Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 3
PETITIONER:
PUNJAB URBAN PLANNING & DEV. AUTHORITY
Vs.
RESPONDENT:
M/S SHIV SARASWATI IRON & STEEL RE-ROLLING MILLS
DATE OF JUDGMENT: 24/03/1998
BENCH:
K. VENKATASWAMI, A.P. MISRA
ACT:
HEADNOTE:
JUDGMENT:
J U D G M E N T
K. Venkataswami, J.
Special leave granted.
Heard counsel on both sides.
The appellant filed a suit for specific performance of
the contract in question by returning (delivery) the goods
weighing 124.255 Metric Tonnes rail/blooms or in the
alternative to direct the defendant to pay a sum of Rs. 2
lacs against the non-delivery/Supply of the said goods.
Brief facts are the following:-
According to the appellant, it was agreed between the
parties that the respondent herein accepted the offer for
re-rolling of M.S. bars out of rails and blooms for all
dias, i.e. 10 MM to 20 MM on certain conditions. The
relevant conditions as given in the plaint are the
following:-
Condition No. 2
Steel will be supplied weight to weight.
Condition No. 3
The firm will be responsible for the quality of steel
out of the material supplied by the Board.
Condition No. 4
The supplier shall be responsible for the safe custody
of the material supplied by the Board to them.
Condition No. 7
About 2000 Mts. of rail or bloom shall be got re-rolled
from you during 1976-77.
The admitted facts are that the appellant supplied
1992.745 Matric Tonnes rail/blooms in 1997 for re-rolling to
the defendant. The respondent, however, returned 1869.490
Metric tonnes of re-rolled materials as against the supply
of 1992.745 Metric Tonnes rail/blooms. The respondent by its
letter dated 16.11.78 informed the appellant that a balance
of 18.765 Mt. of rail/blooms, in addition to Rounds weighing
2.299 Mt., were lying in its stock and the balance of the
material was burnt while re-heating in the furnace in the
process of re-rolling. According to the appellant, as per
the terms and conditions of the contract, the respondent was
liable to return the entire/equal quantity of the
rail/blooms supplied for re-rolling. As the respondent
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 3
failed to return the entire quantity supplied for re-
rolling, the filing of suit became necessary.
The respondent not only resisted the suit but also
filed a counter-claim stating that it has over supplied the
re-rolled material as such it was entitled to recover a sum
of Rs.1,15,735/- on account of wastage of raw material.
The suit and the counter-claim were tried together. The
plaintiff examined one witness to prove Exh. P1, a letter
(offer ) written by the appellant to the respondent. The
Trial Court framed as many as six issues and found that Exh.
P1 (letter) could not be said to be a valid agreement since
it lacked the signatures of the representatives of the
defendant and in the light of the plaintiff’s (appellant)
failure to place all the relevant documents before the
Court, the terms and conditions of the alleged contract had
not been proved. On the basis, the Trial Court partly
decreed the suit of the appellant to the extent of the
admission made by the respondent in its correspondence about
the balance of rail/blooms available with it after re-
rolling. As regards the counter-claim, it was dismissed on
the ground of failure on the part of the defendant to
substantiate the same. It may be noted that the defendant
has examined any witness.
Aggrieved by the partial decree of the suit, the
appellant preferred an appeal to the Appellate Court. The
Appellate Court carefully considered the matter and found
that the Trial Court was not fully right in holding that all
the terms and conditions of the Agreement were not proved
inasmuch as certain terms and conditions extracted in the
Plaint were admitted by the respondent in the written
statement. Nevertheless, the Appellant Court dismissed
appeal observing as follows:-
"Apparently, the defendant had
carried out work for the plaintiff
Board but in the absence of the
prior correspondence relating to
the offer made by the defendant
Mill as also response given by the
Mill to the letter dated 13.5.1976
Ex. P1. It would be difficult for
the court to gauze conclusively as
to what were the exact terms and
conditions on which the defendant
had agreed to carry out the work.
Further more, from a perusal of Ex.
D1 a notice which was sent on
behalf of the defendant company, it
is apparent that there is some
dispute regarding the
interpretation which the parties
were putting on condition No.2
which says that steel will be
supplied weight to weight inasmuch
as according to the defendant this
term made allowance for the wastage
which according to the plaintiff’s
own witness necessarily took place
on account of re-rolling process.
Since on behalf of the plaintiff,
Gurdial Singh PW1 has only
produced the copy of the agreement
which was exhibited as P1 and no
effort has been made to explain
what according to business
terminology was meant by supply of
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 3
the steel weigh to weight. It can’t
by any stretch of imagination be
held that the terms and conditions
of the agreement that was finally
entered into between the parties
has been duly proved on the
record."
As against the said judgment of the Lower Appellate
Court, a Second Appeal was preferred to the High Court and
it was dismissed in limine. The present appeal by special
leave has been filed in these circumstances.
Ms. Rachna Joshi Issar, counsel for the appellant,
vehemently contended before us that the Trial Court as well
as the First Appellate Court ignored the settled proposition
of law that facts admitted need not be proved. According to
the learned counsel, in the absence of any evidence of the
side of the defendant and more so when the defendant’s
counter-claim was dismissed, the plaintiff’s suit must have
been automatically decreed as prayed for and the partial
decree was not adequate on the facts of this case. learned
counsel again and again laid stress on the terms and
conditions set out in the Plaint which have not been
controverted in the written statement and also the absence
of evidence on the side of the defendant to drive home her
point.
It must be remembered that Exh. P1 is only an offer
made by the appellant/plaintiff, which was preceded by
certain correspondence emanating from the respondent and it
can reasonably be presumed that subsequent to Exh. P1 there
must have been some response from the respondent to the
offer of the appellant. All those documents were not placed
before the Court to appreciate correctly and completely the
transactions between the parties. Further, as rightly
pointed out by the Trial Court and the First Appellate Court
that Gurdial Singh PW1 was examined only to prove Exh. P1
and he was not in a position to explain the intricacies
thereon, in particular, the relevant Condition No.2, which
relates to supply and return of material. The language used,
namely, ’weight to weight’, was not at all explained by PW
1. The whole evidence of PW1 has also not been placed before
us. We are of the view that the Lower Appellate Court was
quite justified in observing that the appellant-Board, for
reasons best known to it, had not placed all materials and
no effort has been made to explain what according business
terminology was meant by supply of the esteem weight to
weight. We cannot take exception to the conclusion taken as
above by the Lower Appellate Court. The plaintiff/appellant
must succeed or fail on his own case and cannot take
advantage of weakness in the defendant/respondent’s case to
get a decree.
Therefore, on the facts as found by the Trial Court and
the Lower Appellate Court, we do not think that any question
of law arises for our consideration, as contended by the
learned counsel, in this appeal. the appeal fails and is
dismissed accordingly with no order as to costs.