Full Judgment Text
REPORTABLE
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NO. 3680 OF 2005
Vishnu (dead) by L.Rs. ...Appellant
versus
State of Maharashtra and others ...Respondents
WITH
CIVIL APPEAL NO. 3681 of 2005
J U D G M E N T
G.S. SINGHVI, J.
1. Whether Clause 30 of B-1 Agreements entered into
between the Government of Maharashtra and the appellant is in the nature of
an arbitration clause is the question which arises for consideration in this
JUDGMENT
appeal filed against judgment dated 6.5.2004 of the learned Single Judge of
the Bombay High Court, Aurangabad Bench.
2. The tenders submitted by the appellant, who is now
represented by his legal representatives, for Tondapur Medium Project,
Jalgaon Medium Project Division, Jalgaon and Hatnoor Canal Division No.3,
Chopda, District Jalgaon were accepted by the Competent Authority and five
agreements were executed between the parties on 19.5.1983 and 5.10.1983
1
Page 1
(hereinafter referred to as ‘B-1 Agreements’).
3. In January 1985, the appellant abandoned the works and
submitted bills for the works already done. He also claimed damages in lieu
of the alleged loss suffered by him.
4. After four years, the appellant served notice under Section
80 CPC and then filed Civil Suit No.995/1989 before the trial Court for
declaring the recovery proceedings initiated by the defendants as illegal, null
and void.
5. During the pendency of the suit, the appellant filed an
application under Section 21 of the Arbitration Act, 1940 (for short, ‘the 1940
Act’) and prayed that the matter may be referred to an Arbitrator by
appointing the Superintending Engineer or any other Arbitrator as the sole
Arbitrator in terms of Clause 30 of B-1 Agreement. The same was dismissed
by the trial Court vide order dated 29.7.1994 on the ground that both the
JUDGMENT
parties had not given consent for making a reference to an Arbitrator.
6. Soon thereafter, the appellant filed an application under
Order VI Rule 17 CPC for leave to amend the plaint and incorporate an
additional prayer for reference of the dispute to an Arbitrator. The same was
allowed by the trial Court vide order dated 27.9.1994.
7. The respondents challenged the aforesaid order in Civil
Revision Application No.153/1995, which was partly allowed by the learned
2
Page 2
Single Judge of the High Court and the order of the trial Court granting leave
to the appellant to amend the prayer clause was set aside.
8. In the meanwhile, the appellant filed application dated
3.2.1995 under Section 20 of the 1940 Act for settlement of accounts and
prayed that respondent Nos.3 and 4 may be directed to file Arbitration
Agreement in terms of Clause 30 of B-1 Agreement executed between the
parties and an Arbitrator may be appointed to decide all the disputes. On
17.6.1995, the trial Court directed the parties to adduce evidence on the
nature of Clause 30 of B-1 Agreement.
9. After considering the evidence adduced by the parties and
by placing reliance on some judgments of the High Courts, the trial Court
allowed the application and declared that Clause 30 of B-1 Agreement is an
arbitration clause. The trial Court also appointed Shri D.G. Marathe, Chief
Engineer (PWD) as an Arbitrator and referred all the disputes to him.
JUDGMENT
10. Civil Revision Application No.447 of 1997 filed by the
respondents against the order of the trial Court was allowed by the learned
Single Judge of the Bombay High Court and it was held that Clause 30 of B-1
Agreement cannot be treated as an arbitration clause. In support of this
conclusion, the High Court relied upon the judgment of this Court in Civil
Appeal No. 4700/1985 – State of Maharashtra v. M/s. Ranjeet Construction.
11. While issuing notice of the special leave petition on
4.1.2005, this Court passed the following order:
3
Page 3
“The learned counsel for the petitioner places reliances on a three
Judge Bench decision of this Court in Mallikarjun Vs. Gulbarga
University 2004 (1) SCC, 372 wherein a similar clause, as arises for
consideration in the present case, was held to be an arbitration
clause.
The abovesaid decision seems to be at divergence from the view
taken by a two Judge Bench decision in Bharat Bhushan Bansal
Vs.U.P. Small Industries Corporation Ltd., Kanpur 1999 (2) SCC,
166 wherein reliance has been placed on two judgments, of this
Court, each by three Judges, namely, State of Orissa Vs. Damodar
Das 1996 (2) SCC, 216 and State of U.P. Vs. Tipper Chand
1980(2) SCC, 341.
Issue notice to the respondents and place for hearing before a three
Judge Bench.
Issue notice also on the prayer for grant of interim relief.”
12. By an order dated 11.07.2005, the three-Judge Bench
referred the matter to the Constitution Bench for resolving the conflicting
opinions expressed by the co-ordinate Benches. However, vide order dated
8.12.2010, the Constitution Bench declined to decide the matter and directed
that the case be listed before the three Judge Bench.
JUDGMENT
13. Shri Rana Mukherjee, learned counsel for the appellant
argued that the impugned order is liable to be set aside because the High
Court’s interpretation of Clause 30 of B-1 Agreement is contrary to the law
laid down in Mallikarjun v. Gulbarga University (2004) 1 SCC 372 and
Punjab State v. Dina Nath (2007) 5 SCC 28. Learned counsel emphasized
that Clause 30 of B-1 Agreement makes the decision of the Superintending
Engineer binding on all parties to the agreement and, therefore, the trial Court
was right in treating the same as an arbitration clause. Shri Mukherjee further
4
Page 4
argued that in view of circulars dated 9.5.1977, 12.8.1982 and 21.5.1983
issued by the State Government, Clause 30 of B-1 Agreements has to be
treated as an arbitration clause and the respondents had no right to challenge
the reference made by the trial Court and thereby question the wisdom of the
State Government.
14. Shri Manish Pitale, learned counsel for the respondents
relied upon the judgments of this Court in State of U.P. v. Tipper Chand
(1980) 2 SCC 341, State of Orissa v. Damodar Das (1996) 2 SCC 216 and
Bharat Bhushan Bansal v. U.P. Small Industries Corporation Ltd., Kanpur
(1999) 2 SCC 166 and argued that Clause 30 of B-1 Agreement cannot be
construed as an arbitration clause simply because the decision of the
Superintending Engineer is made binding on all parties to the contract.
Learned counsel submitted that the judgment in Mallikarjun v. Gulbarga
University (supra) is clearly distinguishable because Clause 30 of the
Agreement, which was interpreted in that case was substantially different
JUDGMENT
from the one under consideration. Shri Pitale pointed out that the
Superintending Engineer of Gulbarga Circle was not directly involved in the
execution of contract between the University and the appellant, whereas
Superintending Engineer, who has been named as the officer in Clause 30 of
B-1 Agreement entered into between the appellant and the State Government
is overall incharge of the work.
15. We have considered the respective arguments. Clauses
5
Page 5
29 and 30 of the B-1 Agreement entered into between the parties read as
under:
“Clause 29.—All works to be executed under the contract shall be
executed under the direction and subject to the approval in all
respects of the Superintending Engineer of the Circle for the time
being, who shall be entitled to direct at what point or points and in
what manner they are to be commenced, and from time to time
carried on.
Clause 30 —Except where otherwise specified in the contract and
subject to the powers delegated to him by Government under the
Code rules then in force the decision of the Superintending Engineer
of the Circle for the time being shall be final, conclusive, and
binding on all parties to the contract upon all questions, relating to
the meaning of the specifications, designs, drawings, and
instructions, hereinbefore mentioned and as to the quality of
workmanship, or materials used on the work, or as to any other
question, claim, right, matter, or thing whatsoever, if any way
arising, out of, or relating to or the contracts designs, drawings,
specifications, estimates, instructions, orders, or these conditions or
otherwise concerning the works, or the execution, or failure to
execute the same, whether arising, during the progress of the work,
or after the completion or abandonment thereof.”
16. Para 224 of the Maharashtra Public Works Manual, as
JUDGMENT
amended by Government C.M. No. CAT-1070/460 – DSK.2, dt.9/5/1977,
reads as under:
“Para 224 – Clause 30 of B-1 and B-2 Agreement forms lays down
that the decision of the Superintending Engineer in certain matters
relating to the contract would be final. The Superintending Engi-
neer’s decision taken under this clause should be considered as that
taken as an Arbitrator and this should be considered as the decision
taken under the Arbitration Act. The decisions taken by the Super-
intending Engineer under the other clauses should be considered
different from his decision taken under clause 30 of B-1 and B-2
tender agreement as an arbitrator.”
17. We shall first consider the question whether Clause 30 of
6
Page 6
B-1 Agreement can be construed as an arbitration clause. A conjoint reading
of Clauses 29 and 30 of B-1 Agreements entered into between the parties
shows that the appellant had to execute all works subject to the approval in
all respects of Superintending Engineer of the Circle, who could issue
directions from time to time about the manner in which work was to
commence and execute. By virtue of Clause 30, decision of the
Superintending Engineer of the Circle was made final, conclusive and binding
on all the parties in respect of all questions relating to the meaning of the
specifications, designs, drawings, quality of workmanship or materials used
on the work or any other question relating to claim, right, matter or things
arising out of or relating to the contract designs, drawings, specifications,
estimates, instructions, orders, etc. These two clauses by which the
Superintending Engineer was given over all supervisory control were
incorporated for smooth execution of the works in accordance with the
approved designs and specifications and also to ensure that quality of work is
JUDGMENT
not compromised. The power conferred upon the Superintending Engineer of
the Circle was in the nature of a departmental dispute resolution mechanism
and was meant for expeditious sorting out of problems which could crop up
during execution of the work. Since the Superintending Engineer was made
overall in-charge of all works to be executed under the contract, he was
considered by the parties to be the best person who could provide immediate
resolution of any controversy relating to specifications, designs, drawings,
quality of workmanship or material used, etc. It was felt that if all this was
7
Page 7
left to be decided by the regular civil Courts, the object of expeditious
execution of work of the project would be frustrated. This is the primary
reason why the Superintending Engineer of the Circle was entrusted with the
task of taking decision on various matters. However, there is nothing in the
language of Clause 30 from which it can be inferred that the parties had
agreed to confer the role of arbitrator upon the Superintending Engineer of the
Circle.
st
18. In Russell on Arbitration, 21 Edn., the distinction
between an expert determination and arbitration has been spelt out in the
following words:
“Many cases have been fought over whether a contract’s chosen
form of dispute resolution is expert determination or arbitration.
This is a matter of construction of the contract, which involves an
objective enquiry into the intentions of the parties. First, there are
the express words of the disputes clause. If specific words such as
‘arbitrator’, ‘arbitral tribunal’, ‘arbitration’ or the formula ‘as an ex-
pert and not as an arbitrator’ are used to describe the manner in
which the dispute resolver is to act, they are likely to be persuasive
although not always conclusive…. Where there is no express word-
ing, the court will refer to certain guidelines. Of these, the most im-
portant used to be, whether there was an ‘issue’ between the parties
such as the value of an asset on which they had not taken defined
positions, in which case the procedure was held to be expert deter-
mination; or a ‘formulated dispute’ between the parties where de-
fined positions had been taken, in which case the procedure was
held to be an arbitration. This imprecise concept is still being relied
on. It is unsatisfactory because some parties to contract deliberately
choose expert determination for dispute resolution. The next guide-
line is the judicial function of an arbitral tribunal as opposed to the
expertise of the expert; …. An arbitral tribunal arrives at its deci-
sion on the evidence and submissions of the parties and must apply
the law or if the parties agree, on other consideration; an expert, un-
less it is agreed otherwise, makes his own enquiries, applies his
own expertise and decides on his own expert opinion....”
JUDGMENT
8
Page 8
19. A clause substantially similar to Clause 30 of B-1
Agreement was interpreted by a three Judge Bench in State of U.P v. Tipper
Chand (supra) and it was held that the same cannot be construed as an
arbitration clause. Paragraphs 2 and 3 of the judgment which contain the
reasons for the aforesaid conclusion are reproduced below:
“2. The suit out of which this appeal has arisen was filed by the re-
spondent before us for recovery of Rs. 2000 on account of dues re-
coverable from the Irrigation Department of the petitioner State for
work done by the plaintiff in pursuance of an agreement, clause 22
of which runs thus:
“Except where otherwise specified in the contract the deci-
sion of the Superintending Engineer for the time being shall
be final, conclusive and binding on all parties to the contract
upon all questions relating to the meaning of the specifica-
tions, design, drawing and instructions hereinbefore men-
tioned. The decision of such Engineer as to the quality of
workmanship, or materials used on the work, or as to any
other question, claim, right, matter or things whatsoever, in
any way arising out of or relating to the contract, designs,
drawing specifications, estimates, instructions, orders, or
these conditions, or otherwise concerning the works, or the
execution or failure to execute the same, whether arising dur-
ing the progress of the work, or after the completion or aban-
donment of the contract by the contractor, shall also be final,
conclusive and binding on the contractor.”
JUDGMENT
3. After perusing the contents of the said clause and hearing learned
Counsel for the parties we find ourselves in complete agreement
with the view taken by the High Court. Admittedly the clause does
not contain any express arbitration agreement. Nor can such an
agreement be spelled out from its terms by implication, there being
no mention in it of any dispute, much less of a reference thereof. On
the other hand, the purpose of the clause clearly appears to be to
vest the Superintending Engineer with supervision of the execution
of the work and administrative control over it from time to time.”
9
Page 9
20. In State of Maharashtra v. M/s. Ranjeet Construction
(supra), the two Judge Bench of this Court interpreted Clause 30 of the
agreement entered into between the parties, which is almost identical to the
clause under consideration, relied upon the judgment in State of U.P. v.
Tipper Chand (supra) and held that Clause 30 cannot be relied upon for
seeking a reference to an Arbitrator of any dispute arising under the contract.
21. In State of Orissa v. Damodar Das (supra), the three
Judge Bench interpreted Clause 21 of the contract entered into between the
appellant and the respondent for construction of sump and pump chamber etc.
for pipes W/S to Village Kentile. The respondent abandoned the work before
completion of the project and accepted payment of the fourth running bill.
Subsequently, he raised dispute and sent communication to the Chief
Engineer, Public Health, Orissa for making a reference to an Arbitrator. The
Subordinate Judge, Bhubaneswar allowed the application filed by the
respondent under Section 8 of the 1940 Act and the order passed by him was
JUDGMENT
upheld by the High Court. This Court referred to Clause 25 of the agreement,
relied upon the judgment in State of U.P. v. Tipper Chand (supra) and held
that the said clause cannot be interpreted as providing resolution of dispute by
an Arbitrator. Paragraphs 9 and 10 of the judgment, which contain discussion
on the subject, are extracted below:
“9. The question, therefore, is whether there is any arbitration
agreement for the resolution of the disputes. The agreement reads
thus:
10
Page 10
“25. Decision of Public Health Engineer to be final.— Except
where otherwise specified in this contract, the decision of the
Public Health Engineer for the time being shall be final, con-
clusive and binding on all parties to the contract upon all ques-
tions relating to the meaning of the specifications; drawings
and instructions hereinbefore mentioned and as to the quality
of workmanship or materials used on the work, or as to any
other question, claim, right, matter or thing, whatsoever in any
way arising out of, or relating to, the contract, drawings, speci-
fications, estimates, instructions, orders or these conditions, or
otherwise concerning the works or the execution or failure to
execute the same, whether arising during the progress of the
work or after the completion or the sooner determination
thereof of the contract.”
10. Section 2(a) of the Act defines “arbitration agreement” to mean
“a written agreement to submit present or future differences to arbi-
tration, whether an arbitrator is named therein or not”. Indisputably,
there is no recital in the above clause of the contract to refer any
dispute or difference present or future to arbitration. The learned
counsel for the respondent sought to contend from the marginal
note, viz., “the decision of Public Health Engineer to be final” and
any other the words “claim, right, matter or thing, whatsoever in
any way arising out of the contract, drawings, specifications, esti-
mates, instructions, orders or these conditions, or otherwise con-
cerning the works or the execution or failure to execute the same,
whether arising during the progress of the work or after the comple-
tion or the sooner determination thereof of the contract” and con-
tended that this clause is wide enough to encompass within its am-
bit, any disputes or differences arising in the aforesaid execution of
the contract or any question or claim or right arising under the con-
tract during the progress of the work or after the completion or
sooner determination thereof for reference to an arbitration. The
High Court, therefore, was right in its conclusion that the aforesaid
clause gives right to arbitration to the respondent for resolution of
the dispute/claims raised by the respondent. In support thereof he
relied on Ram Lal Jagan Nath v. Punjab State through Collector
AIR 1966 Punj 436. It is further contended that for the decision of
the Public Health Engineer to be final, the contractor must be given
an opportunity to submit his case to be heard either in person or
through counsel and a decision thereon should be given. It envis-
ages by implication existence of a dispute between the contractor
and the Department. In other words, the parties construed that the
Public Health Engineer should be the sole arbitrator. When the
claim was made in referring the dispute to him, it was not referred
to the court. The respondent is entitled to avail of the remedy under
JUDGMENT
11
Page 11
Sections 8 and 20 of the Act. We find it difficult to give acceptance
to the contention. A reading of the above clause in the contract as a
conjoint whole, would give us an indication that during the progress
of the work or after the completion or the sooner determination
thereof of the contract, the Public Health Engineer has been em-
powered to decide all questions relating to the meaning of the speci-
fications, drawings, instructions hereinbefore mentioned and as to
the quality of workmanship or material used on the work or as to
any other question, claim, right, matter or thing whatsoever in any
way arising out of, or relating to, the contract drawings, specifica-
tions, estimates, instructions, orders or those conditions or other-
wise concerning the works or the execution or failure to execute the
same has been entrusted to the Public Health Engineer and his deci-
sion shall be final. In other words, he is nominated only to decide
the questions arising in the quality of the work or any other matters
enumerated hereinbefore and his decision shall be final and bind the
contractor. A clause in the contract cannot be split into two parts so
as to consider one part to give rise to difference or dispute and an-
other part relating to execution of work, its workmanship etc. It is
settled now that a clause in the contract must be read as a whole. If
the construction suggested by the respondent is given effect then the
decision of the Public Health Engineer would become final and it is
not even necessary to have it made rule of the court under the Arbi-
tration Act. It would be hazardous to the claim of a contractor to
give such instruction and give power to the Public Health Engineer
to make any dispute final and binding on the contractor. A careful
reading of the clause in the contract would give us an indication that
the Public Health Engineer is empowered to decide all the questions
enumerated therein other than any disputes or differences that have
arisen between the contractor and the Government. But for clause
25, there is no other contract to refer any dispute or difference to an
arbitrator named or otherwise.”
JUDGMENT
(emphasis supplied)
22. In K.K. Modi v. K.N. Modi (1998) 3 SCC 573, this Court
interpreted Clause 9 of the Memorandum of Understanding signed by two
groups of Modi family. Group ‘A’ consisted of Kedar Nath Modi (younger
brother of Seth Gujjar Mal Modi and his three sons) and Group ‘B’ consisted
of five sons of Seth Gujjar Mal Modi. To resolve the disputes and differences
12
Page 12
between two groups, the financial institutions, which had lent money, got
involved. Ultimately, a Memorandum of Understanding was signed by the
parties on 24.1.1989, Clause 9 of which reads as under:
“Implementation will be done in consultation with the financial in-
stitutions. For all disputes, clarifications etc. in respect of imple-
mentation of this agreement, the same shall be referred to the Chair-
man, IFCI or his nominees whose decisions will be final and bind-
ing on both the groups.”
The Chairman, Industrial Finance Corporation of India (IFCI) formed a
committee of experts to assist him in deciding various questions. The
committee of experts and the Chairman held discussion with both the groups.
On 8.12.1995, the Chairman, IFCI gave his detailed report / decision. In his
covering letter, the Chairman indicated that the Memorandum of
Understanding had been substantially implemented during 1989 to 1995 and
with his decisions on the disputes / clarifications given by him, it will be
possible to implement the remaining part. The report of the Chairman was
JUDGMENT
neither filed in the competent Court as an award nor any application was
submitted for making the report a rule or decree of the Court. However, the
Chairman issued series of directions for implementing the report. On
18.5.1996, the appellants filed a petition under Section 33 of the 1940 Act in
the Delhi High Court challenging report dated 8.12.1995 by asserting that it
was an award in arbitration proceedings. The opposite parties filed civil suit
in the High Court to challenge the report of the Chairman.
23. One of the questions formulated by this Court was
13
Page 13
whether Clause 9 of the Memorandum of Understanding constituted an
Arbitration Agreement and whether the decision of the Chairman, IFCI
constituted an award. The two Judge Bench first culled out the following
attributes of an Arbitration Agreement:
“(1) The arbitration agreement must contemplate that the decision
of the tribunal will be binding on the parties to the agreement,
(2) that the jurisdiction of the tribunal to decide the rights of parties
must derive either from the consent of the parties or from an order
of the court or from a statute, the terms of which make it clear that
the process is to be an arbitration,
(3) the agreement must contemplate that substantive rights of parties
will be determined by the agreed tribunal,
(4) that the tribunal will determine the rights of the parties in an im-
partial and judicial manner with the tribunal owing an equal obliga-
tion of fairness towards both sides,
(5) that the agreement of the parties to refer their disputes to the de-
cision of the tribunal must be intended to be enforceable in law and
lastly,
(6) the agreement must contemplate that the tribunal will make a de-
cision upon a dispute which is already formulated at the time when
a reference is made to the tribunal.
JUDGMENT
The other factors which are relevant include, whether the agreement
contemplates that the tribunal will receive evidence from both sides
and hear their contentions or at least give the parties an opportunity
to put them forward; whether the wording of the agreement is con-
sistent or inconsistent with the view that the process was intended
to be an arbitration, and whether the agreement requires the tribunal
to decide the dispute according to law.”
The Court then referred to several precedents including English cases and
held:
“In the present case, the Memorandum of Understanding records
the settlement of various disputes as between Group A and Group B
14
Page 14
| putes between Groups A<br>division of assets in agreed<br>med body and under a sch<br>Clause 9 is intended to<br>se in the implementation o<br>on of the Chairman, IFCI<br>udicial determination by th<br>ominate another person fo<br>een made final and bindin<br>or any different decision t | |
| the parties to | the dispute. |
| f the settlem | ent already a |
| rding of evide | nce etc. are |
| airman, IFCI is to be bin | |
JUDGMENT
(emphasis supplied)
24. In Bharat Bhushan Bansal v. U.P. Small Industries
15
Page 15
Corporation Limited, Kanpur (1999) 2 SCC 166, the two Judge Bench
interpreted Clauses 23 and 24 of the agreement entered into between the
parties for execution of work of construction of a factory and allied buildings
of the respondent at India Complex, Rai Bareli. Those clauses were as under:
“Decision of the Executive Engineer of the UPSIC to be final on cer-
tain matters
23. Except where otherwise specified in the contract, the decision of
the Executive Engineer shall be final, conclusive and binding on both
the parties to the contract on all questions relating to the meaning,
the specification, design, drawings and instructions hereinbefore
mentioned, and as to the quality of workmanship or materials used
on the work or as to any other question whatsoever in any way aris-
ing out of or relating to the designs, drawings, specifications, esti-
mates, instructions, orders or otherwise concerning the works or the
execution or failure to execute the same whether arising during the
progress of the work, or after the completion thereof or abandon-
ment of the contract by the contractor shall be final and conclusive
and binding on the contractor.
Decision of the MD of the UPSIC on all other matters shall be final
24. Except as provided in clause 23 hereof, the decision of the Man-
aging Director of the UPSIC shall be final, conclusive and binding
on both the parties to the contract upon all questions relating to any
claim, right, matter or thing in any way arising out of or relating to
the contract or these conditions or concerning abandonment of the
contract by the contractor and in respect of all other matters arising
out of this contract and not specifically mentioned herein.”
JUDGMENT
It was argued on behalf of the appellant that Clause 24 should be construed as
an arbitration clause because the decision of the Managing Director was
binding on both the parties. The two Judge Bench analysed Clauses 23 and
24 of the agreement, referred to the judgment in K.K. Modi v. K.N. Modi
(supra), State of U.P. v. Tipper Chand (supra), State of Orissa v. Damodar
16
Page 16
Das (supra) and observed:
“In the present case, the Managing Director is more in the category
of an expert who will decide claims, rights, or matters in any way
pertaining to the contract. The intention appears to be more to avoid
disputes than to decide formulated disputes in a quasi-judicial man-
ner. In para 18.067 of Vol. 2 of Hudson on Building and Engineering
Contracts. Illustration (8) deals with the case where, by the terms of
a contract, it was provided that the engineer
“shall be the exclusive judge upon all matters relating to the
construction, incidents, and the consequences of these
presents, and of the tender, specifications, schedule and draw-
ings of the contract, and in regard to the execution of the
works or otherwise arising out of or in connection with the
contract, and also as regards all matters of account, including
the final balance payable to the contractor, and the certificate
of the engineer for the time being, given under his hand, shall
be binding and conclusive on both parties.”
It was held that this clause was not an arbitration clause and that the
duties of the Engineer were administrative and not judicial.
Since clause 24 does not contemplate any arbitration, the application
of the appellant under Section 8 of the Arbitration Act, 1940 was
misconceived. The appeal is, therefore, dismissed though for reasons
somewhat different from the reasons given by the High Court. there
will, however, be no order as to costs.”
JUDGMENT
25. The aforesaid judgments fully support the view taken by
us that Clause 30 of B-1 Agreement is not an arbitration clause.
26. The issue deserves to be looked into from another angle.
In terms of Clause 29 of B-1 Agreement, the Superintending Engineer of the
Circle was invested with the authority to approve all works to be executed
under the contract. In other words, the Superintending Engineer was to
supervise execution of all works. The power conferred upon him to take
decision on the matters enumerated in Clause 30 did not involve adjudication
17
Page 17
of any dispute or lis between the State Government and the contractor. It
would have been extremely anomalous to appoint him as Arbitrator to decide
any dispute or difference between the parties and pass an award. How could
he pass an award on any of the issues already decided by him under Clause
30? Suppose, he was to decline approval to the designs, drawings etc. or was
to object to the quality of materials etc. and the contractor had a grievance
against his decision, the task of deciding the dispute could not have been
assigned to the Superintending Engineer. He could not be expected to make
adjudication with an un-biased mind. Even if he may not be actually biased,
the contractor will always have a lurking apprehension that his decision will
not be free from bias. Therefore, there is an inherent danger in treating the
Superintending Engineer as an Arbitrator. This facet of the problem was
highlighted in the judgment of the two Judge Bench in Bihar State Mineral
Development Corporation and another v. Encon Builders (I)(P) Limited
(2003) 7 SCC 418. In that case, the agreement entered into between the
JUDGMENT
parties contained a clause that any dispute arising out of the agreement shall
be referred to the Managing Director of the Corporation and his decision shall
be final and binding on both the parties. After noticing several precedents, the
two Judge Bench observed:
“There cannot be any doubt whatsoever that an arbitration agree-
ment must contain the broad consensus between the parties that the
disputes and differences should be referred to a domestic tribunal.
The said domestic tribunal must be an impartial one. It is a well-
settled principle of law that a person cannot be a judge of his own
cause. It is further well settled that justice should not only be done
but manifestly seen to be done.
18
Page 18
Actual bias would lead to an automatic disqualification where the
decision-maker is shown to have an interest in the outcome of the
case. Actual bias denotes an arbitrator who allows a decision to be
influenced by partiality or prejudice and thereby deprives the liti-
gant of the fundamental right to a fair trial by an impartial tribunal.
As the acts of bias on the part of the second appellant arose during
execution of the agreement, the question as to whether the respon-
dent herein entered into the agreement with his eyes wide open or
not takes a back seat. An order which lacks inherent jurisdiction
would be a nullity and, thus, the procedural law of waiver or estop-
pel would have no application in such a situation.
It will bear repetition to state that the action of the second appellant
itself was in question and, thus, indisputably, he could not have ad-
judicated thereupon in terms of the principle that nobody can be a
judge of his own cause.”
27. We may now notice the judgments relied upon by the
learned counsel for the appellant and find out whether the proposition laid
down therein supports his argument that Clause 30 should be treated as an
arbitration clause.
JUDGMENT
28. The facts of Mallikarjun v. Gulbarga University case
(supra) were that the respondent-University had accepted the tender
submitted by the appellant for construction of an indoor stadium. In
pursuance of the work order issued by the competent authority, the appellant
completed the construction. Thereafter, he invoked the arbitration clause for
resolution of the disputes which arose from the execution of the project.
Superintending Engineer, PWD, Gulbarga Circle was entrusted with the task
of deciding the disputes. The parties filed their respective claims before the
Superintending Engineer. He considered the same and passed an award. The
19
Page 19
appellant filed execution petition in the Court of Principal Civil Judge (Senior
Division), Gulbarga. The respondent filed an objection petition under Section
47 of the CPC. The Executing Court rejected the objection. The University
challenged the decision of the Executing Court and pleaded that the
agreement on the basis of which the dispute was referred to the
Superintending Engineer was not an arbitration agreement and, as such,
award made by him cannot be treated as one made under the 1940 Act. The
High Court accepted the plea of the University and set aside the order of the
trial Court. Clause 30 of the agreement which came up for interpretation by
this Court was as under:
“The decision of the Superintending Engineer of Gulbarga Circle
for the time being shall be final, conclusive and binding on all par-
ties to the contract upon all questions relating to the meaning of the
specifications, designs, drawings and instructions hereinbefore men-
tioned and as to the quality of workmanship or material used on the
work, or as to any other question, claim, right, matter, or thing
whatsoever, in any way arising out of or relating to the contract de-
signs, drawings, specifications, estimates, instructions, orders or
those conditions, or otherwise concerning the works or the execu-
tion or failure to execute the same, whether arising during the
progress of the work, or after the completion or abandonment
thereof in case of dispute arising between the contractor and Gul-
barga University.”
JUDGMENT
After analyzing the aforesaid clause and making a reference to essential
elements of arbitration agreement enumerated in Bihar State Mineral
Development Corporation v. Encon Builders (I)(P) Limited (supra), the three
Judge Bench held:
“Applying the aforesaid principle to the present case, clause 30 re-
quires the Superintending Engineer, Gulbarga Circle, Gulbarga, to
20
Page 20
give his decision on any dispute that may arise out of the contract.
Further, we also find that the agreement postulates present or future
differences in connection with some contemplated affairs inasmuch
as there also was an agreement between the parties to settle such
difference by a private tribunal, namely, the Superintending Engi-
neer, Gulbarga Circle, Gulbarga. It was also agreed between the
parties that they would be bound by the decision of the Tribunal.
The parties were also ad idem.
In the aforesaid view of the matter, it must be held that the agree-
ment did contain an arbitration clause.”
The Bench distinguished the judgment in Bharat Bhushan Bansal’s case by
making the following observations:
“A bare comparison of clause 30 of the contract agreement involved
in the present matter and clauses 23 and 24 involved in Bharat
Bhushan Bansal case would show that they are not identical.
Whereas clause 30 of the agreement in question provides for resolu-
tion of the dispute arising out of the contract by persons named
therein; in terms of clause 24, there was no question of decision by
a named person in the dispute raised by the parties to the agree-
ment. The matters which are specified under clauses 23 and 24 in
Bharat Bhushan Bansal case were necessarily not required to arise
out of the contract, but merely claims arising during performance of
the contract. Clause 30 of the agreement in the present case did pro-
vide for resolution of the dispute arising out of the contract by the
Superintending Engineer, Gulbarga Circle, Gulbarga. For that rea-
son, the case relied upon by the learned counsel for the respondent
is distinguishable.
JUDGMENT
Once clause 30 is constituted to be a valid arbitration agreement, it
would necessarily follow that the decision of the arbitrator named
therein would be rendered only upon allowing the parties to adduce
evidence in support of their respective claims and counter-claims as
also upon hearing the parties to the dispute. For the purpose of con-
stituting the valid arbitration agreement, it is not necessary that the
conditions as regards adduction of evidence by the parties or giving
an opportunity of hearing to them must specifically be mentioned
therein. Such conditions, it is trite, are implicit in the decision-mak-
ing process in the arbitration proceedings. Compliance with the
principles of natural justice inheres in an arbitration process. They,
irrespective of the fact as to whether recorded specifically in the ar-
bitration agreement or not are required to be followed. Once the
21
Page 21
principles of natural justice are not complied with, the award made
by the arbitrator would be rendered invalid. We, therefore, are of
the opinion that the arbitration clause does not necessitate spelling
out of a duty on the part of the arbitrator to hear both parties before
deciding the question before him. The expression “decision” sub-
sumes adjudication of the dispute. Here in the instant case, it will
bear repetition to state, that the disputes between the parties arose
out of a contract and in relation to matters specified therein and,
thus, were required to be decided and such decisions are not only fi-
nal and binding on the parties, but they are conclusive which clearly
spells out the finality of such decisions as also their binding nature.
A clause which is inserted in a contract agreement for the purpose
of prevention of dispute will not be an arbitration agreement. Such a
provision has been made in the agreement itself by conferring
power upon the Engineer-in-Charge to take a decision thereupon in
relation to the matters envisaged under clauses 31 and 32 of the said
agreement. Clauses 31 and 32 of the said agreement provide for a
decision of the Engineer-in-Charge in relation to the matters speci-
fied therein. The jurisdiction of the Engineer-in-Charge in relation to
such matters are limited and they cannot be equated with an arbitra-
tion agreement. Despite such clauses meant for prevention of dis-
pute arising out of a contract, significantly, clause 30 has been in-
serted in the contract agreement by the parties.
The Superintending Engineer, Gulbarga Circle, Gulbarga, is an offi-
cer of the Public Works Department in the Government of Kar-
nataka. He is not an officer of the University. He did not have any
authority or jurisdiction under the agreement or otherwise either to
supervise the construction works or issue any direction(s) upon the
contractor in relation to the contract job. He might be an ex officio
member of the Building Committee, but thereby or by reason
thereof, he could not have been given nor in fact had been given an
authority to supervise the contract job or for that matter issue any
direction upon the contractor as regards performance of the con-
tract.”
JUDGMENT
(emphasis supplied)
29. In Punjab State v. Dina Nath (supra), the two Judge
Bench was called upon to consider whether clause 4 of work order No.114
dated 16.5.1985 constituted an arbitration agreement. The clause in question
was as under:
22
Page 22
“Any dispute arising between the department and the contractor/so-
ciety shall be referred to the Superintending Engineer, Anandpur
Sahib, Hydel Circle No.1, Chandigarh for orders and his decision
will be final and acceptable/binding on both the parties.”
After noticing the judgment in K.K. Modi v. K.N. Modi, the Court observed:
“Keeping the ingredients as indicated by this Court in K.K.Modi in
mind for holding a particular agreement as an arbitration agreement,
we now proceed to examine the aforesaid ingredients in the context
of the present case:
(a) Clause 4 of the Work Order categorically states that the deci-
sion of the Superintending engineer shall be binding on the
parties.
(b) The jurisdiction of the Superintending Engineer to decide the
rights of the parties has also been derived from the consent of
the parties to the Work Order.
(c) The agreement contemplates that the Superintending Engineer
shall determine substantive rights of parties as the clause en-
compasses all varieties of disputes that may arise between the
parties and does not restrict the jurisdiction of the Superin-
tending Engineer to specific issues only.
(d) That the agreement of the parties to refer their disputes to the
decision of the Superintending Engineer is intended to be en-
forceable in law as it is binding in nature.
JUDGMENT
The words “any dispute” appears in clause 4 of the Work Order.
Therefore, only on the basis of the materials produced by the parties
in support of their respective claims a decision can be arrived at in
resolving the dispute between the parties. The use of the words “any
dispute” in clause 4 of the Work order is wide enough to include all
disputes relating to the said Work Order. Therefore, when a party
raises a dispute for non-payment of money after completion of the
work, which is denied by the other party, such a dispute would come
within the meaning of “arbitration agreement” between the parties.
Clause 4 of the Work Order also clearly provides that any dispute
between the department and the contractor shall be referred to the
Superintending Engineer, Hydel Circle No.1, Chandigarh for orders.
The word “orders” would indicate some expression of opinion,
which is to be carried our, or enforced and which is a conclusion of a
body (in this case Superintending engineer, Hydel Circle No.1,
23
Page 23
Chandigarh). Then again the conclusion and decision of the Superin-
tending Engineer will be final and binding on both the parties. This
being the position in the present case and in view of the fact that
clause 4 of the Work Order is not under challenge before us, the de-
cision that would be arrived at by Superintending Engineer, Hydel
Circle No.1, Chandigarh must also be binding on the parties as a re-
sult whereof clause 4 must be held to be a binding arbitration agree-
ment.”
The Bench distinguished the judgment in State of Orissa v. Damodar Das
(supra) by making the following observations:
“From a plain reading of this clause in Damodar Das it is evident
that the powers of the Public Health Engineer were essentially to su-
pervise and inspect. His powers were limited to the questions relat-
ing to the meaning of the specifications, drawings and instructions,
quality of workmanship or materials used on the work or as to any
other question, claim, right, matter, drawings, specifications, esti-
mates, instructions, orders or these conditions or otherwise concern-
ing the works or the execution or failure to execute the same. How-
ever, in the case before us, the Superintending Engineer was given
full power to resolve any dispute arising between the parties which
power in our view is wide enough to cover any nature of dispute
raised by the parties. The clause in the instant case categorically
mentions the word “dispute” which would be referred to him and
states “his decision would be final and acceptable/binding on both
the parties.”
JUDGMENT
30. In our opinion, neither of the judgments relied upon by
Shri Mukherjee help the cause of his client. In Mallikarjun’s case, this Court
noted that Superintending Engineer, Gulbarga Circle, Gulbarga was not an
officer of the University and he did not have any authority or jurisdiction
either to supervise the construction work or issue any direction to the
contractor in relation to the project. The Court also emphasized that the
parties had agreed that any dispute arising from the contract would be
24
Page 24
referred to the decision of the Superintending Engineer. These factors are
missing in the instant case. Likewise, Clause 4 of the work order which came
up for interpretation in Punjab State v. Dina Nath (supra) contemplated
resolution by the Superintending Engineer of any dispute arising between the
department and the contractor. Therefore, the relevant clause of the work
order was rightly treated as an Arbitration Agreement.
31. In view of the above discussion, we hold that the High
Court had rightly held that Clause 30 of B-I Agreement is not an Arbitration
Agreement and the trial Court was not right in appointing the Chief Engineer
as an Arbitrator.
32. Before concluding, we may observe that circulars issued
by the State Government may provide useful guidance to the authorities
involved in the implementation of the project but the same are not conclusive
of the correct interpretation of the relevant clauses of the agreement and, in
JUDGMENT
any case, the Government’s interpretation is not binding on the Courts.
33. In the result, the appeals are dismissed.
.........................................J.
(G.S. SINGHVI)
.........................................J.
(V. GOPALA GOWDA)
.........................................
25
Page 25
J.
(C. NAGAPPAN)
New Delhi,
October 4, 2013.
JUDGMENT
26
Page 26