Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 3
CASE NO.:
Appeal (civil) 4737 of 2007
PETITIONER:
N.R. Constructions Pvt. Ltd
RESPONDENT:
Sri Ram Badan Singh & Ors
DATE OF JUDGMENT: 09/10/2007
BENCH:
Tarun Chatterjee & P. Sathasivam
JUDGMENT:
JUDGMENT
(Arising out of SLP (C) No. 15858 OF 2006)
P. Sathasivam, J.
1) Leave granted.
2) This appeal is directed against the judgment dated
19.07.2006 passed by the High Court of Jharkhand at
Ranchi in C.R. No.65 of 2006 whereby the learned single
Judge dismissed the Civil Revision filed by the appellant
herein against the order dated 28.06.2006 passed by the
Subordinate Judge-I, Bokaro in Execution Case No. 2 of
2001 rejecting the appellant\022s prayer for adjustment of the
cross-award under the provisions of Order XXI Rules 18
and 19 of the Code of Civil Procedure.
3) The only question, inter alia, arises in this appeal is
whether the provisions of Order XXI Rules 18 and 19 of the
C.P.C. are applicable in case of adjustment of the cross-
award as claimed by the appellant herein?
4) The appellant entered into a partnership with the
respondents and a partnership deed was executed on
14.04.1992. The purpose of the partnership was for
completion of certain contract work which the appellant had
obtained. One of the terms of the agreement provided for
arbitration, i.e., - \023that if there be any dispute among the
partners, the same can be referred to the
Arbitrator/Arbitrators as appointed by the partners who
would decide the names in accordance with the provisions
of the Indian Arbitration Act, if not otherwise settled by the
partners with mutual consent.\024
5) As the disputes which arose in the year 1995 among
the partners could not be settled by mutual agreement and
the work could not be completed, the partners, by mutual
consent, appointed four persons as Arbitrators. On
19.04.1997, the Arbitrators, after hearing both the parties,
submitted their award. There is no specific reference
whether the award is an interim award or a final award.
According to the appellant, the award dated 19.04.1997 was
acted upon by the parties and was never challenged by any
of them. Thereafter, the Arbitrators passed various awards.
It is not in dispute that none of those awards passed after
19.4.1997 was ever challenged by any of the parties.
Finally on 25.11.2000, the Arbitrators passed an award.
According to the appellant, in this award, it was not stated
that whether the issues covered by the earlier awards and
especially the award dated 19.4.1997 are to be merged in
the final award.
6) The appellant herein, being aggrieved by the award
dated 25.11.2000, filed an application under Section 34 of
the Arbitration and Conciliation Act, 1996 (hereinafter
referred to as \023the Act). The respondents filed Execution
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 3
Case No. 2 of 2001 for enforcement of the Award dated
25.11.2000. By order dated 27.6.2003, the application filed
by the appellant under Section 34 of the Act was dismissed
by the learned subordinate Judge. On 1.7.2003, the
appellant herein filed Execution Case No. 5 of 2003 for
enforcement of the award dated 19.4.1997. Against the
dismissal of the application filed under Section 34 of the
Act, on 26.8.2003, the appellant filed an Arbitration Appeal
No. 6 of 2001 before the High Court of Jharkhand at
Ranchi. By order dated 29.4.2004, the High Court
dismissed the said appeal. The special leave petition
against the said order was also dismissed by this Court on
10.1.2005 with a modification as to the rate of interest.
7) The respondents filed an objection under Section 47
of the C.P.C. in Execution Case No.5 of 2003. The said
objection was numbered as Misc. Case No. 7 of 2005. The
case of the respondents before the Executing Court was
that the so-called award of 19.04.1997 was nothing but a
provisional direction of the Arbitrators for successful
completion of the job and it cannot be treated as an interim
award and was not enforceable as an arbitral award. All the
directions given in the award dated 19.04.1997 have
merged in the award dated 25.11.2000. After hearing both
the parties, the Executing Court by order dated 27.5.2005
dismissed Misc. Case No. 7 of 2005 holding that the interim
award was not executable. Aggrieved by the same,
respondent No.1 herein preferred C.R.No. 75 of 2005.
Though the Civil Revision stands admitted but no stay of
execution has been granted till date. Thereafter, the
appellant filed an application under Order XXI Rules 18 and
19 of the C.P.C. read with Section 36 of the Act in
Execution Case No. 2 of 2001 for adjustment of the amount
and for recording of full satisfaction of the amount. By
order dated 28.6.2006, the executing Court, after finding
that the question of cross-decree under Order XXI Rules 18
and 19 is not maintainable, rejected the said application.
Questioning the said order, the appellant preferred C.R.No.
65 of 2006 before the High Court of Jharkhand at Ranchi.
By the impugned order dated 19.07.2006, the High Court
dismissed the Revision. Hence, the present appeal by way
of special leave has been filed before this Court.
8) We have heard Dr. R.G. Padia, learned senior
counsel, appearing for the appellant and Mr. Bhaskar P.
Gupta, learned senior counsel, appearing for the
respondents.
9) Though the learned senior counsel appearing on
either side, made elaborate submissions as to awards dated
19.4.1997 and 25.11.2000 and applicability of Order XXI
Rules 18 and 19 of C.P.C., in the light of the order to be
passed hereunder, we are of the view that there is no need
to traverse the same. However, in order to understand the
rival claim, it is useful to refer Order XXI Rules 18 and 19
which read as under:
\023Rule 18. Execution in case of cross-decrees- (1)
Where applications are made to a Court for the
execution of cross-decrees in separate suits for the
payment of two sums of money passed between the
same parties and capable of execution at the same
time by such Court, then \026
(a) if the two sums are equal, satisfaction shall be
entered upon both decrees; and
(b) if the two sums are unequal execution may be
taken out only by the holder of the decree for the
larger sum and for so much only as remains after
deducting the smaller sum, and satisfaction for
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 3
the smaller sum shall be entered on the decree for
the larger sum as well as satisfaction on the
decree for the smaller sum.
(2) \005\005\005\005\005\005\005\005\005\005\005\005
(3) \005\005\005\005\005\005\005\005\005\005\005..
(4) \005\005\005\005\005\005\005\005\005\005\005..\024
\023Rule 19. Execution in case of cross-claims under
same decree \026 Where application is made to a Court
for the execution of a decree under which two parties
are entitled to recover sums of money from each other,
then \026
(a) if the two sums are equal, satisfaction for both shall
be entered upon the decree; and
(b) if the two sums are unequal, execution may be
taken out only by the party entitled to the larger sum
and for so much only as remains after deducting the
smaller sum, and satisfaction for the smaller sum
shall be entered upon the decree.\024
Both the learned senior counsel fairly admitted that Rule 18 is
not applicable to the case on hand. From a bare reading of the
Rules, extracted supra, it is clear that Rule 18 is applicable in
the case where the applications are made to the Court for
execution of the cross-decrees in separate suits for payment of
two sums of money passed between the same parties and
Rule 19 is applicable in the case where the application is made
to the Court for the execution of a decree under which two
parties are entitled to recover sums of money. As rightly
observed by the High Court, in the case on hand, neither the
application has been made for execution of cross-decrees in
separate suits for the payment of money in between the
parties nor the application is for execution of a decree in which
the parties are entitled to recover sums of money from each
other. In our opinion, in the instant case, the particulars
furnished clearly show that the applications were in respect of
two awards in the same arbitration case and as such the
provisions of Rules 18 and 19 of Order XXI of C.P.C. are not
applicable. It is also relevant to mention that in the Objection
Petition under Section 34 of the Act the issue regarding
interim award and final award came up for consideration
before the subordinate Court, Bokaro. The said objection
petition was dismissed on 27.6.2003 and the appeal preferred
also met the same result at the hands of the High Court of
Jharkhand. This Court also confirmed the order of the High
Court except in the rate of interest. In the light of these
materials and earlier orders including this Court and various
clauses in the awards dated 19.04.1997 and 25.11.2000,
learned subordinate Judge rejected the petition filed by the
appellant herein. The High Court by the impugned order
accepted the said factual conclusion and dismissed the
Revision.
10) In view of the conclusion based on the factual
details furnished in both the execution cases while agreeing
with the said conclusion of the Courts below, we are of the
view that there is no need to refer various decisions relied on
by both the parties. On the other hand, we are in agreement
with the said conclusion.
11) In the light of the above discussion, the appeal fails
and the same is dismissed. There shall be no order as to
costs.