their right to seek restitution by award of
damages; or seek restitution rather they affirmed the contract and went ahead
with it.
It was then argued that the appellants had to start construction
immediately as a very strict stipulation was contained in the auction notice
(Condition No. 9). It was also represented in the sale deed that construction
work on the plot should be commenced within one year from the date of
handing over the possession of the land and the construction of building
should be completed within 3 years. The extension beyond 3 years was to
be given subject to payment of a penalty of Rs.20,000/- per month but in no
case the period would be extended beyond 2 years. Clause 13 of the terms
of the auction also provided that any violation of any terms and conditions
would lead to forfeiture of purchase of right of the property and the property
would stand reverted to the government without paying any compensation
for the property. Because of the condition contained in clauses 9 and 13 of
the terms of auction the appellants inspite of having knocked the doors of the
court had to start with the construction otherwise they ran the risk of their
right to the property being forfeited. We do not find any merit in this
submission. At the time of initiating the legal proceedings in the Court, it
was open to the appellants to either affirm the contract without prejudice to
their right seeking damages by way of restitution for loss caused by alleged
misrepresentation or to rescind the contract by getting the declaration that
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 11 of 19
the contract was not binding on the appellants. The appellants elected the
first option. Had the appellants rescinded the contract and prayed for
declaration that the contract was not binding on them, then, on its being so
declared, terms 9 and 13 of the auction notice would not have bound the
appellants in any way. The court while granting the relief could have
moulded the relief according to facts and situation prevalent. It would not
have in any way affected the appellants. The appellants cannot be permitted
to sit on the fence in indecision and take a chance. By putting up the
construction of basement and the other floors above the appellants have
encumbered the property. The respondent cannot be fastened with the
liability to pay for the construction put up by the appellants with full
knowledge of true facts.
The appellants have founded their case on the plea of avoidance of
contract as vitiated by misrepresentation on the part of respondents or
mistake on the part of the appellants or in the alternative, on the ground of
frustration. Let us test if the appellants have any legs to stand on, on either
of the pleas.
Misrepresentation is defined in Section 18 of the Contract Act.
Effect of mistakes is dealt with by Sections 21 and 22 of the Contract Act.
According to Section 19 of the Contract Act when consent to an
agreement is caused by misrepresentation, the agreement is a contract
voidable at the option of the party whose consent was so caused. The latter
may, if he thinks fit, insist that the contract shall be performed and that he
shall be put in the position in which he would have been if the
representations made had been true. According to Section 2 clause (i), an
agreement which is enforceable by law at the option of one or more of the
parties thereto, but not at the option of the other or others, is a voidable
contract. It is not necessary for us to record a clear finding whether there
was a misrepresentation on the part of the respondents or not. Suffice it to
observe that a voidable contract confers the right of election on the party
affected to exercise its option to avoid the legal relations created by the
contract or to stand by the contract and insist on its performance. However,
his election to stand by the contract once exercised would have the effect of
ratification of the contract with the knowledge of misrepresentation on the
part of the other party and that would extinguish its power of avoidance. In
the very nature of the right conferred on the party affected, the law expects it
to exercise its option promptly and communicate the same to the opposite
party; for until the right of avoidance is exercised, the contract is valid, and
things done thereunder may not thereafter be undone.
A right to rescind for misrepresentation can be lost in a variety
of ways, some depending on the right of election. A representee on
discovering the truth loses his right to rescind if once he has elected not to
rescind. But he may lose even before he has made any election where by
reason of his conduct or other circumstances it would be unjust or
inequitable that he retains the right. For instance where third parties have
acquired rights under the contract; again where it would be unjust to the
representor because it is impossible to restore him to his original position.
Restitutio in integrum is not only a consequence of rescission, its
possibility is indispensable to the right to rescind. Again, delay in election
may make it unjust that the right to elect should continue. For this reason
the right to rescission for misrepresentation in general must be promptly
exercised. (See, Indian Contract and Specific Relief Acts - Pollock and
Mulla, Eleventh Edition, Volume I, pp. 269-270).
Chitty on Contracts (Volume I, Twenty-Eighth Edition 1999,
para 25-003) states - "Once the innocent party has elected to affirm the
contract, and this has been communicated to the other party, then the choice
becomes irrevocable. There is no need to establish reliance or detriment by
the party in default. Thus the innocent party, having affirmed, cannot
subsequently change his mind and rely on the breach to justify treating
himself as discharged".
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 12 of 19
Under Section 20 of the Contract Act, a mistake of fact avoids
the agreement when both the parties to an agreement are under a mistake as
to a matter of fact essential to the agreement. It is necessary that both the
parties should be under a mistake. On the appellants’ own showing, the
respondents were not under mistake; according to the appellants, the
respondents knew the correct facts and yet misrepresented. The appellants
pleadings of misrepresentation and mistake in the alternative, in the facts
and circumstances of the case, are mutually destructive. Under Section 21 a
contract is not voidable because it was caused by a mistake as to any law in
force in India. The appellants cannot rely on the pleading of mistake of their
part or misrepresentation on the part of the respondents as to the
applicability of Urban Ceiling Law and FAR as provided by the bye-laws,
both being the laws in force in India. Here again, the vitiating effect of
alleged mistake shall stand obliterated no sooner it is found that the
appellants have, in spite of the so-called mistake being discovered, yet,
chosen to stand by the contract, ratifying the same by their conduct and went
ahead to exercise the rights which accrued to them under the same contract
which they are pleading to be vitiated by the mistake.
The doctrine of frustration, as applicable in India in contracts
stands, codified in Section 56 of the Contract Act. It provides :
56. An agreement to do an act
impossible in itself is void.
A contract to do an act which, after
the contract is made, becomes impossible,
or, by reason of some event which the
promisor could not prevent, unlawful,
becomes void when the act becomes
impossible or unlawful.
Where one person has promised to do
something which he knew, or, with
reasonable diligence, might have known,
and which the promisee did not know to be
impossible or unlawful, such promisor must
make compensation to such promisee for
any loss which such promisee sustains
through the non-performance of the promise.
The doctrine was so enunciated by this Court in Satyabrata
Ghose Vs. Mugneeram Bangur and Co. and Anr.- 1954 SCR 310 :
"The first paragraph of the section
lays down the law in the same way as in
England. It speaks of something which is
impossible inherently or by its very nature,
and no one can obviously be directed to
perform such an act. The second paragraph
enunciates the law relating to discharge of
contract by reason of supervening
impossibility or illegality of the act agreed
to be done. The wording of this paragraph is
quite general, and though the illustrations
attached to it are not at all happy, they
cannot derogate from the general words used
in the enactment.
This much is clear that the word
"impossible" has not been used here in the
sense of physical or literal impossibility.
The performance of an act may not be
literally impossible but it may be
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 13 of 19
impracticable and useless from the point of
view of the object and purpose which the
parties had in view; and if an untoward
event or change of circumstances totally
upsets the very foundation upon which the
parties rested their bargain, it can very well
be said that the promisor finds it impossible
to do the act which he promised to do.
In M/s Alopi Parshad and Sons. Ltd. Vs. Union of India -
(1960) 2 SCR 793, this Court clarified that the courts have no power to
absolve a party from liability to perform a contract merely because the
performance becomes onerous; the expressed covenants in a contract cannot
be ignored only on account of unexpected and uncontemplated turn of
events after the contract. However, a consideration of the terms of the
contract in the light of circumstances, when it was made, shows that the
parties never agreed to be bound in a fundamentally different situation which
unexpectedly emerges, the contract ceases to bind at that point, not because
the Court in its discretion considers it just and reasonable to qualify the
terms of the contract but because on its true construction it does not apply in
that situation. Here again, it has to be noted that the doctrine of frustration
can only apply to executory contracts and not the transactions which have
created a demise in praesenti (See, H.V. Rajan Vs. C.N. Gopal and Ors. -
AIR 1975 SC 261, 265). In Raja Dhruv Dev Chand Vs. Harmohinder
Singh & Anr., (1968) 3 SCR 339, their Lordships held - "There is a clear
distinction between a completed conveyance and an executory contract, and
events which discharge a contract do not invalidate a concluded transfer".
In the auction notice it was represented that the land in question was
freehold as well as ceiling free. The Ceiling Act does not apply to the
Government lands. It is admitted before us, that the government was aware
(though it may have had the intention right from the beginning to exempt the
land from the Ceiling Act) that the land which was being auctioned was not
exempted from ceiling and the exemption could only be granted after the
transfer of the land to a private person. The appellants received a notice
under Section 38 of the Ceiling Act informing that they own excess land in
Jaipur City as prescribed under Section 4 of the Urban Land Ceiling Act and
had not submitted their return under Section 6 read with Section 15 within
the prescribed period. Appellants were directed to appear before the
competent authority on 17.04.1997 to explain why action should not be
taken against them under Section 38 of the Act. Soon after the receipt of
the said letter, the appellants applied for exemption under the Act which was
granted promptly on 11.8.1997. Exemption was given subject to various
conditions which were imposed by the exemption order. It was stated that
para-meters of the Jaipur Municipal Corporation regarding construction
would be applicable. According to the appellants this virtually amounted to
unilaterally reducing the FAR 2 to FAR 1.75. The second condition was that
the plot will not be transferred without prior approval of the State
Government even though the property could be mortgaged to financial
institutions for taking loan without parting with possession. According to
the appellants, imposition of these conditions were contrary to the
representation contained in the auction advertisement that the property was
freehold. It was argued that it is well known that the transfer of freehold
property is freely transferable and does not require any permission. In
imposing such condition the government was taking away the freehold
character of the property. The representation that the property was ceiling
exempted was a very material representation which had induced the
appellants to offer a very high bid. That the action of the State in making a
representation that the property was ceiling free, although it knew that there
was a ceiling limit not only amounted to misrepresentation under Section 18
of the Indian Contract Act but in fact amounted to fraud because any
representation with knowledge that the representation was not true would
amount to fraud. It was argued that the contract having been induced by
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 14 of 19
misrepresentation, it was open to the appellants to avoid the contract under
Section 19 of the Contract Act.
Per contra, it was contended on behalf of the respondents that so far as
the order dated 11th August, 1997 under the Ceiling Act, imposing certain
conditions, is concerned, the stand of the State has always been that it is not
going to enforce any of these conditions. That even today the stand of the
State is that it is not going to enforce any of the conditions as imposed in the
exemption order.
Other aspects of the plea founded on Section 19 of the Contract Act
have already been dealt with hereinbefore.
So far as the Ceiling Act is concerned, the Act itself has been repealed
by the Notification dated October 7, 1999 as published in the Rajasthan
Gazette dated October 11, 1999. With the repeal of the Ceiling Act, all
proceedings under the Ceiling Act have abated. Reference may be made to a
decision of this Court in Pandit Madan Swaroop Shrotiya Public
Charitable Trust vs, State of U.P. & Others, 2000 (6) SCC 325.
So far as the order dated 11th August, 1997 under the Ceiling Act is
concerned, the stand taken by the State through out has been that it is not
going to enforce any of those conditions. It was so submitted by the learned
Advocate General while appearing for the State of Rajasthan before the High
Court. The aforesaid fact is admitted by the appellants themselves in their
memo of appeal [Ground (u)]. Even today, the stand of the State is that it is
not going to enforce any of those conditions as imposed under the exemption
order. This apart the process for obtaining exemption from land ceiling did
not in any manner affect the appellants for the reason that their plans were
sanctioned even before the question was raised as to the application of the
Urban Land Ceiling Act to the property. The appellants as per their letter,
couched as representation, dated 10.10.1997 had started digging for the
basement in February, 1997 immediately upon the sanction of building
plans. The process of construction began immediately. Thus, the condition
imposed in the exemption order were not an impediment in any manner It
is appellants’ own case that they had started construction of a multi-storeyed
complex upon the property which clearly implies that the appellants had
never the intention of the transferring the land as plots and therefore the
condition inhibiting the transfer of plots was irrelevant so far as the
appellants are concerned.
It is the appellants who delayed the payment of sale consideration on
the dates stipulated for payment. For the period of delay they agreed to pay
interest to the State Government voluntarily; they voluntarily paid stamp
duty and bore registration charges as stated above in the end of December,
1996 and got the sale deed executed on 7th January, 1997 on which date the
possession was delivered to them and thereafter they voluntarily paid the
charges for the approval of building plans with FAR 1.75 and proceeded
with construction work for establishing Hotel-cum- Commercial Complex
by demolition of existing structure of Dr. Hellings Bunglow standing on the
land in question, levelling the same, digging deep foundation, constructing
basement and thereafter further raising construction of ground floor and
other floors. They cannot now be permitted to turn round and claim refund
of any amount which they allege to have spent including the claim for the
interest. The appellants have voluntarily paid the entire money, entered into
possession, raised construction and incurred expenditure voluntarily and as
such they are not entitled to any refund or any claim and declaration as such
on the ground of frustration or impossibility of performance of the contract.
Every contract including one by auction is subject to provisions of
law. Whenever any action is taken in performance of a contract, it must
conform to the law in force at the time when action is taken. In the instant
case when the appellants applied for approval of building plans it is the law
that is in force at that time, which would be applicable. Doctrine of
promissory estoppel is not available when any action is desired to be taken
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 15 of 19
in contravention of the provisions of law. The terms and conditions of the
sale as announced when the property was put to sale were in accordance
with law and no guarantee was given (nor could have been given) that the
law would not change, or that the terms and conditions would be
enforceable even in violation of law which may be in force. FAR was a
matter of law and the FAR was fixed either by the JDA or JMC in exercise
of its statutory powers. The contract when entered into, the FAR approved
by JDA was 2 and its subsequent reduction in 1996 to 1.75 would not
invalidate the contract or by treating as a breach of the contract nor can it be
treated by the Government.
In reply to the contention raised on behalf of the State
Government that the appellants having failed to rescind the contract
immediately on coming to know of the breach or misrepresentation by the
government, it could not exercise their right of rescinding the contract under
Section 39 or avoiding under Section 19 of the Contract Act later on, it was
submitted on behalf of the appellants that this contention of the State
Government was devoid of any force. According to the appellants the legal
right to avoid a contract or rescind the contract can be waived but there is no
principle of law which requires the exercise of the right of repudiation of
the contract to be done immediately on coming to know about the
misrepresentation or breach of contract. It was open to the aggrieved party
to persuade the defaulting party to rectify the situation and to wait till the
defaulting party refuses to rectify its default before exercising its right of
repudiation of the contract. Reference was made to Sikkin Subba
Associates vs. State of Sikkim, 2001 (5) SCC 629, wherein this Court
observed as follows:
"Waiver involves a conscious, voluntary and
intentional relinguishment or abandonment of a
known, existing legal right, advantage, benefit,
claim or privilege, which except for such a waiver,
the party would have enjoyed. The agreement
between the parties in this case is such that its
fulfilment depends upon the mutual performance
of reciprocal promises constituting the
consideration for one another and the reciprocity
envisaged and engrafted is such that one party who
fails to perform his own reciprocal promise cannot
assert a claim for performance of the other party
and go to the extent of claiming even damages for
non-performance by the other party. He who seeks
equity must do equity and when the condonation or
acceptance of belated performance was conditional
upon the future good conduct and adherence to the
promises of the defaulter, the so-called waiver
cannot be considered to be forever and complete it
itself so as to deprive the State, in this case, of its
power to legitimately repudiate and refuse to
perform its part on the admitted fact that the
default of the appellants continued till even the
passing of the award in this case. So far as the
defaults and consequent entitlement or right of the
State to have had the lotteries either foreclosed or
stopped further, the State in order to safeguard its
own stakes and reputation has continued the
operation of lotteries even undergoing the miseries
arising out of the persistent defaults of the
appellants. The same cannot be availed of by the
appellants or used as a ground by the arbitrator to
claim any immunity permanently for being
pardoned, condoned and waived of their
subsequent recurring and persistent defaults so as
to deny or denude forever the power of the State as
the other party to the contract to put an end to the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 16 of 19
agreement and thereby relieve themselves of the
misfortunes they were made to suffer due to such
defaults. Once the appellants failed to deposit the
prize money in advance within the stipulated time,
the time being of the essence since the prizes
announced after the draw have to be paid from out
of only the prize money deposited, the State was
well within its rights to repudiate not only due to
continuing wrongs or defaults but taking into
account the past conduct and violations also
despite the fact that those draws have been
completed by declaration or disbursement of prize
amounts by the State from out of its own funds.
The conclusion to the contrary that the State has
committed breach of the contract is nothing but
sheer perversity and contradiction in terms."
In our view, this decision has no application to the facts of the present
case. In the said case the appellants therein was appointed as "organising
agent" for lotteries of the Respondent State. Subsequently, disputes arose
which led to termination of the agency by the State. Appellants therein got
an arbitrator appointed under Section 8 of the Arbitration Act, 1940. Claims
and counter-claims were filed and evidence adduced by the parties before
the Arbitrator. Arbitrator made its award determining the amount payable
by the State to the appellants at Rs.37,75,00,000/- and the amount payable
by the appellants to the State by way of counter-claim at Rs.4,61,35,242/-.
District Judge made the award the rule of the court. This was in challenge in
the High Court of Sikkim where there were only two Judges. Chief Justice
set aside the award while the other Judge held that the matter required to be
remitted to the arbitrator for re-determining the quantum of damages. The
court thereafter by its order dated 29th September 1995 directed the matter to
be placed before the incoming Chief Justice/Judge. Subsequently both the
Chief Justice and the other Judge were, in due course, succeeded by new
incumbents to those offices. The new Judge fixed the date of hearing and
before him the appellants filed an application opposing the hearing of the
appeal in view of section 98(2) CPC. This application was dismissed by the
Division Bench as not maintainable in view of the reference made by the
Division Bench. This was challenged in this Court. After resolving the
controversy on the aforesaid point, the Court proceeded to examine the
award made by the arbitrator. It was held that the award under challenge
stood vitiated on account of several errors of law, apparent on the face of it
and such infirmities go to substantiate the claim of the State that the
arbitrator not only acted arbitrarily and irrationally on a perverse
understanding or misreading of the materials but was also found to have
misdirected himself on the vital issues rendering the award to be bad in law.
The arbitrator and the District Judge had recorded a finding that the State in
spite of warnings and threats did not actually stop draws or to other
subsequent draws by the appellants and allowed the lotteries to go on
without any break. That the State government had condoned or waived the
lapses and defaults. In this context, the observations quoted above were
made by this court. It would be seen that this contract was an executory
contract and not completed contract of sale of property. It was observed that
a waiver involves a conscious, voluntary and intentional relinquishment or
abandonment in known existing legal right. There were persistent and
continuous defaults. Even if the past lapses were taken to have been waived
by the State, it was observed by the Court that the State could not be
compelled to condone the continues wrong and defaults of the appellants to
their disadvantage and detriment. Observations quoted above are of no
avail to the appellants as in that case the court found that the appellants were
continuing with the defaults in an executory contract. The principle laid
down in the said case would not be applicable to the facts of the present
case.
Reliance was also placed on M/s Motilal Padampat Sugar Mills
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 17 of 19
Co.Ltd. vs. State of U.P. & Others [1979 (2) SCC 409]. In this case the
point which fell for consideration was whether the assurance given by
respondent No.4 (Chief Secretary or advisor to the Government) on behalf
of the State of U.P. that the appellants would be exempt from payment of
sales tax for a period of three years from the date of commencement of
production could be enforced against the State government. On behalf of the
respondent-State, plea of waiver by the appellants were raised. The Court
rejected this plea of waiver. It was held that waiver is essentially a question
of fact and it must be properly pleaded and proved which the State had failed
to do. It was also held that waiver means abandonment of a right and it may
be either express or implied from conduct, but its basic requirement is that it
must be ’an intentional act with knowledge’. On facts it was found that
there was no waiver and the court observed:
"Now in the present case there is nothing to show
that at the date when the appellant addressed the
letter dated June 25, 1970, it had full knowledge of
its right to exemption under the assurance given by
respondent 4 and that it intentionally abandoned
such right. It is difficult to speculate what was the
reason why the appellant addressed the letter dated
June 25, 1970 stating that it would avail of the
concessional rates of Sales Tax granted under the
letter dated January 20, 1970. It is possible that
the appellant might have thought that since no
notification exempting the appellant from Sales tax
had been issued by the State Government under
Section 4-A, the appellant was legally not entitled
to exemption and that is why the appellant might
have chosen to accept whatever concession was
being granted by the State Government. The claim
of the appellant to exemption could be sustained
only on the doctrine of promissory estoppel and
this doctrine could not be said to be so well
defined in its scope and ambit and so free from
uncertainty in its application that we should be
compelled to hold that the appellant must have had
knowledge of its right to exemption on the basis of
promissory estoppel at the time when it addressed
the letter dated June 25, 1970. In fact, in the
petition as originally filed, the right to claim total
exemption from Sales Tax was not based on the
plea of promissory estoppel which was introduced
only by way of amendment."
In the present case, we have found as a fact that the appellants even
after acquiring the knowledge of fact regarding reduction of FAR from 2.00
to 1.75 and that the land was not ceiling free elected to affirm the contract
by getting their plans approved with FAR 1.75 and started putting up
construction. They started digging the foundations and continued to build
even after knowing that the land was not ceiling free. Thus, the reliance
placed on the ratio of law laid down in M/s Motilal Padampat Sugar Mills
Co.Ltd.’s case (supra) is of no avail to the appellants.
Relying upon a decision of this Court in Ningawwa Vs. Byrappa &
Others [1968 (2) SCR 797], it was contended by Shri Shanti Bhushan,
learned senior counsel that a contract or other transaction induced or tainted
by fraud is not void, but only voidable at the option of the parties defrauded,
unless it is avoided, the transaction is valid. Further, drawing a distinction
between fraudulent misrepresentation as to the character of the document
and fraudulent misrepresentation as to the contents thereof it was argued that
in the case of former the transaction is void while in the case of latter it is
merely voidable. It was also urged that the appellants could avoid the
transaction at any time. In our view, this judgment is of no assistance to the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 18 of 19
appellants as on facts we have found that the default committed by the
respondent-State, if any, stood condoned by the appellants.
In either case, we find that the appellants are not entitled to any relief
in the realm of the law of contracts. In spite of having acquired knowledge
of the true facts assuming that there was any mistake or misrepresentation to
begin with and having learnt that the title which was sought to be conferred
on them by the respondents was not such full title as they had contemplated
it to be, they proceeded to have the sale deed executed and registered in their
favour, seeking extensions of time and paying interest for the period of delay
in payment. The contract stood accomplished into a demise and the
transaction ended. It is writ large that the appellants had elected to stand by
the contract by digging the land, sinking the basement and raising about 9
floors above, investing crores of rupees. They have by their own conduct
rendered the position irreversible and restitution impractical. We have not
been shown any law or authority based whereon the appellants may annul
and avoid a concluded contract and fix liability on respondents for the cost
of their construction which they have voluntarily chosen to raise in spite of
being aware of all the relevant facts and circumstances.
The learned counsel for the appellants referred to the provisions of
Section 90 (1) and (2) of Jaipur Development Authority Act, 1982, which
read as under:
"90 Control by State Government -
(1) The Authority shall exercise its powers and
perform its duties under this Act in
accordance with the policy framed and the
guidelines laid down, from time to time by
the State Government for development of
the areas in the Jaipur Region.
(2) The Authority shall be bound to comply
with such directions which may be issued,
from time to time, by the State Government
for efficient administration of this Act."
It was contended that the State Government has the complete control
over the JDA and therefore could direct the JDA to adhere to the FAR 2.0 as
against the FAR 1.75 provided under the 1996 Regulations. We do not find
much force in this submission. A reading of this section clearly shows that
the Government can direct the authority to exercise its powers and perform
its duty in accordance with the policy framed and the guidelines laid down
from time to time. Policy and guidelines can be issued for general
application or for a class of persons or area or based on some such other
criteria as may withstand the test of Article 14 of the Constitution. The
power conferred by Section 90 cannot be exercised by the Government to
give directions to increase the FAR in one individual or particular case. The
appellants cannot claim a right to get exemption from the prevalent law nor
heard to say that since the Government had the power to give direction, its
failure to exercise the power of issuing direction by reference to Section 90
of the JDA Act, it has perpetuated the breach of contract.
Counsel for the appellants also brought to our notice the provisions of
Section 298(1) of the Rajasthan Municipalities Act, 1959 to contend that
Government had the power to cancel or modify the Bye-laws framed by the
Board and the failure to do so reflects that the government did not intend to
stick to the representation made by it in the auction notice or in the sale
deed. Section 298 reads as under:
"298 Power of Government to cancel or modify
bye-laws and rules of boards--
(1) The State Government may at any time by
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 19 of 19
notification in the Official Gazette repeal
wholly or in part or modify any rule or bye-
law made by any board.
Provided that before taking any action under this
sub-section, the State Government shall
communicate to the board the grounds on which it
proposes to do so, fix a reasonable period for the
board to show cause against the proposal and
consider the explanation and objections, if any of
the board."
Section 298 provides that the State Government has the power to
cancel or modify bye-laws or rules framed by the board. Again this is of no
avail to the appellants. Power under Section 298 is in the nature of power of
superintendence. It is a general power given to the Government that in case
the Government feels that the bye-laws framed or the orders issued are not
reasonable or are detrimental to the public interest or there is any other good
ground available, then, it can repeal the bye-laws wholly or in part or modify
any rule or bye-law made by the Board after inviting objections. The power
could not have been exercised to suit the needs of an individual case as has
been contended by the learned senior counsel for the appellants.
It may be noted that the learned senior counsel for the respondent
pointed out during the course of hearing that the amended bye-laws were
more beneficial to the appellants as there was number of exemptions to be
taken into account while calculating the FAR, namely, storage on all floors,
balcony, guard-door, lobby, terrace garden, service floor, AC plant room,
locker, dark room, PBX room, guard room, power house, lift room and the
lift well. Under the amended bye-laws of 1996 the appellants would get
more covered area thus causing no prejudice to them. This has been
strongly refuted by the counsel for the appellants. We need not go into this
disputed question as it is of no consequence to the points already decided.
For the reasons stated above, we do not find any merit in these appeals
and the same are dismissed with no order as to costs.