Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 5
PETITIONER:
SECRETARY TO THE GOVERNMENT, TRANSPORT DEPTT. MADRAS
Vs.
RESPONDENT:
MUNUSWAMY MUDALIAR & ORS.
DATE OF JUDGMENT29/08/1988
BENCH:
MUKHARJI, SABYASACHI (J)
BENCH:
MUKHARJI, SABYASACHI (J)
RANGNATHAN, S.
CITATION:
1988 AIR 2232 1988 SCR Supl. (2) 673
1988 SCC Supl. 651 JT 1988 (4) 730
1988 SCALE (2)1070
ACT:
Arbitration Act, 1940: S. 5-Chosen Arbitrator-Removal
of-Apprehension of bias-To be based on cogent materials.
HEADNOTE:
The dispute as to the refund of earnest money deposit to
the respondent-contractor was referred to an arbitrator
named in the arbit-ration clause of the agreement. The
respondent filed claim before him. During the pendency of
the claim before the said arbitrator, there was succession
to that office by another incumbent. The succeeding Officer
wanted to continue the arbitration proceedings but before
that the respondent made an application under s. 5 of the
Arbitration Act for removal of the arbitrator on the ground
that he being an employee of the State the petitioner
apprehended bias. The Judge, City Civil Court found that the
Chief Engineer of the Circle concerned was in favour of the
cancellation of the contract in question and when it came to
be terminated the construction was sought to be entrusted at
the risk and cost of the petitioner on the advice or the
proposal of the Chief Engineer. Being of the view that the
arbitrator, the Superintending Engineer, being subordinate
to the said Chief Engineer, would necessarily have a leaning
to accept the attitude expressed by latter, he concluded
that there could legitimately be a bias in the mind of the
arbitrator. The High Court dismissed the appeal in limine.
Allowing the appeal by special leave,
HELD: A named and agreed arbitrator cannot and should
not be removed in exercise of a discretion vested in the
court under s. 5 of the Act unless there is allegation
either against his honesty or capacity or mala fide or
interest in the subject matter or reasonable apprehensiors
of the bias. [677E-F]
A predisposition to decide for or against one party,
without proper regard to the true merits of the dispute is
bias. There must be reasonable apprehension of that
predisposition based on cogent materials. Mere imagination
PG NO 673
PG NO 674
of a ground cannot be an excuse for apprehending bias.
[677F-G; 678C]
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 5
International Authority lndia v.K.D. Bali & Anr.,J.T.
1988 2 S.C.1. and Commercial Arbitration, by Mustill &
Boyd., [1982] Edn. p.214, Hulsbury’s Laws of England, 4th
Edn. Vol. 2, para 551, p. 282 referred to.
In the instant case, when the parties entered into the
contract they knew the terms of the contract including
arbitration clause providing that the Superintending
Engineer of a particular Circle shall be the arbitrator.
They also knew the scheme and the fact that the said
Superintending Engineer was subordinate to the Chief
Engineer of the Circle. ln spite of that the parties agreed
and entered into arbitration and indeed submitted to the
jurisdiction of the arbitrator at that time to begin with,
who however, could not complete the arbitration because he
was transferred and succeeded by a successor. In these
circumstances no bias could reasonably be apprehended and
made a ground for removal of a named contractor. In numerous
contracts with the Government, clauses requiring the
Super"intending Engineer or some official of the Government
to be the arbitrator are there. It cannot be said that the
Superintending Engineer as such cannot be entrusted with
the work or arbitration and that apprehension simpliciter
in the mind of the contractor without any tangible ground,
would he a justification for removal. [677C-F]
The case is remanded back to the Judge, City Civil
Court, Madras to appoint the Superintending Engineer, Trichy
to be the arbitrator in accordance with the arbitration
agreement. [678C-D]
JUDGMENT:
CIVIL APPELLATE JURISDICTION: Civil Appeal No. 3251 of
1988.
From the Judgment" and Order dated 21.9.l984 of the
Madras High Court in C.R.P. No.3482 of 1984.
A.V.Rangam for the Appellant
P. Krishna Rao and K.R.Nagaraja for the Respondents.
The Judgment of the Court was delivered by
SABYASACHI MUKHARJI,J.Leave granted and the appeal is
disposed of by the following judgment.
PG NO 675
This appeal arises out of an order of the High Court of
Madras, dated 21st September, 1984. The appellant is the
Secretary to the Government, Transport Deptt. , Madras, and
the respondent No. 1 is the managing partner of M/s.
National Company, which was the successful tenderer of the
work of construction of a bridge across the river Coovum at
Koyambedu within the corporation limit of the city of Madras
and accordingly the necessary contract was executed between
the respondent No. 2-the Superintending Engineer
(Highways) World Bank Project Circle, Madras, and the said
Company on 28th April, 1979.
According to the conditions of the contract between the
parties, the work should have been completed on or before
5th November, 1980. The said National Company, however,
according to the appellant, did not even commence the work
till 21.9.1981. and despite extension of time until
31.10.1981 the said firm failed and neglected even to
commence the job. Consequently, the contract in favour of
the said firm was determined absolutely at their risk and
cost, according to the appellant. The respondent herein, in
his individual capacity as managing partner of the said
Company filed a suit in the City Civil Court, Madras, being
O.S. No. 3996/82 claiming damages alleged to have been
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 5
caused as a result of the said determination of the said
contract and for refund of earnest money deposit etc.
In view of the Arbitration Clause under the agreement
between the parties, the appellant filed a petition for
referring the dispute to the arbitrator for further
proceedings and the City Civil Court? Madras, accepting the
appellant’s prayer, passed orders directing both the parties
to refer the disputes to the arbitrator, and stayed the
suit. As per the order of the City Civil Court, Madras, the
respondent filed claim petition before the arbitrator,
namely, Superintending Engineer (Highways & Rural Works)
Rural Roads Circle, Tiruchirapalli, being the second
respondent herein.
During the pendency of the claim before the said
arbitrator, the respondent filed another application
seeking to change the arbitrator on the ground that the
arbitrator being an employee of the State Government, an
Engineer from any sector other than the sector of Tamil Nadu
or a retired Engineer of the State Government might be
appointeded arbitrator.
The contract between the parties, inter alia, contained
the following Arbitration Clause:
PG NO 676
"(3) The arbitrator for fulfilling the duties set forth
in the arbitration clause of the Standard Preliminary
Specification shall be Superintending Engineer (H) Rural
Roads Tiruchira Palli Circle."
Pursuant to this the Superintending Engineer of that
Circle, at the relevant time, was previously appointed as
arbitrator. There was succession to that office by ’another
incumbent and the succeeding Superintending Engineer wanted
to continue the arbitration proceedings but before that an
application was made under Section 5 of the Arbitration Act,
l940 (hereinafter called ‘the Act’) for removal of the
arbitrator, before the learned Judge of the City Civil
Court, Madras.
The learned Judge by his order sought to revoke the
authority of the named arbitrator. The learned Judge in his
order dated 6th March,1984, inter alia, observed as follows:
"The apprehension of bias on the part of the Arbitrator
is made to rest on the ground that the first respondent in
the counter filed before the Arbitrator to the claim made by
the petitioner referred to G.O. Ms. 409/Transport Dated
7.4.83 which in turn made a reference to a letter
No.114879/D2/81. Dated 30. 10.82 of the Chief Engineer, H &
RW."
In the order of the learned Judge, City Civil Court, he
stated that the Chief Engineer of the Circle concerned was
in favour of the cancel-lation of the contract in question
and the contract entrusted to the petitioner came to be
terminated and the construction was sought to be entrusted
at the risk and cost of the petitioner on the advice or the
proposal of the Chief Engineer. The Superintending Engineer
is sub-ordinate to the Chief Engineer, therefore, the
learned Judge, City Civil Court was of the view, as he says
in the judgment, "It is not unreasonable to say that the
successive Superintending Engineer of this particular
department who will be subordinate to the Chief Engineer
will necessarily have a leaning to accept the attitude
expressed by the Chief Engineer." The learned Judge came to
the conclusion that there could legitimately be a bias in
the mind of the arbitrator who was the Superintending
Engineer against the appellant. The High Court also did not
examine this aspect and dismissed the appeal in limine.
Hence, this appeal.
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 4 of 5
Apprehension of bias in the mind of the arbitrator is a
good ground for removal of the arbitrator under section 5 of
PG NO 677
the Act. The learned Judge, City Civil Court, had directed
the parties to submit a list of three engineers willing to
be appointed as arbitrator and if the parties express
consensus one of the three from the list of the petitioner
or from the list of the respondent would. be chosen and
appointed as arbitrator and in case there is no consensus
between the parties then from among six engineers to be
mentioned by both the parties three each in a separate list
one of them will be selected by draw of lots and appointed
as arbitrator. The parties were directed to submit a list of
three engineers of their choice who would be willing to be
appointed as arbitrator in the matter within a stipulated
period.
This is a case of removal of a named arbitrator under
Section 5 of the Act which gives jurisdiction to the Court
to revoke the authority of the arbitrator. When the parties
entered into the contract, the parties knew the terms of the
contract including arbitration clause. The parties knew the
scheme and the fact that the Chief Engineer is superior and
the Superintending Engineer is subordinate to the Chief
Engineer of the particular Circle. ln spite of that the
parties agreed and entered into arbitration and indeed
submitted to the jurisdiction of the Superintending Engineer
at that time to begin with, who, however, could not complete
the arbitration because he was transferred and succeeded by
a successor. In those circumstances on the facts stated no
bias can reasonably be apprehended and made a ground for
removal of a named arbitrator. ln our opinion this cannot
be, at all, a good or valid legal ground. Unless there IS
allegation against the named arbitrator either against his
honesty or capacity or mala fide or interest in the subject
matter or reasonable apprehension of the bias, a name and
agreed arbitrator cannot and should not be removed in
exercise of a discretion vested in the Court under section 5
of the Act.
Reasonable apprehension of bias in the mind of a
reasonable man can be a ground for removal of the
arbitrator. A predisposition to decide for or against one
party, without proper regard to the true merits of the
dispute is bias. There must be reasonable apprehension of
that predisposition. The reasonable apprehension must be
based on cogent materials. See the observations of Mustill
and Boyd, Commercial Arbitration, 1982 Edition, page 214.
Halsbury’s Laws of England, Fourth Edition, Volume 2, para
551, page 282 describe that the test for bias is whether a
reasonable intelligent man, fully appraised of all the
circumstances, would feel a serious apprehension of bias.
This Court in International Authority of lndia v. K.D.
Bali and Anr., J.T. l9988 2 S.C. I held that there must be
PG NO 678
reasonable evidence to satisfy that there was a real
likelihood of bias. Vague suspicions of whimsical,
capricious and unreasonable people should not be made the
standard to regulate normal human conduct. In this country
in numerous contracts with the Government, clauses requiring
the Superintending Engineer or some official of the Govt. to
be the arbitrator are there. It cannot be said that the
Superintending Engineer, as such cannot be entrusted with
the work of arbitration and that an apprehension,
simpliciter in the mind of the contractor without any
tangible ground, would be a justification for removal. No
other ground for the alleged apprehension was indicated in
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 5 of 5
the pleadings before the learned Judge or the decision of
the learned Judge. There was, in our opinion, no ground for
removal of the arbitrator. Mere imagination of a ground
cannot be an excuse for apprehending bias in the mind of the
chosen arbitrator.
In that view of the matter, the order made by the
learned Judge. City Civil Court, and the decision of the
High Court cannot be sustained and they are set aside. The
appeal is allowed. We remand the case back to the learned
Judge, City Civil Court, to ask the Government to appoint
the Superintending Engineer. Trichy, to be an arbitrator in
accordance with the arbitration agreerment. The arbitrator
will proceed according to the evidence of the parties and
after considering all the relevant facts according to the
agreement and make an award in accordance with law. There
will be no order as to costs.
P.S.S. Appeal allowed.