Full Judgment Text
REPORTABLE
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NO(S). 1539 OF 2019
(ARISING OUT OF SLP (C) NO. 13551 OF 2013)
| JAIPRAKASH ASSOCIATES LTD. (JAL)<br>THROUGH ITS DIRECTOR | .....APPELLANT(S) |
|---|---|
| VERSUS | |
| TEHRI HYDRO DEVELOPMENT<br>CORPORATION INDIA LTD. (THDC)<br>THROUGH ITS DIRECTOR | .....RESPONDENT(S) |
J U D G M E N T
A.K. SIKRI, J.
Leave granted.
2) The appellant herein was awarded the contract under which it
was to execute certain Works. Agreement in this behalf was
th
signed on 18 December, 1998. Some disputes arose between
the parties. Since the agreement contained an arbitration clause,
two claims raised by the appellant were referred for arbitration.
Signature Not Verified
Digitally signed by
MANISH SETHI
Date: 2019.03.12
17:58:28 IST
Reason:
The arbitral tribunal was of three Arbitrators. This arbitration was
under the Arbitration and Conciliation Act, 1996 (hereinafter
Civil Appeal arising out of SLP (C) No. 13551 of 2013 Page 1 of 25
referred to as the ‘1996 Act’). The majority award pronounced on
October 10, 2010 allowed the two claims to certain extent. On
the said claims awarded, the Arbitrators also granted interest at
the rate of 10% per annum from the date when the arbitration was
invoked, i.e., October 09, 2007, till 60 days after the award.
Future interest at the rate of 18% per annum till the date of
payment was also awarded.
3) Dispute which has travelled upto this Court pertains only to the
question as to whether the Arbitrators could award any interest in
view of Clauses 50 and 51 of the General Conditions of Contract
(GCC) which governed the terms between the parties. The
objections were filed before the High Court. A Single Judge of the
High Court of Delhi passed the order dated November 15, 2011
quashing the award limited to the interest that was awarded by
the Arbitrators. The appellant preferred intra-court appeal which
has been dismissed by the Division Bench of the High Court,
thereby upholding the judgment of the Single Judge. The effect is
that the High Court has held that no interest is payable as
Clauses 50 and 51 of GCC bar the arbitrators from granting
interest.
Civil Appeal arising out of SLP (C) No. 13551 of 2013 Page 2 of 25
4) It may be pointed out that on interpreting Clauses 50 and 51 of
the General Conditions of Contract, the view taken by the High
Court is that these clauses categorically provide that no interest
would be payable to the contractor on the money due to him. The
said Clauses read as under:
" Clause 50.0 Interest on money due to the contractor
No omission on the part of the Engineer in charge to pay
the amount due upon measurement or otherwise shall
vitiate or make void the contract, nor shall the contractor
be entitled to interest upon any guarantee or payments in
arrears nor upon any balance which may on the final
settlement of his account, be due to him.
Clause 51.0 No claim for delayed payment due to
dispute etc.
No claim for interest or damage will be entertained or be
payable by the corporation in respect of any amount or
balance which may be lying with the corporation owing to
nay dispute, different or misunderstanding between the
parties or in respect of any delay or omission on the part of
he Engineer in charge in making intermediate or final
payments on in any other respect whatsoever.”
The Award makes the following observations in this behalf:
"As seen from above, Clause 50.0 and 51.0 of the
Contract deny interest on the Claimant’s dues by the
Respondent due to dispute etc. However as per above
quoted judgment of Hon’ble Supreme Court of India, the
claim for interest can be considered by the Arbitration
Tribunal.”
Notwithstanding the same, the learned Arbitrators granted
the interest by relying upon the law declared by this Court in
Civil Appeal arising out of SLP (C) No. 13551 of 2013 Page 3 of 25
Board of Trustees for the Port of Calcutta v. Engineers-De-Space-
1
Age and following observations from the said judgment were
quoted:
"………..In other words, according to their Lordships the
arbitrator is expected to act and make his award in
accordance with general law of the land but subject to an
agreement, provided, the agreement is valid and legal.
Lastly, it was pointed out that interest pendent like is not a
matter of substantive law, interest for the period anterior to
reference. Their Lordship concluded that when the
agreement between the parties does not prohibit grant of
interest and where a party claims interest and that dispute
is referred to the arbitrator, he will have the power to award
interest pedente lite for the simple reason that in such a
case it is presumed that interest was implied term of the
agreement between the parties; it is then a matter of
exercise of discretion by the arbitrator. The position of law,
has, therefore, been clearly stated in the aforesaid
decision of the Constitution Bench.
…………………...Strictly construed the term of the contract
merely prohibits the Commissioner from paying interest to
the contractor for delayed payment but once the matter
goes to the arbitration the discretion of the Arbitrator is not,
in any manner, stifled by this term of the contract and the
Arbitrator would be entitled to consider the question of
grant of interest pendent lite and award interest if he finds
the claim to be justified. We are, therefore, of the opinion
that under the clause of the contract the Arbitrator was in
no manner prohibited from awarding interest pendente
lite.”
5) As stated above, the High Court, on the other hand, has taken the
view that if interest is prohibited as per the expressed terms of the
contract between the parties, the Arbitrator does not get
jurisdiction to award interest. Further, insofar as interpretation to
the aforesaid clauses is concerned, the High Court noticed that
1 (1996) 1 SCC 516
Civil Appeal arising out of SLP (C) No. 13551 of 2013 Page 4 of 25
these Clauses were on the same terms as Clause 1.2.14 and
1.2.15 of the contract which were subject matter of construction in
Tehri Hydro Development Corporation (THDC) Limited & Anr. v.
2
Jai Prakash Associates Limited . In the said judgment, this Court
has categorically held that those clauses to mean that no interest
was payable on claim for delayed payment due to the contractor.
Therefore, same construction needed to be given to Clauses 50
and 51 of GCC in the instant case.
6) Mr. Rupinder S. Suri, learned senior counsel appearing for the
appellant made two-fold submissions before us, which are to the
following effect:
(i) In the first place, it is submitted that judgment in Jayprakash
Associates Limited case is contrary to the earlier judgment
rendered by this Court in State of Uttar Pradesh v. Harish
3
Chandra and Company . Both the judgments are by the Benches
of Three-Judges. His submission is that judgment of Harish
Chandra is earlier in point of time, which has not been taken note
of in Jayprakash Associates Limited case. In such a scenario, as
per Mr. Suri, the judgment which is passed earlier should hold the
field and, therefore, we should be guided by the law laid down in
Harish Chandra case.
2 (2012) 12 SCC 10
3 (1999) 1 SCC 63
Civil Appeal arising out of SLP (C) No. 13551 of 2013 Page 5 of 25
(ii) Second submission, in the alternative, is that in order to
resolve the conflict, the matter should be referred to a larger
Bench.
7) Dilating on the first submission, an attempt of Mr. Suri was to
show that the clauses of the contract in question, when
interpreted correctly would clearly bring about that these clauses
did not prohibit the Arbitrators from granting interest. The learned
counsel emphasised the words “or any other respect whatsoever”
occurring in Clause 51 of the GCC and argued that these are to
be read ejusdem generis and should take their colour from the
earlier part of clause. He submitted that when these words are
read in the aforesaid manner, it is only in those cases where
some amount or balance is lying with the respondent because of
any dispute, difference or misunderstanding between the parties
etc., interest is not payable. Such a situation would not arise in
those cases where claim is raised on other counts and awarded
by the Arbitrators. He also submitted that Clause 51 in the
contract in the instant case was similar to Clause 1.9 of the
contract in Harish Chandra case and the Court interpreted the
said clause to mean that Arbitrator was not precluded from
awarding the interest.
Civil Appeal arising out of SLP (C) No. 13551 of 2013 Page 6 of 25
8) In this hue, his alternate submission was that two similar or
almost identical clauses are interpreted in a different manner in
Harish Chandra case and Jayprakash Associates case and,
therefore, conflict arises which needs to be resolved.
9) Mr. Gourab Banerji, learned Senior Counsel appearing for the
respondent gave equally emphatic reply to the aforesaid
submissions of Mr. Suri. His first argument was that clauses in
Harish Chandra case and the present case were altogether
different. Insofar as the instant case is concerned, it was
governed by the law laid down in Jayprakash Associates
judgment which was in fact a case between the same parties and
in that case the Court had, while construing the identically worded
clauses, came to the conclusion that the Arbitrators were
precluded from granting any interest. His another contention was
that there was a difference between the scheme provided under
the Arbitration Act, 1940 (hereinafter referred to as the ‘1940 Act’)
when contrasted with the 1996 Act. He argued that most of the
judgments cited by the appellant including Harish Chandra were
under 1940 Act whereas in the instant case award was passed
under the 1996 Act. He also referred to certain recent judgments
which have been rendered by this Court touching upon this very
Civil Appeal arising out of SLP (C) No. 13551 of 2013 Page 7 of 25
aspect. The precise manner in which he structured his
arguments are recapitulated below:
10) In the first instance, he pointed out that even the arbitrators
accepted, on the interpretation of GCC Clauses 50 and 51, that
these clauses deny interest on the appellant’s dues by the
respondent due to dispute etc. Notwithstanding the same, the
majority opinion awarded the interest relying upon the judgment
of this Court in Board of Trustees for the Port of Calcutta . The
learned Single Judge of the High Court, while reversing the
aforesaid view, pointed out that 1996 Act had altered the position
contained in the 1940 Act. Under the new Act, an arbitrator could
not award pendente lite interest when there was an express bar
against award of such an interest. This legal position is contained
in Section 31(7)(a) of the 1996 Act and the legal position stood
crystallised in the case of Sayeed Ahmed and Company v. State
4
of Uttar Pradesh & Ors. . Therefore, held the learned Single
Judge, when Clauses 50 and 51 of GCC imposed a complete bar
on arbitral tribunal to award pendente lite interest, the arbitrators
had no jurisdiction to award interest. Mr. Banerji submitted that
the learned Single Judge even noticed the judgment in Harish
Chandra case and distinguished the same on the ground that it
4 (2009) 12 SCC 26
Civil Appeal arising out of SLP (C) No. 13551 of 2013 Page 8 of 25
arose under the 1940 Act. Furthermore, clause 1.9 in Harish
Chandra case was indeed restrictive and differed from the
wordings of Clauses 50 and 51 of the GCC which were closer to
Clause G1.09 in Sayeed Ahmed case. On that basis, Harish
Chandra judgment was distinguished which position has been
upheld by the Division Bench of the High Court also. Mr. Banerji
submitted that by the time Division Bench decided the case in
September, 2012, it had the benefit of another judgment of this
Court in THDC case which was not only between the same
parties but even the clauses in the said case are pari materia with
the clauses in the present case.
11) We have considered the respective submissions and have gone
through the legal position contained in the case laws cited before
us by both the parties.
12) Insofar as power of the arbitral tribunal in granting pre-reference
and/or pendente lite interest is concerned, the principles which
can be deduced from the various judgments are summed up
below:
(a) A Constitution Bench judgment of this Court in the case of
Secretary, Irrigation Department, Government of Orissa & Ors. v.
Civil Appeal arising out of SLP (C) No. 13551 of 2013 Page 9 of 25
5
G.C. Roy exhaustively dealt with this very issue, namely, power
of the arbitral tribunal to grant pre-reference and pendente lite
interest. The Constitution Bench, of course, construed the
provisions of the 1940 Act which Act was in vogue at that time. At
the same time, the Constitution Bench also considered the
principle for grant of interest applying the common law principles.
It held that under the general law, the arbitrator is empowered to
award interest for the pre-reference, pendente lite or post award
period. This proposition was culled out with the following
reasoning:
"43. The question still remains whether arbitrator has the
power to award interest pendente lite, and if so on what
principle. We must reiterate that we are dealing with the
situation where the agreement does not provide for grant
of such interest nor does it prohibit such grant. In other
words, we are dealing with a case where the agreement is
silent as to award of interest. On a conspectus of
aforementioned decisions, the following principles emerge:
(i) A person deprived of the use of money to which he is
legitimately entitled has a right to be compensated for the
deprivation, call it by any name. It may be called interest,
compensation or damages. This basic consideration is as
valid for the period the dispute is pending before the
arbitrator as it is for the period prior to the arbitrator
entering upon the reference. This is the principle of
Section 34, Civil Procedure Code and there is no reason
or principle to hold otherwise in the case of arbitrator.
(ii) An arbitrator is an alternative form ( sic forum) for
resolution of disputes arising between the parties. If so, he
must have the power to decide all the disputes or
differences arising between the parties. If the arbitrator has
no power to award interest pendente lite, the party
5 (1992) 1 SCC 508
Civil Appeal arising out of SLP (C) No. 13551 of 2013 Page 10 of 25
claiming it would have to approach the court for that
purpose, even though he may have obtained satisfaction
in respect of other claims from the arbitrator. This would
lead to multiplicity of proceedings.
(iii) An arbitrator is the creature of an agreement. It is open
to the parties to confer upon him such powers and
prescribe such procedure for him to follow, as they think fit,
so long as they are not opposed to law. (The proviso to
Section 41 and Section 3 of Arbitration Act illustrate this
point). All the same, the agreement must be in conformity
with law. The arbitrator must also act and make his award
in accordance with the general law of the land and the
agreement.
(iv) Over the years, the English and Indian courts have
acted on the assumption that where the agreement does
not prohibit and a party to the reference makes a claim for
interest, the arbitrator must have the power to award
interest pendente lite. Thawardas [ Seth Thawardas
Pherumal v. Union of India , (1955) 2 SCR 48 : AIR 1955
SC 468] has not been followed in the later decisions of this
Court. It has been explained and distinguished on the
basis that in that case there was no claim for interest but
only a claim for unliquidated damages. It has been said
repeatedly that observations in the said judgment were not
intended to lay down any such absolute or universal rule
as they appear to, on first impression. Until Jena case
[(1988) 1 SCC 418 : (1988) 1 SCR 253] almost all the
courts in the country had upheld the power of the arbitrator
to award interest pendente lite. Continuity and certainty is
a highly desirable feature of law.
(v) Interest pendente lite is not a matter of substantive law,
like interest for the period anterior to reference (pre-
reference period). For doing complete justice between the
parties, such power has always been inferred.”
It is clear from the above that the Court decided to fall back
on general principle that a person who is deprived of the use of
money to which he is legitimately entitled to, has a right to be
Civil Appeal arising out of SLP (C) No. 13551 of 2013 Page 11 of 25
compensated for the deprivation and, therefore, such
compensation may be called interest compensation or damages.
(b) As a sequitur, the arbitrator would be within his jurisdiction
to award pre-reference or pendente lite interest even if agreement
between the parties was silent as to whether interest is to be
awarded or not.
(c) Conversely, if the agreement between the parties
specifically prohibits grant of interest, the arbitrator cannot award
pendente lite interest in such cases. This proposition is
predicated on the principle that an arbitrator is the creature of an
agreement and he is supposed to act and make his award in
accordance with the general law of the land and the agreement.
This position was made amply clear in G.C. Roy case in the
discussion that ensued thereafter:
"44. Having regard to the above consideration, we think
that the following is the correct principle which should be
followed in this behalf:
Where the agreement between the parties does not
prohibit grant of interest and where a party claims
interest and that dispute (along with the claim for
principal amount or independently) is referred to the
arbitrator, he shall have the power to award interest
pendente lite. This is for the reason that in such a
case it must be presumed that interest was an
implied term of the agreement between the parties
and therefore when the parties refer all their disputes
— or refer the dispute as to interest as such — to the
arbitrator, he shall have the power to award interest.
Civil Appeal arising out of SLP (C) No. 13551 of 2013 Page 12 of 25
This does not mean that in every case the arbitrator
should necessarily award interest pendente lite. It is
a matter within his discretion to be exercised in the
light of all the facts and circumstances of the case,
keeping the ends of justice in view.”
(d) Insofar as 1940 Act is concerned, it was silent about the
jurisdiction of the arbitrator in awarding pendente lite interest.
However, there is a significant departure on this aspect insofar as
1996 Act is concerned. This distinction has been spelt out in
Sayeed Ahmed case in the following manner:
" Re: Interest from the date of cause of action to date
of award
7. The issue regarding interest as noticed above revolves
around Clause G1.09 of the Technical Provisions forming
part of the contract extracted below:
“G. 1.09. No claim for interest or damages will be
entertained by the Government with respect to any
money or balance which may be lying with the
Government or any become due owing to any
dispute, difference or misunderstanding between the
Engineer-in-Charge on the one hand and the
contractor on the other hand or with respect to any
delay on the part of the Engineer-in-Charge in
making periodical or final payment or any other
respect whatsoever.”
xx xx xx
14. The decisions of this Court with reference to the
awards under the old Arbitration Act making a distinction
between the pre-reference period and pendente lite period
and the observation therein that the arbitrator has the
discretion to award interest during pendente lite period in
spite of any bar against interest contained in the contract
between the parties are not applicable to arbitrations
governed by the Arbitration and Conciliation Act, 1996.”
Civil Appeal arising out of SLP (C) No. 13551 of 2013 Page 13 of 25
13) The aforesaid position is reiterated in Sree Kamatchi Amman
Constructions v. Divisional Railway Manager (Works), Palghat &
6
Ors. and Union of India v. Bright Power Projects (India) Private
7
Limited . Later judgment is by a bench of three Judges. This
legal position is reiterated in Sri Chittaranjan Maity v. Union of
8
India which is authored by one of us (Nazeer, J.). In that case,
the Court considered the same very question which falls for
determination by us, namely, whether the arbitral tribunal was
justified in awarding interest on delayed payments in favour of the
appellant? After noticing that clause 16(2) of GCC in that case
bars the payment of interest, it was held that under the 1996 Act,
the position wherein is different from 1940 Act, the interest could
not be awarded. Following observations from this judgment may
be noted:
"16. Relying on a decision of this Court in Ambica
Construction v. Union of India [ Ambica Construction v.
Union of India , (2017) 14 SCC 323] , the learned Senior
Counsel for the appellant submits that mere bar to award
interest on the amounts payable under the contract would
not be sufficient to deny payment on pendente lite interest.
Therefore, the arbitrator was justified in awarding the
pendente lite interest. However, it is not clear from Ambica
Construction [ Ambica Construction v. Union of India ,
(2017) 14 SCC 323] as to whether it was decided under
the Arbitration Act, 1940 (for short “the 1940 Act”) or under
the 1996 Act. It has relied on a judgment of Constitution
Bench in State of Orissa v. G.C. Roy [ State of Orissa v.
G.C. Roy , (1992) 1 SCC 508] . This judgment was with
6 (2010) 8 SCC 767
7 (2015) 9 SCC 695
8 (2017) 9 SCC 611
Civil Appeal arising out of SLP (C) No. 13551 of 2013 Page 14 of 25
reference to the 1940 Act. In the 1940 Act, there was no
provision which prohibited the arbitrator from awarding
interest for the pre-reference, pendente lite or post-award
period, whereas the 1996 Act contains a specific provision
which says that if the agreement prohibits award of interest
for the pre-award period, the arbitrator cannot award
interest for the said period. Therefore, the decision in
Ambica Construction [ Ambica Construction v. Union of
India , (2017) 14 SCC 323] cannot be made applicable to
the instant case.”
14) In a recent judgment in the case of Reliance Cellulose Products
9
Limited v. Oil and Natural Gas Corporation Limited , the entire
case law on the subject is revisited and legal position re-
emphasised. That was also a case which arose under the 1940
Act. The Court held that under the 1940 Act, an arbitrator has
power to grant pre-reference interest under the Interest Act as
well as pendente lite and future interest, however, he is
constricted only by the fact that an agreement between the
parties may contain an express bar to the award of pre-reference
and/or pendente lite interest. Further, the Court has evolved the
test of strict construction of such clauses, and unless there is a
clear and express bar to the payment of interest that can be
awarded by an arbitrator, clauses which do not refer to claims
before the arbitrators or disputes between parties and clearly bar
payment of interest, cannot stand in the way of an arbitrator
awarding pre-reference or pendente lite interest. Further, unless
9 (2018) 9 SCC 266
Civil Appeal arising out of SLP (C) No. 13551 of 2013 Page 15 of 25
a contractor agrees that no claim for interest will either be
entertained or payable by the other party owing to dispute,
difference, or misunderstandings between the parties or in
respect of delay on the part of the engineer or in any other
respect whatsoever, leading the Court to find an express bar
against payment of interest, a clause which merely states that no
interest will be payable upon amounts payable to the contractor
under the contract would not be sufficient to bar an arbitrator from
awarding pendente lite interest. Further, the grant of pendente
lite interest depends upon the phraseology used in the
agreement, clauses conferring power relating to arbitration, the
nature of claim and dispute referred to the arbitrator, and on what
items the power to award interest has been taken away and for
which period. Also, the position under Section 31(7) of the 1996
Act, is wholly different, inasmuch as Section 31(7) of the 1996 Act
sanctifies agreements between the parties and states that the
moment the agreement says otherwise, no interest becomes
payable right from the date of the cause of action until the award
is delivered.
15) After discussing and analysing almost all the judgments on this
subject, the legal position is summed up in the following manner:
Civil Appeal arising out of SLP (C) No. 13551 of 2013 Page 16 of 25
"24. A conspectus of the decisions that have been referred
to above would show that under the 1940 Act, an arbitrator
has power to grant pre-reference interest under the
Interest Act, 1978 as well as pendente lite and future
interest. However, he is constricted only by the fact that an
agreement between the parties may contain an express
bar to the award of pre-reference and/or pendente lite
interest. Since interest is compensatory in nature and is
parasitic upon a principal sum not having been paid in
time, this Court has frowned upon clauses that bar the
payment of interest. It has therefore evolved the test of
strict construction of such clauses, and has gone on to
state that unless there is a clear and express bar to the
payment of interest that can be awarded by an arbitrator,
clauses which do not refer to claims before the arbitrators
or disputes between parties and clearly bar payment of
interest, cannot stand in the way of an arbitrator awarding
pre-reference or pendente lite interest. Thus, when one
contrasts a clause such as the clause in Second Ambica
Construction case [ Ambica Construction v. Union of India ,
(2017) 14 SCC 323 : (2018) 1 SCC (Civ) 257] with the
clause in Tehri Hydro Development Corpn. Ltd. [ Tehri
Hydro Development Corpn. Ltd. v. Jai Prakash Associates
Ltd. , (2012) 12 SCC 10 : (2013) 2 SCC (Civ) 122] , it
becomes clear that unless a contractor agrees that no
claim for interest will either be entertained or payable by
the other party owing to dispute, difference, or
misunderstandings between the parties or in respect of
delay on the part of the engineer or in any other respect
whatsoever, leading the Court to find an express bar
against payment of interest, a clause which merely states
that no interest will be payable upon amounts payable to
the contractor under the contract would not be sufficient to
bar an arbitrator from awarding pendente lite interest
under the 1940 Act. As has been held in First Ambica
Construction case [ Union of India v. Ambica Construction ,
(2016) 6 SCC 36 : (2016) 3 SCC (Civ) 36] , the grant of
pendente lite interest depends upon the phraseology used
in the agreement, clauses conferring power relating to
arbitration, the nature of claim and dispute referred to the
arbitrator, and on what items the power to award interest
has been taken away and for which period. We hasten to
add that the position as has been explained in some of the
judgments above under Section 31(7) of the 1996 Act, is
wholly different, inasmuch as Section 31(7) of the 1996 Act
sanctifies agreements between the parties and states that
the moment the agreement says otherwise, no interest
Civil Appeal arising out of SLP (C) No. 13551 of 2013 Page 17 of 25
becomes payable right from the date of the cause of action
until the award is delivered.”
16) In this whole conspectus and keeping in mind, in particular, that
present case is regulated by 1996 Act, we have to decide the
issue at hand. At this stage itself, it may be mentioned that in
case clauses 50 and 51 of GCC put a bar on the arbitral tribunal
to award interest, the arbitral tribunal did not have any jurisdiction
to do so. As pointed out above, right from the stage of arbitration
proceedings till the High Court, these clauses are interpreted to
hold that they put such a bar on the arbitral tribunal. Even the
majority award of the arbitral tribunal recognised this.
Notwithstanding the same, it awarded the interest by relying upon
Board of Trustees for the Port of Calcutta case. The High Court,
both Single Bench as well as Division Bench, rightly noted that
the aforesaid judgment was under the 1940 Act and the legal
position in this behalf have taken a paradigm shift which position
is clarified in Sayeed Ahmed and Company case. This rationale
given by the High Court is in tune with the legal position which
stands crystallised by catena of judgments as noted above.
17) Another reason given by the High Court is equally convincing.
The Clauses 50 and 51 of GCC are pari materia with Clauses
1.2.14 and 1.2.15 of GCC in THDC case. Those clauses have
Civil Appeal arising out of SLP (C) No. 13551 of 2013 Page 18 of 25
been interpreted by holding that no interest is payable on claim
for delayed payment due to the contractor. Same construction
adopted in respect of these clauses, which, in fact, is a case
between the same parties, is without any blemish.
18) In this backdrop, the only argument of the appellant that remains
to be considered is as to whether such a construction is contrary
to the judgment in Harish Chandra case.
19) Complete answer to this argument is provided in Reliance
Cellulose Products Limited judgment. Following discussion
contained therein which discussed THDC judgment would amply
demonstrate this:
"Also, unlike the clause in Tehri Hydro Development
Corporation Ltd. (Supra), clause 16 does not contain
language which is so wide in nature that it would interdict
an arbitrator from granting pendente lite interest. It will be
remembered that the clause in Tehri Hydro Development
Corportation Ltd. (supra) spoke of no claim for interest
being entertained or payable in respect of any money
which may be lying with the Government owing to
disputes, difference or misunderstanding between the
parties and not merely in respect of delay or omission;
Further, the clause in Tehri Hydro Development
Corporation Ltd. (supra) goes much further and makes it
clear that no claim for interest is payable “in any other
respect whatsoever.”
It is pertinent to mention that the aforesaid judgment also
discusses and analyses Harish Chandra case. In the first place,
Civil Appeal arising out of SLP (C) No. 13551 of 2013 Page 19 of 25
the judgment in Harish Chandra case is under the 1940 Act.
More pertinently, this judgment is explained and distinguished in
Sayeed Ahmed and Company case in the following paragraphs:
"17. The appellant strongly relied upon the decision of this
Court in State of U.P. v. Harish Chandra & Co. [(1999) 1
SCC 63] to contend that Clause 1.09 of the contract did
not bar the award of interest. The clause barring interest
that fell for consideration in that decision was as under:
(SCC p. 67, para 9)
“1.09. No claim for delayed payment due to dispute,
etc .—No claim for interest or damages will be
entertained by the Government with respect to any
moneys or balances which may be lying with the
Government owing to any dispute, difference; or
misunderstanding between the Engineer-in-Charge
in making periodical or final payments or in any other
respect whatsoever.”
This Court held that the said clause did not bar award of
interest on any claim for damages or for claim for payment
for work done. We extract below the reasoning for such
decision: (SCC p. 67, para 10)
“ 10 . A mere look at the clause shows that the claim
for interest by way of damages was not to be
entertained against the Government with respect to
only a specified type of amount, namely, any moneys
or balances which may be lying with the Government
owing to any dispute, difference between the
Engineer-in-Charge and the contractor; or
misunderstanding between the Engineer-in-Charge
and the contractor in making periodical or final
payments or in any other respect whatsoever. The
words ‘or in any other respect whatsoever’ also
referred to the dispute pertaining to the moneys or
balances which may be lying with the Government
pursuant to the agreement meaning thereby security
deposit or retention money or any other amount
which might have been with the Government and
refund of which might have been withheld by the
Government. The claim for damages or claim for
payment for the work done and which was not paid
Civil Appeal arising out of SLP (C) No. 13551 of 2013 Page 20 of 25
for would not obviously cover any money which may
be said to be lying with the Government .
Consequently, on the express language of this
clause, there is no prohibition which could be culled
out against the respondent contractor that he could
not raise the claim for interest by way of damages
before the arbitrator on the relevant items placed for
adjudication.”
(emphasis supplied)
18. In Harish Chandra [(1999) 1 SCC 63] a different
version of Clause 1.09 was considered. Having regard to
the restrictive wording of that clause, this Court held that it
did not bar award of interest on a claim for damages or a
claim for payments for work done and which was not paid.
This Court held that the said clause barred award of
interest only on amounts which may be lying with the
Government by way of security deposit/retention money or
any other amount, refund of which was withheld by the
Government.
19. But in the present case, Clause G1.09 is significantly
different. It specifically provides that no interest shall be
payable in respect of any money that may become due
owing to any dispute, difference or misunderstanding
between the Engineer-in-Charge and contractor or with
respect to any delay on the part of the Engineer-in-Charge
in making periodical or final payment or in respect of any
other respect whatsoever. The bar under Clause G1.09 in
this case being absolute, the decision in Harish Chandra
[(1999) 1 SCC 63] will not assist the appellant in any
manner.”
20) It is also pertinent to note that the judgment in Sayeed Ahmed
and Company distinguishing the restrictive wording in Harish
Chandra has been consistently followed by this Court in number
of cases thereafter. In this scenario, when we find that Harish
Chandra case which is of the vintage of 1940 Act and is
distinguished in Sayeed Ahmed and Company coupled with the
Civil Appeal arising out of SLP (C) No. 13551 of 2013 Page 21 of 25
fact that the ratio of Sayeed Ahmed and Company has been
consistently followed, there is no reason to deviate from the
construction to Clauses 50 and 51 of the GCC given by the
arbitral tribunal in the first instance as well as the High Court.
Above all, these clauses is pari materia with with Clauses 1.2.14
and 1.2.15 of GCC in THDC case which was a judgment between
the same parties.
21) Insofar as argument based on the principle of ejusdem generis is
concerned, the Division Bench has held that that is not applicable
in the present case. We find that it is rightly so held. Ejusdem
generis is the rule of construction. The High Court has negated
this argument in the following manner:
"18. The rule of ejusdem generis guides us that where two
or more words or phrases which are susceptible of
analogous meaning are cupled together, a noscitur a
sociis, they are to be understood to mean in their cognate
sense and take colour from each other but only if there is a
distinct genus or a category. Where this is lacking i.e.
unless there is a category, the rule cannot apply.”
As rightly held, the rule of ejusdem generis would be
applied only if there is distinct genus or a category, which is
lacking in the instant case. This rule is applicable when particular
words pertaining to a clause, category or genus are followed by
general words. In such a situation, the general words are
Civil Appeal arising out of SLP (C) No. 13551 of 2013 Page 22 of 25
construed as limited to things of same kind as those specified. In
that sense, this rule reflects an attempt ‘to reconcile
incompatibility between the specific and general words in view of
the other rules of interpretation that all words in a statute are
given effect if possible, that a statute is to be construed as a
whole and that no words in a statute were presumed to be
superfluous’. (See Lokmat Newspapers Pvt. Ltd. v.
10
Shankarprasad ). In fact, construing the similar clause, this
Court in the case of Bharat Heavy Electricals Limited v. Globe Hi-
11
Fabs Limited has held that rule of ejusdem generis is not
applicable inasmuch as:
"12. The rule of ejusdem generis has to be applied with
care and caution. It is not an inviolable rule of law, but it is
only permissible inference in the absence of an indication
to the contrary, and where context and the object and
mischief of the enactment do not require restricted
meaning to be attached to words of general import, it
becomes the duty of the courts to give those words their
plain and ordinary meaning. As stated by Lord Scarman:
“If the legislative purpose of a statute is such that a
statutory series should be read ejusdem generis, so
be it, the rule is helpful. But, if it is not, the rule is
more likely to defeat than to fulfil the purpose of the
statute. The rule like many other rules of statutory
interpretation, is a useful servant but a bad master.”
So a narrow construction on the basis of ejusdem generis
rule may have to give way to a broader construction to
give effect to the intention of Parliament by adopting a
purposive construction.
10 (1999) 6 SCC 275
11 (2015) 5 SCC 718
Civil Appeal arising out of SLP (C) No. 13551 of 2013 Page 23 of 25
xx xx xx
15. A word of caution is here necessary. The fact that the
ejusdem generis rule is not applicable does not
necessarily mean that the prima facie wide meaning of the
word “other” or similar general words cannot be restricted
if the language or the context and the policy of the Act
demand a restricted construction. In the expression “defect
of jurisdiction or other cause of a like nature” as they occur
in Section 14(1) of the Limitation Act the generality of the
words “other cause” is cut down expressly by the words “of
a like nature”, though the rule of ejusdem generis is strictly
not applicable as mention of a single species “defect of
jurisdiction” does not constitute a genus. Another example
that may here be mentioned is Section 129 of the Motor
Vehicles Act which empowers any “police officer
authorised in this behalf or other person authorised in this
behalf by the State Government” to detain and seize
vehicles used without certification of registration or permit.
The words “other person” in this section cannot be
construed by the rule of ejusdem generis for mention of
single species, namely, “police officer” does not constitute
a genus but having regard to the importance of the power
to detain and seize vehicles it is proper to infer that the
words “other person” were restricted to the category of
government officers. In the same category falls the case
interpreting the words “before filing a written statement or
taking any other steps in the proceedings” as they occur in
Section 34 of the Arbitration Act, 1940. In the context in
which the expression “any other steps” finds place it has
been rightly construed to mean a step clearly and
unambiguously manifesting an intention to waive the
benefit of arbitration agreement, although the rule of
ejusdem generis has no application for mention of a single
species viz. written statement does not constitute a genus.
16. In the present case we noticed that the clause barring
interest is very widely worded. It uses the words “any
amount due to the contractor by the employer”. In our
opinion, these words cannot be read as ejusdem generis
along with the earlier words “earnest money” or “security
deposit”.
Civil Appeal arising out of SLP (C) No. 13551 of 2013 Page 24 of 25
22) The upshot of the aforesaid discussion would be to hold that the
conclusions of the High Court in the impugned judgment are
correct and need no interference. This appeal is accordingly
dismissed.
.............................................J.
(A.K. SIKRI)
.............................................J.
(S. ABDUL NAZEER)
.............................................J.
(M. R. SHAH)
NEW DELHI;
FEBRUARY 07, 2019
Civil Appeal arising out of SLP (C) No. 13551 of 2013 Page 25 of 25