Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 3
CASE NO.:
Appeal (civil) 665 of 2001
Special Leave Petition (civil) 15881 of 1999
Special Leave Petition (civil) 666 of 2001
Special Leave Petition (crl.) 1476 of 2000
PETITIONER:
M.D. KERALA STATE BEV. (M & M) CORPN. LTD. & ANR.
Vs.
RESPONDENT:
K.M.K. SALIM AND ORS.
DATE OF JUDGMENT: 17/01/2001
BENCH:
S.N.Phukan, S.S.M.Quadri
JUDGMENT:
L.....I.........T.......T.......T.......T.......T.......T..J
J U D G M E N T
Syed Shah Mohammed Quadri, J. Leave is granted.
These two appeals are between the same parties and arise out
of the proceedings relating to award of contract for
handling loading and unloading operations in the appellants
Corporation. They can conveniently be disposed of together.
Civil Appeal No.665 of 2001 @ S.L.P.(C) NO.15881 of 1999 is
directed against the order of a Division Bench of the High
Court of Kerala at Ernakulam in O.P.NO.19616 of 1999 dated
September 20, 1999. Civil Appeal No.666 of 2001 @ S.L.P.
(C)No.1476 of 2000 is directed against an interim order
passed by a learned Single Judge of the High Court of Kerala
at Ernakulam on December 3, 1999 in O.P. No.30284 of 1999
which is offshoot of the order impugned in the
aforementioned Civil Appeal. The facts giving rise to these
appeals are as follows. The appellants invited tenders for
handling loading and unloading operations in the Kerala
State Beverages (M & M) Corporation Liquor Godown in
Valanjavattom, Tiruvalla on September 14, 1998. In response
to the said invitation for tenders, 12 persons including
respondent Nos.1 to 3 filed tenders. Respondent Nos.1 & 2
filed a joint tender and quoted the lowest rates. However,
the appellants, after negotiations, awarded the contract to
respondent No.3 at the rate lower than that quoted by
respondent Nos.1 & 2 on October 23, 1998. On October 26,
1998 respondent Nos.1 & 2 questioned the validity of order
of the appellant awarding the contract to respondent No.3 in
the High Court in O.P.No.20911 of 1998 which was dismissed
by a learned Single Judge of that court on November 26,
1998. But on appeal (Writ Appeal No.2692 of 1998), a
Division Bench of the High Court set aside the order of the
learned Single Judge and directed the appellants to
reconsider the tenders and pass appropriate orders within
one month of the order; for reporting compliance, the case
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 3
was directed to come up on July 23, 1999. The writ appeal
was thus allowed on June 24, 1999. The appellants issued
notice to respondent Nos.1 to 3 and conducted interview on
July 12, 1999. The contract was awarded to respondent No.3
by order issued on July 21, 1999. It is that order which
was quashed by the Division Bench in O.P.No.19616 of 1999 by
the order, impugned in the first- mentioned civil appeal.
By the said impugned order the Managing Director of the
first appellant was directed to consider the tenders afresh
and pass appropriate orders within two weeks from the date
of that order keeping in view the observations of the High
Court in Writ Appeal No.2692 of 1998. On fresh
consideration of the tenders, the Managing Director awarded
the contract to respondent Nos.1 & 2 on October 1, 1999.
Thereafter, respondent Nos.1 & 2 filed O.P.NO.30284 of 1999
seeking a writ of mandamus directing the appellants to enter
into an agreement with them within ten days without
insisting on any licence from the District Labour Officer in
terms of award of the work. In the said O.P. a direction
was sought in the above terms in C.M.P. NO.51612 of 1999.
On December 3, 1999, a learned Single Judge of the High
Court issued an interim direction to the first appellant as
prayed for. That order is the subject matter of appeal in
C.A.No.666 of 2001 @ S.L.P.(C) No.1476 of 2000. Pursuant
thereto, respondent Nos.1 & 2 complied with all the
formalities and have been carrying on loading and unloading
operations. Dr. Rajeev Dhawan, the learned senior counsel
appearing for the appellants, contended that the High Court
ought not to have interfered with the order of the
appellants awarding the contract to respondent No.3 on
October 23, 1998. The reasons for awarding the contract to
respondent No.3, submitted the learned counsel, were neither
irrelevant nor arbitrary within the meaning of Wednesbury
principle. So also, the High Court ought not to have
interfered with the award of contract to respondent No.3 by
quashing the order of the appellant dated June 24, 1999.
The subsequent order of the Managing Director awarding the
contract in favour of respondent Nos.1 & 2, was under the
threat of contempt. He argued that if this Court were to
set aside the impugned order of the Division Bench of the
High Court, the award of contract in favour of respondent
Nos.1 & 2, would consequently stand set aside. Mr. K.
Sukumaran, the learned senior counsel appearing for
respondent Nos.1 & 2, contended that the High Court directed
fresh consideration of the tenders of respondent Nos.1 to 3
by the Managing Director of the first appellant and he
awarded the contract in favour of respondent Nos.1 & 2. As
the secretary of the first appellant did not conduct himself
properly in carrying out the directions of the High Court
dated June 24, 1999, the Managing Director was ordered to
consider afresh the question of awarding tenders. He
submitted that after award of contract in their favour,
respondents executed an agreement with the appellants, paid
the security deposit and furnished the bank guarantee and
that respondent No.3, the affected party, did not challenge
the order of award of contract in their favour so this is
not a fit case for interference by this Court under Article
136 of the Constitution. We have considered the contentions
of the learned counsel of the parties. We are of the view
that by the impugned order the High Court did not direct the
Managing Director of the first appellant to award the
contract in favour of respondent Nos.1 & 2 but ordered him
to consider afresh the competing claims of the tenderers and
he, on fresh consideration, awarded the contract in favour
of respondent Nos.1 & 2. The choice of awarding the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 3
contract to respondent Nos.1 and 2 is that of the Managing
Director of the first appellant. Inasmuch as respondent
Nos.1 & 2, after award of contract, complied with all the
formalities by entering into an agreement, paying the
security deposit and furnishing bank guarantee, it will not
be appropriate, having regard to the subsequent developments
and the facts of this case, to deal with the correctness or
otherwise of the reasoning of the High Court in the impugned
orders. In this view of the matter, while leaving the
questions of law open, we decline to interfere with the
orders under challenge in these appeals. The appeals are
accordingly disposed of. No costs.