Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 50
CASE NO.:
Writ Petition (civil) 4677 of 1985
PETITIONER:
M.C. Mehta
RESPONDENT:
Union of India & Ors.
DATE OF JUDGMENT: 18/03/2004
BENCH:
Y.K. Sabharwal & H.K. Sema.
JUDGMENT:
J U D G M E N T
INTERLOCUTORY APPLICATION NO.1785/01
IN
INTERLOCUTORY APPLICATION NO.22 AND
IN
WRIT PETITION (CIVIL) NO.4677 OF 1985
[With IA Nos.1806, 1815, 1817-1818, 1819, 1822, 1823, 1824, 1825,
1794 and 1795 in IA No.1785 in WP (C) No.4677/85, WP (C)
NO.410/2002, IA No.1832, 1835-1836, 1838 and 1839-1840 in IA
No.1785 in IA No.22 in WP (C) No.4677/85, WP (C) No.661/2002,
WP (C) No.428/2002, WP (C) No.624/2002 and Contempt Petition
(C) No.568/2002 in WP (C) No.428/2002]
Y.K. Sabharwal, J.
The main question to be examined in these matters is whether the
mining activity in area upto 5 kilometers from the Delhi-Haryana border on
the Haryana side of the ridge and also in the Aravalli hills causes
environment degradation and what directions are required to be issued.
The background in which the question has come up for consideration may
first be noticed.
The Haryana Pollution Control Board (HPCB) was directed by orders
of this Court dated 20th November, 1995 to inspect and ascertain the
impact of mining operation on the Badkal Lake and Surajkund -
ecologically sensitive area falling within the State of Haryana. In the report
that was submitted, it was stated that explosives are being used for rock
blasting for the purpose of mining; unscientific mining operation was
resulting in lying of overburden materials (topsoil and murum remain)
haphazardly; and deep mining for extracting silica sand lumps is causing
ecological disaster as these mines lie unreclaimed and abandoned. It was,
inter alia, recommended that the Environmental Management Plan (EMP)
should be prepared by mine lease holders for their mines and actual
mining operation made operative after obtaining approval from the State
Departments of Environment or HPCB; the EMP should be implemented
following a time bound action plan; land reclamation and afforestation
programmes shall also be included in the EMP and must be implemented
strictly by the implementing authorities. The report recommended
stoppage of mining activities within a radius of 5 kms. from Badkal Lake
and Surajkund (tourist place). The Haryana Government, on the basis of
the recommendations made in the report, stopped mining operations within
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 50
the radius of 5 kms of Badkal Lake and Surajkund.
The mine operators raised objections to the recommendations of
stoppage of mining operations. According to them, pollution, if any, that
was generated by the mining activities cannot go beyond a distance of 1
km. and the stoppage was wholly unjustified.
NEERI Report and earlier directions
By order dated April 12, 1996, the Court sought the expert opinion of
National Environmental Engineering Research Institute (NEERI) on the
point whether the mining operations in the said area are to be stopped in
the interest of environmental protection, pollution control and tourism
development and, if so, whether the limit should be 5 kms. or less. NEERI
in its inspection report dated 20th April, 1996, inter alia, recommended that:
"6.1 Mining. (1) Detailed exploratory operations
need to be undertaken to facilitate the estimation
of reserves in the region, and for scientific
management of mining operations.
(2) The mine lease-owners need to undertake
the mining operations in series, i.e. mining
activities must be completed to full potential in a
block before moving to the next. This will help in
reclamation of land in the block in which mining
operations have been completed.
(3 to (9) ...
(10) The Environmental Management Plans
(EMP) being formulated by the mine-owners
should include land rejuvenation and afforestation
programmes, and other measures necessary to
protect the quality of the environment and human
health. The mining operations should commence
only after the approval of EMPs by a designated
authority. A time-bound action plan needs to be
initiated for the implementation of the measures
delineated in the Environmental Management
Plans.
(11) & (12) ...
(13) The question of lifting the ban on mining
operations needs to be considered in conjunction
with the implementation of stringent pollution
control, land reclamation, green belt, and other
Environmental Management measures so as to
facilitate the availability of construction materials
and employment opportunities for the workers
along with the protection of environment and
public health.
(14) It is considered necessary to prepare a
Regional Environmental Management Plan for
urgent implementation to enable eco-friendly
regional development in the area."
On consideration of the reports, this Court came to the conclusion
that the mining activities in the vicinity of tourist resorts are bound to cast
serious impact on the local ecology. The mining brings extensive
alteration in the natural land profile of the area. Mined pits and unattended
dumps of overburdened left behind during the mining operations are the
irreversible consequences of the mining operations and rock blasting,
movement of heavy vehicles, movements and operations of mining
equipment and machinery cause considerable pollution in the shape of
noise and vibration. The ambient air in the mining area gets highly
polluted by the dust generated by the blasting operations, vehicular
movement, loading/unloading/transportation and the exhaust gases from
equipment and machinery used in the mining operations. It was directed
that in order to preserve environment and control pollution within the
vicinity of two tourist resorts, it is necessary to stop mining activity within 2
kms. radius of the tourist resorts of Badkal Lake and Surajkund. The Court
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 50
further directed the Director, HPCB to enforce all the recommendations of
NEERI contained in para 6.1 of its report so far as the mining operations in
the State of Haryana are concerned. Further, it was directed that failing to
comply with the recommendations may result in the closure of the mining
operations and that the mining leases within the area from 2 kms. to 5
kms. radius shall not be renewed without obtaining prior no objection
certificate from the HPCB as also from the Central Pollution Control Board
(CPCB). Unless both the Boards grant no objection certificate, the mining
leases in the said area shall not be renewed. (M.C. Mehta v. Union of
India & Ors. [(1996) 8 SCC 462]).
Present Issues
The aspects to be examined include the compliance of the
conditions imposed by the Pollution Boards while granting no objection
certificate for mining and also compliance of various statutory provisions
and notifications as also obtaining of the requisite clearances and
permissions from the concerned authorities before starting the mining
operations.
In matters under consideration, the areas of mining fall within the
districts of Faridabad and Gurgaon in the Haryana State.
I.A. No.1785/01 has been filed by the Delhi Ridge Management
Board praying that the Government of Haryana be directed to stop all
mining activities and pumping of ground water in and from area upto 5 kms
from Delhi-Haryana border in the Haryana side of the Ridge, inter alia,
stating that in the larger interest of maintaining the ecological balance of
the environment and protecting the Asola Bhatti Wildlife Sanctuary and the
ridge located in Delhi and adjoining Haryana, it is necessary to stop
mining. In the application, it has been averred that the Asola Bhatti Wildlife
Sanctuary is located on the southern ridge which is one of the oldest
mountain ranges of the world and represents the biogeographical outer
layer of the Aravalli mountain range which is one of the most protected
areas in the country. The sanctuary is significant as it is instrumental in
protecting the green lung of National Capital of Delhi and acts as a carbon
sink for the industrial and vehicular emissions of the country’s capital which
is witnessing rapid growth in its pollution level each year. The ridge, it is
averred, is a potential shelter belt against advancing desertification and
has been notified a wildlife sanctuary and reserve forest by the
Government of National Capital Territory of Delhi. Regarding the mining
activities, it is averred that for extraction of Badarpur (Silica sand), there is
large scale mining activity on the Haryana side just adjacent to the wildlife
sanctuary of the ridge which activities threaten the sanctuaries habitat and
also pumping of large quantity of ground water from mining pits. It was
also stated that the ground water level was being depleted as a result of
the mining activity. Further, the query dust that comes out of mining pits is
a serious health hazard for human population living nearby and also the
wild animals inhabiting the sanctuary pointing out that the mining and
extraction of ground water had been banned in National Capital Territory of
Delhi and the ridge being protected as per the order of this Court, it is
necessary, that the ridge on the Haryana side is also protected - that being
the extension of the range and, therefore, mining, withdrawal of ground
water and destruction of flora, etc. should also be restricted outside Delhi
or at least upto 5 kms. from Delhi-Haryana border towards Haryana.
On 6th May, 2002, this Court directed the Chief Secretary,
Government of Haryana to stop, within 48 hours, all mining activities and
pumping of ground water in and from an area upto 5kms. from Delhi-
Haryana border in the Haryana side of the ridge and also in the Aravalli
Hills. The question to be considered is whether the order shall be made
absolute or vacated or modified.
Our examination of the issues is confined to the effect on ecology of
the mining activity carried on within an area of 5 Kms. of Delhi-Haryana
Border on Haryana side in areas falling within the district of Faridabad and
Gurgaon and in Aravalli Hills within Gurgaon District. The question is
whether the mining activity deserves to be absolutely banned or permitted
on compliance of stringent conditions and by monitoring it to prevent the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 4 of 50
environmental pollution.
EPCA Visits
In terms of the order passed by this Court on 22nd July, 2002,
Environmental Pollution Central Authority (EPCA) was directed to give a
report with regard to environment in the area preferably after a personal
visit to the area in question without any advance notice. It may be noted
that EPCA was constituted by the Government of India under notification
dated 29th January, 1998 issued in exercise of power under Section 3(1) &
(3) of the Environment (Protection) Act, 1986 (for short, ’the EP Act’) Mr.
Bhure Lal was appointed its Chairman. The EPCA was constituted with a
view to protect and improve the quality of environment and preventing,
controlling and abetting environmental pollution. EPCA has also the power
to deal with environment issues pertaining to National Capital Region
which may be referred to it by the Central Government. The EPCA has
jurisdiction over the National Capital Region as defined in clause (f) of
Section 2 of the National Capital Region Planning Board Act, 1985. The
Districts of Gurgaon and Faridabad are part of the National Capital Region,
under Section 2(f) read with the Schedule of the said Act.
The Chairman of the CPCB is a convenor member of EPCA. EPCA
made a surprise visit to the area to see the mining sites. The mining sites
visited are located in the villages of Anangpur, Pali, Mohabatabad and
Mangar, which fall within the notified area of 5 km radius from the Delhi
border in the Faridabad district. EPCA also visited mining sites that are
located outside the notified zone in Kot area, EPCA also held consultation
with the officials of the Central Groundwater Board and obtained their
opinion on this matter. On August 7, 2002, members of the EPCA visited
the mining sites located within five km radius from Delhi border. The
objectives of the visit, as per EPCA, were as follows :
1. Assessment of the level of compliance with
the conditions laid down in the regulatory
procedures like the No Objection Certificate
(NOC) granted by authorities to the mine
owners;
2. Evidence of land and habitat degradation in
and around the mining sites;
3. Evidence of misuse and shortage of ground
water in the area;
4. Assessment of the implication of such
activities for the local ecology and drinking
water sources in the area.
During the visit, prima facie, EPCA found evidence of clear violation
of some of the key conditions of order of this court dated May 10, 1996.
EPCA Ist Report and Recommendations
The EPCA gave its report dated 9th August, 2002. It would be useful
to reproduce the said report in extenso as under:
"Anangpur area and its vicinity : EPCA inspected
the mining sites owned by Mohan Ram and
Company as well as at least 5 other mining sites
in this area, which EPCA is not clear who owns.
At the time of visit there was no mining taking
place. So EPCA members assessed level of
compliance with some of the key conditions laid
down in the NOCs. There was clear evidence of
violation of the following conditions.
i. The excavated pits should be filled with fly
ash or municipal solid waste in the bottom
layers. The top soil should be used as a top
layer while filling the pit. Land reclamation
and tree plantation should be done in a
planned manner over the reclaimed mine
pits.
ii. The applicant shall not discharge any
effluent or groundwater outside their lease
premises and shall take appropriate
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 5 of 50
measures for rainwater harvesting and
reuse of water so as not to affect adversely
the ground water table of the area. No
mining operation shall be carried out in the
water table area.
iii. The green belt proposed in the environment
management plan around the proposed
mining lease area and along the road side
shall be developed.
The most serious violation noticed by the EPCA
was the continuation of mining even after reaching
the ground water level which has been disallowed
by the regulatory agencies. Photographs taken by
EPCA, which show deep mining pits have turned
into large lakes of ground water. In this mining
lease area EPCA members saw extensive and
deep water bodies. The water was blue,
indicating that this was groundwater and not
surface water runoff collected in the pits.
Even more serious violation noticed was
configuration of water pipes laid out to draw water
out of the pits to throw them over hills and let the
water flow out. This is a grave misuse of precious
ground water in an area where ground water is the
only source of water for the local population - both
urban and rural.
EPCA members talked to local villagers who
complained that water table in the area has gone
down over a period of time and that the village is
facing water shortage. While earlier ground water
could be tracked at the depth of 30-35 ft. now
deep bore wells have been dug to get drinking
water, in addition, noise and dust pollution from
the mining sites are a problem.
Goodwill mine in Pali village : EPCA found similar
violation of conditions and evidence of mining
sites reaching the level of ground water in deep
pits and pipes fitted to drain out water here as
well.
During the long drive to various mining sites,
EPCA could not see any credible sign of green
belt along the roads. Moreover, one important
condition of NOCs is that "a safe distance should
be maintained from the road to overburden dumps
and the mine pits in accordance with the
directions/notifications of the department of
environment, Haryana and bureau of mines." But
EPCA noticed mining sites very close to the roads
and also very close to the ecologically sensitive
area of Asola sanctuary near the Goodwill mines.
Stone crushing sites in Pali : EPCA has inspected
the stone crushing sites in the area. All sites had
a lot of material and trucks being loaded. It is
difficult to establish if these are the left over
material from the past or were products from
banned sites or from sites from outside the notified
area. EPCA was informed that after the Hon’ble
Supreme Court directive of May 2002, the stone
crushers were not being operated, except
between the hours of 5 am to 9 am. EPCA was,
therefore, unable to verify the working conditions
of these crushers. But it did not find any evidence
of afforestation as stipulated by the NEERI
directive or any evidence of dust minimizing
equipment.
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 6 of 50
Mining around Mangar village : Again the same
situation was found around Anangpur. The
villagers interviewed here were caught between
the devastation of the mines, desperate shortage
of drinking water and the only livelihood option
that these manual stone quarries provided.
Legal mining in Kot area : As mining is banned
along the 5 km radius from the Delhi border,
EPCA also visited some mines that are outside
the notified area to ascertain the state of the
environment. In this area, surface mining is being
done and not deep mining. Therefore, as yet, the
groundwater reserves are not being touched in
this region. The entire area was like a giant dust
field. We saw no evidence of any afforestation or
even dust minimising efforts being undertaken in
the areas that are being mined. We did see one
tanker of water, which was sprinkling the roads,
unable to stop the dust from swirling. EPCA could
not see any protection for the workers from dust.
As this area will clearly emerge as a major mining
in the future, it is important that the mining area is
properly demarcated and environment
management plan implemented to enable
scientific mining to minimize degradation of the
environment.
Faridabad-Gurgaon road : EPCA saw mining
alongside the road. Though the mines were
closed because of the Hon’ble court directive,
EPCA saw vast pits and mining activity in this
area. This is the road for the proposed bypass
from Delhi.
3. The present laws and regulations in the
area
We have assessed the current applicable laws
and regulations in the area, which govern land use
and mining so as to understand what efforts have
been made by different agencies to ensure
compliance.
? In may 1992, parts of the Aravalli range
were declared ecologically sensitive under
the Environment (Protection) Act. Under
this notification, certain activities - including
all new mining operations, including
renewals of mining leases - are restricted
and permission has to be sought from the
Ministry of Environment and Forests. This
notification is valid for reserved forests in
the districts of Gurgaon in Haryana and
Alwar in Rajasthan.
? In August 1992, the Forest Department of
Haryana had issued a notification under the
Punjab Land Preservation Act 1900,
banning the clearing and breaking up the
land not under cultivation, quarrying of
stone... in the Badkal area without prior
permission of the forest department. This
ban was for 30 years. Earlier it had already
issued a similar notification for the Pali area
for 25 years.
? In 1996, the Hon’ble Supreme Court banned
all mining activity within 2 kms of the Badkal
and Surajkund tourist resorts.
? In the same order, it ordered that mining
leases within the area from 2 km to 5 km
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 7 of 50
radius shall not be renewed without
obtaining no-objection certificates from the
Haryana Pollution Control Board as also the
Central Pollution Control Board (CPCB). It
stipulated that "unless both the boards grant
no objection certificate, the mining leases in
the said area shall not be renewed".
? Mining in the 2-5 kms was allowed under
condition that there would be strict
adherence to the environment management
plan laid down by the NEERI. It has to be
noted here that the CPCB had in its report
to the Hon’ble Court in 1996 stated that the
"deep mining for silica is causing an
ecological disaster". CPCB has
recommended that mining activity "should
be stopped within a radius of 5 kms from
Badkal and Surajkund. The subsequent
report of NEERI dated 20.4.1996,
recommended green belt at 1 km radius all
around the boundaries of the two lakes. On
this basis, the Hon’ble Court directed that
radius be extended to 2 kms for a green belt
and to cushion the impacts of air and noise
pollution.
? The Hon’ble Court in its order asked the
agencies to ensure enforcement of the
recommendations of NEERI. It directed that
"failure to comply with the recommendations
may result in the closure of the mining
operations."
4. Compliance and enforcement : absent and
missing
To discuss the future strategy for this area, it
would be important to assess the track-record of
the different agencies in ensuring that the previous
orders and directives are enforced and complied
with.
1. No mining within 2 kms of Badkal and
Surajkund : Probably enforced. But difficult
to assess as the area is hilly.
2. Mining within 2-5 kms should get permission
from Haryana Pollution Control Board and
CPCB. The CPCB has issued 2 NOCs,
dated December 20, 2001 and May 6, 2002.
No further record has been found of NOCs
given for mining in this area. EPCA has not
been able to find the NOCs granted by the
Haryana Pollution Control Board.
Compliance with the environmental management
plans recommended by NEERI as directed by the
Hon’ble Supreme Court.
S.
No.
Directive
Enforced or not
1.
200 mts wide green belt
along Surajkund and
Badkal
Shrubs and wild growth.
No real evidence of good
afforestation.
2.
100 mts wide green belt
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 8 of 50
outside mining lease
boundary
Definitely not done. EPCA
did not see afforestation,
except for some recent
plantation of dying and
dead trees in one or two
places. The sign boards
were more prominent
than the trees they were
supposed to show.
3.
100 mts open
peripheral area around
stone crusher zone with
green belt
Not done
4.
Green belt on either
side of the road
between Surajkund and
Badkal.
We saw large scale
construction on this road
- from schools to
management colleges
and housing colonies.
5.
Mining should
commence only after
the environmental
management plan
(EMP) is approved by a
designated authority
There is no evidence of
an environmental
management plan being
adhered to in this region.
Adherence to the conditions of the No-objection
Certificate granted by CPCB for mining
S.
No.
Directive
Enforced or not
1.
Mining to be done with
approved mining plan
No evidence
2.
Excavated pit to be
filled by fly ash or
municipal solid waste in
the bottom layers.
Overburden should be
used in the middle
layer. Top soil on top
layer and afforestation.
EPCA saw no evidence
that this recommendation
had even been attempted
to be followed. All
abandoned mines were
left open and degraded.
The entire region was
pockmarked with deep
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 9 of 50
holes and overburdens.
3.
No discharge of effluent
or groundwater outside
lease premises. Must
take measures for rain
water harvesting and
reuse of water so as
not to affect the
groundwater table in
the areas. No mining
operations shall be
carried out in the water
table area.
Not done. Gross
violation. See section on
water for details.
4.
Ambient air quality
standards to be
complied with.
No evidence. Mine was
closed.
5.
Noise level at the
boundary shall conform
with noise standards
No evidence. Mine was
closed.
6.
Green belt around
lease area and
roadside
Not done.
7.
Clearance of
groundwater board for
the usage of the
groundwater will be
obtained, for the
conservation of
groundwater and to
ascertain that there will
be no impacts on the
groundwater table of
the area.
No evidence.
Groundwater board has
not given any clearance
that we could ascertain.
From the above, it is clear that little or nothing has
been done to seriously comply with the directives
of the Hon’ble Supreme Court as well as to
enforce the regulations and conditions laid down
by the authorities for environmental management
of the mining areas.
5. Impact on groundwater reserves
It has been argued by the Government of Haryana
in its IA no.1785 of 2001 that the expert committee
constituted by it under the Chairmanship of the
principal conservator of forests has submitted that
there is a water divide between the two
boundaries of the two states which prevents the
flow of water from Delhi side to Haryana side. It
has, therefore, argued that the mining on the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 10 of 50
Haryana side is not affecting the water balance in
the Delhi side of the ridge.
It has further said that only in four pits the
groundwater was pumped regularly and in two pits
occasionally. Therefore, it has argued that little or
no impact on groundwater reserves is possible.
5.1 Groundwater Board
EPCA requested the Central Ground Water Board
(CGWB) for its opinion. The Board has based its
recommendations on the data available with it as
well as a field survey.
The key issues are :
1. On the issue of the ridge providing a water
divide between the two states, the CGWB
has maintained that while the surface water
divide follows the Delhi-Haryana border,
except in the catchment of Bhuria Nala, ‘the
surface water divide may not be the
groundwater divide in the strict sense due to
secondary porosity and also flat topped
nature of the hills.’ It also states that the
Aravalli hills are highly fractured, jointed and
weathered making the major recharge zone
for the surrounding areas.
2. On the impact on the groundwater reserves
due to mining, the Board has found that its
observation wells have shown an increase
in groundwater levels in Anangpur, Mangar,
after the mining has been stopped in May.
Therefore, in spite of monsoon failure and
continued abstraction of water, the
observation wells have noted increased
water levels within just 2 months of the
mining being closed.
The groundwater levels in a tube well
monitored in Mewla Maharajpur during mid
July and first week of August showed a rise of
0.18 metres, A higher rise - 0.71 to 0.78 metres
was observed in the two tube wells near the
Mangar mines and Pali mines in the two
months since the mines were closed. This
clearly points to the impact of mining on
groundwater reserves.
This fact was also confirmed in the interviews
done by EPCA at site.
3. CGWB also notes that contrary to what has
been claimed, the mined water is not being
pumped into abandoned pits to recharge the
groundwater. Instead the groundwater
pumped is discharged into the surrounding
nalas, leading to "wastage" of groundwater.
For instance, in the case of Anangpur
mines, the water was pumped into the
Bhuria Nala and in the case of Pali, the
groundwater was discharged into a nala to
the Badkal lake and from Manger mine
towards Dhauj lake causing "enormous
losses to groundwater resources of the
area". The mined water is also full of silt,
which reduces recharge as well.
4. Furthermore, CGWB notes that the large
surface lakes in the mines are leading to
huge losses of groundwater through
evaporation.
5. The Central Ground Water Authority
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 11 of 50
(CGWA) has notified these areas - South
district of NCT Delhi, Faridabad,
Ballabhgarh Municipal Corporation area,
Gurgaon town as water stressed areas and
has put regulatory measures on ground
water development in these areas.
Given all this, CGWB concludes that the
"dewartering of mines in the Aravalli hills has
affected groundwater regimes of the mine area as
well as buffer zone resulting in the depletion of
ground water resources."
5.2 Compliance with groundwater related
regulations
The NOC given by the Central Pollution Control
Board, includes an explicit condition regarding
ground water :
That the mine owner will ensure that there is
no discharge of effluent of ground water
outside lease premises. They must take
measures for rain water harvesting and
reuse of water so as not to affect the
groundwater table in the areas. Most
importantly, it stipulates that no mining
operations shall be carried out in the water
table area.
This condition has been grossly violated. Even
the Haryana government’s affidavit in court
accepts that pumping of ground water is taking
place, though it attempts to soften the issue by
arguing that it is only being done in a few cases.
Under this condition, mining is not allowed in the
water table area. EPCA saw deep and extensive
pits of mines with vast water bodies. EPCA also
saw evidence of pumps and pipes being used to
drain out the ground water so that mining could
continue. Therefore, the miners are mining for
silica, but also in the process, mining and
destroying the ground water reserves of the areas.
In times of such water stress and desperation, this
water mining is nothing less than a gross act of
wastage of a key resource. This time the stress
has been further aggravated by the failure of
monsoon. Notices have been issued in the
nearby housing colonies stating that fall in
groundwater table due to lack of rains is
responsible for water shortage in the area this
season. This only indicates how important it is to
conserve ground water in the region for long term
sustainability of drinking water sources. Ground
water is the only source of drinking water here."
On the basis of study and visit as well as the report of the Central
Ground Water Board, EPCA made the following recommendations :
"1. The ban on the mining activities and
pumping of ground water in and from an
area upto 5 kms. from the Delhi-Haryana
border in the Haryana side of the ridge and
also in the Aravalli Hill must be maintained.
2. Not only must further degradation be halted
but, all efforts must be made to ensure that
the local economy is rejuvenated, with the
use of plantations and local water
harvesting based opportunities. It is indeed
sad to note the plight of people living in
these hills who are caught between losing
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 12 of 50
their water dependent livelihood and
between losing their only desperate
livelihood to break stones in the quarries. It
is essential that the Government of Haryana
seriously implements programmes to
enhance the land based livelihood of people
? agriculture, animal care and forestry.
Local people must not be thrown into
making false choices, which may secure
their present but will destroy their future.
Already, all the villages visited by EPCA
complained of dire and desperate shortages
of drinking water. Women talked about long
queues before taps to collect water.
Clearly, water resources of the region are
critical inputs to development and cannot be
wasted and destroyed like this. The state
government must come up with strategies to
involve local communities in the future
development of this region.
We have been given to understand that
under the mining lease, 10 per cent of the
royalty is to be given to local villagers. We
have also understood that the turnover is of
the mining operations in this area is
substantial ? between Rs.50 lakhs to Rs. 1
crore a day were the gross estimates
provided to us. However, we do not have
any estimate of the money that has been
given to villagers from this revenue. But
there was little evidence in these poor and
destitute villages that any effort had been
made to share the proceeds with them.
3. The Central Ground Water Board must be
consulted urgently about what should be
done with the huge standing water in the
area. This is a valuable national resource
and the Board should be asked if the water
is best conserved by covering it to stop
evaporation or should it be used for
recharge and storage with further water
harvesting efforts.
4. The Ministry of Environment and Forests
(MOEF) should be asked to extend the
notification under the Environment
(Protection) Act to the Faridabad part of the
Aravalli and ridge as well. Currently, the
notification is only for Gurgaon district. This
notification declaring it an ecologically
sensitive area will help to regulate the
activities in this region.
5. It is not clear to us if adequate planning for
water is being done in the large scale
construction activities being undertaken in
this area. This aspect is outside the
purview of this report but needs to be
examined carefully.
6. It must also be noted that Gurgaon-
Faridabad road is being proposed as the
major bypass for the city of Delhi. The
Hon’ble Court will note its directives on the
air pollution case in this regard. It has been
said to the court in that matter that the
Government of Haryana is intending to
widen the road and bids have even been
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 13 of 50
issued to this effect. Therefore, it is all the
more important that the mining activity along
the road must not be allowed. The 5 kms.
ban from the border of Delhi will take care of
this requirement.
7. EPCA would also recommend that the
mining area outside the 5 kms. area must
be demarcated and regulated. In this
context, EPCA would like to draw the
attention of the court to the violations and
gross disregard for regulations found in the
present mines. It is not out of place to
mention that these mines are owned by very
powerful and highly placed individuals in the
establishment. In a related case the High
Court of Punjab and Haryana has directed
on 20.4.2001 a CBI enquiry on the basis of
a public interest litigation filed by a
journalist. In its order the Hon’ble Court
maintained that its examination has found
evidence that illegal mining operations are
going on in the area. The Hon’ble Court
also noted the bias of the State Government
to shield the offenders and has said that
because there is prima facie evidence of the
involvement of a ‘person who holds the high
position of the cabinet minister in the state’,
the enquiry should be done by CBI. This
enquiry is still ongoing.
During the examination of the case, EPCA
was told of other persons involved in the
mining activity who are highly influential and
part of the ruling political parties in the state
and Centre.
In this respect, EPCA would recommend
that tighter and constant monitoring of the
area must be done by a Central
Government agency. To increase
accountability, EPCA would also
recommend that the environment
management plan (EMP) for the mining
area as well as the conditions of the NOC
should be made a public document. All
other subsequent monitoring reports of this
region must be available publicly, preferably
on the website of the monitoring agency."
With the report, a note given by the Chairmen, Central Ground
Water Board on impact of pumping of ground water from mines and
ground water regime in mining area and its buffer zone in Aravalli hills of
NCT Delhi, Faridabad and Gurgaon Districts of Haryana was also
annexed. The said note reads as under :
Based on available data with Central Ground
Water Board and a quick survey in and around
mining area in Aravalli hills, following observations
are made -
"1. The area under consideration forms part of
Aravalli range from where mining of silica-
sand and other construction material was
being carried out. The mining of silica sand
was mainly carried out below water table by
dewatering the mines whereas mining for
other construction material is carried out
above water table. The major mining areas
are Anangpur, Pali, Manger and
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 14 of 50
Mohabbatabad.
2. The surface water divide in the area
approximately follows Delhi-Haryana
boarder except the catchment of Bhuria
Nala flowing in Haryana State, which
extends in Asola area of Delhi State also.
The formations in the Aravalli hills are highly
fractured, jointed and weathered making it
the major recharge zone for the surrounding
areas. The surface water divide may not be
ground water divide in strict sense due to
secondary porosity and also flat-topped
nature of the hills.
3. The pumping of ground water during mining
of Silica sand affects ground water regime
of surrounding area. During the field visit, it
was reported by local people that during the
dewatering of mines there was decline in
ground water levels and reduction in
discharge in surrounding wells whereas
after stoppage of pumping the rise in water
levels and increase in discharge has been
reported. In few observation wells on down
stream side of mines rise in ground water
levels has been observed in Anangpur,
Manger and villages after stoppage of
abstraction of ground water from deep
mines. The ground water levels in a tube
well monitored in Mewla Maharajpur during
mid July 2002 and first week of August 2002
were 24.39 and 24.57 m. below ground
level respectively, showing a rise of 0.18 m.
Ground water levels in tube well located at
temple near Manger mine in second week
of July 2002 and first week of August, 2002
were 51.70 and 49.99. m. below ground
level respectively showing a rise of 0.71 m.
Similarly, ground water level in a tube well
at Indernagar in Delhi area near Pali mine in
third week of June 2002 and first week of
August 2002 were 59.68 and 58.90 m.
below ground level respectively showing a
rise of 0.78 m. The stoppage of dewatering
of mines has resulted in rise of ground
water levels in surrounding areas.
4. It has been observed that drainage pattern
of the area has been modified due to
haphazard mining and dumping of waste
material which has bearing on natural path
of ground water flow in the area.
5. It is claimed that abandoned pits act as
recharge pits and in some cases the
pumped ground water is put in these pits so
there may not be substantial modification in
the conditions of ground water regime. All
the ground water pumped out from
Anangpur mine has not been put into
abandoned adjoining pits resulting in
wastage of ground water by discharge into
Bhuria Nala. Observation have indicated
that Bhuria Nala which was ephemeral
stream became a perennial stream during
mining operations and now flow has
stopped after closure of mining activity.
Similarly, pumped out ground water from
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 15 of 50
Pali mine was being discharged in a
easterly flowing nala to Badkal Lane and
from Manger mine in a south westerly
flowing nala towards Dhauj lake causing
enormous losses to ground water resources
of the area. Further, the pumped out water
cannot be recharged effectively due to its
high silt content. In silica sand mines the
water table has been intersected and in
presently exposed to the atmosphere
causing huge losses to ground water
through evaporation.
6. Studies conducted by Central Ground Water
Board have revealed that water levels in
Faridabad new town which falls in buffer
zone of mine area have declined by 1.44
m/year. The decline of ground water level
in the towns has been attributed to over
development of ground water for domestic
and industrial uses which is totally
dependent on ground water. The pumping
out of ground water for mining of silica sand
in recharge zone might have aggravated the
declining trend of ground water levels which
otherwise would have contributed to the
buffer zone.
7. Central Ground Water Authority has notified
South district of NCT Delhi and Faridabad
and Ballabhgarh Municipal
Corporation area and Gurgaon town and
adjoining industrial area in August 2000,
October 1998 and December 2000
respectively mainly on consideration of over
development of ground water resources
resulting in substantial decline in ground
water levels. Regulatory measures on
ground water development have been
imposed in these areas.
8. Therefore, it is observed that dewatering of
mines in Aravalli hills has affected ground
water regime of the mine area as well as
buffer zone resulting in depletion of ground
water resources."
When the aforesaid report came up for consideration, some of the
mine owners submitted that their mines had not been inspected by Bhure
Lal Committee. Particulars of the mines that were stated to have not been
inspected were filed on 23rd September, 2002. Bhure Lal Committee was
requested to carry out the inspection of the said areas/mines. The
Committee was also permitted to associate such other organizations or
persons as it may deem fit and proper for the purpose of inspection.
EPCA 2nd Report and Recommendations
In terms of the aforesaid order, 26 mines were inspected and report
dated 21st October, 2002 was submitted. The observations made as a
request of inspection in regard to each mine are as follows :
"The numbers indicated in parenthesis are serial
number of mines given in the list of mines
furnished by Kailash Vasudev, senior advocate to
the Hon’ble Supreme Court that was forwarded to
EPCA.
1. (no.9)
Name of Mine/Area : New Anangpur Silica Sand
Mines M/s S.P. Sethi,
Location : Village New Anangpur, Distt. Faridabad.
Total Area of Land on lease/Actual area under
mining activity : 186.52 hec.
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 16 of 50
Mineral Extracted : Silica Sand Mines
Status of Mining : Above groundwater level
Whether groundwater is extracted : No.
Status of environmental clearances : No clearance
given. No environmental management plan.
This mine is located very close to the Delhi border
(in close proximity to the Asola sanctuary). EPCA
members were shown two pits, which were not
being worked currently. There was no
groundwater exploitation seen in these pits. Only
brown stagnant rain water was seen. But what
was very clear was that this mining lease was
adjoining the boundary of Delhi. Only recent
plantation of sapling was noticed along the path.
2. (13)
Name of Mine/Area: Anangpur Silica Sand Mines
M/s. Mohan Ram and Co.
Location : Village Anangpur, Distt. Faridabad.
Total Area of Land on lease/Actual area under
mining activity : 175.00 Hec.
Mineral Extracted: Silica Sand Mines.
Status of Mining : Below groundwater level
Whether ground water is extracted : Yes
Status of environmental clearances : NOC granted
by state pollution control board for renewal of
lease in 1999. No environmental management
plan.
This mine has large pits where sand and silica
was being extracted. This was a working mine
and had large amount of water in the two pits.
EPCA members also saw a pipe, which was
currently unused, meant for pumping out the water
from the pits. The pits were at least 100-150 feet
deep and the groundwater had been clearly
exploited for some time. Large amount of
overburden were also seen in the area.
3. (12)
Name of Mine/Area: Anangpur Silica sand mines,
M/s. S.P. Sethi, Anangpur.
Location: Village Anangpur Distt. Faridabad.
Total Area of Land on lease/Actual area under
mining activity: 489.34 hec.
Mineral Extracted : Silica sand, China clay,
ordinary sand, stone road material (RM) and
masonry stone (MS)
Status of Mining : Below groundwater table
Whether ground water is extracted : Yes.
Status of environmental clearances: No clearance
given. No environmental management plan.
The mining pit here has tuned into a huge
groundwater lake, Groundwater is fully exposed.
Extensive oberburden could be seen near the pits.
It was very evident that no major efforts were
made to create plantation in the area. Some new
and young saplings could be seen along side the
paths leading to the pits. Clearly these were
planted very recently.
4. (8)
Name of Mine/Area: Anangpur Silica sand mines,
M/s. Rajdhani Minerals Corporation.
Location: Village Anangpur Distt. Faridabad.
Total Area of Land on lease/Actual area under
mining activity: 188.47 hec.
Mineral Extracted : Silica sand, China clay,
ordinary sand, stone RM and MS
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 17 of 50
Status: seen one closed pit. Did not see any
water.
Status of environmental clearances: NOC granted
by State Pollution Control Board.
5. (7)
Name of Mine/Area: Mewla maharajpur Silica
sand mines, M/s K.C. Ahuja & Co.
Location: Village Mewla Maharajpur Distt..
Faridabad.
Total Area of Land on lease/Actual area under
mining activity: 162.905 hec.
Mineral Extracted : Silica sand, China clay,
ordinary sand, stone road material (RM) and
masonry stone (MS)
Status : surface mining from the rocks
Whether ground water is extracted : No.
Status of environmental clearances: No clearance
given. No environmental management plan.
One pit seen, Mostly stone being quarried. Some
water seen. No evidence of tree plantation seen
in the area. But mine pits are ajoining road.
6. (19)
Name of Mine/Area: M/s. Ramkrishna Purni Devi..
Location: Village Badkal Distt. Faridabad.
Total Area of Land on lease/Actual area under
mining activity: 369.4 hec.
(Of this 121 hec. Falls within 2 km of Badkal
Tourist Complex where mining has been banned)
Mineral Extracted : Silica sand, ordinary sand,
road metal, masonry stone and minor mineral
Status: mining above groundwater table
Whether ground water is extracted : No.
Status of environmental clearances: No clearance
given. No environmental management plan.
EPCA members saw one pit located next to the
border of Delhi. The mining area is hard rock and
the pit was being worked for stone. The mining
site was at the boundary of Delhi and the Asola
sanctuary was seen at a close distance. This
mine is also adjoining the road.
7. (2)
Name of Mine/Area: Mohan Ram & Co. Proprietor
Kartar Singh.
Location: Village Pali Distt. Faridabad.
Mineral extracted : Ordinary stone, road metal,
masonry stone
Under litigation in High Court of Delhi.
8. (11)
Name of Mine/Area: Pali Silica Sand Mines, M/s
Goodwill Mineral Corporation.
Location: Village Pali, Distt. Faridabad.
Total Area of Land on lease/Actual area under
mining activity: 50.5 hec.
Mineral Extracted : Silica sand, China clay, sand
Status of Mining : Below water table.
Whether ground water is extracted : Yes.
Status of environmental clearances: NOC granted
by State Pollution Control Board in 1999 for
renewal of lease. Asked to comply with conditions
laid down by CPCB as well. No environmental
management plan as yet.
A deep pit with extensive water body. Pipes
pumps and generators could be seen at the site.
Water is extracted from the pit. Very little
plantation could be seen at the site. The pit is
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 18 of 50
contiguous to other mines in the area and the
extent of groundwater being exploited is massive
and the expanse is vast. Some trees have been
planted along the roadside. This mine is adjoining
the main Delhi bypass of Faridabad-Gurgaon,
which is being tendered for a four-lane highway.
9. (17)
Name of Mine/Area: M/s. Sheeshpal Singh
Location: Village Pali, Distt. Faridabad.
Total Area of Land on lease/Actual area under
mining activity: 127.95 hec.
Mineral Extracted : Silica, China clay, sand,
quartzite
Status: Below groundwater table.
Whether ground water is extracted : Yes.
Status of environmental clearances: No clearance
given. No environmental management plan.
Large lake of ground water could be seen at the
site. The lake apparently covers a few contiguous
mining pits. No efforts to create plantation in the
area except a few young saplings which seemed
to have been planted very recently. Huge
overburden could be seen near the pits. This
mine is adjoining the main Delhi bypass of
Faridabad-Gurgaon, which is being tendered for a
four lane highway.
10. (20)
Name of Mine/Area: M/s. Ram Chandar
Location: Village Gothra, Mohatabad, Distt.
Faridabad.
Total Area of Land on lease/Actual area under
mining activity: 296 hec.
Mineral Extracted : Silica sand, ordinary sand,
road metal and masonry stone.
Status: Below groundwater table
Whether ground water is extracted : Yes.
Status of environmental clearances: No clearance
given. No environmental management plan.
Deep mining pits with large water bodies could be
seen. The mine is also contiguous to the other
mines so the amount of water that is being
exploited is massive and uncontrolled. Huge
amounts of overburden were also seen in the
area. In this mine some efforts have been made
to create plantations and the trees, unlike those
seen in other areas, were more mature. This mine
is adjoining the main bypass of Faridabad-
Gurgaon, which is being tendered for a four-lane
highway.
11. (22)
Name of Mine/Area: M/s. Maruti Minerals.
Location: Plot No.1 Village Manger, Distt.
Faridabad.
Total Area of Land on lease/Actual area under
mining activity: 63.225 hec.
Mineral Extracted : Silica sand, China clay,
ordinary sand, road metal and masonry stone.
Status: above groundwater.
Whether ground water is extracted :No .
Status of environmental clearances: clearance
given. No environmental management plan.
Observed surface stone mining. No water seen.
New lease and so the mines have not reached
ground water levels as yet. But mine ear Delhi
bypass of Faridabad-Gurgaon road.
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 19 of 50
12A. (1)
Name of Mine/Area: M/s. Seven Mines and
Minerals Pvt. Ltd.
Location: Plot No.6, Village Manger, Distt.
Faridabad.
Total Area of Land on lease/Actual area under
mining activity: 59.3875 hec.
Mineral Extracted : Ordinary sand, road metal and
masonry stone.
Status: Above groundwater table
Whether ground water is extracted : No.
Status of environmental clearances: Clearance
given. No environmental management plan.
Observed surface stone mining. No water seen.
New lease and so the mines have not reached
groundwater levels as yet. But mine near Delhi
bypass of Faridabad-Gurgaon Road.
12B.
Name of Mine/Area: M/s. Seven Mines & Minerals
Pvt. Ltd.
Location: Plot No.8, Village Manger, Distt.
Faridabad.
Total Area of Land on lease/Actual area under
mining activity: 63.75 hec.
Mineral Extracted : Ordinary sand, road metal and
masonry stone.
Status: Above groundwater table
Whether ground water is extracted : No.
Status of environmental clearances: Clearance
given. No environmental management plan.
Observed surface stone mining. No water seen.
New lease and so the mines have not reached
groundwater levels as yet. But mine near Delhi
bypass of Faridabad-Gurgaon road.
13. (25)
Name of Mine/Area: M/s. Ashok Minerals industry
Location: Plot No.7, Village Manger, Distt.
Faridabad.
Total Area of Land on lease/Actual area under
mining activity:67.00 hec.
Status: Above groundwater table
Whether ground water is extracted : No.
Status of environmental clearances: No clearance
given. No environmental management plan.
Observed surface stone mining. No water seen.
New lease and so the mines have not reached
groundwater levels as yet. But mine is on the
Delhi bypass of Faridabad-Gurgaon road.
14. (23)
Name of Mine/Area: M/s. Jaikrishan Impex Pvt.
Ltd.
Location: Plot No.2 & 3, Village Manger, Distt.
Faridabad.
Total Area of Land on lease/Actual area under
mining activity: 44.785 hec and 56.4375 hec.
Mineral Extracted : Stone mining
Status: Below groundwater table
Whether ground water is extracted : Yes.
Status of environmental clearances: No clearance
given. No environmental management plan.
Was shown one pit with small water collection.
But at a distance seen another pit with large
amount of groundwater collected. This mine is
being worked and clearly water must have been
pumped from the mine. Deep pits seen. But mine
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 20 of 50
is near Delhi bypass of Faridabad-Gurgaon road.
15. (10)
Name of Mine/Area: M/s. Faridabad Gurgaon
Minerals.
Location: Plot No.5 Village Manger, Distt.
Faridabad.
Total Area of Land on lease/Actual area under
mining activity:33.0375 hec.
Mineral Extracted : Ordinary sand, road metal and
masonry stone
Status: Below groundwater table
Whether ground water is extracted : Yes.
Status of environmental clearances: No clearance
given. No environmental management plan.
Exposed groundwater could be seen. This mine
was also been worked. Deep pits seen in this
mine.
16. (24)
Name of Mine/Area: M/s. Patram Mines and
Minerals Pvt. Ltd.
Location: Plot No.11, Village Manger, Distt.
Faridabad.
Total Area of Land on lease/Actual area under
mining activity: 126.75 hec.
Mineral Extracted : Silica sand and stone
Status: Above groundwater table.
Whether ground water is extracted : No.
Status of environmental clearances: No clearance
given. No environmental management plan.
Stone quarry. No water seen. Some efforts have
been made to create plantation.
17. (18)
Name of Mine/Area: M/s. Sheeshpal Singh
Location: Village Pali, Distt. Faridabad.
Total Area of Land on lease/Actual area under
mining activity: 44.48 hec.
Mineral Extracted : Solica/Ord. Sand & stone, road
metal and masonry stone
Status: Above groundwater table
Whether ground water is extracted : No.
Status of environmental clearances: No clearance
given. No environmental management plan.
Recent lease. Mining activity had recently started.
New pit seen and as yet only stone was being
quarried.
18. (4)
Name of Mine/Area: Pali Silica Sand Mines, M/s.
S.P. Sethi.
Location: Village Pali, Distt. Faridabad.
Total Area of Land on lease/Actual area under
mining activity: 82.20 hec.
Mineral Extracted : Silica/Ord. Sand, china clay
stone (road metal and masonry)
Status: Below groundwater table
Whether ground water is extracted : Yes.
Status of environmental clearances: NOC given by
State Pollution Control Board in 1999 for renewal
of lease. No environmental management plan.
Pit with little water seen. Being worked. Large
amount of overburden was seen close to mine. 1
hec of plantation created near mine.
19. (3)
Name of Mine/Area: Pali Silica Sand Mines, M/s.
P.K. Sethi
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 21 of 50
Location: Pali, Distt. Faridabad.
Total Area of Land on lease/Actual area under
mining activity: 162 hec.
Mineral Extracted : Sand china clay, stone (road
and masonry)
Status: Above groundwater table
Whether ground water is extracted : No.
Status of environmental clearances: No clearance
given. No environmental management plan.
Pit with no water seen. Being worked. Large
amount of overburden was seen close to mine.
20. (5)
Name of Mine/Area: Pali Silica Sand Mines, M/s.
Lucky Minerals
Location: Village Pali, Distt. Faridabad.
Total Area of Land on lease/Actual area under
mining activity: 261.36 hec.
Mineral Extracted : Sand, china clay stone (road
metal and masonry)
Status: Above groundwater table
Whether ground water is extracted : No.
Status of environmental clearances: No clearance
given. No environmental management plan.
Pit with no water seen. Being worked. Large
amount of overburden was seen close to mine.
Nominal plantation seen. But area with lessee is
very large over - 261 ha - and no idea if other
mines in the area have reached water levels.
21. (6)
Name of Mine/Area: Mohabatabad Silica sand
mines, M/s. P.K. Sethi
Location: Village Mohtabad, Distt. Faridabad.
Total Area of Land on lease/Actual area under
mining activity: 399.59 hec.
Mineral Extracted : Sand, china clay, stone (road
metal and masonry)
Status: Above groundwater table
Whether ground water is extracted : No.
Status of environmental clearances: No clearance
given. No environmental management plan.
Shown pit where stone is being quarried. But area
with lessee is very large over - almost 400 hec. -
and no idea if other mines in the area have
reached water level as yet.
22. (14)
Name of Mine/Area: M/s. Tejvir Singh and Co.
Location: Village Bandhwari, Distt. Gurgaon.
Total Area of Land on lease/Actual area under
mining activity: 91.20 hec.
Mineral Extracted : Silica Sand, Ord. Sand, china
clay, quartz & stone mine.
Status: Above groundwater table
Whether ground water is extracted : No.
Status of environmental clearances: Clearance
given. No environmental management plan.
Stone quarry. Very recent lease granted and
clearance has only been done in April 2002.
Large seemingly abandoned, pits seen on road.
Labourer colony near on road near mine and a
number of trucks seen on this road carrying
material. No plantation seen.
23. (15)
Name of Mine/Area: Mr. Ashok Gupta
Location: Village Balola, Distt. Gurgaon.
Total Area of Land on lease/Actual area under
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 22 of 50
mining activity: 19.15 hec.
Mineral Extracted : Silica Sand and china clay.
Status: Above groundwater table
Whether ground water is extracted : No.
Status of environmental clearances: Clearance
given. No environmental management plan.
Stone quarry Recent lease and clearance of
January 2002. No plantation seen. The mine is
on the main Delhi bypass - Gurgaon-Faridabad
road, which is being developed as a four-lane
bypass.
24. (16)
Name of Mine/Area: Mr. Ashok Gupta
Location: Plot No.3, Village Behrampur, Distt.
Gurgaon.
Total Area of Land on lease/Actual area under
mining activity: 94.05 hec.
Mineral Extracted : Silica sand quartzites.
Status: Above groundwater table
Whether ground water is extracted : No.
Status of environmental clearances: No clearance
given. No environmental management plan.
Stone quarry. Recent lease. No plantation seen.
But near village. As this mine is near the five km
radius, other mines with crushers and blasting
seen at close distance.
(11B - 22)
Name of Mine/Area: M/s. Maruti Minerals
Location: Village Haidpur, Distt. Gurgaon.
Total Area of Land on lease/Actual area under
mining activity: 18.125 hec.
Mineral Extracted : Stone
Status: Above groundwater table
Whether ground water is extracted : No.
Status of environmental clearances: No clearance
given. No environmental management plan.
Stone quarry. No plantation seen. Near
habitation of Gurgaon town.
25. (21)
Name of Mine/Area: Mr. Karan Singh
Location: Village Nathpur, Distt. Gurgaon.
Total Area of Land on lease/Actual area under
mining activity: 5.996 hec.
Mineral Extracted : Silica Sand .
Status: Above groundwater level (surface mining)
Whether ground water is extracted : No.
Status of environmental clearances: No Clearance
given. No environmental management plan.
Stone quarry. No plantation seen. Mine on main
Delhi-Gurgaon road at the border of Delhi. Mine
lease recently awarded at the edge of the DLF
residential colony. Allegations that illegal mining
is being done at the Delhi side of this mine. Next
to the protected area of Delhi forest.
In respect of the ground water regime the report states that :
"The key issue to examine is the impact of mining
on the ground water regime in the region. It is
evident from the inspection done by EPCA that
ground water reserves are being exploited and
destroyed, it must be stressed that it is not a
matter of individual mines reaching ground water
levels or not, the issue to examine is the water
regime of the entire area."
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 23 of 50
The report further states that "during its inspection to the mines,
Kartar Singh Badana, Minister of Cooperatives in the State and also a
mine owner told EPCA members that the impact of ground water
abstraction is minimal. He maintained that the miners were harvesting the
water and not allowing it to flow to the Yamuna, where it would be lost to
the State. A perusal of the reports of the ground water regime shows that
this contention cannot be upheld."
It is also stated in the report that "the geology and geomorphology of
the area comprises oldest exposed lithology with upland units. The rock
type is mainly quartzite and these rise 150-200 metres above ground level
in the quartzite’s the ground water aquifers occur in the weathered zones
and interspaces within interconnected joints and fractures. According to
the CGWB, the unconfined aquifer is about 50 metres thick. But between
the 50-110 metre below ground level (bgi) a thick clay layer ranging in
thickness from 25-60 metres separates the top unconfined aquifer from
the confined aquifer.
The mines inspected by EPCA were below 150 feet (45 metres) and
on checking it was found that most mines were further operating at 20-100
feet (6-30 metres) below water levels. This means that the mines are
abstracting water from the confined aquifer. As annual rainfall mostly
replenishes the unconfined or top aquifer levels, the mining activity is
destroying a non-renewable resource. EPCA saw deep and extensive pits
of mines with vast waterbodies ? stretching at times to a kilometer and
more. EPCA also saw evidence of pumps and pipes being used to drain
out the ground water so that mining could continue. Therefore, the miners
are mining for silica, but also in the process mining and destroying the
ground water reserves of the areas.
The NOC given by the Central Pollution Control Board includes an
explicit condition regarding ground water :
"That the mine owner will ensure that there is no
discharge of effluent or ground water outside
lease premises. They must take measures for
rain water harvesting and reuse of water so as not
to affect the ground water table in the areas. Most
importantly, it stipulates that there should be no
mining operations shall be carried out in the water
table area."
The report of the Central Ground Water Board states very
categorically that the ground water table is already at a critical stage in
Faridabad. It states, ‘The stage of ground water development of
Faridabad block is 89.02 percent in dark category and no further
abstraction of ground water should be carried out to avoid any adverse
environment impact on ground water regimes. Thus no additional tube
wells are advisable to be constructed for community water supply scheme
even though they may not affect the storage in Badkhal lake.’ The report
further states that ‘The domestic water supply to Faridabad town has to be
catered and there are no surface water source which can be tapped.’
EPCA further observes that most of the mining is happening inside
the municipal area of Faridabad. In fact, Department of Mines and
Geology states in the letter dated October 12, 2002, ‘it is submitted that
the mineral rights of the mines vests with the State Government....The
surface rights of villages Badkhal, Pali, Gothra, Mohabtabad, Anangpur,
Mewla Maharajpur are with municipal corporation, Faridabad, and
Manager revenue estate are with gram panchayat.’
Sensitivity of this region is further accentuated by its close proximity
to the reserved forests of Asola sanctuary located at the border of Delhi
and Haryana and other ecologically sensitive areas like Surajkund and
Badkhal lake.
Even in Gurgaon, the CGWB report indicates that the ground water
scenario is grim. According to CGWB, the ‘ground water development of
Guirgaon block is 124 per cent, indicating that the entire block in which
Gurgaon town is situated is over exploited.’ The ground water levels are
also falling dangerously according to the report of CGWB which
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 24 of 50
recommends strict regulatory measures for ground water use.
The EPCA, while reaffirming the recommendations that had been
made in its earlier report dated 9th August, 2002, made the following
recommendations :
"The overall assessment of the environmental
impact of the mining activities in the area
especially its implication for ground water level in
the region reaffirms EPCA’s assessment
presented in its earlier report. EPCA upholds its
earlier recommendations made vide the report
submitted to the Hon’ble Supreme Court on
August 9, 2002.
EPCA is concerned that if mining is allowed to
continue in this area, it will have serious
implications for the groundwater reserve which is
the only source of drinking water in the area.
EPCA has also noticed uncontrolled construction
activities that will expand urban habitation
considerably in future. Unless immediate
measures are taken to conserve and augment
water resources in the area acute survival crisis is
expected. Interviews with local villagers in the
vicinity of mines confirm that water shortage is
already a serious problem in the region.
The extent of degradation in and around mines is
the evidence of failure to enforce basic rules for
ecological safeguards. Recent attempts at
planting trees are cosmetic. Exposed ground
water lakes observed in mining sites only
reconfirms the worst fears. If mining could not be
stopped in so many pits even after reaching
groundwater level there is no guarantee that even
some of those mines still at the surface level will
abide by the stipulated norms when they reach the
water table."
Submissions for Confirming or varying Order dated 6th May, 2002
Having regard to the ground realities as reflected in the aforesaid
reports, should the order passed on 6th May, 2002 be varied is the
question? The continuance of the order has been strenuously objected to
by the mining lease holders and also by the Government of Haryana.
Various applications have been filed seeking vacation of the order and in
support thereof, submissions have been made mainly by Mr. Shanti
Bhushan, Dr. Rajeev Dhawan, Mr. Kapil Sibbal, Mr. K.B. Rohtagi and Mr.
Dhruv Mehta representing the lease holders and Mr. Mukul Rohtagi,
learned Additional Solicitor General representing the Government of
Haryana. We have also heard Mr. Raju Ramachandran and Mr.Altaf
Ahmad, learned Additional Solicitor Generals for the Ministry of
Environment and Forest, Government of India, Mr. C.S. Vaidyanathan and
Mr. Kaushik (in support of IA No.1825/2002 filed by the villagers). Mr.
Ranjit Kumar, learned Amicus and Mr. M.C. Mehta, Advocate/petitioner-in-
person and Mr. Kailash Vasudeva for Government of Delhi have made
submissions in support of closure of mining activity and for making the
order dated 6th May, 2002 absolute by prohibiting all mining activities and
pumping of ground water in and from an area upto 5 kms. from Delhi-
Haryana Border in the Haryana side of the Ridge and also in the Aravalli
Hills.
Notifications Regarding Mining on Aravalli Hills
The notification dated 7th May, 1992 issued by the Ministry of
Environment and Forest, Government of India under Section 3(2)(v) of the
EP Act read with Rule 5 of the Rules made under the said Act has
considerable bearing on the aspect of mining in Aravalli Hills. The
notification, inter alia, bans all new mining operations including renewals of
mining leases and sets out the procedure for taking prior permission
before undertaking such an activity. The notification, in so far as material
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 25 of 50
for the present purposes, reads :
"S.O.319(E) - Whereas a Notification under
Section 3(1) and Section 3(2) (v) of the
Environment (Protection) Act, 1986 (29 of 1986)
inviting objections against restricting certain
activities in specified area of Aravalli Range which
are causing Environmental Degradation in the
Region was published in the Gazette of India Part
II-Section 3 sub-section (ii) vide S.O. 25 (E) dated
9th January 1992;
And whereas all objections received have
been duly considered by the Central Government;
Now, therefore, in exercise of the powers
conferred by sub-section (1) and clause (v) of sub-
section (2), of Section 3 of the Environment
(Protection) Act, 1986 (29 of 1986), read with rule
5 of the Environment (Protection) Rules, 1986 the
Central Government hereby prohibits the carrying
on the following process and operations, except
with its prior permission, in the areas specified in
the Table appended to this Notification :
(i) ......
(ii) (a) All new mining operations including
renewals of mining leases
(b) Existing mining leases in
sanctuaries/national Park and areas
covered under Project Tiger and/or
(c) Mining is being done without
permission of the competent authority
(iii) Cutting of trees;
(iv) Construction of any clusters of dwelling
units, farmhouses, sheds, community
centers, information centers and any other
activity connected with such construction
(including roads a part of any infrastructure
relating thereto);
(v) ......
2. Any person who desires to undertake any of
the above mentioned processes or operations in
the said areas, shall submit an application to the
Secretary, Ministry of Environment and Forests,
New Delhi, in the attached application form
(annexure) specifying, inter alia, details of the area
and proposed process or operation. He shall also
furnish an Environment Impact Statement and an
Environmental Management Plan along with the
application and such other information as may be
required by the Central Government for
considering the application.
(3) The Central Government in the Ministry of
Environment and Forests shall, having regard to
the guidelines issued by it from time to time for
giving effect to the provisions of the said Act, grant
permission within a period of three months from
the date of receipt of the application or where
further information has been asked for from the
applicant, within a period of three months from the
date of the receipt of such information, or refuse
permission within the said time on the basis of the
impact of the proposed process or operation on
the environment in the said area.
4. For seeking permission under this
Notification, an application in the prescribed form
(see Annexure), duly filled in, may be submitted to
the Secretary, ministry of Environment and
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 26 of 50
Forests, Paryavaran Bhavan, CGO Complex, Lodi
Road, New Delhi.
XXX XXXX XXXX
3.(b)(ii) Erodability classification of the proposed
land.
5.(a) Water balance at site surface and ground
water availability and demand.
XXX XXXX XXXX
12.(a) Environmental Impact Assessment Report:
(b) Environmental Management Plan : prepared
as per Guidelines of MEF issued from time
to time.
(c) Detailed Feasibility Report.
(d) Proposal for diversion of forest land under
Forest (Conservation) Act, 1980 including
benefit cost analysis.
13. Recommendations of the State Pollution
Control Board and/or the State Department of
Environment and Forests."
The aforesaid notification, restricting mining activities in Aravalli
range is relevant for mining operation in Gurgaon district wherein part of
Aravalli hills range exist.
The powers vested in the Central Government in terms of the
aforesaid notification dated 7th May, 1992 were delegated to the State
Governments concerned, namely, Rajasthan and Haryana by issue of
notification dated November 29, 1999 by the Central Government, Ministry
of Environment and Forest. The said notification reads thus :
MINISTRY OF ENVIRONMENT AND FORESTS
NOTIFICATION
New Delhi, the 29th November, 1999
S.O.1189(E).-In exercise of the powers conferred
by section 23 of the Environment (Protection) Act,
1986 (29 of 1986), (hereinafter referred to as the
said Act), read with sub-rule (4) of rule 5 of the
Environment (Protection) Rules, 1986, the Central
Government hereby delegates the powers
conferred on it to take measures for protecting and
improving the quality of the environment and
preventing, controlling and abating environmental
pollution, to be exercised also by the State
Governments as notified in the Notification of the
Government of India in the Ministry of
Environment and Forests S.O. NO.319(E) dated
7th May, 1992 subject to certain conditions which
are as follows :
(i) the State Governments concerned, namely,
Haryana and Rajasthan shall constitute an
Expert Committee for each state as per the
composition given in the Schedule-I
annexed to this Notification;
(ii) each State Government shall also constitute
a Monitoring Committee, under the
chairmanship of the District Collector
concerned (Gurgaon in Haryana and Alwar
in Rajasthan) as given in the Schedule-II
annexed to this Notification which shall inter
alia monitor the compliance of the
conditions stipulated while according
environmental clearance by such State
Governments and report to such State
Government about the violations, if any, and
the action taken thereon;
(iii) The District Collectors of Gurgaon in
Haryana and Alwar in Rajasthan shall be
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 27 of 50
authorised by the respective State
Governments to take necessary action
under section 5 of the said Act in respect of
cases where the project proponents fail to
implement the conditions.
2. The State Government concerned shall
initiate steps to prepare a Master Plan for the
development of the area covered by the
Notification S.O. 319(E) dated 7th May, 1992
integrating environmental concerns and keeping in
view the future land use of the area. This Master
Plan shall be prepared by the concerned state
agency, approved by the competent authority and
finally published within two years from the date of
issue of this Notification, in accordance with the
procedure laid down in the Town and Country
Planning Act or any other similar Act of the
respective State Government. The State
Government concerned shall implement the
Master Plan forthwith after its final publication.
3. Any person desirous of undertaking any of
the activities mentioned in the Notification
No.319(E) dated 7th May, 1992 shall submit an
application to the Secretary, Department of
Environment of the Government of
Haryana/Rajasthan, as the case may be. The
applicant shall also furnish environment impact
statement and an environment management plan
and such other information as may be prescribed
by such State Governments. The application after
due scrutiny shall be placed before the Expert
Committee for its recommendations. Based on
the recommendations of the Expert Committee,
the Department of Environment in the State
Government concerned shall take a final decision
and convey the same to the applicant within three
months from the date of receipt of application or
when further information has been asked for from
the applicant within three months from the date of
receipt of such information.
4. The Ministry of Environment and Forests
retains appellate power against rejection of any
proposal and the National Environmental
Appellate Authority constituted under the National
Environment Appellate Authority Act, 1997 (22 of
1997) shall continue as an Appellate Authority
against approval."
Schedule I and II of the notification sets out the composition of the
Expert Committee and of the Monitoring Committee. Some controversy
and confusion in respect of constitution of committees insofar as it relates
to appointment of an expert from non-government organization, was
brought to our notice but the delegation in favour of State Governments
having been withdrawn now, it is not necessary to examine this aspect.
The Central Government, in terms of notification dated 28th February,
2003, has withdrawn the delegation in favour of State Governments.
Notification of 27th January, 1994 Regarding Environment Impact
Assessment (EIA)
Another notification which is of considerable importance on aspect of
mining is dated 27th January, 1994, as amended on 4th May, 1994. The
notification has been issued by Ministry of Environment and Forest,
Government of India, in exercise of powers conferred by sub-section (1)
and clause (5) of sub-section (2) of Section 3 of the EP Act read with
clause (d) of sub-rule (3) of Rule 6 of the EP Rules stipulating that
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 28 of 50
expansion or modernization of any activity (if the pollution load is to exceed
the existing one) or a new project listed in Schedule I of the notification
shall not be undertaken in any part of India unless it has been accorded
environmental clearance by the Central Government in accordance with
the procedure specified in the notification.
The issue in these matters is about the interpretation of the
notification, its applicability also to mining leases granted earlier to the
issue of the notification i.e. at the time of the renewal of such mining lease.
The notification dated 27th January, 1994, to the extent material for the
present purpose, reads as under :
"S.O.60(E) Whereas a notification under clause
(a) of sub-rule (3) of rule 5 of the Environment
(Protection) Rules, 1986 inviting objections from
the public within sixty days from the date of
publication of the said notification, against the
intention of the Central Government to impose
restrictions and prohibitions on the expansion and
modernization of any activity or new projects being
undertaken in any part of India unless
environmental clearance has been accorded by
the Central Government or the State Government
in accordance with the procedure specified in that
notification was published as S.O. No.80(E) dated
28th January, 1993:
And whereas all objections received have
been duly considered;
Now, therefore, in exercise of the powers
conferred by sub-section (1) and clause (v) of sub-
section (2) of section 3 of the Environment
(Protection) Act, 1986 (29 of 1986) read with
clause (d) of sub-rule (3) of rule 5 of the
Environment (Protection) Rules, 1986, the Central
Government hereby directs that on and from the
date of publication of this notification in the Official
Gazette expansion or modernization of any activity
(if pollution load is to exceed the existing one) or a
new project listed in Schedule I of this notification
shall not be undertaken in any part of India unless
it has been accorded environmental clearance by
the Central Government in accordance with the
procedure hereinafter specified in this notification.
2. Requirements and procedure for seeking
environmental clearance of projects:
1.(a) Any person who desires to undertake any
new project or the expansion or
modernization of any existing industry or
project listed in Schedule I shall submit an
application to the Secretary, Ministry of
Environment and Forests, New Delhi.
The application shall be made in the
proforma specified in Schedule II of this
notification and shall be accompanied by a
project report which shall, inter alia, include
an Environmental Impact Assessment
Report/Environment Management Plan
prepared in accordance with the guidelines
issued by the Central Government in the
Ministry of Environment and Forests from
time to time.
(b) Cases rejected due to submission of
insufficient or inadequate data and plans
may be reviewed as and when submitted
with complete data and plans. Submission
of incomplete data or plans for the second
time would itself be a sufficient reason for
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 29 of 50
the Impact Assessment Agency to reject the
case summarily.
II. In case of the following site specific
projects:
(a) mining;
(b) to (d) ...
(e) prospecting and exploration of major
minerals in areas above 500 ha.,
The project authorities will intimate the
location of the project site to the Central
Government in the Ministry of Environment
and Forests while initiating any investigation
and surveys. The Central Government in
the Ministry of Environment and Forests will
convey a decision regarding suitability or
otherwise of the proposed site within a
maximum period of thirty days. The said
site clearance shall be granted for a
sanctioned capacity and shall be valid for a
period of five years for commencing the
construction, operation or mining.
III.(a) The reports submitted with the application
shall be evaluated and assessed by the
Impact Assessment Agency, and if deemed
necessary it may consult a Committee of
Experts, having a composition as specified
in Schedule-III of this Notification. The
Impact Assessment Agency (IAA) would be
the Union Ministry of Environment and
Forests. The Committee of Experts
mentioned above shall be constituted by the
IAA or such other body under the Central
Government authorised by the IAA in this
regard.
(b) The said Committee of Experts shall have
full right of entry and inspection of the site
or, as the case may be, factory premises at
any time prior to, during or after the
commencement of the operations relating to
the project.
(c) The Impact Assessment Agency shall
prepare a set of recommendations based on
technical assessment of documents and
data, furnished by the project authorities,
supplemented by data collected during visits
to sites or factories, if undertaken, and
interaction with affected population and
environmental groups, if necessary.
Summary of the reports, the
recommendation and the conditions, subject
to which environmental clearance is given,
shall be made available subject to the public
interest to the concerned parties or
environmental groups on request.
Comments of the public may be solicited, if
so decided by Impact Assessment Agency,
within thirty days of receipt of proposal, in
public hearings arranged for the purpose
after giving thirty days notice of such
hearings in at least two newspapers.
Public shall be provided access, subject to
the public interest, to the summary of the
reports/Environmental Management Plans
at the Headquarters of the Impact
Assessment Agency.
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 30 of 50
The assessment shall be completed within a
period of ninety days from receipt of the
requisite documents and data from the
project authorities and completion of public
hearing where required, and decision
conveyed within thirty days thereafter.
The clearance granted shall be valid for a
period of five years for commencement of
the construction or operation.
No construction work preliminary or
otherwise, relating to the setting up of the
project may be undertaken till the
environmental and/or site clearance is
obtained.
IV. In order to enable the Impact Assessment
Agency to monitor effectively the
implementation of the recommendations
and conditions subject to which the
environmental clearance has been given the
project authorities concerned shall submit a
half-yearly report to the Impact Assessment
Agency. Subject to the public interest, the
Impact Assessment Agency, shall make
compliance reports publicly available.
V. If no comments from the Impact
Assessment Agency are received within the
time limit, the project would be deemed to
have been approved as proposed by project
authorities.
3. Nothing contained in this Notification shall
apply to :
(a) any item falling under entry nos.3, 18 and
20 of the Schedule I to be located or
proposed to be located in the areas covered
by the Notifications S.O. No.102(E) dated
1st February, 1989; S.O. 114(E) dated 20th
February, 1991, S.O. No.416(E) dated 20th
June, 1991 and S.O. No.319(E) dated 7th
May, 1992.
(b) any item falling under entry Nos.1, 2, 3, 4, 5,
7, 9, 10, 12, 13, 14, 16, 17, 19, 21, 25 and
27 of Schedule-I if the investment is less
than Rs.50 crores.
(c) any item reserved for Small Scale Industrial
sector with investments less than Rs.1
crore.
4. Concealing factual data or submission of
false, misleading data/reports, decisions or
recommendations would lead to the project being
rejected. Approval, if granted earlier on the basis
of false data would also be to be revoked.
Misleading and wrong information will cover the
following :
-- False information;
-- False data.
-- Engineered reports.
-- Concealing of factual data.
-- False recommendations of decisions.
SCHEDULE-I
(See paras 1 and 2)
LIST OF PROJECTS REQUIRING
ENVIRONMENTAL CLEARANCE FROM THE
CENTRAL GOVERNMENT.
1. Nuclear Power and related projects such as
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 31 of 50
Heavy Water Plants, nuclear fuel complex,
rare earths.
2 to 19 ...
20. Mining projects (major minerals) with leases
more than 5 hectares.
21 to 29 ...
XXX XXXX XXXX
SCHEDULE III
(See sub-para III(a) of Para 2)
COMPOSITION OF THE EXPERT COMMITTEES
FOR ENVIRONMENTAL IMPACT ASSESSMENT
1. The Committee will consist of experts in the
following disciplines :
(i) Eco-System Management
(ii) Air/Water Pollution Control
(iii) Water Resource Management
(iv) Flora/Fauna Conservation and Management
(v) Land Use Planning
(vi) Social Sciences/Rehabilitation
(vii) Project Appraisal
(viii) Ecology
(ix) Environmental Health
(x) Subject Area Specialists.
(xi) Representatives of NGOs/Persons
Concerned With Environmental Issues.
2. The Chairman will be an outstanding and
experienced ecologist or environmentalist or
technical professional with wide managerial
experience.
3. The representative of IAA will act as
Member-Secretary
4. Chairman and members will serve in their
individual capacities except those specifically
nominated as representatives.
5. The membership of a Committee shall not
exceed 15.
EXPLANATORY NOTE REGARDING THE
IMPACT ASSESSMENT NOTIFICATION DATED
27TH JANUARY, 1994
1 to 3. ...
4. Public Hearing
Public hearings could be called for in case
of projects involving large displacement or having
severe environmental ramifications.
5 to 7. ...
8. Exemption for projects already initiated
For projects listed in Schedule-I to the
notification in respect of which the required land
has been acquired and all relevant clearances of
the State Government including NOC from the
respective State Pollution Control Boards have
been obtained before 27th January, 1994, a project
proponent will not be required to seek
environmental clearance from the IAA. However,
those units who have not as yet commenced
production will inform the IAA."
Reference may also be made to a notification issued by the Haryana
Government on November 28, 2001 with a view to enforce the
recommendations of NEERI contained in para 6.1 of its report so far as
mining operations in the State of Haryana are concerned. In terms of the
notification, the Designated Authority and the Monitoring Committee were
directed to impose the conditions mentioned in the notification while
according environmental clearance. This notification, it seems, was issued
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 32 of 50
in the purported attempt to comply with the directions of this Court as
contained in the order dated 10th May, 1996 as reported in M.C. Mehta’s
case (supra).
We may also refer to the circular dated May 14, 2002 issued by the
Ministry of Environment and Forest noticing that in the past several units
had come up in violation of the notification dated 27th January, 1994 and a
view had been taken earlier that such units are permitted to apply for
environment clearance by 31st March, 1999. For period of five years, there
was no circular or notification granting any time to apply for EIA under
notification dated 27th January, 1994. The period to apply for environment
clearance was extended upto 30th June, 2001 which deadline was
extended upto 31st March, 2003, stating that it was to give opportunity to
defaulting units to avail of the last and final opportunity to obtain ex post
facto environment clearance. The notification dated 27th January, 1994 is
applicable also to construction activity. It seems that this circular was
issued to give opportunity to those who had undertaken constructions after
issue of notification without compliance of stipulations therein. We are,
however, not concerned in these matters with the construction which may
have come up in breach of the notification. It does not appear that MOEF
intended to legalise the commencement or continuance of mining activity
without compliance of stipulations of the notification. In any case, a
statutory notification cannot be notified by issue of circular. Further, if
MOEF intended to apply this circular also to mining activity commenced
and continued in violation of this notification, it would also show total non-
sensitivity of MOEF to the principles of sustainable development and the
object behind the issue of notification. The circular has no applicability to
the mining activity.
Central Empowered Committee (CEC) - Its Suggestions
The notification dated 27th January, 1994 is mandatory. The
compliance of the notification before commencement of any mining
operation is essential and cannot be dispensed with. The MOEF has not
so far conducted Environment Impact Assessment in respect of any of the
mining lease under the notification dated 27th January, 1994.
Before the order dated 6th May, 2002 was passed, the lease holders
had not made any application before the Ministry for grant of EIA. The
applications were filed during the pendency of these matters under the
order of this Court. The EIA applications of the lease holders are lying with
CEC. CEC was constituted in terms of notification dated 17th September,
2002, issued by the Government of India, Ministry of Environment and
Forest in exercise of power conferred by Section 3(3) of the EP Act for the
purposes of monitoring and ensuring compliance of the order of this Court
covering the subject matter of forest and wildlife and related issues arising
out of the said order and one of the functions of the Committee in terms of
the notification is to monitor the implementation of the orders of this Court
and place reports of non-compliance before the Court including in respect
of encroachment and removals, working plans, compensatory
afforestation, plantations and other conservation issues.
In the order dated 31st October, 2002, this Court has observed that
no mining activity can be carried out without remedial measures taking
place and for this purpose, it is necessary that environment impact
assessment is done and the applications dealt with before any mining
activity can be permitted. It was also observed that the application of lease
holders for environmental clearance can be disposed of them of within a
period to be specified by this Court. In terms of order dated 25th
November, 2002, the Central Empowered Committee was asked to file its
suggestions in regard to the time for considering the applications for grant
of EIA. The CEC had received large number of voluminous Environment
Impact Assessment plans only in the last few days which are being
examined further stating that the process of examination and formulation of
suggestions is likely to take some more time. On 24th January, 2003, the
CEC was granted time to file its report upto 8th February, 2003. CEC has
filed three reports, the last having been filed on 7th February, 2003.
In an interim report dated 22nd June, 2003 CEC stated that the
complete information had not been supplied to it by the State of Haryana.
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 33 of 50
The report states that as per the information provided by the Haryana
State, in Faridabad district there are 21 sanctioned major mineral mines
with the varying size from 44.48 hectare to 516.518 hectare. In Gurgaon
districts 54 mining leases have been sanctioned varying in size from 5.96
hectare to 802.322 hectare. All the mines of major minerals were
operating in Faridabad district without obtaining statutory environmental
clearance under the EP Act. It also noticed that in respect of the Aravalli
Hills range being an acknowledged as eco friendly area under the Aravalli
notification, clearances were being granted on the basis of examination of
an expert group without any public hearing or participation of NGOs or the
affected people. As already noticed, the delegation in favour of the State
has been now withdrawn. The report further observes that most of the
mines are operating in violation of approved plans. Instead of doing
section wise mining (bench mining) the mining operations are carried on
unscientifically with the sole aim to make maximum profits which has
resulted in number of fatal accidents involving labourers, hazards to the
adjoining population, indiscriminate scattering of the over burden, wasteful
manner of mining with complete disregard to mineral conservation aspect,
rendering reclamation of mined area impossible. Further it points out that
several mining leases have been granted in areas where plantations were
undertaken with the financial assistance provided by international donor
agencies. Mining activities are permitted in a manner which is destroying
the ground water table and also the deep aquifers thereby causing
irreparable damage to the critical ground water reserves. There is no
effective mechanism to ensure compliance of various conditions stipulated
while granting statutory approvals. No deterrent action was taken against
mines even in those cases where during monitoring serious violations and
non compliance of conditions were found. The CEC has made the
following suggestions :
"I) For major mineral mines above 5 hectare in
Faridabad district, mining activity may be
allowed to be undertaken only after the
required environmental clearances are
accorded by the Ministry of Environment
and Forest (MOEF);
ii) the powers delegated to the State
Government by notification dated 27.1.1997
to grant environmental clearances in
respect of areas of Gurgaon district falling
within Aravalli notification dated 7.5.1992
requires to be reconsidered as the
presumptions on the basis of which powers
were delegated to the State Government
have been found to be incorrect;
iii) mining activity may be allowed in respect of
areas notified under Section 4 and 5 of the
PLP Act, which for the purpose of FC Act
are ‘forest’ even as per the State
Government records, only after obtaining
prior approval under the said Act from the
MOEF;
iv) all mining leases granted in respect of areas
where plantations have been raised under
the financial assistance received from any
international donor agencies may be
cancelled forthwith. The concerned
authorities may be prohibited from allowing
any mining operations, allowing renewals or
grants of fresh leases in such areas;
v) mining activity may be allowed only as per
the approved Mining Plans. Mines which
are found to be operating at variance with
the approved Mining Plans may be made
liable for cancellation of lease and payment
of exemplary compensation;
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 34 of 50
vi) in view of rampant and indiscriminate
mining, which was being done, a high level
monitoring committee may be constituted
comprising representatives of the State
Government, MOEF, Indian Bureau of
Mines, Director General of Mine Safety and
reputed NGOs. This Committee may be
empowered to monitor the implementation
of the conditions imposed while approving
Mining Plans, grants of environmental
clearances and other approvals/clearances.
Whenever any violation is detected, the
Committee should have the powers to direct
closure of the defaulting mines and also to
impose fines commensurate with the
seriousness of the violation;
vii) in addition to the above (vi), the Officials of
the State Government, Indian Bureau of
Mines, MOEF, Director General of Mine
Safety may independently monitor, at least
once in three months, to ensure compliance
of all statutory conditions;
viii) the State Government may identify and
notify officials, who would ensure
enforcement of the directions given by the
Monitoring Committee and or the above
mentioned officials;
ix) no mining activity may be allowed without
obtaining ‘No Objection Certificate’ from the
Central Groundwater Board to ensure that
the water table and the underground
aquifers are not adversely affected;
x) before allowing resumption of mining activity
in any approved mining lease, the status of
compliance of the conditions of the
approved Mining Plans, approved
Environmental Management Plans,
environmental clearances and other
statutory conditions/clearances may be
ascertained. Suitable and adequate
compensation/penalty for non-compliance of
stipulations may be recovered, otherwise
such stipulations would remain only on
paper;
xi) in respect of forest area, including areas
notified under Section 4 and 5, net present
value of the land leased out for mining may
be recovered as per the Hon’ble Supreme
Court order dated 30.10.2002 in I.A. No.566
in Writ Petition (Civil) No.202/95 (forest
matter);
xii) a suitable system of securing adequate
bank guarantee, bank deposit or other
personal guarantee from the mine owner
may be worked out to ensure compliance of
all statutory and other conditions;
xiii) after considering the annual approved rate
of mining and mineral deposits in the area,
optimum size of the mines may be
determined in respect of approved mines to
ensure optimum utilization of the mineral
resources;
xiv) presently, the over burden is not stacked as
per approved Minining Plan, which makes it
practically impossible to carry out any
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 35 of 50
reclamation work. The over burden
dumping may be allowed only at identified
sites within the mining lease area as per
approved Mining Plans;
xv) for the purpose of afforestation, the funds
may be recovered from the mine owners
and deposited with the forest department for
undertaking afforestation in a planned
manner;
xvi) the identification of the consultants for
preparation of the EIA’s should be done by
the regulating agency instead of by the mine
owners to ensure good and credible reports.
It is important that payment to the
consultants should also be routed through
the regulating agency and not directly by the
mine owners."
The report of CEC dated 7th February, 2003 mentions that the State
Government, despite letters, had not made available to the Committee the
following information :
i) mine wise details of stipulated conditions,
which have been fulfilled and those which
have not been fulfilled
ii) details of five major mineral mines in
Faridabad and Gurgaon Districts which
have fulfilled all the conditions stated in the
approved mining plans, environmental and
other clearances;
iii) details of the mines where mining activity
has been undertaken without obtaining
requisite environmental clearance.
In the absence of the information as aforesaid the CEC gave its
suggestions on the basis of information available to it which are as under:
i) the ban on mining activity may continue up
to 2 km from Surajkund and Badkal Lakes,
as per the Hon’ble Court’s order dated
10.5.1996;
(ii) each of the existing mines may be
physically inspected by Inspection Team(s)
comprising officials of the State
Government, Indian Bureau of Mines,
Director General of Mines Safety and the
Ministry of Environment and Forest to report
the specific conditions which have not been
fulfilled/violated especially in respect of :
a. sectionwise (benchwise) mining to be
done as per approved mining plan;
b. storage of top soil as per approved
mining plan;
c. dumping of over-burden in identified
area as per the approval mining plan;
d. plantations as per Environmental
Management Plan;
e. observance of mines safety Rules and
Regulations;
f. damage to the plantations raised under
externally aided projects (foreign
funding);
g. damage if any to the water
table/underground acquifers; and
h. compliance of environmental clearance
stipulations;
The Inspection Team(s) may submit the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 36 of 50
reports to the State Government and the
Ministry of Environment & Forest (MOEF)
with copies to the Central Empowered
Committee (CEC) for their comments and
for carrying out verification, if found
necessary.
(iii) suitable penalties for non-
compliance/violation of various conditions,
as found by the above Inspection Team(s)
or by the CEC may be imposed. Norms for
quantifying the penalties for violation of
various conditions may be formulated by the
State Government with the concurrence of
the CEC. No mine may be allowed to
resume mining activity without first paying
the penalty imposed on it.
(iv) mining activity may completely be prohibited
in area where plantations have been
undertaken with the foreign
assistance/funding (externally aided
projects). Mining leases already
granted/approved in all such areas may be
cancelled;
(v) yearwise requirement of funds for
implementation of various conditions under
which mining has been approved may be
computed for each mine. To ensure
compliance of these conditions, adequate
safeguards by way of bank guarantee,
mortgage of immovable assets, pledge of
movable assets, personnel guarantee of the
lessee or others (supported by adequate
assets) may be put in place;
(vi) MOEF may examine the Environment
Impact Assessment Report/Environment
Management Plan of individual major
mineral mines and proposals for approval
under the FC Act, if the mining lease is in
’forest’ as per the Hon’ble Supreme Courts
order dated 12.12.1996 in Writ Petition (C)
No.206/95, and take decision(s) thereon,
including regarding measures for protecting
the water table and underground acquifers,
in a time bound manner; and
(vii) regular inspection of the mines may be
undertaken by the identified officials of the
State Government, Indian Bureau of Mines
and Director General of Mines Safety.
Mines which are found to have violated the
conditions may be made liable to pay stiff
penalties including closure of the mines."
Some mining leases were granted prior to notification dated 27th
January, 1994 and some after the issue of that notification. Even in
respect of the leases granted prior to 27th January, 1994, the renewal of
most of the leases has come up after issue of notification. Some of the
leases are for extraction of major mineral, some for extraction of minor
mineral and some for extraction of both major and minor mineral. In
respect of none of the leases, before commencement of mining activity,
EIA was obtained from the MOEF. In respect of mining in Aravalli Hills in
Gurgaon, the relevant notifications dated 7th May, 1992, 29th November,
1999 and 28th January, 2003 have been noticed earlier. Under the
notification dated 7th May, 1992, no permission was granted by the MOEF
though some applications were pending before it when power was
delegated to the State Government. Permissions were granted by the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 37 of 50
State Government after the powers were delegated to it. The delegation in
favour of the State has since been withdrawn.
Legal Parameters
The natural sources of air, water and soil cannot be utilized if the
utilization results in irreversible damage to environments. There has been
accelerated degradation of environment primarily on account of lack of
effective enforcement of environmental laws and non-compliance of the
statutory norms. This Court has repeatedly said that the right to live is a
fundamental right under Article 21 of the Constitution and it includes the
right to of enjoyment of pollution-free water and air for full enjoyment of life.
(See Subhash Kumar v. State of Bihar [AIR 1991 SC 420].
Further, by 42nd Constitutional Amendment, Article 48-A was
inserted in the Constitution in Part IV stipulating that the State shall
endeavour to protect and improve the environment and to safeguard the
forest and wildlife of the country. Article 51A, inter alia, provides that it
shall be the duty of every citizen of India to protect and improve the natural
environment including forest, lakes, rivers and wildlife and to have
compassion for living creatures. Article 47 which provides that it shall be
the duty of the State to raise the level of nutrition and the standard of living
and to improve public health is also relevant in this connection. The most
vital necessities, namely, air, water and soil, having regard to right of life
under Article 21 cannot be permitted to be misused and polluted so as to
reduce the quality of life of others. Having regard to the right of the
community at large it is permissible to encourage the participation of
Amicus Curiae, the appointment of experts and the appointments of
monitory committees. The approach of the Court has to be liberal towards
ensuring social justice and protection of human rights. In M.C. Mehta v.
Union of India [(1987) 4 SCC 463], this Court held that life, public health
and ecology has priority over unemployment and loss of revenue. The
definition of ’sustainable development’ which Brundtland gave more than 3
decades back still holds good. The phrase covers the development that
meets the needs of the present without compromising the ability of the
future generation to meet their own needs. In Narmada Bachao Andolan
v. Union of India & Ors. [(2000) 10 SCC 664], this Court observed that
sustainable development means the type or extent of development that
can take place and which can be sustained by nature/ecology with or
without mitigation. In these matters, the required standard now is that the
risk of harm to the environment or to human health is to be decided in
public interest, according to a "reasonable person’s " test. [See Chairman
Barton : The Status of the Precautionary Principle in Australia : (Vol. 22)
(1998) (Harv. Envtt. Law Review, p. 509 at p.549-A) as in AP Pollution
Control Board vs. Prof. M.V. Nayuder (Retd) & Ors. [(1999) 2 SCC
718].
The mining operation is hazardous in nature. It impairs ecology and
people’s right of natural resources. The entire process of setting up and
functioning of mining operation require utmost good faith and honesty on
the part of the intending entrepreneur. For carrying on any mining activity
close to township which has tendency to degrade environment and are
likely to effect air, water and soil and impair the quality of life of inhabitants
of the area, there would be greater responsibility on the part of the
entrepreneur. The fullest disclosures including the potential for increased
burdens on the environment consequent upon possible increase in the
quantum and degree of pollution, has to be made at the outset so that
public and all those concerned including authorities may decide whether
the permission can at all be granted for carrying on mining activity. The
regulatory authorities have to act with utmost care in ensuring compliance
of safeguards, norms and standards to be observed by such
entrepreneurs. When questioned, the regulatory authorities have to show
that the said authorities acted in the manner enjoined upon them. Where
the regulatory authorities, either connive or act negligently by not taking
prompt action to prevent, avoid or control the damage to environment,
natural resources and peoples’ life, health and property, the principles of
accountability for restoration and compensation have to be applied.
The development and the protection of environments are not
enemies. If without degrading the environment or minimising adverse
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 38 of 50
effects thereupon by applying stringent safeguards, it is possible to carry
on development activity applying the principles of sustainable
development, in that eventuality, the development has to go on because
one cannot lose sight of the need for development of industries, irrigation
resources and power projects etc. including the need to improve
employment opportunities and the generation of revenue. A balance has
to be struck. We may note that to stall fast the depletion of forest, series of
orders have been passed by this Court in T.N. Godavarman’s case
regulating the felling of trees in all the forests in the country. Principle 15
of Rio Conference of 1992 relating to the applicability of precautionary
principle which stipulates that where there are threats of serious or
irreversible damage, lack of full scientific certainty shall not be used as a
reason for proposing effective measures to prevent environmental
degradation is also required to be kept in view. In such matters, many a
times, the option to be adopted is not very easy or in a straight jacket. If
an activity is allowed to go ahead, there may be irreparable damage to the
environment and if it is stopped, there may be irreparable damage to
economic interest. In case of doubt, however, protection of environment
would have precedence over the economic interest. Precautionary
principle requires anticipatory action to be taken to prevent harm. The
harm can be prevented even on a reasonable suspicion. It is not always
necessary that there should be direct evidence of harm to the environment.
Bearing in mind the aforesaid principles, we have to consider the
main question: should the mining activity in areas in question be banned
altogether or permitted and, if so, conditions to be provided therefor? The
reports and suggestions of NEERI, EPCA and CEC have already been
extensively noted. The effect of mining activity in area upto 5 km. from
Delhi-Haryana border on Haryana side of the ridge and also in the Aravalli
Hills is to be seen in light of these reports and another report dealt later.
One of the aspect stated in these reports is about carrying on of mining
activity in close proximity to the residential area and/or main roads carrying
traffic.
Mines and Minerals (Regulation and Development) Act and Rules
thereunder
The grant of mining lease is governed by the Mines and Minerals
(Regulation and Development) Act, 1957 (for short, ’the MMRD Act) which
was enacted to provide for the development and regulation of mines and
minerals under the control of the Union. Section 13 is the rule making
power of the Central Government. The Central Government is empowered
to make rules to provide for the manner in which rehabilitation of flora and
other vegetation, such as trees, shrubs and the like destroyed by reason of
any mining operation shall be made in the same area or in any other area
selected by the Central Government (whether by way of reimbursement of
the cost of rehabilitation or otherwise) by the person holding the mining
lease. Section 18, inter alia, casts a duty upon the Central Government to
take all such steps as may be necessary for the conservation and
systematic development of minerals in India and for the protection of
environment by preventing or controlling any pollution which may be
caused by mining operations and for such purposes, the Central
Government may, by notification in the official gazette, make such rules as
it thinks fit.
The Mineral Concession Rules, 1960 have been framed by the
Central Government in exercise of the powers conferred by Section 13 of
the MMRD Act. Chapter IV of these Rules relate to grant of mining leases
in respect of land in which the minerals vest in the Government. Rule
22(4), inter alia, provides that on receipt of the communication from the
State Government of the precise areas to be granted for mining purpose,
the applicant shall submit a mining plan, within the period stipulated in the
Rules, to the Central Government for its approval. The applicant, on
approval of the mining plan by the Central Government, shall submit the
same to the State Government to grant mining lease over that area. Rule
4A, inter alia, provides that notwithstanding anything contained in Sub-
rule(4), the State Government shall be competent to approve mining plan
of open cost mines (mines other than underground mines) in respect of
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 39 of 50
now metallic or industrial minerals, named therein, one of it being Silica
sand. The mining plan, as provided in sub-rule (5) of Rule 22, shall, inter
alia, incorporate the mineral reserves of the area and the plan of area
showing, inter alia, water courses, limit of reserves and other forest areas
and density of trees, if any, assessment of impact of mining activity on
forest, land surface and environment including air and water pollution;
details of the scheme of restoration of the area by afforestation, land
reclamation, use of pollution control devices and such other measures as
may be directed by the Central Government or the State Government from
time to time. A tentative scheme of mining and annual programme and
plan for excavation from year to year for five years is also required to be
incorporated in the mining plan. Rule 22(5) was inserted in the Rules by
notification dated 27th September, 1994 to which certain amendments were
made in terms of notification dated 17th January, 2000 also inserting by
same notification Rule 22(4A). Sub-rule(4) to Rule 22 ad been earlier
inserted by notification dated 27th September, 1994.
The grant of permission for mining and approving mining plan and
the scheme by the Ministry of Mines, Government of India by itself does
not mean that mining operation can commence. It cannot be accepted that
by approving Mining Plan and Scheme by Ministry of Mines, Central
Government is deemed to have approved mining and it can commence
forthwith on such approval. Section 13 of the MMRD Act and the Rules
made in exercise of powers under the said section, deal, inter alia, with the
aspect of grant of mining of lease and not commencement of mining
operations. Rules made under Section 18, however, deal with
commencement of mining operations and steps required to be taken for
protection of environment by proventing or controlling any pollution which
may be caused by mining operation. A mining lease holder is also
required to comply with other statutory provisions such as Environment
(protection) Act, 1986, Air (Prevention and control of Pollution) Act, 1981,
The Water (Prevention and Control of Pollution) Act, 1974, Forest
(Conservation) Act, 1980. Mere approval of the mining plan by
Government of India, Ministry of Mines would not absolve the lease holder
from complying with the other provisions.
Rules 31 to 41 contained in Chapter V of the Mineral Conservation
and Development Rules, 1988 framed under Section 18 of the MMRD Act
deal with the measures required to be taken by the lessee for the
protection of environment from any adverse effect of mining or irreversible
consequences thereof. These Rules, inter alia, provide that every holder
of a mining lease shall take all possible precautions for the protection of
environment and control of pollution while conducting mining operations in
the area; shall, wherever top soil exists and is to be excavated for mining
operations, remove it separately and utilize for restoration or rehabilitation
of the land which is no longer required for mining operations. The holder is
also required to take steps so that the overburden, waste rock, rejects and
fines generated during prospecting and mining operations or tailings, slims
and fines produced during sizing salting and benefication or metallurgical
operations shall be stored in separate dumps which shall be properly
secured to prevent escape of material therefrom in harmful quantities
which may cause degradation of environment. Wherever possible, the
waste rock, overburden etc. shall be back-filled into the mines excavation
with a view to restoring the land for its original use as far as possible and
wherever it is not feasible during mining operation, the waste dumps shall
be suitably tarraced and stabilized through vegetation or otherwise. It is
also required that the phased restoration, reclamation and rehabilitation of
lands affected by mining operation shall be undertaken which work shall be
completed before the conclusion of mining operations and the
abandonment of mine. Air pollution due to fines, dust and smoke or
gaseous emissions during mining operations and related activities shall be
controlled and kept within ’permissible limits’ specified under various
environmental laws of the country including the Air (Prevention and Control
of Pollution) Act, 1981 and the Environment (Protection) Act, 1986 by the
holder of mining lease. Further, noise arising out of such operations shall
be abated or controlled by the lessee at the source so as to keep it within
the permissible limit. The mining operations shall be carried out in such a
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 40 of 50
manner so as to cause least damage to the flora of the area and nearby
areas. Every holder of mining lease shall take immediate measures for
planting in the same area or any other area as selected by the authorized
officer and not less than twice the number of trees destroyed by reason of
any mining operation and look after them during the subsistence of the
licence/lease and restore, to the extent possible, other flora destroyed by
mining operations.
The aforesaid measures are not required to remain only on paper
but strictly complied for the protection of environment and control of
pollution as a result and consequence of mining operations.
National Forest Policy
In respect of mining in the forest area, we may also refer to the
National Forest Policy, 1988 issued by Ministry of Environment and Forest,
Government of India which, inter alia, notices that over the years, forests in
the country have suffered serious depletion. One of the reason of it is
inadequacy of protection measure and diversion of forest land to non-
forest uses. Without ensuring compensatory afforestation and essential
environmental safeguards; and the tendency to look upon forests as
revenue earning resource. The basic objectives of the policy, inter alia,
are maintenance of environment stability through preservation and, where
necessary, restoration of the ecological balance that has been adversely
disturbed by serious depletion of the forests of the country and checking
the soil erosion and water conservation and increasing substantially the
forest/tree cover through massive afforestation and social forestry
programmes. It provides that the National goal should be to have a
minimum of 1/3rd of the total land area of the country under forest or tree
cover. In the hills and in mountains regions, the aim should be to maintain
2/3rd of the area under such cover in order to prevent erosion and land
degradation and to ensure the stability of the fragile eco-system. It also
provides that a massive need based and time bound programme of
afforestation and tree planting, with particular emphasis on fuel wood and
fodder development, on all degraded and denuded lands in the country,
whether forest or non-forest land, is a national imperative.
Mining in Forest Area
The question of permitting mining in the area where large scale of
afforestation with foreign funding has taken place is required to be
examined keeping in view the National Forest Policy which also provides
that forest land or land with tree cover should not be treated merely as a
resource readily available to be utilized for various projects and
programmes but as a national asset which requires to be properly
sasfeguarded for providing sustained benefits to the entire community.
Diversion of forest land for any non-forest purpose should be subject to the
most careful examinations by specialists from the standpoint of social and
environmental costs and benefits. The mining and industrial development
should be consistent with the needs for conservation of trees in forest. It
provides that no mining should be granted to any party, private or public,
without a proper mine management plan appraised from the environmental
angle and enforced by adequate machinery.
Our attention was drawn by learned counsel appearing for lease-
holders to the part of national policy which provides that beneficiaries who
are allowed mining and quarrying in forest land and in land covered by
trees should be required to repair and re-vegetate the area in accordance
with established forestry practices to submit that the policy itself
contemplates mining operations in the forest area. For present, we are not
suggesting a complete ban of mining operations on forest land so long as it
is possible to undertake the said operation on the sustainable development
principles and after obtaining due approvals under various statutory
provisions including Section 2 of the Forest (Conservation) Act, 1980. At
the same time, we are unable to appreciate the commencement and
continuation of mining over areas on which crores of the foreign funds
have been spent for afforestation and plantation. Further, it is also not
possible to accept the contention urged on behalf of the lease holders that
only that part of such leased land where allegedly damage has been
caused to plantation as a result of mining operations, be excluded from
mining and not the entire area of the lease. For example, if the mining
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 41 of 50
area is 5 hectare and damages as a result of mining is to plantation in an
area of 1 hectare, it is not practicable or reasonable to exclude only that 1
hectare and permit the mining operation on the rest of the mining area.
Reference can also be usefully made to the part of the State of Forest
Report, 1999 issued by Forest Survey of India in relation to Haryana. It,
inter alia, provides that large scale plantations were carried out under
Aravalli project since 1992. The document claims increase of the forest
cover in the State as a result of plantation under the Aravalli project. It,
inter alia, mentions that forest cover increase in Gurgaon and Faridabad is
mainly due to plantation raised under the Aravalli project which was started
in early 1990s. In these matters, neither the State nor the leaseholders
can be permitted to turn round and now take a stand that the areas
covered under the Aravalli project is not forest. The National Forestry
Action Programme of December 2000 issued by the Ministry of
Environment and Forest, Government giving project profile also makes
detailed reference to the institution building and integrated national
resource development in the Aravalli region, Haryana under the project
implementing agency of Forest Department, Government of Haryana. The
project profile, inter alia, states that the Central to such a policy is
rehabilitation of common lands to meet the needs of the rural poor and to
reduce soil and water erosion and the proposed programme was
envisaged to bring the benefit of integrated development of the Aravalli
eco-system to the whole community, particularly, to the poorer sections.
The project, it is stated, has been implemented in Aravalli hills situated in
the five districts of Haryana including Gurgaon. One of the expected
outcome of the project is the reduced soil erosion and improved water
regime in the rehabilitated area will be drastically reduce and run-off
leading to recharge of constantly depleting ground water resources. It
records that Haryana Forest Department has implemented a project on the
eco-restoration of common lands in the Aravalli hills, from June 1990 to
October 1999. The project is being funded by Delegation of European
Communities. The total cost was 28.8 million ECU in which external
assistance was to the extent of 23.2 million EUC.
Aravallis Hill Range
The Aravallis, most distinctive and ancient mountain chain of
peninsular India, mark the site of one of the oldest geological formations in
the world. Heavily eroded and with exposed outcrops of the slate rock and
granite, it has summits reaching 4950 feet above sea level. Due to its
geological location, the Aravalli range harbours a mix of Saharan,
Ethiopian, Peninsular, oriental and even Malayan elements of flora and
fauna. In the early part of this century, the Aravallis were well wooded.
There were dense forests with waterfalls and one could encounter a large
number of wild animals. Today, the changes in the environment at Aravalli
are severe. Though one finds a number of tree species in the hills, timber
quality trees have almost disappeared. Despite the increase of population
resulting in increase of demand from the forest, It cannot be questioned
nor has been questioned that to save the ecology of the Aravalli mountain,
the laws have to be strictly implemented. The notification dated 7th May,
1992 was passed with a view to strictly implement the measures to protect
the ecology of the Aravalli range. The notification was followed more in its
breach.
In the aforesaid background, any mining activity on the area under
plantation under Aravalli project cannot be permitted. The grant of leases
for mining operation over such an area would be wholly arbitrary,
unreasonable and illogical.
Report of CMPDI on Aravalli
The Central Mine Planning & Design Institute Limited (CMPDI) on
being asked by the Central Pollution Control Board to conduct a study of
environmental problems of Aravalli hills and preparation of action plan for
restoration of environmental quality in Gurgaon district, after extensive
examination, has submitted to CPCB its final report in July 2003. CMPDI
is a subsidiary of Coal India Limited (Government of India Enterprise). The
report in respect of Aravalli range in Gurgaon district has been prepared by
CMPDI with the following objectives :
1. To prepare status report of the pollution problems in the Aravalli
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 42 of 50
Hills.
2. To prepare environmental management plan to abate various
environmental problems
3. To prepare action plan for restoration of environmental quality.
The environmental problems in the Aravalli Range in Gurgaon
district have been identified and remedial measures including the pollution
control guidelines and action plan for various stakeholders have been
suggested by CMPDI. It has been noticed that in large scale mining
projects what is still required is a proposal on district level as to what will
be mined, how it will be mined and with what method and many such areas
of environmental concern which had not been adequately addressed
keeping in view the environmental degradation of the Aravalli Hills. It has
also been noticed that the Aravalli notification restricts process and
operations under certain categories of the land in district. Though the
records of such lands are available at every village level map, there is no
record available in the district level in respect of these areas to undertake
realistic appraisal and effective monitoring of mining and other projects at
the macro level on such lands. While noticing that, notification dated 29th
November, 1999, inter alia, made provision for preparing a master plan
integrating the environmental concerns and the future land use of the area,
but the master plan prepared on 28th August, 2002 does not, inter alia,
address the issue of natural resource assessment and water Resource
status; the areas near crushing zone and active mining zone remain a
matter of concern and concerted efforts have not been given to the quality
of roads and the dust suppression measures to maintain the air quality
within safe limits. The guidelines of operation in an eco-friendly manner
have been issued by the State Government but the compliance is only
partial, inasmuch as wind breaking walls are not proper, pollution control
devices are not operating and the green belt around the crushing zones
are not maintained. Identification of mines in the district is difficult. There
does not seem to be mechanism to upgrade the mining technologies and
methodologies to minimize the impact due to mining in the eco-sensitive
zones in the district. There is no identified land where overburden could
be temporarily dumped prior to being utilized for void filling and for other
purposes. There does not seem to adequate awareness among the
people in respect of the environmental problems. In some parts of the
district, the ground water potential is already in the dark category. Lack of
water conservation measures and rainwater harvesting may ultimately lead
to water scarcity in the near future.
Having identified the environmental problems, various actions have
been recommended by CMPDI for the eco restoration in the Aravalli
Range in Gurgaon district. It has been, inter alia, recommended that it is
imperative on the part of the State Government to improve inter-
departmental co-ordination among various Government departments to
achieve the common objective, i.e., ecological restoration of Aravalli Hills
in the district. The master plan should indicate the proposed eco-
restoration plan to compensate the environmental degradation by the
proposed activities in the master plan. Rehabilitation programmes for the
abandoned mines areas either to convert these to water reservoirs and
eco-parks or reclamation by filling by rural waste, urban waste or fly ash.
The master plan should be detailed to show the areas where overburden
could be dumped, areas where waste material could be stocked, areas
where plantation could be carried out, etc.etc. The planning should, inter
alia, include environmental impact and concerns of activities of one sector
on the other sectors in the district, e.g., afforestation should be planned not
only with a view to increase vegetation on the hills but also to be
supplement for fuel, fodder etc. in the district. All efforts should be made to
preserve the ground water resources. Water shed management and
rainwater harvesting to be implemented in the Aravalli hills regions on war
footing. In the areas where mining deeper than the ground water table of
the area is to be carried out, adequate provision of pollution control and
conservation of water resources should be made. There should be
frequent inspections of the mining operations to ensure that these are in
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 43 of 50
line with the requirement for sustainable development. The inspections
may be carried out at an interval of three months. There should be
continual source of revenue from the mining operations to the fund,
recommended to be created, for the eco-restoration of the Aravalli hills.
The minimum period of lease should be for 15-20 years. This will induce
the mine operators to take environmental protection measures more
seriously. The State Pollution Control Board shall undertake regular
monitoring to check compliance and to assess the ambient air quality,
water quality and other environmental protection measures. The Ministry
of Environment and Forest should take initiative to appoint a Central
Agency to monitor the eco-restoration efforts and to provide technical
support to the implementing organizations. The renewal of mining lease
and granting new leases should be effected after examining the
environmental protection measures taken by the lessee. Requisite data
should be displayed on the internet to arouse awareness in public and for
further usage. Stringent action should be taken for water conservation.
The Forest Department may even carry out the afforestation on behalf of
mine operators. Expenses should, however, be borne by the mine
operators. The afforestation shall be carried out keeping in view, inter alia,
the consideration of checking the soil erosion. The mine lessee should
implement the environmental management plan and mining plan approved
by the concerned authority. In future, efforts in respect of search for
sustainable development should broadly take into consideration resource
potential in the region, the demand of the products and the supply options.
Though the demand for the niche products existing in the Aravalli range
which is one of the oldest mountain ranges in India will continue to grow,
the supply options need to be given a closer look due to eco-sensitivity of
the region. The environmental cost needs to be internalized in the cost of
the product and there is need to limit the supply options. Noticing that the
Aravalli range prevents the desert from spreading into Indo-Gangetic
plains, it has been suggested that all future planning should not only
concentrate to meet the ever growing demand of the products but due
consideration should also be given to protect the chain. All the
developmental activities should, therefore, be planned in a coherent
manner and there should be integrated approach for sustainable
development.
CMPDI has noticed that in the Aravalli Hills, a large number of
activities, operations of stone crushers and deforestation besides other
activities are causing environmental degradation. These mines are usually
located in the clusters in remote mineral rich districts/areas where living
standards is lower and understanding of people towards environmental
impact is also poor. In the past, the mine operators took no note of
environmental damage. In fact, they were not even conscious about it.
The attitude of mining community is to ignore the environmental concerns.
In majority of the cases, the environmental concerns are ignored for
making quick profits. The small mines (less than 5 hectares) and the
mining of minor minerals which are no doubt small individually but have
damaging characteristics when in clusters, e.g. the mines of granite,
marble, slates, quartzite etc. (falling under minor minerals) are no less
damaging than the others, especially when the processing is taken into
consideration. The mining activities results in disturbance of land surface,
altering drainage pattern and land use, besides the pollution problems,
which may lead to the environmental problems of air, water and noise
pollution and solid waste pollution.
It has been suggested that the short term and long term action plan
for the restoration of environmental quality of the area shall be prepared
separately. The action plan shall be prepared in such a way that it should
be a guiding tool also in the hands of the state pollution control boards and
Government agencies for enforcement of the environmental laws for the
restoration of environmental quality of the area. Monitoring programme
shall include frequency of monitoring for air quality, water quality, ground
water, solid wastes, noise level etc.
In respect of water resources, it has been, inter alia, suggested that
in order to draw water resource management plan, it is essential to assess
the water quality of the various components of the hydrologic cycle, i.e.,
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 44 of 50
stream, ground water, surface water etc. It has been pointed out that since
the surface water potential is not promising in the district, there is
increased dependence on the ground water for meeting the agricultural,
domestic and industrial requirement resulting in depletion of ground water
resources in the district. It has been suggested that utmost care is
required for further development of ground water in the areas where the
recharge of the ground water is low.
Dealing with the flora and fauna, it has been pointed out that the
earliest account shows that at one time the Aravalli hills were well covered
with dhauk (Anogeissus pendula). Now, except in few places, viz., the Jhir
Forest in Firozpur Jhirka (dedicated to Mahadeo Temple) and near
Bhondsi recently regenerated with dhauk, the Aravallis are by and large,
bereft of vegetation in the district.
It has been noticed that in order to take stock of the environmental
problems, CPCB and CMPDI team made several visits to Aravalli hills and
held discussion with the mine operators, State officials and local people.
There are number of mining projects etc. which are already existing and
there is also tremendous potential to further increase the industrial and the
other development activities. The environmental impact due to mining
projects on air quality, water quality, noise level, overburden etc. have
been noticed and it has been pointed out that the opening of new projects
will further affect some of the environmental attributes.
The report notices that the environmental degradation has taken
place due to mining activities. The existing crusher units are also not
functioning on the environmental sound systems. The situation warrants
closer look on various components of the systems affecting the
environmental attributes in the area, devising pragmatic approaches to
facilitate eco-restoration of the Aravalli hills and offering broad framework
to the industrial units to function under environmentally sustainable
framework. The suggestions also include the enactment of rules for grant
of mine leases to levy a separate charge for dump removal, ecological
restoration in the area, the technology to be used for mining operations
and post mining land use and mine decommissioning. As far as
environmental protection in the Aravalli hills is concerned, planning and
provisions must start from the stage of grant of mine lease and what all it
should include have been set out. It has been, inter alia, suggested that
the environmental framework shall include the framework for
environmental clearance such as depth of cutting, area of plantation and
the type of plantation, which are attributes related to closure planning as
also framework for monitoring and for forestry besides air quality, land use
pattern etc. In nutshell, it has been suggested that it is imperative on the
part of the mine operators to carry out the mine operations in such a
fashion that it has least impact on the ecology of the area. The pollution
prevention guidelines have been suggested in para 7.1.1.2
Having regard to the detailed study, the recommendations and
action plan has been dealt with in Chapter VIII of the report, inter alia,
suggesting that concerted efforts from various departments are needed.
The report states that though the environmental upgradation measures
need to be taken more seriously by the mine and other industrial
operators, there is need on the part of the State Government to
immediately start these measures in the areas where degradation has
already taken place. The other recommendations have already been
broadly noticed.
No one has raised any objection to the recommendations contained
in the report of CMPDI. We accept the recommendations in principle.
Modification of Order dated 6th May, 2002 Regarding Mining in
Aravalli
Now, the question is should mining activities in the Aravalli range in
Gurgaon district be permitted to restart and, to that extent, the order dated
6th May, 2002 be modified, meanwhile directing implementation of
recommendations in the report of CMPDI and earlier referred reports. The
other option is to first constitute a monitoring committee directing it to
individually examine and inspect mines from environmental angle in the
light of the said recommendations and file a report in this Court in respect
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 45 of 50
of individual mines with its recommendations for restart or otherwise as
also recommendation, if any, for the payment by the mine operators and/or
by State Government towards environmental fund having regard to the
precautionary principles and polluter pays principle and on consideration of
that report, to decide the aspect of modification of the order dated 6th May,
2002, partially or entirely. We are of the view that the second option is
more appropriate. We are conscious of observations in CMPDI that
measures for protecting the environment can be undertaken without
stopping mine operations and also the suggestions of MOEF to permit
mining subject to the mine lease holders undertaking to comply with such
conditions which remain to be complied, but, having regard to the
enormous degradation of the environment, in our view, the safer and the
proper course is to first constitute a Monitoring Committee, get a report
from it and only thereafter consider, on individual mine to mine basis, lifting
of ban imposed in terms of order dated 6th May, 2002. Before concluding
this aspect, we may note that assuming there was any ambiguity about the
applicability of order dated 6th May, 2002 to mining in Aravalli Range, it is
clarified that the said order would be applicable to all the mines in Aravalli
hill range in Gurgaon district.
Applicability of notification dated 27th January, 1994
The notification has been reproduced in the earlier part of the
judgment. It, inter alia, applies to mining projects (major minerals) with
leases of more than 5 hectares. It can neither be disputed nor has been
disputed that the notification is mandatory. It, inter alia, provides that on
and from the date of its publication in official Gazette expansion or
modernization of any activity (if pollution load is to exceed the existing one)
or a new project listed in Schedule A of this notification shall not be
undertaken in any part of India unless it has been accorded environmental
clearance by the Central Government in accordance with the procedure
specified therein. The contention urged on behalf of the lease-holders is
that the leases in question do not relate to expansion or modernization of
any activity as postulated by the notification. Further, it is contended, that
the notification applies to ’a new project’ which means that it will apply to
mining lease granted after issue of notification. It has been strenuously
contended that the renewal of existing mining lease is neither ’an
expansion’ nor ’modernization’ nor is it a ’new project’ and, therefore, the
notification will have no applicability at the time of consideration of the
renewal of the lease. Reliance has been placed on a decision of this Court
in Narmada’s case (supra) holding that the notification is clearly
prospective and, inter alia, prohibits the undertaking of a new project listed
in Schedule I without prior environmental clearance from the Central
Government. The contention urged was that since in Narmada’s case,
where construction had commenced nearly 8 years prior to the notification,
same very notification was not held applicable. On the same analogy, it
cannot have any applicability to the leases granted prior to the issue of
notification.
No doubt, the notification is prospective but the question here is
whether it would be applicable when the aspect of renewal comes up for
consideration after the issue of the notification. In Narmada’s case, it was
not held that this notification will not apply at the stage of renewal. The
observations made in para 129 of the said decision and relied upon by
learned counsel for the lease holders have no relevance to determine the
applicability of the notification at the stage of renewal. In Narmada’s
case, the environmental clearance had been granted in the year 1987 and
this Court noticing that when it was granted by the Prime Minister,
whatever studies were available were taken into consideration, it was
known that the construction of the dam would result in submergence and
the consequent effect which the reservoir will have on the ecology of the
surrounding areas and various studies relating to environmental impact
had been taken into consideration and that there was no obligation to
obtain the statutory clearance under 1994 notification.
In the present case, regarding the manner of grant of no objection
certificate from environmental angle for proposed mining activity, by way of
illustration, we may refer to the order dated 18th January, 1999 issued by
Haryana State Pollution Control Board whereby no objection certificate for
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 46 of 50
renewal of lease was granted stipulating that the applicant Som Prakash
Sethi in respect of mining activity at village Anangpur, district Faridabad
shall also seeking environmental clearance of its mining project in
compliance with this notification without even mentioning any time limit for
it and admittedly till date that had not been done. None bothered to find
out whether conditions in the order has been complied or not. Further the
letter dated 25th January, 2003, sent to Principal Secretary of Central
Empowered Committee by Director Mines and Ecology, Haryana shows
how the State Government has been circumventing the legal requirements
and permitting mining. In that letter, it has been stated that pending
approval of the environmental plan, the mining lessees undertook the
mining operation of the minor mineral on issue of short term permit, in
cases where the fresh mining leases were granted and in case of renewal
of mining leases, the mining activities were going on. This is despite
conditions in the judgment dated 10th May, 1996 by this Court that the
Director Mining and Ecology Haryana would be responsible for mining in
the State of Haryana.
Be that as it may and reverting to legal position, in Ambica Quarry
Works v. State of Gujarat & Ors. [(1987) 1 SCC 213], though a case
under Forest (Conservation) Act, 1980 rejecting the contention that
approval at the stage of renewal was not necessary and also the plea that
since the leaseholders had invested sum of money in mining operation, it
was the duty of the authorities to renew the lease, it was held that having
regard to the awareness that deforestation and ecological imbalances as a
result of deforestation have become social menaces and the same should
be prevented and that the concept that power coupled with the duty
enjoined upon the respondents to renew the lease stood eroded by the
mandate of the FC Act. It was held that The primary duty was to the
community and that duty took precedence. In such cases, the obligation to
the society must predominate over the obligation to the individuals. It
would be apposite to reproduce what was said by Justice Mukherjee (as
he then was) in paras 14 and 15 which read thus :
"14. Here the case of the appellants is that they
have invested large sums of money in mining
operations. Therefore, it was the duty of the
authorities that the power of granting permission
should have been so exercised that the
appellants had the full benefits of their
investments. It was emphasized that none of the
appellants had committed any breach of the
terms of grant nor were there any other factors
disentitling them to such renewal. While there
was power to grant renewal and in these cases
there were clauses permitting renewals, it might
have cast a duty to grant such renewal in the
facts and circumstances of the cases specially in
view of the investments made by the appellants in
the areas covered by the quarrying leases, but
renewals cannot be claimed as a matter of right
for the following reasons.
15. The rules dealt with a situation prior to the
coming into operation of 1980 Act. ’1980 Act’ was
an Act in recognition of the awareness that
deforestation and ecological imbalances as a
result of deforestation have become social
menaces and further deforestation and ecological
imbalances should be prevented. That was the
primary purpose writ large in the Act of 1980.
Therefore the concept that power coupled with
the duty enjoined upon the respondents to renew
the lease stands eroded by the mandate of the
legislation as manifest in 1980 Act in the facts
and circumstances of these cases. The primary
duty was to the community and that duty took
precedence, in our opinion, in these cases. The
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 47 of 50
obligation to the society must predominate over
the obligation to the individuals."
In Rural Litigation and Entitlement Kendra v. State of U.P.
[1989 Supp.(1) SCC 504], agreeing with views expressed in Ambica
Quarry Workers, it was held that the FC Act applies to renewals as well
and even if there was a provision for renewal in the lease agreement on
exercise of lessee’s option, the requirement of the Act had to be satisfied
before such renewal could be granted. In State of M.P. & Ors. v.
Krishnadas Tikaram [1995 Supp.(1) SCC 587], these two decisions
were relied upon and it was held that even the renewal of lease cannot be
granted without the prior concurrence of the Central Government. It is
settled law that the grant of renewal is a fresh grant and must be
consistent with law.
We are unable to accept the contention that the notification dated
27th January, 1994 would not apply to leases which come up for
consideration for renewal after issue of the notification. The notification
mandates that the mining operation shall not be undertaken in any part of
India unless environmental clearance by the Central Government has
been accorded. The clearance under the notification is valid for a period
of five years. In none of the leases the requirement of notification was
complied with either at the stage of initial grant of the mining lease or at
the stage of renewal. Some of the leases were fresh leases granted after
issue of the notification. Some were cases of renewal. No mining
operation can commence without obtaining environmental impact
assessment in terms of the notification.
The Applicability of Forest (Conservation) Act, 1980 to areas
treated as forest by State Forest Department
The provisions of the Act provide for the conservations of forest and
for matters connected therewith or ancillary or incidental thereto. Any
forest land or portion thereof cannot be used for any non-forest purposes
or assigned by way of leases or otherwise to any private person or to any
authority, corporation, agency or any other organization not owned,
managed or controlled by the Government, except with the prior approval
of the Central Government. Mining activity within forest area cannot be
permitted in contravention of the provisions of the Act. The Act makes the
contravention of any of the provisions of Section 2 as an offence
punishable in the manner provided in the Act.
The controversy is in respect of certain leases where area under
the lease is covered under notification issued under Section 4 and/or 5 of
the Punjab Land Preservation Act, 1900. The question is whether such
area is ’forest’ of any kind.
Under Section 3 of the aforesaid Act, whenever it appears to the
State Government that it is desirable to provide for the conservation of
sub-soil water or the prevention of erosion in any area subject to erosion
or likely to become liable to erosion, such Government may by notification
make a direction accordingly. Under Section 4(b), the State Government
has power to regulate, restrict or prohibit the quarrying of stone or the
burning of lime at placed where such stone or lime had not ordinarily been
so quarried or burnt prior to the publication of the notification under section
3. Section 5(b) in respect of any specified village or villages, or part or
parts thereof, comprised within the limits of any area notified under section
3, the State Government may, by special order, temporarily regulate,
restrict or prohibit the quarrying of any stone or the burning of any lime at
places where such stone or lime had ordinarily been so quarried or burnt
prior to the publication of the notification under section 3. In respect of
some mining areas notifications have been issued under Section 4 and in
respect of some notifications have been issued both under Sections 4 and
5. The submission is that invoking of Sections 3, 4 and 5 is only to
conserve sub-soil water and prevention of the area from erosion of land
and is not to create any forest. It has been pointed out that in cases
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 48 of 50
where the notifications have been issued, only felling of trees had been
prohibited and not quarrying of stone.
It cannot be disputed that the State Forest Department has been
treating and showing the aforesaid areas as ’forest’. The contention urged
on behalf of the State Government is that it was on account of erroneous
view point of Forest Department. In fact and law, such area is not ’forest’
and mining is not prohibited and, therefore the question of seeking
permission under Section 2 of the FC Act does not arise.
In the instant case, it is not necessary to decide the legal effect of
issue of the notification under Section 4 and/or 5 of the Act. Not only in
their record the area has been shown as forest but the affidavits have been
filed in this Court stating the area to be ’forest’. In T.N. Godavarman
Thirumulkpad v. Union of India & Ors. [(1997) 2 SCC 267] , this Court
held that the term ’forest’ is to be understood in the dictionary sense and
also that any area regarded as a forest in Government record irrespective
of ownership would be a forest. The State of Haryana, besides having
filed affidavits in the forest matters treating such areas as forest for the
purposes of the FC Act has been seeking prior approval from the Central
Government for diversion of such land for non-forestry purpose.
Reference in this connection may also be made to the affidavit dated 8th
December, 1996 filed by Banarsi Das, Principal Chief Conservator of
Forest, Chandigarh, Haryana in Civil Writ No.171 of 1996 Environmental
Awareness Forum v. State of Jammu & Kashmir and Ors. Our
attention has also been drawn to letter dated 26th November, 2002
addressed by Divisional Forest Officer, Faridabad to Mining Officer,
Faridabad forwarding to him a list of blocked forest areas of Faridabad
district and requesting him to ensure that the said forest areas are not
affected by any mining operations as also to a letter dated 17th September,
2001 sent by Principal Chief Conservator of Forest, Haryana (Panchkula)
to Director of Environment, Haryana stating therein that no mining activity
can be permitted in the area. On the facts and circumstances of the case,
we cannot permit the State Government to take a compete summersault in
these proceedings and contend that the earlier stand that the area is
’forest was under some erroneous impressions. In the present case, for
the purposes of the FC Act, these areas shall be treated as forest and for
use of it for non-forestry purpose, it would be necessary to comply with the
provisions of the FC Act.
We may also note that assuming that there was any confusion or
erroneous impression, it ought to have been first sorted out at appropriate
level and where affidavits had been filed in this Court, clarifications/orders
sought before issue of the mining lease in respect of such area.
Impact of Mining on Ground Water
Where during mining water level is touched, the Monitoring
Committee shall carve out that area and it was agreed on behalf of the
leaseholders that they would co-operate and not undertake any mining in
such an area.
Non-payment of royalty to the villagers
A controversy has been raised about non-payment of royalty by the
leaseholders to villagers on whose behalf it was contended that the order
dated 6th May, 2002 prohibiting mining should not be varied till the
leaseholders discharge their liability to pay royalty to the villagers. On the
other hand, mine leaseholders dispute the claim put-forth on behalf of the
villagers and it has been submitted that no amount is payable by them and
the villagers can make their claim, if any, from the State Government.
The dispute of this nature cannot be properly adjudicated in these
proceedings. We leave it open to be adjudicated before appropriate forum
in accordance with law.
Leases in respect of minor mineral
Though notification dated 27th January, 1994 is not applicable to
minor minerals, but having regard to what we have discussed above in
regard to degradation of environment and the required standard about the
risk of harm to the environment or to human health to be decided in public
interest according to ’reasonable person’s test’, and the report of CMPDI,
we direct the Monitoring Committee to examine the leases granted for
extraction of minor mineral in light thereof and file its report. The
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 49 of 50
Committee would, however, bear in mind that the notification dated 27th
January, 1994 as such is not applicable to these leases.
Mining in Faridabad District
Having examined the matter, we are of the view that though the
study conducted by CMPDI relates to mining activity in Aravalli Hills in
Gurgaon district, in public interest the general safeguards and suggestions
in that report deserve to be implemented in respect of mining in Faridabad
district as well.
We have already extracted the recommendations of NEERI, as also
violations noticed in the reports submitted by EPCA and the suggestions of
EPCA, CEC and CMPDI. The Monitoring Committee shall inspect the
leases in question in Faridabad District as well in the light of these
recommendations and file its report containing suggestions on
recommencement or otherwise of the mining activity therein.
It may be reiterated that if, despite stringent conditions, the
degradation of environment continues and reaches a stage of no return,
this Court may have to consider, at a later date, the closure of mining
activity in areas where there is such a risk.
As earlier noticed as well, it would not be expedient to lift the ban on
mining imposed in terms of the order of this Court dated 6th May, 2002
before ensuring implementation of suggestions of CMPDI and other
recommendations of experts (NEERI, EPCA and CEC). The safer course
is to consider this question, on individual basis after receipt of report of the
Monitoring Committee.
Environment Impact assessment applications
During the course of hearing environment assessment applications
in terms of notification dated 27th January, 1994 have been filed by some
of the leaseholders. In case, those applications are presently with Central
Empowered Committee, the same shall be forthwith forwarded by CEC to
MOEF. The adverse effect, if any, and extent thereof on human health
and ecology shall be examined while deciding impact of these activities.
There is also the desirability of transparency in such matter. The MOEF is
directed to consider the said applications within a period of 10 weeks.
Monitoring Committee
With a view to monitor the overall eco-restoration efforts in the
Aravalli Hills and to provide technical support to the implementing
organizations and also to monitor implementation of recommendations
contained in reports referred herein, it is necessary to constitute a
Monitoring Committee. The heads of the following departments would be
members of the Monitoring Committee :
1. Regional Officer of State Pollution Control Board.
2. Forest Department
3. District Administration
4. Department of Mining & Geology
5. Irrigation Department
6. Regional Officer of CGWB
7. Agriculture Department
8. District Industry Department.
9. Chairman - CPCB.
Besides above, MOEF is directed to appoint an officer from Central
Ground Water Board to be a member of the Monitoring Committee. The
following persons as representatives of public shall also be members of
the said Committee :
1. Prof. Dilip Biswas,
Ex Chairman, CPCB.
2. Mr. Valmiki Thapar,
3. Mr. Bhure Lal.
The MOEF would act as a nodal agency of the Monitoring
Committee. The Secretary of MOEF is directed to appoint an officer not
below the rank of a Joint Secretary in the Ministry for the said purpose.
The Monitoring Committee is directed to inspect the mines in
question and file a report within a period of three months, inter alia,
containing suggestions for recommencement of mining in individual cases.
All concerned individuals and departments are directed to render full co-
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 50 of 50
operation to the Monitoring Committee.
Conclusions
1. The order dated 6th May, 2002 as clarified hereinbefore cannot be
vacated or varied before consideration of the report of the Monitoring
Committee constituted by this judgment.
2. The notification of environment assessment clearance dated 27th
January, 1994 is applicable also when renewal of mining lease is
considered after issue of the notification.
3. On the facts of the case, the mining activity on areas covered under
Section 4 and/or 5 of Punjab Land Preservation Act, 1900 cannot be
undertaken without approval under the Forest (Conservation) Act,
1980.
4. No mining activity can be carried out on area over which plantation
has been undertaken under Aravalli project by utilization of foreign
funds.
5. The mining activity can be permitted only on the basis of sustainable
development and on compliance of stringent conditions.
6. The Aravalli hill range has to be protected at any cost. In case
despite stringent condition, there is an adverse irreversible effect on
the ecology in the Aravalli hill range area, at a later date, the total
stoppage of mining activity in the area may have to be considered.
For similar reasons such step may have to be considered in respect
of mining in Faridabad District as well.
7. MOEF is directed to prepare a short term and long term action plan
for the restoration of environmental quality of Aravalli hills in
Gurgaon district having regard to what is stated in final report of
CMPDI within four months.
8. Violation of any of the conditions would entail the risk of cancellation
of mining lease. The mining activity shall continue only on strict
compliance of the stipulated conditions.
The matters are directed to be listed after reopening of courts after
summer vacation on receipt of the report from the Monitoring Committee.