OM SWAYAMBHU SIDDHIVINAYAK vs. HARISCHANDRA DINKAR GAIKWAD AND ORS.

Case Type: Restoration Application

Date of Judgment: 04-11-2025

Preview image for OM SWAYAMBHU SIDDHIVINAYAK vs. HARISCHANDRA DINKAR GAIKWAD AND ORS.

Full Judgment Text


2025:BHC-AS:47203
906-ARA-21-2025-OJ-F.doc


IN THE HIGH COURT OF JUDICATURE AT BOMBAY
CIVIL APPELLATE JURISDICTION
ARBITRATION APPEAL NO. 21 OF 2025
Om Swayambhu Siddhivinayak …Appellant
Versus
Harischandra Dinkar Gaikwad
and Ors. …Respondents
Digitally
signed by
SHRADDHA
KAMLESH
TALEKAR
Date:
2025.11.07
14:23:41
+0530
SHRADDHA
KAMLESH
TALEKAR
Mr. Dinesh D. Tiwari a/w. Pulkeshi Gaikwad, Antony Parel and
E. Siddiqui i/b Dinesh Tiwari and Associates, for Appellant.

Dr. Uday Warunjikar, Senior Advocate a/w. Sumit S. Kate, for
Respondents.
CORAM : SOMASEKHAR SUNDARESAN, J.
Date : November 4, 2025
Oral Judgment :
Context and Factual Background:
1. This is an Appeal filed under Section 37 of the Arbitration
and Conciliation Act, 1996 (“ the Act ”) challenging an order dated March
11, 2025 (“ Impugned Order ”) rejecting an application filed by the
Appellant under Section 8 of the Act. The disputes and differences
between the parties relate to transactions between them arising out of a
Development Agreement, dated May 3, 2011 (“ Development
Agreement ”) and a further Supplemental Agreement dated May 25,
2021 (“ Supplemental Agreement ”).
Page 1 of 18
November 4, 2025
Shraddha
::: Uploaded on - 07/11/2025 ::: Downloaded on - 07/11/2025 14:18:54 :::

906-ARA-21-2025-OJ-F.doc


2. The Appellant, Om Swayambhu Siddhivinayak (“ Developer ”)
had agreed under the Development Agreement to provide a certain
specified area of developed property to the Respondents, who are the
owners of the land on which the development was to take place
(“ Owners ”). The Owners have filed Special Civil Suit No. 157 of 2024
th
before the 4 Joint Civil Judge, Senior Division, Kalyan, inter alia,
seeking specific performance of the provision of certain saleable area to
the Owners (in the quantum of 8,937 sq.ft and 4927 sq.ft.), and a
cancellation of the Supplemental Agreement.

3. It is the case of the Appellant that Clause 30 of the
Development Agreement, which contains the arbitration clause, is an
expansive clause and all disputes and differences between the parties in
connection with the development contracted in that Development
Agreement are amenable to arbitration, and therefore, no Civil Court
could take cognizance of any dispute between the parties in connection
with the Development Agreement.
4. A detailed reading of the Impugned Order would show that
the Learned District Court was swayed by only one factor, namely, that
Supplemental Agreement did not contain any arbitration clause and the
Development Agreement alone contains an arbitration clause. In
Page 2 of 18
November 4, 2025
Shraddha
::: Uploaded on - 07/11/2025 ::: Downloaded on - 07/11/2025 14:18:54 :::

906-ARA-21-2025-OJ-F.doc


paragraph 4 of the Impugned Order, it is recorded by the Learned Judge
that the suit is for cancellation of the Development Agreement as well as
the Supplemental Agreement. The Learned Judge was persuaded to
rule that in the absence of an arbitration clause in the subsequent
agreement and considering the nature of the dispute, the arbitrator is
not competent and empowered to decide the disputes between the
parties. Therefore, the Learned Judge refused to refer the parties to
arbitration and has continued to deal with the suit himself.
Contentions of the Parties:
5. Dr. Warunjikar, Learned Senior Advocate on behalf of the
Respondents seeks to defend the Impugned Order on the premise that
the parties had a layered and a structured approach of dispute
resolution divided between Clause 13 of the Development Agreement,
and Clause 30 of the Development Agreement. According to him,
Clause 30 of the Development Agreement deals with all disputes and
differences connected to the development contracted in the
Development Agreement, but Clause 13 deals with the provision of the
developed area in terms of Clauses 1 and 2, for which, the parties had
agreed that they would approach a Court for a declaration which would
be binding on the parties. Dr. Warunjikar would also contend that the
Page 3 of 18
November 4, 2025
Shraddha
::: Uploaded on - 07/11/2025 ::: Downloaded on - 07/11/2025 14:18:54 :::

906-ARA-21-2025-OJ-F.doc


Suit seeks a declaration that the Supplemental Agreement is a product
of fraud and that arbitral tribunals cannot adjudicate serious allegations
of fraud.
6. Mr. Dinesh Tiwari, Learned Advocate on behalf of the
Appellant would submit that even a plain reading of the prayers in the
Suit would demonstrate that the relief sought is of specific performance
of the Development Agreement, which is subject matter of the
arbitration agreement. As regards the distinction between Clause 13 and
Clause 30, Mr. Tiwari would contend that the specific performance
sought by the Respondents is for delivery of a developed area that is at
variance with the area set out in Clauses 1 and 2 of the Development
Agreement. Therefore, he would submit, that the scope of jurisdiction
under Clause 13, even accepting the contentions on behalf of the
Respondents, would take the plaint outside the scope of Clause 13, and
therefore, within the scope of Clause 30.
7. It is also seen that prayer 11(a) in the plaint seeks a
declaration that the Supplemental Agreement is a product of fraud, and
therefore, should be cancelled as not being binding on the parties.

Analysis and Findings:
8. Having heard Learned Advocates for both the parties at
Page 4 of 18
November 4, 2025
Shraddha
::: Uploaded on - 07/11/2025 ::: Downloaded on - 07/11/2025 14:18:54 :::

906-ARA-21-2025-OJ-F.doc


length and having examined the material on record with the benefit of
their assistance, I am constrained to find that the Impugned Order is
not sustainable.
9. At the threshold, the provisions of Section 8 of the Act must
be noticed. It is settled law that under section 8(1) of the Act, a judicial
authority before which an action is brought in a matter, which is subject
matter of an arbitration agreement, shall (if a party to the arbitration
agreement, or any person claiming through or under it, applies) refer
the parties to arbitration, unless it is found that prima facie , no valid
arbitration agreement exists.
10. A plain reading of Section 8(1) of the Act would indicate that
the judicial authority before whom a proceeding is brought is required
to refer the parties to arbitration, unless such authority comes to a
prima facie finding that no valid arbitration agreement exists. The scope
of review by the Section 8 Court is restricted to examining the subject
matter of the proceedings before it, compare it with the subject matter
of the arbitration agreement and unless it comes to a prima facie view
that no valid arbitration agreement exists, it is required to refer the
parties to arbitration.

Page 5 of 18
November 4, 2025
Shraddha
::: Uploaded on - 07/11/2025 ::: Downloaded on - 07/11/2025 14:18:54 :::

906-ARA-21-2025-OJ-F.doc


11. Once it is found that an arbitration agreement exists in
respect of the same subject matter as that of the proceedings before the
Section 8 Court, the correct forum to deal with all matters is the arbitral
forum. If the Section 8 Court prima facie finds that the existence itself
is in doubt, the Court would not need to refer the dispute to arbitration.
12. The Impugned Order is conspicuously silent on the analysis
on any of these facets. It summarily states that the Supplemental
Agreement does not contain an arbitration clause. This appears to be
the sole ground on which the Section 8 application has been rejected.
Indeed, the Impugned Order also refers to the “nature” of the issues
involved but does not allude to whether the allegation of fraud would, in
the facts of the case, bring the matter outside the jurisdiction of an
arbitral tribunal. While the reasons provided in the Impugned Order
are sketchy and primarily limited to the Supplemental Agreement not
having had an arbitration clause, it is well settled that an appeal is a
continuation of the proceedings, and therefore, despite the absence of
reasons in the Impugned Order, I have examined the material on record
in the same manner as the Section 8 Court ought to have examined,
considering that Section 37 is an appellate provision.

13. It is now well stated that the Section 8 Court must only
Page 6 of 18
November 4, 2025
Shraddha
::: Uploaded on - 07/11/2025 ::: Downloaded on - 07/11/2025 14:18:54 :::

906-ARA-21-2025-OJ-F.doc


restrict its examination to examining the subject matter of the
proceedings before it and compare it with the subject matter of the
arbitration agreement. Once subject matter commonality is established,
if the Section 8 Court is prima facie of the view that a valid arbitration
agreement exists, it is obliged to refer the parties to arbitration. If the
Section 8 Court comes to a prima facie view that a valid arbitration
agreement does not exist, the Section 8 Court may then proceed to deal
with the proceedings before it.
14. Having examined the Development Agreement, in my
opinion, Clause 30 is expansive in its terms and all disputes and
differences in connection with the Development Agreement, would fall
within the ambit of the arbitrable disputes between the parties. The
Section 8 Court has indeed come to the view that an arbitration
agreement exists in the Development Agreement. There is not a
whisper in the Impugned Order about the distinction between Clause 13
and Clause 30 of the Development Agreement that is now being sought
to be made in these proceedings.
15. The reliance by Dr. Warunjikar upon Clause 13 appeared
attractive at first blush. Despite this distinction not even finding
mention in the Impugned Order, I have given it careful consideration.
Page 7 of 18
November 4, 2025
Shraddha
::: Uploaded on - 07/11/2025 ::: Downloaded on - 07/11/2025 14:18:54 :::

906-ARA-21-2025-OJ-F.doc


Clause 13 refers to delivery of saleable area under Clause 1 and Clause 2
to be referred to a “ nyayalay ” (Court) while Clause 30 refers to dispute
resolution by “ lavaad ” (arbitration). The Development Agreement is in
Marathi. The use of the word “ nyayalay ” and not “ nyayadhikaran ”
(tribunal) would perhaps be suggestive of the parties perhaps intending
to go to a Court in relation to Clause 1 and Clause 2. However, I am
unable to be persuaded by this theory for multiple reasons.
16. First , there is no carve-out in either Clause 30 or in Clause 13,
for exclusion of disputes under Clauses 1 and 2 from the arbitration
agreement, for Clause 13 to be read strictly as a provision for exclusion
from arbitration. A commercial contract must be read with commercial
commonsense, and it is indicative that when read harmoniously, the
reference to resolution under Clause 13 need not be exclusively meant
for a Court as contradistinguished from an arbitral tribunal. The
reference could well be to the dispute resolution forum.
17. Second , indeed, the prayer in the Suit is for delivery of
saleable areas that is far removed in size from the contracted terms of
what is to be delivered under Clauses 1 and 2 of the Development
Agreement. Clause 13 deals with the obligations owed in terms of
Clauses 1 and 2 of the Development Agreement. Seen in this light, it is
Page 8 of 18
November 4, 2025
Shraddha
::: Uploaded on - 07/11/2025 ::: Downloaded on - 07/11/2025 14:18:54 :::

906-ARA-21-2025-OJ-F.doc


not inexorable for Clause 13 to be interpreted as rendering the Court to
be an exclusive forum for resolution of disputes under Clause 1 and
Clause 2.
18. Third , the contention that the parties had agreed to resolve
all development-related disputes by arbitration and to resolve the
consideration for the development i.e. the delivery of saleable area to
the Respondents outside the scope of arbitration does not sound
reasonable or commonsensical. If the parties have multiple reciprocal
promises that form consideration in a contract, and they desired to keep
one type of dispute out of arbitration, they would have used
exclusionary language, which they have not.
19. Fourth, the Supplemental Agreement records satisfaction of
the flow of consideration under the Development Agreement, which is
disputed by the Respondents (the plaintiffs in the Suit) and they seek a
declaration that the Supplemental Agreement is not enforceable. The
prayer about the Supplemental Agreement is essentially a prayer about
the flow of consideration under the Development Agreement, and
therefore the Supplemental Agreement need not be out of the scope of
the subject matter of the arbitration agreement contained in the
Development Agreement. The absence of exclusionary language, and
Page 9 of 18
November 4, 2025
Shraddha
::: Uploaded on - 07/11/2025 ::: Downloaded on - 07/11/2025 14:18:54 :::

906-ARA-21-2025-OJ-F.doc


indeed the variance in the area to be delivered when one compares
Clauses 1 and 2 with the reliefs sought in the Suit, in my opinion, the
fine distinction sought to be drawn between Clause 13 and Clause 30
gets eroded.
20. Finally , since specific performance of the Development
Agreement is sought, even leaving aside the variation in the quantum of
the saleable area claimed by the Respondents in the Suit with the
entitlements under Clauses 1 and 2, the dispute squarely relates to the
terms and conditions of the Development Agreement, which is subject
matter of Clause 30, which is a conventional and expansive arbitration
clause without any exclusions in its language. Therefore, in my opinion,
the subject matter of the Suit is covered by the subject matter of the
arbitration agreement.
21. The Learned Judge has indeed found that an arbitration
agreement exists in the Development Agreement. However, he has
focused on the absence of an arbitration clause in the Supplemental
Agreement. Since that instrument purported to record the discharge of
consideration under the Development Agreement, arguably, it did not
need a separate arbitration clause, when Clause 30 of the Development
Agreement squarely deals with disputes relating to that instrument and
Page 10 of 18
November 4, 2025
Shraddha
::: Uploaded on - 07/11/2025 ::: Downloaded on - 07/11/2025 14:18:54 :::

906-ARA-21-2025-OJ-F.doc


discharge of consideration would fall within its scope. The
Supplemental Agreement, which seeks to record that the consideration
under the Development Agreement stands discharged, is an adjectival
element of the substance of the Development Agreement.
Fraud Contention and Case Law Analysed:
22. The judgement of the Supreme Court in the case of Sushma
1
Shivkumar Daga is squarely on point and the following extracts lend
themselves for application in the facts of this case :
14. The basic purpose for bringing an amendment in Section 8 (as
well as Section 11 of the Arbitration Act) was to minimise the scope
of judicial authority in matters of arbitration, except on the ground
where prima facie, no valid arbitration agreement exists.
24. After the 2015 amendment, primarily the court only has to see
whether a valid arbitration agreement exists. Additionally, the clear
non-arbitrability of cases, such as where a party to the agreement is
statutorily protected, such as a consumer "has also to be seen by the
Court" (Booz Allen & Hamilton Inc. Vs. SBI Home Finance Ltd.,
(2011) 5 SCC 532). Short of the narrow field stated above, the scope
of judicial scrutiny at the stage of Section 11(6) or Section 8 is
extremely limited.
25. Objections will nevertheless be raised both on Section 8 and
Section 11 applications. These objections can be genuine, such as
where there is no arbitration clause or where the matter is itself
1
Sushma Shivkumar Daga Vs. Madhurkumar Ramkrishnaji Bajaj & Ors. – 2023 SCC
OnLine SC 1683
Page 11 of 18
November 4, 2025
Shraddha
::: Uploaded on - 07/11/2025 ::: Downloaded on - 07/11/2025 14:18:54 :::

906-ARA-21-2025-OJ-F.doc


non-arbitrable, but often these objections could be only to wriggle
out of the statutory commitment of parties to a defined process of
redressal mechanism .
29. The third objection is regarding fraud. The plea of fraud raised
by the appellants in their objection to the Section 8 application has
never been substantiated. Except for making a bald allegation of
fraud there is nothing else. This Court has consistently held that a
plea of fraud must be serious in nature in order to oust the
jurisdiction of an arbitrator. In Rashid Raza v. Sadaf Akhtar ((2019)
8 SCC 710), this Court laid down two conditions which must be
satisfied before the Court can refuse to refer the matter to the
arbitrator, a forum consciously decided by parties in an agreement.
The first is whether the plea permeates the entire contract and above
all, the arbitration agreement, rendering it void or secondly, whether
the allegation of fraud touches upon the internal affairs of the parties
inter se having no implication in the public domain. The allegations
must have some implication in public domain to oust the jurisdiction
of an arbitrator, if an allegation of fraud exists strictly between the
parties concerned, the same will not be termed to be as a serious
nature of fraud and hence would not be barred for arbitration.
[Emphasis Supplied]
23. The aforesaid case also has a bearing on the element of fraud
pressed into service by Dr. Warunjikar. To begin with the Impugned
Order makes no analysis of the law on the point. The plaint alleges that
the Supplemental Agreement is of product of fraud and signatures of the
Plaintiffs had been taken on blank paper, with the content being set out
Page 12 of 18
November 4, 2025
Shraddha
::: Uploaded on - 07/11/2025 ::: Downloaded on - 07/11/2025 14:18:54 :::

906-ARA-21-2025-OJ-F.doc


in the signed pages subsequently. I am also mindful that the reliefs
sought in the Suit include cancellation of the Supplemental Agreement.
24. It is now settled law that bilateral disputes of fraud are not
necessarily outside the scope of arbitration. The law on arbitral
tribunals being empowered to deal with allegations of fraud has been
distilled and articulated in very clear terms, moving away from the
2
position obtaining from N. Radhakrishnan , where the Supreme Court
had taken a view that where fraud was alleged in the books of accounts
and records of a partnership firm, it fell in the domain of the Courts,
whereby repelling a Section 8 Application was held to be right.
25. However, the law since moved on from that position. The
principle that rights in rem cannot be adjudicated by arbitration, which
is essentially a forum privately created by parties enjoying mutual rights
and obligations in personam has been applied to fraud. Therefore,
where there is a fraud against society at large ( in rem ) as opposed to
fraud within the scope of implementing the contract or inducing a con-
tract, which contract contains an arbitration clause, the issue of fraud
would indeed be arbitrable.

2
Radhakrishnan v. Maestro Engineers – (2010) 1 SCC 72
Page 13 of 18
November 4, 2025
Shraddha
::: Uploaded on - 07/11/2025 ::: Downloaded on - 07/11/2025 14:18:54 :::

906-ARA-21-2025-OJ-F.doc


3
26. In Ayyasamy , the Supreme Court held that the mere allega-
tion of fraud would not dispel arbitrability. It is only in cases where it is
found that allegations are very serious that the Section 8 Court may ig-
nore the arbitration agreement and continue with the proceedings. Even
the existence of the arbitration agreement itself having been obtained by
fraud was kept within the ambit of potential non-arbitrability.

27. However, after Ayyasamy , the law has been emphatically
summarised and set out by a three-judge bench of the Supreme Court in
4
Deccan , repelling the case for not being referred to arbitration where it
was argued that an arbitral tribunal could not be called upon to cancel
three written instruments, and that when there is a serious allegation of
fraud, the arbitrator’s jurisdiction gets ousted. The following extract is
noteworthy:-
6. We have, in our judgment in Avitel Post Studioz Ltd. v. HSBC
PI Holdings (Mauritius) Ltd. 10, laid down the law on invocation of
the "fraud exception" in some detail, which reasoning we adopt and
follow. The said judgment indicates that given the case law since N.
Radhakrishnan, it is clear that N. Radhakrishnan, as a precedent, has
no legs to stand on. If the subject-matter of an agreement between the
parties falls within Section 17 of the Contract Act, 1872, or involves
fraud in the performance of the contract, as has been held in the afore-
3
Ayyasamy Vs. A. Paramasivam – (2016) 10 SCC 386
4
Deccan Paper Mills Co. Ltd. Vs. Regency Mahavir Properties – (2021) 4 SCC 786
Page 14 of 18
November 4, 2025
Shraddha
::: Uploaded on - 07/11/2025 ::: Downloaded on - 07/11/2025 14:18:54 :::

906-ARA-21-2025-OJ-F.doc


said judgment, which would amount to deceit, being a civil wrong, the
subject-matter of such agreement would certainly be arbitrable. Fur-
ther, we have also held that merely because a particular transaction
may have criminal overtones as well, does not mean that its subject-
matter becomes non-arbitrable. We have no doubt that Shri Navare is
right in his submission that there is no averment that the agreement
dated 20-5-2006 and the deed of confirmation dated 13-7-2006 were
not entered into at all, as a result of which the arbitration clause would
be non-existent. Further, it is equally clear that the suit is one that is
inter partes with no "public overtones", as has been understood in
paras 34 and 35 of Avitel, as a result of which this exception would
clearly not apply to the facts of this case.
[Emphasis Supplied]
28. This is an emphatic declaration of the law by a larger bench of
the Supreme Court. Evidently, the Supreme Court has ruled that fraud
in inducing a party into executing a contract as set out in Section 17 of
the Indian Contract Act, 1872, or fraud in the performance of a contract,
would be in the nature of a civil wrong and is eminently arbitrable.
Merely on the ground that there are “criminal overtones” or because a
party claims that there are “public overtones”, the dispute would not be-
come non-arbitrable. Deccan has also dealt with the proposition that a
prayer to declare an instrument illegal, a relief envisaged under Section
31 of the Specific Relief Act, 1963, would not be rendered non-arbit-
rable. Merely because Courts have the power to grant specific perform-
Page 15 of 18
November 4, 2025
Shraddha
::: Uploaded on - 07/11/2025 ::: Downloaded on - 07/11/2025 14:18:54 :::

906-ARA-21-2025-OJ-F.doc


ance, it would not follow that the parties could not agree upon a
privately chosen arbitral tribunal having the same power to grant such
declaratory specific relief.
29. The Supreme Court held that the relief that is sought and
granted in the form of declaring an instrument to be void, would end up
being a relief in personam among the parties to that instrument and not
a relief in rem . The following extracts from Paragraphs 21 and 22 would
be appropriate:
The principle behind the section is to protect a party or a person hav-
ing a derivative title to property from such party from a prospective
misuse of an instrument against him. A reading of Section 31(1) then
shows that when a written instrument is adjudged void or voidable, the
Court may then order it to be delivered up to the plaintiff and can-
celled —in exactly the same way as a suit for rescission of a contract
under Section 29. Thus far, it is clear that the action under Section
31(1) is strictly an action inter partes or by persons who obtained de-
rivative title from the parties, and is thus in personam.
22. Let us see whether Section 31(2) makes any difference to this
position in law. According to the judgment in Aliens Developers, the
moment a registered instrument is cancelled, the effect being to remove
it from a public register, the adjudicatory effect of the court would
make it a judgment in rem. Further, only a competent court is em-
powered to send the cancellation decree to the officer concerned, to ef-
fect such cancellation and "note on the copy of the instrument con-
tained in his books the fact of its cancellation". Both reasons are incor-
Page 16 of 18
November 4, 2025
Shraddha
::: Uploaded on - 07/11/2025 ::: Downloaded on - 07/11/2025 14:18:54 :::

906-ARA-21-2025-OJ-F.doc


rect. An action that is started under Section 31(1) cannot be said to be
in personam when an unregistered instrument is cancelled and in rem
when a registered instrument is cancelled. The suit that is filed for can-
cellation cannot be in personam only for unregistered instruments by
virtue of the fact that the decree for cancellation does not involve its
being sent to the registration office — a ministerial action which is
subsequent to the decree being passed.
[Emphasis Supplied]
Directions and Order:
30. In these circumstances, this appeal is finally disposed of by
allowing it, and quashing and setting aside the Impugned Order.
31. Dr. Warunjikar requests that this judgement be stayed for a
period of four weeks to enable the Respondents to pursue their
prospects in appeal. I do not think a case for a stay is made out in view
of the reasons set out above, and the quality of reasoning in the
Impugned Order.
32. However, since the Impugned Order is set aside and the
parties are being referred to arbitration, the Respondents are given four
weeks’ time to consent to the identity of the arbitrator.
33. As a corollary, I also take note of the fact that an interim
application has been heard by the Learned Judge. While this Appeal has
Page 17 of 18
November 4, 2025
Shraddha
::: Uploaded on - 07/11/2025 ::: Downloaded on - 07/11/2025 14:18:54 :::

906-ARA-21-2025-OJ-F.doc


been heard today, orders have been reserved in the Interim Application.
Since a determination of this Appeal answers a jurisdictional question, it
is clarified that pursuant to this judgement, the Learned District Court is
denuded of jurisdiction in view of the decision taken herein.
34. Therefore, the continuance of the Suit would be
inappropriate, and since the subject matter of the Suit would need to be
referred to arbitration, it is made clear that the Learned District Court
ought not to pronounce its judgement reserved on the interim
application considered by it.
35. All actions required to be taken pursuant to this order, shall
be taken upon receipt of a downloaded copy as available on this Court’s
website.
[ SOMASEKHAR SUNDARESAN, J.]
Page 18 of 18
November 4, 2025
Shraddha
::: Uploaded on - 07/11/2025 ::: Downloaded on - 07/11/2025 14:18:54 :::