Full Judgment Text
IN THE HIGH COURT OF DELHI AT NEW DELHI
% Judgment delivered on: 12.07.2021
+ ARB.P. 275/2021 & I.A. No. 2725/2021
M/S JYOTI SARUP MITTAL ..... Petitioner
versus
THE EXECUTIVE ENGINEER-XXIII, SOUTH
DELHI MUNICIPAL CORPORATION ..... Respondent
Advocates who appeared in this case:
For the Petitioner : Mr Aayushmaan Vatsyayana
For the Respondent : Mr Sandeep Bajaj with Ms Aakanksha and
Mr Asav Rajan, Advocates.
CORAM
HON’BLE MR JUSTICE VIBHU BAKHRU
JUDGMENT
VIBHU BAKHRU, J
1. The petitioner has filed the present petition under Section 11 of
the Arbitration and Conciliation Act, 1996 (hereinafter the ‘A&C Act’),
inter alia , praying that an arbitrator be appointed to adjudicate the
disputes that have arisen between the parties in connection with the
agreement dated 21.11.2006 (hereinafter ‘the Agreement’) entered into
by the petitioner with the respondent (hereinafter ‘SDMC’) for
executing the works relating to “Improvement to Drainage System and
Roads Ready Mix Concrete in Ward No. C-47 & 48 in the West Zone”
Signature Not Verified
Digitally Signed
By:DUSHYANT
RAWAL
ARB P. 275 of 2021 Page 1 of 21
falling under the Executive Engineer-XXIII, MC Primary School, 10
Block, Subhash Nagar, New Delhi-110027.
2. In terms of the Agreement, SDMC awarded the contract for
execution of the works in question to the petitioner at a contract price
of ₹25,30,28,517/- In terms of the tender conditions, SDMC called upon
the petitioner to deposit the performance security in the form of a Bank
Guarantee for an amount of ₹1,02,00,000/-, which is equivalent to 5%
of the contract price. The Agreement stipulated 06.12.2006 as the
commencement date and 05.12.2008 as the date of completion of the
works.
3. The petitioner completed the works on 31.05.2010, however, it
claims that the execution of the improvement work was hampered due
to various reasons attributable to the respondent including dismal
condition of the approach roads; frequent shutdown of the RMC Plant;
heavy rains; over hanging high tension line rendering it unsafe to deploy
JCP Machine/RMC Batch Mix Truck; and daily intervention of rural
village representatives. Notwithstanding the said hindrances, the
petitioner completed the works on 31.05.2010 and SDMC issued the
completion certificate on 27.01.2012.
4. The petitioner states that due to delay in the execution of works
caused due to various hindrances, it was entitled to 1371 days of
additional time for completion of the contract. The petitioner applied
for an extension of time for completion of the contract to the concerned
authority by an application dated 16.09.2010. However, the Executive
Signature Not Verified
Digitally Signed
By:DUSHYANT
RAWAL
ARB P. 275 of 2021 Page 2 of 21
Engineer claims that the said application was submitted by the
petitioner on 14.11.2011. However, it is not disputed that the said
request remained pending.
th
5. On 16.08.2011, the petitioner submitted its 24 and Final Bill for
verification and payment. However, despite several requests, the same
was not processed till March, 2017.
6. The petitioner claims that despite repeated requests to the
concerned Executive Engineer, SDMC for payment of dues, the same
was not cleared. The petitioner claims that it sent a notice to the
concerned Executive Engineer, SDMC pursuant to which, a hearing
was conducted on 11.08.2016.
7. The petitioner has also placed a letter dated 11.08.2016 issued by
the Executive Engineer, SDMC on record. The said letter indicates that
a meeting was held on that date (11.08.2016) and the Representatives
of the petitioner had been heard in response to “ the notice for
litigation/arbitration ” issued by the petitioner. The Executive Engineer
had raised queries regarding delay and finalization of the contract and
the letter indicates that he had been informed by the staff of SDMC that
the delay was on account of various formalities that were to be
completed by the petitioner and misplacement of record due to long
illness and demise of the concerned Joint Engineer. According to the
SDMC, the payment was pending for various reasons including non-
finalization of extra items and substitute items and non-finalization of
the petitioner’s request for extension of time. The said letter indicates
Signature Not Verified
Digitally Signed
By:DUSHYANT
RAWAL
ARB P. 275 of 2021 Page 3 of 21
that the petitioner was requested not to file any litigation/arbitration
case and SDMC would finalize the contract within a period of three
months.
8. The petitioner’s Final Bill was cleared on 01.03.2017, pursuant
to which, ₹1,50,16,762/- was paid by SDMC to the petitioner.
9. The petitioner claims that the Final Bill as cleared did not include
several items and had also not considered the petitioner’s claim for
extension of time. And, he continued to pursue with the Executive
Engineer, SDMC for finalization of the pending issues. The petitioner
claims that he was informed that the Executive Engineer had sent the
extension of time case with recommendation from the competent
authority to extend the time without levy of compensation to the
Standing Committee of the Executive Engineers, where the matter was
pending for a long time. The petitioner also sent a letter dated
15.02.2018 informing the Executive Engineer that the case for
extension of time had been considered favorably and accordingly,
claimed that a balance payment of ₹2,58,32,744/- was also due and
payable by SDMC. It also provided the details thereof. The petitioner
claims that his efforts for release of the balance payment was in vain.
10. Finally, the petitioner issued a notice dated 12.05.2020 invoking
the Disputes Resolution Clause and requested the Executive Engineer,
SDMC to settle its claims. But it did not receive any response to the said
notice dated 12.05.2020. Thereafter, it sent a notice dated 13.07.2020
Signature Not Verified
Digitally Signed
By:DUSHYANT
RAWAL
ARB P. 275 of 2021 Page 4 of 21
to the Chief Engineer, SDMC but the said notice also failed to illicit any
response. The petitioner escalated the matter to the Engineer-in-Chief,
SDMC by his letter dated 18.08.2020, however, the disputes remained
unresolved. The petitioner in its notice dated 18.08.2020 requested the
Engineer-in-Chief, SDMC to appoint an arbitrator to adjudicate its
claims. However, the petitioner did not receive any response to the said
notice as well.
11. Thereafter, by a letter dated 23.09.2020 the petitioner requested
the Commissioner, SDMC to appoint a Sole Arbitrator to adjudicate its
claims but received no response to the said notice as well.
12. Consequently, by a letter dated 23.09.2020, the petitioner
requested the Commissioner, SDMC, New Delhi to appoint a Sole
Arbitrator and proposed the names of five arbitrators from the list of the
empaneled arbitrators approved by CPWD, MOUD. However, it did not
receive a response to its letter dated 23.09.2020.
13. The following claims were raised in the aforementioned notices
served by the petitioner to the Executive Engineer, SDMC:
| S.No. | Description | Notice dated<br>12.05.2020 to<br>Executive<br>Engineer | Notice dated<br>13.07.2020 to<br>Chief<br>Engineer | Notice dated<br>18.08.2020 to<br>Engineer in<br>Chief | Notice dated<br>23.09.2020 to<br>the<br>Commissioner | Present<br>Petition dated<br>21.11.2020 |
|---|---|---|---|---|---|---|
| 1. | Amount of<br>part rates<br>kept in 24th<br>RA Bill | 7,03,521/- | 7,03,521/- | 7,03,521/- | 7,03,521/- | 7,03,521/- |
| 2. | Escalation | 2,10,10,389/- | 2,10,10,389/- | 2,10,10,389/- | 2,10,10,389/- | 2,10,10,389/- |
Signature Not Verified
Digitally Signed
By:DUSHYANT
RAWAL
ARB P. 275 of 2021 Page 5 of 21
| 3. | Amount<br>withheld in<br>the 24th RA<br>Bill | 1,50,000/- | 1,50,000/- | 1,50,000/- | 1,50,000/- | 1,50,000/- |
|---|---|---|---|---|---|---|
| 4. | Damages and<br>losses due to<br>prolongation | 34,37,906/- | 34,37,906/- | 34,37,906/- | 34,37,906/- | 34,37,906/- |
| 5. | Security<br>Deposit | 10,54,957/- | 10,54,957/- | 10,54,957/- | 10,54,957/- | 10,54,957/- |
| 6. | Loss of<br>profit, losses<br>and damages<br>due to<br>prolongation<br>of contract | - | 1,03,13,718/- | 1,03,13,718/- | 1,03,13,718/- | 1,03,13,718/- |
| 7. | Land rent for<br>RMC Plant<br>on rented<br>land and<br>shifting at<br>other location<br>during<br>currency of<br>contract | - | 40,00,000/- | 30,00,000/- | 30,00,000/- | 30,00,000/- |
| 8. | Interest at<br>12% per<br>annum up to<br>actual date of<br>realization | Claimed<br>from<br>01.12.2010<br>To be<br>calculated | Claimed<br>from<br>01.03.2010<br>To be<br>calculated | Claimed<br>from<br>01.03.2010<br>To be<br>calculated | Claimed from<br>01.03.2010<br>To be<br>calculated | Claimed<br>from<br>01.03.2010<br>To be<br>calculated |
| 9. | Interest on<br>delayed<br>payment of<br>INR<br>1,50,16,762/-<br>from<br>01.03.2017<br>till<br>01.12.2020 | 1,12,41,589/- | - | - | - | - |
| Total | 3,74,48,362/- | 4,06,21,029/- | 5,13,49,018/- | 5,13,49,018/- | 4,01,21,029/- |
Signature Not Verified
Digitally Signed
By:DUSHYANT
RAWAL
ARB P. 275 of 2021 Page 6 of 21
14. Since, the arbitrator was not appointed, the petitioner has filed
the present petition.
Submissions
15. Mr. Sandeep Bajaj, learned Standing Counsel for SDMC,
submitted that the petition should be dismissed on, essentially, four
grounds. First, he submitted that an agreement to refer the disputes to
arbitration does not exist between SDMC and the petitioner, as the
parties have not signed the General Conditions of the Contract (GCC),
which contains the Arbitration Clause.
16. Second, he contended that Clause 25 of the Agreement provides
for a dispute resolution process, where recourse to arbitration is
contingent on the Commissioner, SDMC appointing an arbitrator. In
this regard, he relied on the decision of the Supreme Court in Oriental
Insurance Company Ltd v. Narbheram Power and Steel Pvt Ltd.:
(2018) 6 SCC 534 .
17. Third, he contended that the invocation of arbitration by the
petitioner was barred by limitation. He submitted that the work was
completed on 31.05.2010. The petitioner had submitted an application
dated 16.09.2010 for extension of time. And, the Completion Certificate
was issued on 27.01.2012. The petitioner had submitted the Final Bill
on 16.08.2011. The same was passed on 01.03.2017 and a sum of
₹1,50,16,762/- was paid to the petitioner. Clause 9 of the Tender
Conditions requires the concerned Executive Engineer (EE) to finalise
Signature Not Verified
Digitally Signed
By:DUSHYANT
RAWAL
ARB P. 275 of 2021 Page 7 of 21
the bill and clear its dues within a period of six months, which expired
on 30.11.2010. Mr Bajaj contended that in the given facts, the
petitioner’s claim is, ex facie , time barred in the absence of any
averment as to any acknowledgement, which could have extended the
period of limitation. Though certain letters were issued by the
petitioner, they present a half-hearted attempt but do not amount to
revival of a time barred debt. He submitted that since the petitioner’s
claim is a money claim, it is barred by limitation as it has been raised
after a decade. Since the claim was first raised either on 16.08.2011 or
27.01.2012, the period of limitation expired in the year 2014. In this
regard, he relied upon the decision of the Supreme Court in Bharat
Sanchar Nigam Limited & Anr. v. Nortel Networks India Pvt Ltd.:
C.A. No. 843-844 of 2021 decided on 10.03.2021 .
18. Fourth, he contended that the petitioner had not complied with
the pre-arbitration procedures as set out in the agreement between the
parties. He stated that recourse to arbitration can be taken after the
aggrieved party has exhausted its remedy of approaching the
Superintending Engineer and subsequently, the Chief Engineer. In this
regard, he relied upon the decision of the Supreme Court in United
India Insurance Co Ltd & Anr. v. Hyundai Engineering and
Construction Co Ltd & Ors.: (2018) 17 SCC 607 , and stated that
arbitration clauses must be construed strictly and therefore, require
completion of pre-arbitration procedures. He submitted that the letters
dated 12.05.2020, 13.07.2020, 18.08.2020 and 23.09.2020 cannot be
Signature Not Verified
Digitally Signed
By:DUSHYANT
RAWAL
ARB P. 275 of 2021 Page 8 of 21
construed as discharge of the procedure prescribed under the arbitration
agreement between the parties.
Reasons and Conclusion
19. At the outset, it would be relevant to refer to Clause 25 of the
GCC. The said Clause is set out below:
“ Settlement of Dispute & Arbitration
Except where otherwise provided in the contract
all questions and disputes relating to the meaning of the
specifications, design, drawings and instructions here-in-
before mentioned and as to the quality of workmanship
or materials as used on the work or as to any other
question, claim, right, matter or thing whatsoever in any
way arising out of or relating to the contract, designs,
drawings, specifications, estimates, instructions, orders
or these conditions or otherwise concerning the works or
the execution or failure to execute the same whether
arising during the progress of the work or after the
cancellation, termination, completion or abandonment
thereof shall be dealt with as mentioned hereinafter:
If the contractor considers any work demanded of him to
be outside the requirements of the contract, or disputes
any drawings, record or decision given in writing by the
Engineer-in-Charge on any matter in connection with or
arising out of the contract of carrying out of the work, to
be unacceptable, he shall promptly within 15 days
request the Superintending Engineer in writing for
written instruction or decision. Thereupon, the
Superintending Engineer shall give his written
instructions or decision within a period of one month
from the receipt of the contractor’s letter.
Signature Not Verified
Digitally Signed
By:DUSHYANT
RAWAL
ARB P. 275 of 2021 Page 9 of 21
If the Superintending Engineer fails to give his
instructions or decision in writing within the aforesaid
period or if the contractor is dissatisfied with the
instructions or decision of the Superintending Engineer,
the contractor may, within 15 days of the receipt of
Superintending Engineer’s decision, appeal to the Chief
Engineer who shall afford an opportunity to the
contractor to be heard, if the latter so desires, and to offer
evidence in support of his appeal. The Chief Engineer
shall give his decision within 30 days of receipt of
contractors appeal. If the contractor is dissatisfied with
this decision, the contractor shall within a period of 30
days from receipt of the decision, give notice to the
Commissioner MCD for appointment of arbitrator failing
which the said decision shall be final binding and
conclusive and not referable to adjudication by the
arbitrator.
Except where the decision has become final, binding and
conclusive in terms of Sub Para (i) above disputes or
difference shall be referred for adjudication through
arbitration a sole arbitrator appointed by the
Commissioner MCD. If the arbitrator so appointed is
unable or unwilling to act or resigns his appointment or
vacates his office due to any reason whatsoever another
sole arbitrator shall be appointed in the manner aforesaid.
Such person shall be entitled to proceed with the
reference from the stage at which it was left by his
predecessor.
It is a terms of this contract that the party invoking
arbitration shall give a list of disputes with amounts
claimed in respect of each such dispute along with the
notice for appointment of arbitrator and giving reference
to the rejection by the Chief Engineer of the appeal.
It is also a term of this contract that no person other than
a person appointed by such Commissioner MCD as
aforesaid should act as arbitrator and if for any reason
Signature Not Verified
Digitally Signed
By:DUSHYANT
RAWAL
ARB P. 275 of 2021 Page 10 of 21
that is not possible, the matter shall not be referred to
arbitration at all.
It is also a term of this contract that if the contractor does
not make any demand for appointment of arbitrator in
respect of any claims in writing as aforesaid within 120
days of receiving the intimation from the Engineer-in-
Charge that the final bill is ready for payment, the claim
of the contractor shall be deemed to have been waived
and absolutely barred and the MCD shall be discharged
and released of all liabilities under the contract in respect
of these claims.
The arbitration shall be conducted in accordance with the
provisions of the Arbitration and Conciliation Act, 1996
(26 of 1996) or any statutory modifications or re-
enactment thereof and the rules made thereunder and for
the time being in force shall apply to the arbitration
proceeding under this clause.
It is also a term of this contract that the arbitrator shall
adjudicate on only such disputes as are referred to him by
the appointing authority and give separate award against
each dispute and claim referred to him and in all cases
where the total amount of the claims by any party exceed
Rs.1,00,000/- the arbitrator shall give reasons for the
award.
It is also a term of the contract that if any fees are payable
to the arbitrator these shall be paid equally by both the
parties.
It is also a term of the contract that the arbitrator shall be
deemed to have entered on the reference on the date he
issues notice to both the parties calling them to submit
their statement of claims and counter statement of claims.
The venue of the arbitration shall be such place as may
be fixed by the arbitrator in his sole direction. The fees,
if any, of the arbitration shall, if required to be paid
before the award is made and published, be paid half and
Signature Not Verified
Digitally Signed
By:DUSHYANT
RAWAL
ARB P. 275 of 2021 Page 11 of 21
half by each of the parties. The cost of the reference and
of the award (including the fees, if any, of the Arbitrator)
shall be in the discretion of the arbitrator who may direct
to any by whom and in what manner, such costs or any
part thereof shall be paid and fix or settle the amount of
costs to be so paid.”
20. Although it was feebly argued that there is no agreement to refer
the disputes to arbitration since the GCC has not been signed by the
parties and a signed copy of the GCC or the agreement has not been
produced, however, it is not in dispute that the GCC includes Clause 25
as set out above and the GCC forms an integral part of the agreement
between the parties. Thus, the contention that there is no agreement
between the parties to refer the disputes to arbitration is not merited.
21. The principal controversy involved in the present petition,
essentially, revolves around the import of the provision that the Sole
Arbitrator would be appointed by “ The Commissioner, MCD ” and “ no
person other than a person appointed by such Commissioner, MCD as
aforesaid should act as arbitrator and if for any reason that is not
possible, the matter should not be referred to arbitration at all .”
22. Concededly, in view of the decisions delivered by the Supreme
Court in TRF Ltd. v. Energo Engineering Projects Ltd.: (2017) 8 SCC
377 and Perkins Eastman Architects DPC & Anr. v. HSCC (India)
Ltd.: Arbitration Application No. 32/2019, decided on 26.11.2019 , it
is no longer permissible for the Commissioner, MCD (Commissioner
SDMC) to appoint an arbitrator unless the petitioner agrees for such
appointment in writing after the disputes have arisen.
Signature Not Verified
Digitally Signed
By:DUSHYANT
RAWAL
ARB P. 275 of 2021 Page 12 of 21
23. It is important to note that the said decisions were rendered in the
context of Sub-section (5) of Section 12 of the A&C Act, which was
introduced by virtue of the Arbitration and Conciliation (Amendment)
Act, 2015. The said Act was enacted pursuant to the recommendations
made by the Law Commission of India in its Report No. 246. The Law
Commission of India had, inter alia , highlighted the necessity to
introduce provisions for ensuring neutrality and independence of
arbitrators. The Commission had drawn heavily from the “IBA
Guidelines on Conflicts of Interest in International Arbitration” and had
indicated the circumstances which would give rise to justifiable doubts
as to independence and impartiality of arbitrators. The Fifth and the
Seventh Schedule, which were introduced in the A&C Act, were in turn
based on the Orange and the Red Lists under the aforementioned IBA
Guidelines. Independence and impartiality of an arbitral tribunal is the
foundation on which the efficacy of the arbitration as an alternate
dispute resolution mechanism rest. The importance of independence
and impartiality of arbitrators cannot be overstated. Considering that the
legislative amendments under Section 12(5) of the A&C Act were
introduced to strengthen arbitration as a dispute resolution mechanism
and the expansive interpretation of the said provision by the Supreme
Court in the cases of TRF Ltd. v. Energo Engineering Projects Ltd
( supra ) and Perkins Eastman Architects DPC and Anr. ( supra ); the
SDMC’s contention that the arbitrator be appointed by the
Commissioner, MCD or not at all, cannot be accepted. The import of
the said contention is that either the arbitral proceedings be conducted
in a manner which can no longer be considered as impartial or free from
Signature Not Verified
Digitally Signed
By:DUSHYANT
RAWAL
ARB P. 275 of 2021 Page 13 of 21
likelihood of bias, or not be conducted at all. This Court is unable to
accept the same.
24. As noted above, in view of Sub-section (5) of Section 12 as
introduced in the A&C Act and the decisions of the Supreme Court in
TRF Ltd. v. Energo Engineering Projects Ltd ( supra ) and Perkins
Eastman Architects DPC and Anr. ( supra ), it is no longer permissible
for the Officer of SDMC to appoint an arbitrator if the other party does
not expressly consent to the same in writing, after the disputes have
arisen. However, the key question to be addressed is whether in such
circumstances, the entire agreement between the parties to refer the
disputes to arbitration is rendered void or non-existent.
25. The Sub-clause that no person other than the person appointed by
the Commissioner, MCD should act as an arbitrator and if that is not
possible, the matter should not be referred to arbitration, must be read
as an integral part of the scheme which entitled the Commissioner,
MCD to appoint an arbitrator. It emphasized that no person other than
the one appointed by Commissioner, MCD should act as an arbitrator.
The latter part of the Clause which provides that in case it was not
possible for the person to act as an arbitrator, the matter should not be
referred to arbitration, is for the sole purpose of emphasizing that only
the person appointed by the Commissioner, MCD should act as an
arbitrator. However, in view of the expansive reading of Section 12(5)
of the A&C Act by the Supreme Court in TRF Ltd. v. Energo
Engineering Projects Ltd ( supra ) and Perkins Eastman Architects
DPC and Anr. ( supra ), it is no longer permissible that only the
Signature Not Verified
Digitally Signed
By:DUSHYANT
RAWAL
ARB P. 275 of 2021 Page 14 of 21
Commissioner, MCD can appoint an arbitrator to adjudicate the
disputes between the parties. In view of the said decisions, the entire
scheme, which is premised on the Commissioner, MCD appointing an
arbitrator, must perish. The provision that the matter should not be
referred to arbitration at all in case it is not possible for the person
appointed by Commissioner, MCD to act as an arbitrator, is premised
on the basis that the Commissioner, MCD is empowered to appoint such
an arbitrator. In such cases where it is not possible for a person
appointed by him to act as an arbitrator, the latter part of the Clause that
emphasizes that the matter would not be referred to arbitration – which
as stated earlier, is only for the purposes of emphasizing that the person
appointed by the appointing authority should act as an arbitrator – may
have some applicability. However, the said limb of Clause 25 of the
GCC must be read in a very restrictive manner and cannot be read to
mean that by virtue of the legislative amendments that require the
disputes to be referred to an independent and impartial arbitrator, the
agreement to refer the disputes to arbitration is rendered ineffective. In
view of the legislative amendment introduced by the Arbitration and
Conciliation (Amendment) Act, 2015, the scheme which empowered
the Commissioner, MCD to unilaterally appoint an arbitrator perishes
and with it, the attendant clause that no other person other than the one
appointed by the Commissioner, MCD should act as an arbitrator is
ineffective.
26. The key question to be addressed is whether the entire Arbitration
Clause must fail, if the mechanism for appointment of an arbitrator by
Signature Not Verified
Digitally Signed
By:DUSHYANT
RAWAL
ARB P. 275 of 2021 Page 15 of 21
the Commissioner, MCD is no longer permissible. This Court is of the
view that the said question must be answered in the negative. Clause
25 of the GCC embodies an agreement between the parties to refer the
disputes to arbitration. It is implicit in the said agreement that the
arbitration must be conducted in a fair and objective manner, by an
impartial and independent arbitrator. And, this forms an essence of the
agreement between the parties; that is, to resolve the disputes by
referring the same to an independent and impartial arbitrator and to
accept his decision as final and binding. This Court is of the view that
this fundamental agreement between the parties would not perish even
if it is no longer permissible to follow the mechanism of appointment
of an arbitrator. Considered in the context of the agreement to refer the
disputes to arbitration, the said Clause can, at best, be said to be
ancillary to the agreement to refer the disputes to arbitration and the
same may be considered severable. Thus, even though the mechanism
for appointment of the arbitrator can no longer be followed, the
agreement between the parties to refer the disputes to arbitration would
still survive.
27. In Chloro Controls India (P) Ltd. v. Severn Trent Water
Purification Inc. & Ors.: (2013) 1 SCC 641 , the Supreme Court had
emphasized that it is the legislative object and the intent of the framers
of the statute to encourage arbitration. The Court had further observed
that it is “ required to exercise its jurisdiction in a pending action, to
hold the parties to the arbitration clause and not to permit them to avoid
their bargain of arbitration ….” Thus, so far as possible, the courts must
Signature Not Verified
Digitally Signed
By:DUSHYANT
RAWAL
ARB P. 275 of 2021 Page 16 of 21
endeavour to ensure that the agreement between the parties to refer the
disputes to arbitration is sustained.
28. This Court had also considered the aforesaid issue in a recent
decision in T.K. Engineering Consortium Pvt. Ltd. v. The Director
(Projects) Rites and Ors.: Arb. P. 553/2020, decided on 08.03.2021 .
The said decision covers the question raised in the present petition as
well.
29. It is also relevant to note that the respondent had not taken any
steps for appointment of an arbitrator, despite the petitioner requesting
it to do so.
30. The Supreme Court in Indian Oil Corporation Ltd. and Ors. v.
M/s. Raja Transport (P) Ltd.: (2009) 8 SCC 520 had held that the
condition that required only the designated authority to nominate the
arbitrator would interfere with the power of the Chief Justice under
Section 11(8) of the A&C Act and, therefore, the said portion of the
arbitration clause was required to be ignored. Thus, in any view of the
matter, since the concerned authority has failed to act on the request of
the petitioner, it would be necessary for this Court to appoint an
arbitrator and the Clause that no person other than the one appointed by
the Commissioner, MCD should act as an arbitrator, cannot be read to
interfere with the power concerning the jurisdiction of this Court to
appoint an arbitrator.
31. The reliance placed by the petitioner on the decision of the
Supreme Court in Oriental Insurance Company Limited v. Narbheram
Signature Not Verified
Digitally Signed
By:DUSHYANT
RAWAL
ARB P. 275 of 2021 Page 17 of 21
Power and Steel Pvt. Ltd. ( supra ), is misplaced. In the said case, the
Supreme Court had considered the question of reference of disputes to
arbitration where it was plainly evident that the disputes were outside
the scope of the Arbitration Clause. The Court had found that in cases
where the appellant Insurance Company had disputed its liability under
a policy, the dispute was outside the scope of the arbitration clause. The
Court found that the parties had clearly agreed and understood that if
the Insurance Company disputed or had not accepted the liability, the
dispute was not arbitrable. In facts of that case, it was evident that the
appellant Insurance Company had disputed its liability under the policy.
The disputes were not related to the quantum of the claim payable but
occasioned by a complete denial of any liability under the policy. The
said disputes were outside the scope of the arbitration clause. In the
present case, it is not SDMC’s contention that the disputes raised are
not arbitrable.
32. The next issue raised by SDMC is that the claims raised by the
petitioner are barred by limitation. The petitioner disputes the same. It
is the petitioner’s case that he had issued a notice to refer the disputes
to arbitration and on receipt of the said notice, the Executive Engineer,
SDMC had convened a meeting. The Executive Engineer had examined
the reasons for delay in finalization of the bill submitted by the
petitioner. He had, inter alia , noted that the finalization had been
delayed for various reasons including that the extra items and substitute
items had not been finalized. Further, the case for extension of time had
not been finalized. After noting the various reasons, the Executive
Signature Not Verified
Digitally Signed
By:DUSHYANT
RAWAL
ARB P. 275 of 2021 Page 18 of 21
Engineer, SDMC had directed other officers to take all necessary action
to finalize the bill for the aforesaid work.
33. It is important to note that the petitioner was requested not to file
any litigation/arbitration case as the Department would finalize the
contract within a period of three months. The Department had
determined that a sum of ₹1.55 crores was payable and had also cleared
the said bill in March 2017. It is, however, the petitioner’s case that the
extension of time was not considered. The petitioner claims that the
concerned officials had recommended its case for extension of time, but
the same had not been considered. It had, accordingly, sent a letter dated
15.02.2018 claiming that an amount of ₹2,58,32,744/- was due and
payable as the extension of time for completion of the contract had been
recommended and, according to the petitioner, he was entitled to such
extension. The petitioner claims that it had pursued SDMC for clearing
the amounts as due to it. It was contended on behalf of the petitioner
that having requested the petitioner to not initiate any action and
assuring the petitioner that the entire matter would be finalized, it is not
open for the SDMC to now state that the petitioner’s claims are barred
by limitation.
34. It is well settled that this Court is not required to examine any
other contentious issues regarding the disputes between the parties at
the stage of referring the parties to arbitration. The examination under
Section 11 of the A&C Act is confined to examining the existence of an
arbitration agreement between the parties.
Signature Not Verified
Digitally Signed
By:DUSHYANT
RAWAL
ARB P. 275 of 2021 Page 19 of 21
35. The Supreme Court has held that where it is ex facie apparent that
the claims raised are beyond limitation, the party’s application under
Section 11 of the A&C Act may be rejected (See: Vidya Drolia v.
Durga Trading Corporation: (2021) 2 SCC 1 ). But in cases where it is
a contentious issue, the same would be beyond the scope of examination
under Section 11 of the A&C Act. Plainly, in this case, the question of
limitation is a contentious one and beyond the standards of examination
under Section 11 of the A&C Act.
36. The contention that the petitioner has not followed the pre-
reference procedure is also erroneous. It is apparent from the record that
the petitioner had sought resolution of its claims before the Executive
Engineer, SDMC. Since the same were not resolved, the petitioner had
also sent a letter to the Superintendent Engineer and thereafter,
escalated it to the Chief Engineer. Thus, the petitioner had exhausted all
avenues for resolution of the disputes before seeking a reference of the
disputes to arbitration.
37. In view of the above, this Court considers it apposite to allow the
present petition. The pending application is disposed of.
38. SDMC had suggested names of two former Chief Justices of the
J&K High Court “for being appointed as an arbitrator”. In view of the
above, this Court proposes to appoint Justice Gita Mittal, former Chief
Justice of the J&K High Court (one of the names as suggested by
SDMC) to be appointed as a Sole Arbitrator to adjudicate the disputes
between the parties.
Signature Not Verified
Digitally Signed
By:DUSHYANT
RAWAL
ARB P. 275 of 2021 Page 20 of 21
39. The parties are at liberty to approach the learned Sole Arbitrator
for eliciting her consent and the disclosure as required under Section
12(1) of the A&C Act. Let the same be furnished before the next date
of hearing.
40. List on 22.07.2021.
VIBHU BAKHRU, J
JULY 12, 2021
RK
Signature Not Verified
Digitally Signed
By:DUSHYANT
RAWAL
ARB P. 275 of 2021 Page 21 of 21