Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 41
PETITIONER:
STATE OF ANDHRA PRADESH
Vs.
RESPONDENT:
STATE OF KARNATAKA & ORS.
DATE OF JUDGMENT: 25/04/2000
BENCH:
R.P.Sethi,U.C.Banerjee,V.N.Khare,G.B.Pattanaik,S.B.Majumdar
JUDGMENT:
PATTANAIK, J.
The State of Andhra Pradesh has filed the suit under
Article 131 of the Constitution of India, impleading the
State of Karnataka, Union of India and State of Maharashtra
as party defendants, seeking relief of declaration and
mandatory injunction on the allegation that the State of
Karnataka, in particular has made gross violations of the
decision of Krishna Water Disputes Tribunal and such
violations have adversely affected the residents of the
State of Andhra Pradesh. The relief sought for in the suit
are as under:
(a) declare that the report /decision dated
24.12.1973 and the further report/deecision dated 27.5.1976
of the Krishna Water Disputes Tribunal (KWDT) in their
entirety are binding upon the three riparian States of
Maharashtra, Karnataka and Andhra Pradesh and also the Union
of India; (b) declare that the riparian States are duty
bound to fully disclose to each other and also to the Union
of India all particulars of all projects undertaken or
proposed after December, 1973 and May, 1976 and to direct
the defendants to ensure that execution thereof are in
conformity with and do not conflict with or violate the
decisions of the KWDT and they do not adversely affect the
rights of the other riparian States; (c) declare that the
party States are entitled to utilise not more than the
quantity of water which is allocated or permitted by the
decisions of the KWDT for the respective projects of the
respective party States before the Tribunal; and that any
variation in either storage or utilisation of the waters by
each such state in respect of each of such projects could
only be with the prior consent or concurrence of the other
riparian States; (d) declare that all the projects executed
and/or which are in the process of execution by the State of
Karnataka which are not in conformity with and conflict with
or violate the decisions of the KWDT, as illegal and
unauthorised.
(e) declare that approvals /sanctions/ clearances/
in-principle clearances granted by the Union of India on or
after KWDT decisions on 24.12.1973 and on 27.5.1976 in
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 41
respect of schemes/projects/ undertaken by the Government of
Karnataka are invalid and direct the Union Government to
review /reconsider all such schemes/ projects proposed /
undertaken by Karnataka, afresh, after obtaining the views
thereon of the other riparian States;
(f) declare that the State of Karnataka and
Maharashtra shall not be entitled to claim any rights
preferential or otherwise in respect of storage, control and
use of waters of the inter- State river Krishna in respect
of the schemes /projects not authorised by the decision of
the KWDT; (g) declare that the Union Government is duty
bound to consult all the riparian States of Maharashtra,
Karnataka and Andhra Pradesh before according any approvals
/ sanctions / clearances / in-principle clearances to any
schemes / projects proposed / undertaken by any of the
riparian States on the inter-State river Krishna and direct
the Union Government to act in terms of the said
declaration; (h) grant a mandatory injunction directing the
State of Karnataka to undo all its illegal, unauthorised
actions regarding projects/ schemes and in particular the
following projects executed by it contrary to the decisions
of KWDT so as to bring them in conformity with the said
decisions:
Almatti Dam under UKP
Construction of Canals/Lifts Schemes on Almatti
Reservoir.
Upper Krishna Projects in K-2 Sub-basin.
Hippargi Weir/Irrigation Schemes.
Construction of Indi and Rampur lift schemes on
Narayanpur reservoir and the canals.
(i) grant a permanent injunction restraining the State
of Karnataka from undertaking, continuing or proceeding with
any further construction in respect of the following
projects: Almatti Dam under UKP Construction of
Canals/Lifts Schemes on Almatti Reservoir
Upper Krishna Projects in K-2 Sub-basin.
Hippargi Weir/Irrigation Schemes.
Construction of Indi and Rampur lift Schemes on
Narayanpur reservoir and the canals.
(j) appoint a team of experts for making a
comprehensive techno-economic evaluation and environmental
impact analysis in respect of the following projects and,
pending orders of this Honble Court on the report of the
team of experts, grant an order of injunction restraining
the Defendant No. 1 State of Karnataka from proceeding
with any further construction in any of the following
projects/schemes: Almatti Dam under UKP Construction of
Canals/ Lifts Schemes on Almatti Reservoir
Upper Krishna Projects in K-2 Sub-basin.
Hippargi Weir/Irrigation Scheme.
Construction of Indi and Rampur lift schemes on
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 41
Narayanpur Reservoir and the canals.
(k) to issue a permanent injunction restraining the
Defendant No. 1 State of Karnataka from growing or allowing
to grow sugarcane or raising other wet crops in the command
areas falling under the projects/schemes within the Upper
Krishna Project; (l) pass a decree in terms of prayers (a)
to (k); and (m) award costs of the present proceeding in
favour of the Plaintiff;
(n) pass such further decree or decrees or other
orders as this Honble Court may deem fit in the facts and
circumstances of the case.
Though there are as many as 14 reliefs sought for as
stated above, but essentially the reliefs relate to the
construction of Almatti Dam under Upper Krishna Project by
the State of Karnataka to a height of 524.256 M. Though the
averments of facts in the plaint have been made in 71
paragraphs, shorn of minute details, the same may be stated
as under: That the dispute between the three riparian
States namely Maharashtra, Karnataka and Andhra Pradesh with
respect to use, distribution and control of the water of
inter- State river Krishna stood resolved by the decisions
of the tribunal, constituted under Section 4 of the
Inter-State Water Disputes Act, 1956 (hereinafter referred
to as the Act) by the decision rendered in 1973 and the
Further decision rendered in 1976. The said decision having
been notified by the Central Government under Section 6,
became binding on all parties. All the parties-States being
constituents of the Federation of Republic of India, the
plaintiff expected that each State, while undertaking their
projects for utilisation of the quantity of water allocated
in their favour by the tribunal would consult with the other
concerned States and would so use, which will not be against
the decision of the tribunal in any manner. But the State
of Karnataka has not been acting in accordance with the
letter and spirit of the decision of the tribunal and on the
other hand has violated the expressed terms and conditions
of the tribunal, which compelled the State of Andhra Pradesh
to invoke the jurisdiction of the Supreme Court under
Article 131 of the Constitution. After indicating the
topography of the river as well as the three riparian States
and the disputes which arose between the States that lead
the Central Government to constitute the Krishna Water
Disputes Tribunal, the plaintiff has stated that the
tribunal framed seven main issues and under issue No. II
with its eight sub-issues, decided the question of equitable
apportionment of the beneficial use of the waters of the
river Krishna and the river Valley by evolving Scheme A
and making the same as its Final Order or decision, which
became binding on all the parties, after the same was
notified by the Union Government under Section 6 of the Act.
It is not necessary for us to reiterate all the facts
leading to the raising of disputes and constitution of the
tribunal, which we have already narrated in judgment in
O.S.1 of 1997, filed by the State of Karnataka. The
plaintiff then has averred as to how on the basis of
agreement between the parties, the 75% dependable flow at
Vijayawada was found to be 2060 TMC and while considering
the case of each State for allocation of their respective
share of water in respect of the aforesaid 75% of dependable
flow, several projects in the river basin, already
undertaken by the States as well as the quantity of water
required for the projects were considered by the tribunal on
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 4 of 41
the basis of which the ultimate figure of allocation were
arrived at. According to the plaint, the tribunal, while
restraining the States of Maharashtra and Mysore from using
more water than allocated in their favour, granted liberty
to the plaintiff-State of Andhra Pradesh to use the
remaining water with the rider that the State of Andhra
Pradesh will not acquire any right to the user of such water
except to the extent allocated to it. The plaintiff also
averred that while making allocation to the three States, no
express provisions were made for sharing of any deficiency
and further the tribunal took note of the fact that out of
100 years, deficiency may occur in 25 years. It was also
averred that to relieve the State of Andhra Pradesh from the
aforesaid difficulty, the tribunal permitted the State of
Andhra Pradesh to store water in the Nagarjunasagar Dam and
in Srisailam Dam and held that for such storage, there would
not be any deduction from its share out of the dependable
flow on the ground that if the water is not allowed to be
stored by the plaintiff-State, then it would flow down and
get submerged in the sea. According to the plaint, the
tribunal did consider the different project reports which
had been produced before it, in relation to the Upper
Krishna Project and allowing the protected utilisation of
103 TMC, it came to the conclusion that the demand of State
of Karnataka to the extent of 52 TMC to be utilised by
Narayanpur Right Bank Canal is worth consideration. After
enumerating the different clauses of the Final Order of the
tribunal in its original report of 1973, the plaintiff has
averred that though the tribunal has made allocation enbloc
in a negative form namely that the State cannot utilise more
than the allocable quantity of water in its share in any
water year but the said enbloc allocation has to be read in
the light of the relevant stand of the parties before the
tribunal, the facts and figures produced before the tribunal
and the ultimate basis on which the conclusion was arrived
at. According to the plaintiff, by taking recourse to the
aforesaid method, it would be crystal clear that party-
States were restrained from utilising in different
sub-basins of river Krishna within their respective
territory, beyond what was considered as the protective use
and the additional quantity allocated to their share. It
has been averred in the plaint that so far as Upper Krishna
Project is concerned within the State of Karnataka, the
tribunal has allocated only 160 TMC of water for being used
and the construction of Almatti Dam to the height of 524
Meters, as indicated by the State of Karnataka, would,
therefore, on the face of it, is in violation of the
decision of the tribunal. After referring to the different
applications for clarifications sought for by different
States under Section 5(3) of the Act and the answer of the
tribunal on the same, the plaintiff has also averred as to
how the tribunal dealt with the contentions raised by the
State of Maharashtra before it, in relation to the
allocation of 52 TMC of water from Narayanpur Right Bank
Canal. According to the plaintiff, though, no doubt in the
Final Order of the tribunal, there has been a mass
allocation of water in favour of the three riparian States
out of the 2060 TMC of water under 75% of dependability at
Vijayawada, which figure was arrived at by consent of the
parties, but a closer scrutiny of the report in its entirety
being examined, it would be apparent that the allocation in
respect of different sub-basins had been made on the basis
of projects undertaken in those sub-basins and consequently,
no State would be entitled to use the entire quantity of
water allocated in their favour in any particular sub-basin.
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 5 of 41
The plaintiff, then has averred that the post award
developments undertaken by the State of Karnataka, intending
to raise the height of Almatti Dam to 524 Meters is nothing
but a gross violation of the decision of the tribunal and,
therefore, this Court should injunct the State of Karnataka
in going ahead with the Almatti Dam upto the height of 524
Meters, as indicated in its project. The plaintiff then
referred to several correspondence made between the State of
Karnataka and State of Andhra Pradesh inter se, as well as
correspondence between these States and Union Government and
Central Water Commission. It has also been averred that
allowing the State of Karnataka to construct the dam at
Almatti up to a height of 524 Metres would be grossly
detrimental to the lower riparian state of Andhra Pradesh
inasmuch as for three months in a year from July to
September, the State of Andhra Pradesh may go dry and the
entire crop in the State would get damaged for paucity of
water. The plaintiff also has averred in several paragraphs
of the plaint, as to how the plaintiff-State has been
demanding from the State of Karnataka to have suitable
information in relation to the construction of the dam at
Almatti and how the plaintiff-State has been prevented from
being favoured with any such information. In paragraph 34
of the plaint, the plaintiff refers to the letter addressed
to the Chief Minister of Andhra Pradesh by the then Union
Minister for Water Resources, proposing to convene a meeting
of Chief Ministers of the Krishna Basin States for
discussing Upper Krishna Project Stage-II and along with the
said letter, the observation of Central Water Commission,
indicating how the project at Almatti creates a physical
capability of water utilisation in excess of 173 TMC, which
would be possible in view of the proposed top of the radial
gate at FRL 521 meters against the required level of 518.7
meters for utilisation of 173 TMC of water. In the
subsequent paragraph of the plaint, it has also been
indicated as to how the State of Andhra Pradesh has been
objecting to the proposals of the State of Karnataka to have
the height of Almatti dam at 524 meters under the guise of
flood protection measure and then how the plaintiff State
requested the Prime Minister of India to intervene in the
matter to avoid violation of the award of the Krishna Water
Disputes Tribunal. In paragraph 39 of the plaint, it has
been averred that the Union Government as well as the
Central Water Commission which are responsible for clearance
of inter-State Projects, bent upon clearing the Almatti
Project up to a dam height of 524 meters without even
consulting the State of Andhra Pradesh, though, according to
the plaintiff in a Federal Structure of the Government, each
constituent State would be entitled to know the progress of
any project in relation to inter-State river, since it may
have several adverse effects on the other States. The
plaintiff also averred that at the behest of the State of
Andhra Pradesh, the United Front Government, which was at
the Centre, constituted a Committee of four Chief Ministers
to examine the issues relating to the construction of
Almatti Dam, which committee in turn, decided to constitute
an Expert Committee with a representative of the Central
Water Commission and Planning Commission, who, however, did
not ultimately participate in the proceedings. The said
Expert Committee has found that the proposal of the Upper
Krishna Project with FRL of 524.256 meters for Almatti Dam
is under consideration and has not been approved by the
Government of India, though many canals have been designed
and constructed for larger capacity meant for future uses
and it is not necessary to build a bigger storage of 227 TMC
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 6 of 41
at Almatti dam with top of shutter at 524.256 meters. The
said Committee had also observed that the FRL on the top of
the shutter be fixed for the present at 519 .6 meters and
the gates be manufactured and erected accordingly and this
will be adequate to take care of the annual requirements of
173 TMC presently envisaged under the Upper Krishna Project.
The said Committee, therefore, suggested the restriction of
the height of the dam at 519.6 meters. The plaintiff
however does not accept of the entitlement of the first
defendant to use 173 TMC under UKP and the height of the dam
at 519.6 meters. From paragraph 52 onwards, the plaintiff
then has made averments indicating the negotiations and
further developments in the matter and then states that the
Ministry of Power, Government of India having indicated that
in principle clearance of construction of Upper Krishna
Hydro- electric power project at Almatti, contemplating the
height of the dam at 524.256 meters was contrary to the
award of the tribunal, and therefore, the plaintiff-State
lodged its objections by letter dated 18th of October, 1996,
to which the reply came that in principle clearance is not
a techno- economic clearance and it is purely an
administrative action to facilitate developmental
activities. The plaintiff, thereafter by its letter dated
18th of December, 1996, requested the Secretary, Ministry of
Water Resources, Govt. of India to ensure forthwith the
publication in the Gazette of India the decision of the
Krishna Water Disputes Tribunal i.e. the report dated
24.12.1973 and the further report dated 27.5.1976 in its
entirety. But since it became apparent that the Defendant
No. 1 State of Karnataka was not at all inclined to resolve
the problem by any amicable discussion nor did it desire any
effort for mediation being undertaken by anyone whatsoever,
the plaintiff had no other alternative but to approach this
Court under Article 131 of the Constitution for declarations
and injunctions against the Defendants for protection of the
rights of the plaintiff State as well as the rights of its
inhabitants flowing from the decision of the Krishna Water
Disputes Tribunal. From paragraph 65 onwards, the plaintiff
has narrated several facts constituting violations of the
decision of the tribunal by the State of Karnataka and from
paragraph 69 onwards, the plaintiff has indicated the role
played by the Central Government in the matter of allowing
the State of Karnataka to raise the height of the dam, which
would ultimately lead to violation of the terms and
conditions as well as the restrictions in the award of the
tribunal and which would infringe the rights of the State of
Andhra Pradesh and its inhabitants. The cause of action for
filing the suit has been indicated in paragraph 73 of the
plaint, namely indulgence of the State of Karnataka in going
ahead with the Upper Krishna Project Stage I and II with the
construction of the Almatti Dam which is in violation of the
decision of the tribunal in letter and spirit.
Defendant No. 1- State of Karnataka in its written
statement, took the stand that the tribunal had not made any
project-wise allocation and on the other hand, the
allocation is enbloc and as such the question of
interpreting the decision of the tribunal to the effect that
there is restriction in the user of water in any particular
Basin is not correct. It has been further averred that the
State of Karnataka had contemplated the height of the Dam at
Almatti as 524.256 m in the Project Report of 1970 itself
and that Report had been filed before the tribunal and had
been marked as document MYPK-3. Neither the State of Andhra
Pradesh nor any other State had raised any objection to the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 7 of 41
said Project Report and there was no issue before the
tribunal on that score and in fact the height of the Almatti
Dam was not a matter of adjudication before the tribunal.
In this view of the matter, the plaintiff-State is not
entitled to raise that issue on the purported allegation
that it amounts to violation of the decision of the
tribunal. It is also contented that an identical issue
having been raised by an individual by filing a writ
petition in the Andhra Pradesh and after dismissal of the
same, the matter having been brought to this Court and the
order of the Andhra Pradesh High Court has been affirmed,
the same question cannot be re-agitated by filing a suit by
the State under Article 131 of the Constitution of India.
In respect of the decision of the Committee, which stated
about the FRL 519.6 m, it has been averred in the written
statement that the said Committee considered the height at
519.6 meters to be sufficient, taking into account the
storage capacity of the dam which will take care of the
annual requirement of 173 TMC in a water year but it did not
take into account the further water that may be needed for
generation of power and the project at Almatti with the
height of the dam beyond 519.6 meters and up to 524.256
meters being only for power generation and the water thus
used for power generation being non-consumptive, there is no
question of violation of any direction of the tribunal when
the State of Karnataka has decided to have the height of the
dam at Almatti at 524.256 meters. It has been specifically
averred in the written statement that the decision of the
tribunal which has been Gazetted under Section 6 of the Act
has not imposed any restriction on any State for
construction of any Project and on the other hand Clause XV
expressly mentioned that : Nothing in the order of the
tribunal shall impair the right or power or authority of any
State to regulate within its boundaries the use of water, or
to enjoy the benefit of water within that State in a manner
not inconsistent with the order of this tribunal and in
view of such specific provision, it is futile for the State
of Andhra Pradesh to contend that the height of the dam at
Almatti should not be raised to 524.256 meters. The
defendant has further averred that the Project at Almatti
has been undertaken at huge cost exceeding Rs.6000 crores
and it is not in national interest to stop the project at
this advance stage and the suit has been filed with the
design to cause delay in the completion of the projects
undertaken by the State of Karnataka. It has been
reiterated that the utilisation of water would be entirely
within the allocated quantity made by the tribunal.
According to Defendant No. 1, the plaintiff has not made
out any case of breach of its legal rights and, therefore
the suit under Article 131 of the Constitution is not
maintainable. The defendant also narrated the background
under which the Central Government set up the tribunal for
adjudication of the disputes between the riparian States and
how ultimately the tribunal gave its report, stating therein
the facts found as well as the decision thereon. The
defendant State has also stated in the written statement
that the Almatti Dam has been designed for utilisation of
173 TMC for Upper Krishna Project in two stages and the
State had indicated that height, right from the inception
before the tribunal itself, though neither any party raised
any objection nor any issue was struck, nor any decision
thereon has been given by the tribunal itself and in this
view of the matter any grievance with regard to the height
of the dam at Almatti would be a fresh water dispute and
would not come within the adjudicated dispute and decision
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 8 of 41
thereon by the tribunal itself and, therefore, the suit
filed under Article 131 is not maintainable. It has been
specifically averred that the storage level at Almatti Dam
from 519.6 meters to 524.256 meters is not at all an
increase, particularly, when the tribunal itself expressly
noted the contemplated completion of the Almatti Dam to the
full height that is the height in Exhibit MYPK-3. The
defendant also referred to the report of the Central Water
Commission dated January 30, 1994, whereunder it has been
indicated that since the power generation is contemplated
under the project at Almatti by way of utilising the extra
storage of water between 519.60 meters and 521 meters, the
project may be treated as a multi-purpose project (the level
required to utilise 173 TMC of water for irrigation is
519.60 meters). The Defendant-State of Karnataka has
specifically averred that even though the dam height is
raised to this final level of 524.256 meters, the quantity
of water that could be utilised for irrigation is only 173
TMC as per allocation made in the Award and any additional
quantity over and above 173 TMC will be let out into the
river after generating power. It has also been contended
that the dispute raised being a water dispute in respect of
an inter-State river, the same is governed by Article 262 of
the Constitution read with Section 11 of the Inter-State
Water Disputes Act, and therefore, suit under Article 131 is
not maintainable. All allegations made by the plaintiff
about the misuse of position have been denied. It has also
been denied that neither there is any requirement of the
decision of the tribunal nor any liability which compels any
State to consult another State in the matter of planning of
the projects for utilisation of its water resources and the
contention raised by the State of Andhra Pradesh in this
regard is wholly mis-conceived. The defendant further
contends that the State of Andhra Pradesh not having
utilised the opportunity to seek clarification under Section
5(3) of the Act with regard to the height of or any other
specification of the Almatti Dam is not entitled to raise
this dispute in this Court by filing a suit under Article
131 of the Constitution. The defendant-State of Karnataka
reiterated that the utilisation of water under the U.K.P.
first at Almatti and later at Narayanpur downstream, is
entirely within the scope of 173 TMC and in any event within
the aggregate share of 734 TMC allocated to the defendant
Karnataka and the construction of the Upper Krishna Project
at Almatti and at Narayanpur is all consistent with the work
specifications prescribed by the Expert technical bodies in
all respect including the provision for river sluices. In
respect of Clause XV of the Final Order of the tribunal, the
defendant averred that the quantity of 155 TMC considered in
respect of Upper Krishna Project does not restrict the
defendant Karnataka from planning increased utilisations by
taking into account quantities of 34 TMC regeneration, 23
TMC of water by diversion of Godavari waters and of 50% of
the surplus flows becoming available after the adoption of
Scheme B devised by the tribunal. It is contended that
the tribunal having not provided for allocation or
utilisation project-wise, so long as there has been no
contravention of the mass allocation made, the plaintiff has
no grievance and is not entitled to file the suit. It has
been stated in the written statement that in the re-
submitted modified proposal dated 21st of April, 1996 for
Upper Krishna Project Stage II as multi-purpose project,
incorporating compliance of the various comments of CWC and
also then again proposing a FRL of 524.256 meters, clearly
stating that even though the dam was to be raised to its
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 9 of 41
final level of 524.256 m, the utilisation for irrigation
would be only 173 TMC as per the readjustment of the
project-wise allocations in the Master Plan within the scope
of the Scheme A allocation of 729 TMC and as such, there
has been no deviation, so far as the height of the dam at
Almatti is concerned. With regard to the allegations made
in the plaint, concerning development seeking a political
solution to the dispute, the defendant-Karnataka denies all
the averments made in that respect and asserts that
execution of projects is within its entitlement and limits
permitted by the decision of the tribunal. With regard to
the initiative taken by the Prime Minister of India by
holding a meeting on 10.8.1996, it has been stated that such
initiative was frustrated by the uncompromising and
unreasonable attitude of political leaders of Andhra
Pradesh. So far as the Committee of four Chief Ministers
are concerned, it has been averred that the Committee of
Experts, constituted by the four Chief Ministers even did
not frame any terms of reference for consideration, though
requested by the State of Karnataka and it conducted the
proceedings in a summary manner. The Chief Minister of
Karnataka in fact had apprised the Chief Minister of West
Bengal about the same by letter dated 19.12.1996 and after
receipt of the so-called report of the Expert Committee, the
Chief Minister of Karnataka had conveyed its reaction to the
findings by his letter dated 25.2.1997 to which the Chief
Minister of West Bengal had replied that the points are
being examined and according to the State of Karnataka, the
matter remained inconclusive and as such cannot have any
binding effect. In the written statement, the defendant No.
1 also averred that the findings of the said Expert
Committee are erroneous. With regard to the allegations in
the plaint that storage of huge quantity of water by
construction of Almatti Dam would affect the interest of
Andhra Pradesh and its inhabitants, the defendant Karnataka
denies the same and also stated that the dam is intended to
utilise about 173 TMC of water for irrigation and the
remaining storage water will be used for non-consumptive
purpose i.e., production of power and, therefore, the water
will flow down to Andhra Pradesh and the said State will not
be affected in any manner. With respect to allegations in
the plaint regarding incorporation of Chamundi Power
Corporation Ltd., the State of Karnataka has averred that
the State is pursuing the matter before the Central
Electricity Authority in accordance with law and the
question of getting the consent of the plaintiff does not
arise. So far as the assertions made in the plaint about
the cascading and far-reaching effect on the environment is
concerned, the State of Karnataka denies the same. On the
question of alleged submergence, it has been averred that
the State of Karnataka would take all adequate steps to
provide compensation in accordance with law and rehabilitate
the displaced population, if any. The assertions that
Almatti Dam would render the major projects in Andhra
Pradesh redundant, has been denied. So far as the
allegation regarding violation of environmental law is
concerned, it has been averred in the written statement that
the applications for environmental clearance are under
process by the Government of India and the State of
Karnataka has not done anything without the appropriate
clearance from the Appropriate Authorities. According to
the defendant-State of Karnataka, the averments in the
plaint are mis-leading and lacking of bona fides and all
allegations and insinuations against the Chief Minister of
Karnataka are denied. All other allegations of illegality
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 10 of 41
being perpetuated by the State of Karnataka have been
denied. So far as creation of Jal Nigam is concerned for
effective execution of the Upper Krishna Project, the State
of Karnataka contends that the said Nigam is wholly
Government owned company and all its activities are
controlled by the Department of Irrigation, Govt. of
Karnataka and, therefore, the allegation of the plaintiff
that the State is abdicating its responsibility for the
execution of the project is incorrect and is denied. It has
been categorically averred that the Karnataka State would be
subjected to irreparable loss if the works at Almatti are
stopped and the State of Andhra Pradesh wants to reap the
benefit of the liberty to use the surplus water flowing in
the river in view of the mass allocation made in favour of
the three States. It has been specifically averred that the
storage of additional water between the height of 519.6 to
524.256 meters will be used for power production only and
not for irrigation till the augmentation of waters by
Godavari diversion and surplus waters under Scheme B is
made available. It has been specifically averred as to how
the Government of Karnataka has sought for approval for
taking up the cluster of hydel projects at Upper Krishna
Project in phases and how the Central Electricity Authority
has accorded in-principle clearance. At the cost of
repetition, the State of Karnataka has averred that there
has been no deviation of the decision of the tribunal and
the Almatti Dam has been planned for utilisation of the
allocated water by the tribunal in favour of the State of
Karnataka. According to this defendant, the State of Andhra
Pradesh being the last riparian State is receipient of
abundant waters comprising the un-utilised share of upper
riparian States in addition to its allocations made in its
own favour and, therefore, no case has been made out
establishing any injurious hardships so as to entitle the
State to get a discretionary relief of injunction. The
defendant also averred that the plaintiff has not placed an
iota of evidence based of any acceptable material
establishing the alleged loss of drinking water, food grains
or unemployment and all such allegations are falacious.
According to the State of Karnataka, all the revised schemes
at all relevant times had been submitted before the
Appropriate Authorities of the Central Government and
projects are being taken up only after getting clearance
from the competent authorities. It has been averred at the
end that the basis of the suit being that the allocation
made by the tribunal is project-wise and the said basis
being in-correct, the plaintiff is not entitled to the
reliefs prayed for by filing the suit under Article 131 of
the Constitution.
Union of India defendant no. 2 in its written
statement raised the preliminary objection about the
maintainability of the suit on the ground that the suit as
framed is not maintainable in view of Article 262 of the
Constitution of India read with Section 11 of Inter-State
Water Disputes Act, 1956. Generally denying the allegations
made in the plaint the Union of India took the positive
stand that Karnataka multipurpose project Stage II which
envisages generation of Hydropower is still under
examination and the project report provides for Hydropower
generation by storing water at the addition of storage space
from 519.6 M to 524.256 M and it has been indicated that
after generating the Hydropower the tail race water after
power generation will be let into the river Krishna and the
utilisation of river Krishna water under UKP will be within
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 11 of 41
173 TMC. With regard to the plaint allegation that under
the Award Tribunal has allocated water projectwise, the
Union of India submitted that the allocation of water is
gross allocation and not the project wise allocation. It
has been further stated that the State is entitled to
utilise the gross amount of water for any such projects and
so long as utilisation by Karnataka is within 173TMC in
upper Krishna project, there is no violation of Krishna
Water Disputes Tribunal Award. It has also been indicated
that Stage I of UKP has been approved and Stage II is under
various examination and not yet been approved. So far as
the plaint case that Central Government is required to
consult other States while clearing projects of one State,
it has been averred that there is no obligation on the
Central Government to consult said party State while
clearing projects of other party State of Krishna basin when
they are within the framework of KWDT Award. The financial
assistance by Central Government is being given to the State
in the shape of grants and loans. So far as Almatti project
in particular is concerned the stand of the Union Government
in its written statement is that UKP stage I has already
been approved and it was approved by the Planning Commission
on 22nd April, 1978 under which the construction of Almatti
Dam to a partial height corresponding to FRL 512.2 m with
solid spillway crest level at EL 500 m and with 12.2 m high
gates. But in view of the technical difficulty of
dismentaling and reerecting the radial gates of such height
in Stage II, the Government of Karnataka desired to do
construction of Almatti dam with full section as required
for ultimate stage and solid crest upto 512 m in UKP Stage I
itself. The revised proposal of Government of Karnataka was
examined by the Central Water Commission and considered by
Technical Appraisal Committee in its 20th Meeting held on
12.5.1982. The TAC recommended that the clearance of the
Government of India for raising Almatti Dam in full width
upto EL 500 m may be accorded subject to the observation
that revised estimate be submitted by the State Government.
Subsequently, the State Government came up with modified
proposals with Almatti spillway crest at EL 509 m and 15.2
high radial gates with a view to reduce submergence under
Stage I of the project. This revised stage I estimate got
the approval of the Planning Commission on 24.4.1990.
According to the written statement of the Central
Government, Stage I of UKP was duly approved by the Central
Water Commission as well as by the Planning Commission with
certain modifications enabling the State Government to take
upto Stage II at later stage. It has further been averred
that the Karnataka Government has revised Upper Krishna
project Stage II (1993) as UKP Stage II Multipurpose project
(1996) and that project is under examination. The State of
Andhra Pradesh has sent their comments to the said project
and various appraising agencies are checking the design of
gates from the structural aspect. But no final approval has
been given. The allegation of State of Andhra Pradesh that
Central Government adopted partisan attitude has been denied
and on the other hand it has been stated that the State of
Andhra Pradesh has not been able to prove that by
constructing Almatti Dam the State of Karnataka will be
utilising more water than allocated by KWDT. It is in this
context the Central Government has also averred that the
State of Andhra Pradesh is constructing Telugu Ganga Project
which is an unapproved Project. So far as the allegation in
the plaint that State of Andhra Pradesh had not been
consulted before the Department of Environment and Forest
cleared the Upper Krishna Project, it has been averred that
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 12 of 41
there is no obligation on the part of Department of
Environment and Forest, Government of India to obtain the
views of State of Andhra Pradesh while clearing of the Upper
Krishna Project of State of Karnataka. According to the
Central Government the Award of the Tribunal is binding on
the parties and the plaintiff has not been able to show any
violation of the decision of the Tribunal.
On behalf of Ministry of Power who is Defendant No. 2
(C) a separate written statement has been filed giving reply
to the averments made in paragraphs 56 and 57 of the plaint
and it has been indicated that the expression In Principle
clearance given by the Central Electricity Authority to
Upper Krishna Project at Almatti does not tantamount to
sanction of the project by the competent authority.
According to the said defendant while appraising various
proposals for power project received from the States due
care is taken by the Ministry of Power for proper
evaluation.
The State of Maharashtra Defendant No.3 filed a
written statement fully supporting the stand taken by the
State of Karnataka and it has been averred in the written
statement that the complaint of State of A.P. proceeds on
certain assumptions which are not correct. With regard to
the main question, namely, whether there was enbloc
allocation or project wise allocation the defendant State of
Maharashtra categorically avers that the Tribunal equitably
allocated the waters of the river Krishna by allocating the
quantities enbloc or in mass quantities. Though it has
discussed individual projects of each State only for the
limited purpose of assessing the needs of each State in
accordance with the principles of equitable distribution.
It has further been stated in the said written statement
that apart from the restrictions expressly stated in the
final order of the Tribunal which has been notified by the
Central Government no other restrictions have been imposed
on the method of use by each State within the allocated
share of the State concerned and Tribunal has not put any
restriction on the storage by each State and according to
Clause VII of the final order the storage of water by each
State would not be considered as use of water by the State
concerned. In the very written statement several paragraphs
of the Report of the Tribunal have been quoted to indicate
that the ultimate allocation was enbloc and not projectwise
and further there has been no restriction or restraint
placed by the Tribunal with regard to storage, size and
height of dams in the Krishna Basin. The State has also
referred to the subsequent conduct, that after the
submission of original report and the decision of the
Tribunal the State of Andhra Pradesh infact filed
clarification note 9 and 10 on 7.5.1975 and 8.5.1975 raising
objection to the storage but ultimately withdrew those notes
and did not want any clarification on the subject of storage
which fortifies stand of the State of Maharashtra that there
is no restriction on any State in respect of storage of
water within the Krishna Basin so long as it does not exceed
the enbloc allocation given by the Tribunal. According to
this defendant the relief sought for in the plaint would
tantamount to a complete re-writing of the decision of the
Tribunal which would be outside the scope of a suit under
Article 131 of the Constitution. After refuting the stand
taken by the State of Andhra Pradesh in the plaint in
paragraph 16 of the written statement the State of
Maharashtra submitted , that the plaintiff does not deserve
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 13 of 41
to be granted any of the prayers prayed for in this para and
the Suit should be dismissed with costs. Having filed the
aforesaid written statement on 7th July, 1997 fully
supporting the stand taken by the State of Karnataka and
seeking relief of the dismissal of the suit filed by the
State of Andhra Pradesh an additional written statement was
filed by the said State on 9th April, 1999 giving a clear go
bye to the earlier wirtten statement and taking a new stand
in relation to the alleged construction of Almatti Dam with
FRL RL 524.56 m. by the State of Karnataka. In this
additional written statement it has been averred that by
raising the dam height at Almatti, there is likelihood of
enormous damage to private and public properties and works
and structures including archeological structures and
pilgrimage places in the State of Maharashtra. There would
also be disruption of communications, enhanced distress and
damages during floods each year due to sedimentation. It
has been further averred that the details of the magnitude,
duration and extent of submergence were not clear to the
State of Maharashtra as the said submergence has not been
discussed by the Tribunal itself but on getting subsequent
documents from the State of Karnataka and on ascertaining
the effect of the proposed Almatti Dam at 524.256 m it
appears that there would be large scale submergence of area
in the State of Maharashtra and no State should be allowed
to have its project which will have deleterious and adverse
effect on the other State. It is in this connection in the
additional written statement it has been further averred
that the said State of Karnataka has not obtained the
relevant clearance from different environment authorities
and forest authorities and even the Central Water Commission
has not given the clearance and, therefore, the State of
Karnataka should be injuncted from raising the dam height
from 519.00 m. to 524.256 m. until and unless the actual
area likely to be submerged is made known after due survey.
In the written statement the adverse effect of submergence
have been indicated in different paragraphs and ultimately
it has been prayed that the prayer h, i & j sought for by
the plaintiff so far as it relates to Almatti Dam under UKP
should be allowed, namely, the State of Karnataka should be
injuncted. Though the State of Maharashtra filed the
aforesaid additional written statement taking the stand
totally contrary to the stand taken earlier but no order had
been passed on the same and it is only when the hearing of
this suit began the Court passed an order that without
prejudice to the contention of the State of Karnataka the
said additional written statement be taken into
consideration on the basis of which an additional issue is
also required to be framed.
On the pleadings of the parties, 22 issues were framed
which are extracted hereinbelow:-
1.Whether the State of Karnataka has violated the
binding decisions dated 24.12.1973 and 27.05.1976 rendered
by the KWDT by executing the projects mentioned in para 66,
68n & 69 of the Plaint? (A.P./KAR) 2.Has this Honble Court
jurisdiction to entertain and try this suit? (MAH.) 3.
Does the Plaintiff prove that the allocation of Krishna
Waters by the KWDT in its Final Order are specific for
projects and not enbloc as contended by the Defendant?
(MAH.) 4.Does the Plaintiff prove that the upper States are
not entitled to construct project without reference to and
consent of the other States? (MAH.) 5.Whether the Plaintiff
is entitled to a declaration that all the projects executed
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 14 of 41
and/or which are in the process of execution by the State of
Karnataka, and not in conformity with or in conflict with
the Decisions of the KWDT are illegal and unauthorised?
(A.P.) 6.Is not the Union Government duty bound to consult
all the riparian States before according any
approval/sanction/clearance in principle clearances to any
schemes, projects proposed/undertaken, by any of the
riparian States on the Inter-State river Krishna? (A.P.)
7.Whether the sanctions and the approvals granted by the 2nd
Defendant to the State of Karnataka for the projects
referred to in Issue I, without the prior concurrence of
State of Andhra Pradesh are valid and binding upon the
Plaintiff?(A.P.) 8.Whether sanctions and the approvals
granted by the 2nd defendant are liable to be reviewed,
reconsidered afresh, after obtaining the views thereon of
the other riparian States?(A.P.). 9.(a) Whether the
construction of the Almatti dam with a FRL of 524.256 m
together with all other projects executed, in progress and
contemplated by Karnataka would enable it to utilise more
water than allocated by the Tribunal? (A.P.) (b) Whether
Karnataka could be permitted to proceed with construction of
such a dam without the consent of other riparian States, and
without the approval of the Central Government? (A.P.)
10.Whether the Plaintiff proves that the reservoir and
irrigation canals as alleged in paragraph 68 of the Plaint
are oversized. If so, are they contrary to the Decision of
the Tribunal? (A.P.) 11.Whether the Plaintiff State of
Andhra Pradesh proves specific allocation/utilisation for
UKP and canals as alleged? (A.P.) 12.Whether State of
Karnataka is entitled to provide for any irrigation under
Almatti canals and other new projects, when no allocation is
made under the decisions of the KWDT? (A.P.) 13.Whether the
Defendant State of Karnataka is entitled unilaterally to
reallocate/readjust the allocation/utilisation under the UKP
or any other project? Is concurrence of other riparian
States necessary? (A.P.) 14.Whether the Union of India can
permit and/or is justified in permitting the State of
Karnataka to proceed with various projects which are in
violation of the decisions rendered by KWDT? (A.P.)
15.Whether Upper Krishna Stage-II Multipurpose Project could
be executed without the environmental clearance under the
Environment (Protection)Act,1986 and the Notification issued
by the Central Government in 1994 in exercise of its power
under the said Act and the Rules made thereunder which
mandatorily requires various analysis including dam break
analysis?(A.P.) 16.Whether the acts of the State of
Karnataka adversely effect or would adversely effect the
State of Andhra Pradesh, and if so, with what
consequences?(KAR) 17.Whether Hippargi was always part of
the UKP and on that basis the KWDT awarded 5 TMC utilisation
thereunder ?(A.P.) 18.Whether the utilisation of water under
Chikkapada Salagi, Heggur and 5 other barrages is not 33 TMC
as assessed by the Plaintiff State?(A.P.) 19.Whether the
cumulative utilisations in the K2 sub-basin is 173 TMC as
claimed by the State of Karnataka or 428.75 TMC as assessed
by the Plaintiff State?(A.P.) 20.Whether the State of
Karnataka has violated the KWDT award by proceeding with
several new projects in the sub-basin such as K-6, K-8 and
K- 9 in respect of which restrictions in quantum of
utilisation have been imposed in the final decision of the
Tribunal? (A.P.) 21.Whether utilisation under Almatti would
be of the order of 91 TMC as claimed in para 66(iii) of the
plaint?(A.P.) 22.To what reliefs if any, the plaintiff is
entitled to?(A.P.) The additional issue framed as 9(C),
because of the additional written statement filed on behalf
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 15 of 41
of defendant no.3 is to the effect, Whether Karnataka can
be permitted to raise the storage level at Almatti dam,
above RL 509.16 meters in view of the likely submergence of
territories in Maharashtra.
Before we take up the different issues framed by the
Court and answer the same in the light of the contentions
raised as well as with reference to the documents filed in
support of the same it would be appropriate for us to notice
the order of this Court dated 30th September, 1997 and its
effect on the ultimate decision of the suit itself
On 30th of September, 1997, this Court passed the
following Order:
Sh. F.S. Nariman, learned Senior counsel for the
State of Karnataka-defendant No. 1 and Sh. T.R.
Andhyarjuna, learned Solicitor General appearing for the
State of Maharashtra- defendant No. 3 referred to the
prayer (a) (at page 72 of the Paper book) and submits that
both these States namely, Karnataka and Maharashtra accept
this claim of the plaint of the State of Andhra Pradesh and
agree to the grant of relief in the suit in terms of prayer
in clause (a) as under: (a) declare that the
report/decision dated 24.12.1973 and the further
report/decision dated 27.5.1976 of the Krishna Waters
Dispute Tribunal (KWDT) in their entirety are binding upon
the three riparian States of Maharashtra, Karnataka and
Andhra Pradesh and also the Union of India. In other words,
there is no controversy in the Suit between the plaintiff
and Defendants 1 and 3 i.e. Andhra Pradesh, Karnataka and
Maharashtra and that the report/decision dated 24.12.1973
and the further report/decision dated 27.5.1976 of the
Krishna Water Disputes Tribunal (KWDT) in their entirety are
binding upon the three riparian States of Maharashtra,
Karnataka and Andhra Pradesh. There is thus no controversy
between the three riparian States to this extent. The
learned Attorney General appearing for the Union of India
submits that he is unable to make any statement today in
this behalf as he has to seek instructions in the matter.
This statement made by the learned counsel for the three
riparian States is placed on record to indicate that a
partial decree to this extent on the basis of admission of
the defendants (1 and 3, Karnataka and Maharashtra) can be
passed and therefore, there is no need to frame any issue to
cover this aspect of the Suit.
In course of hearing of the suit arguments had been
advanced on behalf of the State of Karnataka by Mr. Nariman
that the aforesaid partial decree in terms of prayer a of
OS No. 2 of 1997 unequivocally indicates that the entire
report i.e. 24.12.1973 and the further report dated
27.5.1976 in entirety must be held to be binding upon three
riparian States, and that being the position, there is no
logic on the part of the State of Andhra Pradesh to resist
the prayer of Plaintiff No. 1 in OS No. 1 of 1997 to make
Scheme B binding on parties which Scheme obviously form a
part of the report and the further report. Mr. Ganguli,
learned senior counsel appearing for the State of Andhra
Pradesh on the other hand contended, that a prayer made by
the plaintiff has to be understood in the context of the
averments made in the plaint itself and not bereft of the
same. According to Mr. Ganguli prayer a in the case in
hand, if read in the light of the averments made in the
plaint itself it would only mean that the plaintiff State
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 16 of 41
having averred in the plaint that the Tribunal had made
projectwise allocation which should be read into the final
decision of the Tribunal which has been notified in the
Official Gazette by the Government of India and, therefore,
the State of Karnataka is not entitled to raise the height
of the Dam at Almatti to 524.256 meters whereby it would be
able to store more than 200 TMC of water with the
utilisation capacity of about 400 TMC. It is in this
context Mr. Ganguli placed before us paragraphs 3.1, 3.2
and 3.3 of the written statement to indicate to us as to how
the said defendant understood the prayer a in the plaint.
Mr. Ganguli ultimately urged that the final order of the
Tribunal can be equated with a decree in a civil suit and
decree must be consistent with the judgment and, therefore,
applying the said analogy the final order requires to be
read in the light of the adjudication made by the Tribunal
in the final report. The learned counsel placed reliance on
the following decisions in support of the aforesaid
contentions:-
(i) Kalikrishna Tagore vs. The Secretary of State
LR 15 Indian Appeals 186 at 192.3 (ii) Law Report 25 Indian
Appeals at 107-08 (iii) 1913 Vol. 25 Madras Law Journal 24.
At the outset we are unable to accept the contention
of Mr. Ganguli that the decision of the Tribunal which is
ultimately notified under Section 6 of the Act can be held
to be a decree of a suit and the report being the judgment
and, therefore, the decided case laws on which reliance has
been placed has no application at all. The inter-State
Water Disputes Act having been framed by the Parliament
under Article 262 of the Constitution is a complete Act by
itself and the nature and character of a decision made
thereunder has to be understood in the light of the
provisions of the very Act itself. A dispute or difference
between two or more State Governments having arisen which is
a water dispute under Section 2(C) of the Act and complaint
to that effect being made to the Union Government under
Section 3 of the said Act the Central Government constitutes
a Water Disputes Tribunal for the adjudication of the
dispute in question, once it forms the opinion that the
dispute cannot be settled by negotiations. The Tribunal
thus constituted, is required to investigate the matters
referred to it and then forward to the Central Government a
report setting out the facts as found by him and giving its
decision on it as provided under Sub-Section (2) of Section
5 of the Act. On consideration of such decision of the
Tribunal if the Central Government or any State Government
is of the opinion that the decision in question requires
explanation or that guidance is needed upon any point not
originally referred to the Tribunal then within three months
from the date of the decision, reference can be made to the
Tribunal for further consideration and the said Tribunal
then forwards to the Central Government a further report
giving such explanation or guidance as it deems fit.
Thereby the original decision of the Tribunal is modified to
the extent indicated in the further decision as provided
under Section 5(3) of the Act. Under Section 6 of the Act
the Central Government is duty bound to publish the decision
of the Tribunal in the Official Gazette whereafter the said
decision becomes final and binding on the parties to the
dispute and has to be given effect to, by them. The
language of the provisions of Section 6 is clear and
unambiguous and unequivocally indicates that it is only the
decision of the Tribunal which is required to be published
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 17 of 41
in the Official Gazette and on such publication that
decision becomes final and binding on the parties. It is
not required that the report containing the arguments or
basis for the ultimate decision is also required to be
notified so as to make that binding on the parties. This
being the position, it is difficult to appreciate the
contention of Mr. Ganguli that the decision of the Tribunal
as notified, is in fact a decree of a civil suit and that
decree has to be understood in the light of the judgment of
the suit. We accordingly are not persuaded to accept the
submission of Mr. Ganguli on this point but, at the same
time we cannot accept the argument of Mr. Nariman that the
order of this Court dated 30th September, 1997 passed in the
suit in terms of prayer a must be held to mean that a
decree is to be drawn up in OS 2 of 1997 making the entire
report and the further report binding on the parties. When
a prayer is made in the plaint the said prayer has to be
understood in the light of the assertion of facts on which
the prayer has been made. The defendant State of Karnataka
understood the prayer on that basis as would appear from the
averments made in the written statement of defendant no. 1
in paragraphs 3.1, 3.2 and 3.3. The aforesaid prayer had
been made for the relief that notwithstanding enbloc
allocation made in the final order of the Tribunal which is
the decision of the Tribunal but the very basis to arrive at
that decision being the projectwise allocation contained in
the report the said projectwise allocation must be read into
the enbloc allocation and, therefore, there must be
restriction on the part of the State of Karnataka not to use
more water in Upper Krishna Project than the allocated
quantity of 160 TMC. Thus read the order of this Court
dated 30th September, 1997, cannot be construed to mean that
a decree has to be passed making the entire report as well
as the further report of the Tribunal binding on the
parties. So far as the question whether allocation made
enbloc or projectwise the same has been answered while
discussing issues nos. 1, 3 and 5 and in this view of the
matter the earlier order dated 30th September, 1997 is of no
consequence in disposing of the suit in question.
ISSUE Nos. 1, 3 and 5: Though, there are as many as
22 issues, which have been framed and necessarily to be
answered in the suit, but in course of arguments advanced by
Mr. Ganguli, the learned senior counsel, appearing for the
State of Andhra Pradesh, the entire emphasis was on the
height of Almatti Dam Stage-II at 524.256 meters, as
proposed by the State of Karnataka and as it appears from
various project reports. In view of the arguments advanced
by the counsel for the parties, these three issues
essentially form the bone of contention. It is necessary to
be stated that too many issues have been framed by the three
different States and Court has also permitted such issues to
be struck and most of the issues over-lap one another and in
fact have no bearing in relation to the prayer made by the
plaintiff. But instead of re-framing the issues, arguments
having been advanced by the counsel for the parties, we
would deal with each of them, but with specific emphasis on
the vital issues. So far as the three issues with which we
are concerned at the moment, when read with the paragraphs
of the plaint, dealing with the same, it appears that the
plaintiff Andhra Pradesh has made out a case in the plaint
that under Scheme A which is the decision of the tribunal
and which has been notified by the Central Government under
Section 6 of the Inter-State Water Disputes Act, though
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 18 of 41
there has been allocation of water enbloc but on going
through the report itself and the very basis on which the
mass allocation has been quantified, it would indicate that
project-wise allocation must be read into the so-called mass
allocation. This being the position, in Upper Krishna
Project, the tribunal having allocated only 160 TMC of
water, construction of Almatti Dam to a height of 524.256
meters itself constitutes an infraction of the decision of
the tribunal, and, therefore, the Court should injunct the
State of Karnataka from constructing a dam at Almatti up to
the height of 524.256 meters. The stand of the State of
Karnataka in the written statement filed as well as the
stand of Union Government and State of Maharashtra in its
original written statement filed however is that, there has
been an enbloc allocation by the tribunal and consequently,
there has been no fetter on any State to utilise water up to
a limited quantity in any of its project, except those
mentioned in the order of the tribunal itself and that being
the position, the plaintiff would not be entitled to an
order of injunction in relation to the construction of
Almatti Dam to a height of 524.256 meters. Before we focus
our attention to the evidence on record in answering these
three issues, in the light of arguments advanced by the
counsel for the parties, it must be borne in mind that
injunction being a discretionary remedy, a Court may not
grant an order of injunction, even if all the three
necessary ingredients are established and those ingredients
are prima facie case of infraction of legal rights, such
infraction causes irreparable loss and injury to the
plaintiff and the injury is of such nature that it cannot be
compensated by way of damages. In the case in hand, when
the plaintiff has prayed for an order of mandatory
injunction to injunct the State of Karnataka from
constructing the dam at Almatti to a height of 524.256
meters and makes out a case of infringement of legal rights
of the State of Andhra Pradesh, flowing from the decision of
the Krishna Water Disputes Tribunal, which decision has
become final and binding on being notified by the Union
Government under Section 6, what is required to be
established is that in fact in the said decision of the
tribunal, there has been a project-wise allocation in
respect of Upper Krishna Project and if this is established,
then the further fact required to be established is whether
by construction of Almatti Dam up to a height of 524.256
meters, there has been any infraction of the said decision
of the tribunal which has caused irreparable injury and
damage to the lower riparian State of Andhra Pradesh and the
said damage cannot be compensated by way of damages. Since
the plaintiff-State has to establish all the aforesaid
requirements, so that an order of injunction, as prayed for,
can be granted, let us examine the very first ingredient
namely whether under the decision of the tribunal, there has
at all been a project-wise allocation as contended by Mr.
Ganguli, appearing for the State of Andhra Pradesh or the
allocation was enbloc, as contended by Mr. Nariman,
appearing for the State of Karnataka and reiterated by Mr.
Salve, the learned Solicitor General and Mr. Andhyarujina,
appearing for the State of Maharashtra. While deciding the
Original Suit No. 1 of 1997, filed by the State of
Karnataka, negativing the contention of the said State to
the effect that Scheme B evolved by the tribunal, whether
forms a decision of the tribunal or not, we have already
recorded the finding that Scheme B cannot be held to be
the decision of the tribunal inasmuch as it is only that
order of the tribunal which conclusively decides the dispute
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 19 of 41
referred to, and is capable of being implemented on its own,
can be held to be a decision of the tribunal under Section
5(2) of the Act. In fact the plaintiff in the present suit
also bases its case on the Scheme A and contends that
there has been an infraction of the said Scheme A by the
defendant-State of Karnataka. If we examine the Final Order
of the tribunal contained in Chapter XVI of the Original
Report Exhibit PK1 as well as the modified order after
answering the application for clarifications made by
different States, in the Further Report of December, 1976 in
Chapter VII of Exh. PK2, which has been notified by the
Central Government under Section 6 of the Act in the Gazette
of India dated 31st of May, 1976, it is crystal clear that
the allocation made, has been enbloc and not project-wise
and, therefore, there is no fetter on any of the States in
utilising water in any project to a limited extent,
excepting those contained in Clause (IX) of the decision.
The allocation made to the three States of Maharashtra,
Karnataka and Andhra Pradesh for their beneficial use has
been provided in Clause (V) and subject to such conditions
and restrictions as are mentioned in the subsequent clauses.
Clause (V) of the decision which in fact makes the
allocation, may be quoted herein below in extenso:
Clause V (A) The State of Maharashtra shall not use
in any water year more than the quantity of water of the
river Krishna specified hereunder:- (i) as from the water
year commencing on the 1st June next after the date of the
publication of the decision of the Tribunal in the Official
Gazette upto the water year 1982-83 560 TMC. (ii) as from
the water year 1983-84 up to the water year 1989-90 560 TMC
plus a quantity of water equivalent to 10 per cent of the
excess of the average of the annual utilisations for
irrigation in the Krishna river basin during the water years
1975-76, 1976-77 and 1977-78 from its own projects using 3
TMC or more annually over the utilisations for such
irrigation in the water year 1968-69 from such projects.
(iii) as from the water year 1990-91 up to the water year
1997-98 560 TMC plus a quantity of water equivalent to 10
per cent of the excess of the average of the annual
utilisations for irrigation in the Krishna river basin
during the water years 1982-83, 1983-84 and 1984-85 from its
own projects using 3 TMC or more annually over the
utilisations for such irrigation in the water year 1968-69
from such projects. (iv) as from the water year 1998-99
onwards 560 TMC plus a quantity of water equivalent to 10
per cent of the excess of the average of the annual
utilisations for irrigation in the Krishna river basin
during the water years 1990-91, 1991-92 and 1992-93 from its
own projects using 3 TMC or more annually over the
utilisations for such irrigation in the water year 1968-69
from such projects. (B) The State of Karanataka shall not
use in any water year more than the quantity of water of the
river Krishna specified hereunder:- (i) as from the water
year commencing on the 1st June next after the date of the
publication of the decision of the Tribunal in the Official
Gazette up to the water year 1982-83 700 TMC (ii) as from
the water year 1983-84 up to the water year 1989-90 700 TMC
plus a quantity of water equivalent to 10 per cent of the
excess of the average of the annual utilisations for
irrigation in the Krishna river basin during the water years
1975-76, 1976-77 and 1977-78 from its own projects using 3
TMC or more annually over the utilisations for such
irrigation in the water year 1968-69 from such projects.
(iii) as from the water year 1990-91 up to the water year
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 20 of 41
1997-98 700 TMC plus a quantity of water equivalent to 10
per cent of the excess of the average of the annual
utilisations for irrigation in the Krishna river basin
during the water years 1982-83, 1983-84 and 1984-85 from its
own projects using 3 TMC or more annually over the
utilisations for such irrigation in the water year 1968-69
from such projects. (iv)as from the water year 1998-99
onwards 700 TMC plus a quantity of water equivalent to 10
per cent of the excess of the average of the annual
utilisations for irrigation in the Krishna river basin
during the water years 1990-91, 1991-92 and 1992-93 from its
own projects using 3 TMC or more annually over the
utilisations for such irrigation in the water year 1968-69
from such projects. (C) The State of Andhra Pradesh will be
at liberty to use in any water year the remaining water that
may be flowing in the river Krishna but thereby it shall not
acquire any right whatsoever to use in any water year nor be
deemed to have been allocated in any water year water of the
river Krishna in excess of the quantity specified
hereunder:- (i) as from the water year commencing on the 1st
June next after the date of the publication of the decision
of the Tribunal in the Official Gazette up to the water year
1982-83. 800 TMC (ii) as from the water year 1983-84 up to
the water year 1989-90. 800 TMC plus a quantity of water
equivalent to 10 per cent of the excess of the average of
the annual utilisations for irrigation in the Krishna river
basin during the water years 1990-91, 1991-92 and 1992-93
from its own projects using 3 TMC or more annually over the
utilisations for such irrigation in the water year 1968-69
from such projects. (iii) as from the water year 1990-91 up
to the water year 1997-98 800 TMC plus a quantity of water
equivalent to 10 per cent of the excess of the average of
the annual utilisations for irrigation in the Krishna river
basin during the water years 1982-83, 1983-84 and 1984-85
from its own projects using 3 TMC or more annually over the
utilisations for such irrigation in the water year 1968-69
from such projects. (iv) as from the water year 1998-99
onwards 800 TMC plus a quantity of water equivalent to 10
per cent of the excess of the average of the annual
utilisations for irrigation in the Krishna river basin
during the water years 1990-91, 1991-92 and 1992-93 from its
own projects using 3 TMC or more annually over the
utilisations for such irrigation in the water year 1968-69
from such projects. (D) For the limited purpose of this
Clause, it is declared that :- (i) the utilisations for
irrigation in the Krishna river basin in the water year
1968-69 from projects using 3 TMC or more annually were as
follows:- From projects of the State of Maharashtra- 61.45
TMC From projects of the State of Karnataka- 176.05 TMC From
projects of the State of Andhra Pradesh- 170.00 TMC (ii)
annual utilisations for irrigation in the Krishna river
basin in each water year after this Order comes into
operation from the project of any State using 3 TMC or more
annually shall be computed on the basis of the records
prepared and maintained by that State under Clause XIII.
(iii) evaporation losses from reservoirs of projects using 3
TMC or more annually shall be excluded in computing the 10
per cent figure of the average annual utilisations mentioned
in sub-Clauses A(ii), A(iii), A(iv), B(ii), B(iii), B(iv),
C(ii), C(iii) and C(iv) of this clause.
The aforesaid Clause V, no doubt is in a negative
form, prohibiting the State of Maharashtra and State of
Karnataka from using in any water year more than the water
that has been allotted in their favour respectively but by
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 21 of 41
no stretch of imagination, any restriction can be said to
have been put on any of the States in the aforesaid Clause
V, so long as they do not use more than the quantity
allotted in their favour in any water year. In other words
under Clause V of the decision, the State of Maharashtra is
entitled to use up to 560 TMC in any water year and the
State of Karnataka similarly is entitled to use up to 700
TMC in any water year. The language used by the tribunal in
formulating Clause V of the decision is clear and
unambiguous and as such it is difficult for the Court to
read into it any restrictions as submitted by the learned
senior counsel, appearing for the State of Andhra Pradesh.
We may mention at this stage, that the original report and
the decision of 1973 was marked as Exhibit PK-1 in OS 1/97
and the further repot and the decision of 1976 was marked as
Exhibit PK-2 in OS 1/97, and those two documents having been
referred to by the parties in course of arguments as PK- 1
and PK-2. We have also in judgment referred as PK-1 and
PK-2 which were exhibited as such in OS 1/97.
Mr. Ganguli, the learned senior counsel however
contended before us that before the tribunal, each of the
three riparian States claimed water for their various
projects, covering utilisation to the order of 4269.33 TMC,
as is apparent from Exhibit PKI itself and then at a
subsequent stage of the proceedings before the tribunal, all
the party States agreed that 75% dependable flow up to
Vijayawada in the river Krishna is 2060 TMC, which is,
therefore much less than the total demand made by each of
the States, amounting to 4269.33 TMC. The learned counsel
further urged that all the three States entered into an
agreement on 7.5.1971, indicating therein that 20 of the
projects in Maharashtra, 13 projects in Karnataka and 17
projects in Andhra Pradesh should be protected and the
parties also agreed to the specified quantity of utilisation
of water in respect of each of the projects which could be
treated as protected utilisation and total of such protected
utilisation came to 751.20 TMC, as is apparent from the
Original Report Exhibit PKI. It is the further contention
that since in respect of one project in Maharashtra, five
projects in Karnataka and five projects in Andhra Pradesh,
the parties could not agree to the quantity of utilisation
which should be protected and all the States invited the
tribunal to decide the extent of utilisation to be protected
in respect of those 11 projects and the tribunal adjudicated
the additional utilisation to the extent of 714.91 TMC in
respect of 9 out of the 11 projects and thus the total
protected utilisation out of the dependable flow at 75%
dependability worked out at 1693.36 TMC , which of course
includes 227.25 TMC on minor irrigations. Having thus
arrived at the figure of 1693.36 TMC for protected
utilisation, the balance quantity out of the dependable flow
to the extent of 366.64 TMC was further distributed by the
tribunal to the extent of 50.84 TMC to Andhra Pradesh for
Srisailam reservoir and Jurala Project. Out of the
remaining 315.80 TMC, taking into consideration all germane
factors, the tribunal allocated 125.35 TMC to Maharashtra
and 190.45 TMC to Karnataka. Mr. Ganguli contends that
while making these allocations, so far as Upper Krishna
Project in the State of Karnataka is concerned, the tribunal
merely permitted utilisation of only 52 TMC in the Right
Bank Canal of Narayanpur in addition to the protected
utilisation of 103 TMC already granted in respect of the
Left Bank Canal under the Narayanpur Canal and, therefore,
the total worked out at 155 TMC and there had been no
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 22 of 41
allocation made by the tribunal so far as Almatti Dam is
concerned. At a later stage when in its Further Report
Exhibit PK2, the tribunal allocated additional 5 TMC for
utilisation under Hippargi Project, the conclusion is
irresistible that in Upper Krishna Projects in Hippargi,
Almatti and Narayanpur, a total quantity of 160 TMC was
allocated and this must be read into the Final Order in
Clause (V), though not specifically mentioned therein. It
is in this connection, Mr. Ganguli took us through the
different pages of Exhibit PKI as well as the plaint and the
written statement of the State of Karnataka. But as has
been stated earlier, if the decision of the tribunal is its
Final Order, as notified by the Central Government in
exercise of power under Section 6 of the Act, we really fail
to understand, how the aforesaid limitations can be read
into the said decision, particularly, when Clause (V) of the
decision is clear and there is no ambiguity in the same. It
is undoubtedly true that while considering the question of
extent of allocation of water in favour of the three
riparian States out of 2060 TMC of water at 75%
dependability, the tribunal did take into account the
different projects already undertaken by different States
but consideration of those projects is only for the purpose
of arriving at the quantity of water to be allocated and not
for making any project-wise allocation, as contended by Mr.
Ganguli. In Exhibit PKI itself, the tribunal records to the
following effect : Our examination of the project reports
and other relevant documents has a very limited purpose and
it is to determine what are the reasonable needs of the two
States so that an equitable way may be found out for
distributing the remaining water between the two States. It
is of course, always to be borne in mind that the allocation
of waters though based on consideration of certain projects
being found to be worth consideration are not on that
account to be restricted and confined to those projects
alone. Indeed the States (and this applies to all the
States) would be entitled to use the waters for irrigation
in such manner as they find proper subject always to the
restrictions and conditions which are placed on them.
This unequivocally indicates the purpose for which the
projects of different States were being examined and it is
explicitly made clear that the States should be entitled to
use the waters for irrigation in such manner as they find
proper, subject, always to the restrictions and conditions
which are placed on them. Unless, therefore, any
restriction or conditions in the decision of the tribunal
can be found out for utilisation of a specific quantity of
water out of the total allocated share in the Upper Krishna
Project, there cannot be any fetter on the part of the State
of Karnataka to make such user. In the decision of the
tribunal, there does not appear to be an iota of
restrictions or conditions, which even can be inferred and,
therefore, the submission of Mr. Ganguli, appearing for the
State of Andhra Pradesh on this score cannot be accepted.
In the report of the Krishna Water Disputes Tribunal
Exhibit PK-1 for the purpose of allocation of water in the
Krishna Basin the Tribunal has examined each project of each
of the three States and then recorded its conclusion as to
whether the project is worth consideration. The Tribunal
expressed the meaning of the expression worth
consideration by saying that the expression is used in the
sense that it means the requirements of an area in the State
concerned. It would be appropriate at this stage to quote
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 23 of 41
the exact findings of the Tribunal in this regard:-
In saying that the project is worth consideration we
do not wish to be understood to say that the project, if
feasible, should be adopted. Likewise when we say that the
project is not worth consideration we do not say that no
water should ever be allowed for it. If at some future date
more water becomes available it is possible that more
projects may come upto the worth consideration standard. In
assessing whether the project is worth consideration or not
we have taken into account the physical characteristics of
the area like rainfall etc., the catchment area, the
commanded area, the ayacut of the project, the fact whether
the project is meant for irrigating the scarcity area or not
and such other facts. In other words we determine on
pragmatic considerations what needs of the States of
Maharashtra and Mysore can be satisfied so that an equitable
way may be found out for distributing the balance of the
dependable flows between the two States. It should not be
taken our observations relating to the projects which we
have noted as worth consideration are to be accepted in any
way as final and binding by the Planning Commission or any
other authority.
The aforesaid finding fully negatives the contention
of Mr. Ganguli, appearing for the State of A.P., that the
allocation was projectwise which can be read into the final
order. Clause IX of the final order has placed restriction
on the use of water in the Krishna Basin by the three
States. The reasons for putting such restrictions appears
to be that on the main stream there has been only
restriction on river Bhima whereas on the side streams there
has been restriction in case of Tungbhadra and Vedavathi
sub-basin. Even in case of sub-basin K-3 there has been
restriction on the State of Maharashtra from using more than
7 TMC in any water year from Ghataprabha and the reason for
such restriction is that the requirements of the State of
Mysore for the projects in that sub-basin may suffer.
Similarly restriction has been placed on the State of Andhra
Pradesh not to use more than 6 TMC from the catchment of the
river Koyna, the idea being that the waters of that river
would reach the main streams of river Bhima. Even while
placing such restriction the Tribunal has placed the upper
limit slightly above the total requirements of that State as
assessed from the demands made which had been either
protected or which have held as worth consideration. The
very fact that restrictions have been put by the Tribunal in
several sub-basins and no restriction has been put so far as
sub-basin K-2 wherein Upper Krishna Project of the State of
Karnataka is being carried on clinches the point raised by
the State of Andhra Pradesh and discussed in these three
issues, namely, it is not possible to read any restriction
for quantity of user of water in Upper Krishna Project by
the State of Karnataka and so long as the total user does
not exceed mass allocation, it cannot be said that the
decision of the Tribunal is being violated infringing the
rights of the State of Andhra Pradesh which can be
prohibited by issuing any mandatory injunction. After
receiving the copy of the report and the decision of the
Tribunal under Exhibit PK-1 the State of Andhra Pradesh
filed application for clarification, being clarification
No.4 under Section 5(3) of the Act, requesting reduction of
1.865 TMC from the Koyna Project of State of Maharashtra.
Having filed such application on 5th March, 1976, the
learned Advocate General of the State of Andhra Pradesh did
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 24 of 41
not press the said clarification No.4 on the ground that the
allocations are enbloc which is apparent from Exhibit PK-2
dealing with clarification no.4. Having made an unequivocal
statement before the Tribunal itself that the allocations
are enbloc we fail to understand how the State of Andhra
Pradesh has filed the suit making out a case that there has
been any project-wise allocation by the Krishna Water
Disputes Tribunal. The aforesaid statement of the learned
Advocate General made before the Tribunal has not been
explained either in the plaint filed by the State nor even
in course of hearing of the suit, and in our view, the State
of Andhra Pradesh also fully understood that the allocations
made under Scheme A was enbloc. It further appears from
Exhibit PK-2 that the State of Andhra Pradesh did file a
clarification no. 5 under Section 5(3) of the Act praying
that the maximum quantity which could be utilised in K-5 and
K- 6 sub-basin of the State of Maharashtra and Karnataka
should be specified and ultimately on 23rd August, 1974, the
learned Advocate General for the said State did not press
the clarification as it had no materials on record on which
he could substantiate it. The very fact that State had not
filed any clarification application so far as K-2 sub-basin
is concerned, though it did file such application in respect
of sub-basin K-5 and K-6 as well as in case of Quana Krishna
Lift Irrigation Scheme unequivocally indicates that the
State had no grievance so far as the allocation enbloc made
by the Tribunal and not putting any restriction of the user
in K-2 sub-basin which consists of the Upper Krishna
Project. This in our view, fully clinches the matter and
the conclusion is irresistible that under the decision of
the Tribunal there has been mass allocation and no
project-wise allocation as contended by the State of Andhra
Pradesh in the suit. In the aforesaid premises, we answer
the three issues against the plaintiff and in favour of the
defendants and hold that under the decision of the Tribunal
the allocation of water in river Krishna was enbloc and not
project-wise excepting those specific projects mentioned in
clauses IX and X of the decision.
ISSUE NO.2
Though this issue has been raised at the behest of the
State of Maharashtra but in view of the stand taken by the
said State in the additional written statement and the
additional issues framed thereon, the learned counsel
appearing for the State of Maharashtra did not argue the
question of jurisdiction, and on the other hand contended,
that the jurisdiction of this Court in a suit under Article
131 of the Constitution should not be restricted or narrowed
down and on the other hand the Court should be capable of
granting all necessary reliefs in adjudicating the dispute
raised. That apart on the basis on which the plaintiff
State filed the suit and the relief sought for it cannot be
said that the suit is not maintainable. We, therefore,
answer this issue in favour of the plaintiff.
ISSUE NOS. 4, 6, 7 and 8
These four issues are inter-linked and have been
framed in view of the positive stand taken by the State of
Andhra Pradesh that in case of an inter State river when any
project of one State is considered by the Government of
India or any other appropriate authority the other State
should also be made aware of and their consent should also
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 25 of 41
be taken. Though this stand had been taken by the
plaintiff-State of Andhra Pradesh but all the three
defendants refuted the same. In course of hearing of the
suit the learned counsel Mr. Ganguli has not placed before
us any material or any law which compels the concerned
authority to consult all the riparian States before
sanctioning a project of one State. In the absence of any
legal basis for such stand we are not able to agree with the
stand taken by the State of Andhra Pradesh that the Central
Government was duty bound to take the consent of other
States while sanctioning any project of any of the riparian
States. That apart, these issues are academic in the
context of the Upper Krishna Project of the State of
Karnataka and,in particular, the construction of the Almatti
Dam. Before the Tribunal the State of Karnataka had
submitted the report of Upper Krishna Project of July 1970
which was exhibited before the Tribunal as MYPK-3 and the
said document has been marked as Exhibit PAP-42 in the
present suit. The salient features of the said project, so
far as Almatti Dam height is concerned, was shown as FRL
524.256 m and top of the Dam at 528.786 m. The entire
project itself being there before the Tribunal, though the
Tribunal did not consider it necessary to discuss the
project in particular in view of enbloc allocation made by
it, the grievance of the State of Andhra Pradesh that the
project was being surreptitiously constructed is devoid of
any substance. We, therefore, answer the aforesaid issues
against the plaintiff.
ISSUE NO. 9 (a) (b)
This issue is an important issue in the present suit
and the relief sought for essentially depends upon the
findings arrived at on this issue. The entire issue has to
be decided on the basis as to whether there exists any
prohibition in the decision of the Tribunal from
constructing Dam at Almatti upto 524.256 meter or from
storing any particular quantity of water therein. And if
the answer is in the negative then the prayer for injuncting
the State of Karnataka to raise the Dam height upto 524.256
has to be rejected. If the decision of the Tribunal is
examined from the aforesaid stand point and in view of our
conclusion that it is that final order which has been
notified in the Official Gazette by the Central Government
under Section 6 of the Act which is the decision of the
Tribunal, we find nothing stated therein which even can be
held to be a prohibition or restriction on the power of the
State of Karnataka to have the height of Dam upto a
particular height. In this view of the matter the
plaintiffs prayer to injunct the State of Karnataka from
constructing the Dam height at Almatti upto 524.256 meter
cannot be granted. The issue has two sub-issues ;
Sub-issue a relates to the height of Almatti Dam ;and
sub-issue b being on the question whether State of
Karnataka could be permitted to proceed with the
construction without the consent of the other riparian
States and without the approval of the Central Government?
At the outset it may be stated that though the State of
Karnataka had produced its project report relating to the
construction of the Almatti Dam as per Exhibit PAP-42 but
neither the Tribunal had considered the same nor any
decision has been arrived at on the question of height of
the said Dam. Even after the original report and the
decision being made known under Section 5(2) of the Act as
per Exhibit PK-1 the State of Andhra Pradesh also did not
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 26 of 41
raise any dispute or clarificatory application objecting to
the construction of the Almatti Dam or even to the height of
such Dam under Section 5(3) of the Act. In the absence of a
decision of the Tribunal on the question of construction of
Dam at Almatti or its height and mass allocation made, being
binding upon all parties after being notified under Section
6 of the Act, the grievance relating to the construction of
Dam at Almatti or to its height would be a matter of water
dispute within the meaning of Section 2(C), in as much as it
would be a matter concerning use of water of river Krishna
and, therefore, cannot be a matter for adjudication in a
suit under Article 131 of the Constitution of India. If the
complaint of the State of Andhra Pradesh is that by
construction of Almatti Dam which is an executive action of
the State of Karnataka the State of Andhra Pradesh is likely
to be prejudicially affected then also on such complaint
being made to the Union Government under Section 3(a) the
matter could be referred to a Tribunal for adjudication.
But, we fail to understand how this Court could entertain
the aforesaid lis and decide the same, particularly when the
Tribunal has not focussed its attention on the same nor has
made any adjudication in respect to the construction of Dam
at Almatti or its height. Needless to mention that
notwithstanding the allocation of water in river Krishna
being made enbloc no State can construct any project for use
of water within the State unless such project is approved by
the Planning Commission, the Central Water Commission and
all other Competent Authorities who might have different
roles to play under different specific statutes. Under the
federal structure, like ours, the Central Government
possesses enormous power and authority and no State can on
its own carry on the affairs within its territory,
particulary when such projects may have adverse effect on
other States, particularly in respect of an inter State
river where each riparian State and its inhabitants through
which the river flows has its right. From the averments
made in the plaint it is crystal clear that the State of
Andhra Pradesh feels aggrieved by the proposal of the State
of Karnataka to have the Dam height at Almatti FRL 524.256
m. In the plaint itself in paragraph 51 the plaintiff has
referred to the observation of the Committee to the effect:
For required utilisation of 173 TMC at UKP the height of
the Dam at FRL 519.6 m would be adequate. The Committee
referred to in the said paragraph is Expert Committee which
the four Chief Ministers had appointed, which Committee had
examined the pros and cons of the Almatti Dam and the
aforesaid views of the Expert Committee was approved by the
four Chief Ministers who had been requested by the Prime
Minister of India to intervene and find out the efficacy or
otherwise of the stand of Karnataka to have Almatti Dam upto
the height of FRL 524.256 m. The said Expert Committee had
observed that the proposal of the State of Karnataka of
having Upper Krishna Project with FRL 524.256 m in Stage II
at Almatti has not been approved by the Government of India.
And it has been further observed that it would be desirable
to proceed with utmost caution in the larger interest of the
Nation to wait and watch operation of various Krishna system
upstream and down stream before embarking on creating larger
storage at Almatti Dam than what is needed to suit the
prevailing conditions. We are taking note of the
observations made by the Expert Committee for the purpose
that the plaintiff having failed to establish its case for
getting an injuction, would it be appropriate for this Court
to allow the State of Karnataka to have the height of the
Dam at Almatti at 524.256 m or it would be obviously in the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 27 of 41
larger interest of the country and all the States concerned
to allow the Dam upto the height of 519.6 m and then leave
it open to the States concerned to put forth their
grievances before the Tribunal to be appointed by the
Central Government for resolving the disputes relating to
sharing of water in river Krishna. Reading the plaint as a
whole it appears to us that the plaintiff State had not made
any grievance for having a Dam at Almatti upto a height of
FRL 519.6 m and on the other hand, the entire grievance
centers round the proposal of the State of Karnataka to have
the height at 524.256 m. The report of the Expert Committee
referred to in the plaint has been exhibited as Exhibit
PAP-212 and even that report indicates that the complaint of
Andhra Pradesh was that the height of Almatti Dam at FRL
524.256m which has not been approved as yet by the
Government of India, would adversely affect the lower
riparian State of Andhra Pradesh both in the matter of
irrigation as well as generation of power. The said report
further reveals that the State of Karnataka is desirous of
having the Dam height at FRL 524.256 m so that it can store
its share of water available to it under Scheme B when it
comes. It is only on fructification of Scheme B the need
for a larger storage at Almatti would arise, and therefore,
the State is planning ahead to have the height of the Dam at
524.256m. According to the report of the said Expert
Committee even if the height is allowed not upto 524.256 m
it can be allowed later only when the necessity arises and
technically it is feasible. The report also records that
for utilisation of 173 TMC at Almatti and Narainpur the
height of the Dam required would be 519 m and not 524.256 m.
Thus an expert body appointed by the four Chief Ministers of
4 different States who are not in any way connected with the
inter-State river Krishna taking into account the present
need envisaged by the State of Karnataka for utilisation of
173 TMC at Upper Krishna project and taking into account the
report submitted by Indian Institute of Science at Bangalore
did record a finding that the top of the shutters at Almatti
should be fixed at 519.6 m which will provide a storage of
about 173TMC which along with storage of 37.8 TMC at
Narainpur will be adequate to take care of annual
requirement of 173 TMC envisaged under Upper Krishna
Project. In view of our conclusion in O.S. 1 of 1997
holding that Scheme B is not a decision of the Tribunal,
and as such, cannot be implemented by a mandatory order from
this Court and the stand of the State of Karnataka before
the so called Expert Committee being that they have designed
the height of Almatti Dam at 524.256 m keeping in view that
in the event Scheme B fructifies the State will be able to
get the surplus water and store it as a carry over
reservoir, as observed by the Tribunal itself,
notwithstanding the fact that the plaintiff has failed to
establish a case on its own for getting the relief of
injunction in relation to the construction of Almatti Dam by
the State of Karnataka, it would be reasonable to hold that
though the State can have the Dam at Almatti but the height
of the said Dam should not be more than 519.6 m,
particularly when the State of Karnataka has not been able
to indicate as what is the necessity of having a height of
Dam at 524.256 m when Scheme B is not going to be operated
upon immediately. The Upper Krishna Project Stage II,
detailed project report of October 1993 which has been
exhibited in the present case as PAP 45 also indicates that
minimum FRL required to get 173 TMC utilisation is found to
be 518.7 m. It is in that report it has been indicated that
it is because of probable maximum flood of 31000 qmx., the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 28 of 41
water level is expected to go upto 521 m and, therefore, the
proposal is to keep the height of the gate to 521 from the
crest level with 2 mts. as the gate height. It may be
stated at this stage that the height of the Almatti as
approved by the Competent Authority is crest level 509 meter
and it is in this context to have the height at FRL 524.256
m the State of Karnataka has proposed to have the gate
height of 15 meters. But as has been indicated earlier,
since the entire basis of the State of Karnataka to have the
height of the Dam at 524.256 m is contingent upon
implementation of Scheme B of the Tribunal thereby
entitling the State of Karnataka to get its share in excess
water and continue the Almatti Dam as a carry over reservoir
and since we have decided against the State of Karnataka in
O.S. 1 of 1997 which the State had filed for implementation
of Scheme B, there is absolutely no justification for the
said State to have the Dam height at Almatti of 524.256 m.
We hasten to add that at the same time there cannot be any
injunction or prohibition to the said State of Karnataka for
having the Dam height at Almatti upto 519.6m which would be
in the interest of all concerned.
Mr. Ganguli, the learned senior counsel, appearing
for the State of Andhra Pradesh submitted that the State of
Karnataka in the Project Report filed before the Central
Water Commission in respect of UKP Stage II, itself
indicated that the minimum FRL required at Almatti Reservoir
is 519.60 M as per Exhibit PAP 46. In the written statement
also, the State of Karnataka also indicated that
contemplated height of Dam at 524.256 meters is for
additional storage, though for the purpose of generation of
power which is non-consumptive use and at a height of
524.256 meters, it would utilise 302 TMC, which would be in
excess of the enbloc allocation of 734 TMC. Mr. Ganguli
also contended that the Upper Krishna Multipurpose Stage II
Project Report of 1996 as per Exh. PAP 48, would indicate
that the State has planned irrigation from the water at
Almatti which the State would receive under Scheme B being
implemented. This being the position, the very idea of
having the dam height at Almatti at FRL 526.256, is even
contrary to the mass allocation made in its favour under
Scheme A and, therefore, the State should be injuncted.
We are unable to appreciate this contention of the State of
Andhra Pradesh inasmuch as on today the Central Government
as well as the appropriate authority have not sanctioned the
Upper Krishna Project Stage-II with the dam height at
524.256 meters. It would not be possible for this Court to
pronounce that there will be a violation of the mass
allocation if the State of Karnataka is allowed to have the
dam height at Almatti at 524.256 meters, though as stated
earlier, according to the State of Karnataka itself for
utilisation of 173 TMC, the required dam height is 519.6
meters. It is under these circumstances, we are of the
considered opinion that there should not be any bar against
the State of Karnataka to construct the dam at Almatti upto
the height of 519.6 meters and the question of further
raising its height to 524.256 meters should be gone into by
the tribunal, which learned Solicitor General agreed on
behalf of Govt. of India to be constituted immediately
after the delivery of judgment of these two suits, so as to
mitigate the grievance of each of the riparian States on a
complaint being made by any of the States.. So far as
sub-issue (b) is concerned, we really do not find any
substance in the contention of Mr. Ganguli, the learned
counsel appearing for the State of Andhra Pradesh. Though
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 29 of 41
it may be fully desirable for all the States to know about
the developments of the other States but neither the law on
the subject require that a State even for utilisation of its
own water resources would take the consent of other riparian
States in case of an Inter-State river. So far as the
second part of Issue b is concerned, the answer is
irresistible that the project of each State has to be
approved by the Central Government as well as by other
statutory authorities and the Planning Commission, but for
which a State should not proceed with the construction of
such project. Issues 9(a) and (b) are answered accordingly.
ISSUE 9(C) Issue 9(C) had been framed while allowing
the additional written statement of the State of
Maharashtra, which relates to the question of submergence.
It is to be noted that in the original written statement
filed by the State of Maharashtra, a positive stand had been
taken that under the decision of the tribunal, there has
been an enbloc allocation of water in favour of each of the
three riparian states and as such there was no bar on the
State of Karnataka to have a dam at Almatti up to any height
and, therefore, it was prayed that the suit filed by the
Andhra Pradesh should be rejected. In the additional
written statement that was filed by the State of
Maharashtra, it has however been averred that the eventual
submergence of area within the State of Maharashtra had not
been known earlier and, therefore, neither before the
tribunal nor in the original written statement filed, any
grievance had been made with regard to the construction of
dam at Almatti to a height of 524.256 meters, but since the
joint study made by the officers of both the states have
brought out that a large area within the State of
Maharashtra would get submerged, if Karnataka is permitted
to have the dam height at Almatti up to 524.256 meters, the
State of Maharashtra has brought these facts to the notice
of this Court in the additional written statement and the
additional issue has been framed. In the absence of any
relief being sought for in the plaint by the plaintiff
against the State of Maharashtra, whether the defendant
State of Maharashtra can claim any relief against the co-
defendant is itself a debatable issue. Mr. Andhyarujina,
the learned senior counsel, appearing for the State of
Maharashtra , however contended that a suit filed in the
Supreme Court under Article 131 of the Constitution is of a
very peculiar nature and the normal principle of a suit
filed in an ordinary civil Court should not apply.
According to Mr. Andhyarujina, if a dispute between the two
states involving the existence or extent of a legal right of
one State is being infringed by the action or in-action of
another State, is brought before this Court invoking
jurisdiction under Article 131 of the Constitution, this
Court would be fully justified in entertaining and
adjudicating the said dispute, no matter whether the dispute
is raised as a plaintiff or a defendant in any proceeding
before the Court. It is in this context the learned counsel
referred to the observations of Bhagwati J and Chandrachud
J, in the case of State of Karnataka vs. Union of India,
1978(2) SCR 1, wherein Honble Bhagwati J had indicated that
the original jurisdiction of the Supreme Court under Article
131 on being invoked by means of filing a suit, the Court
should be careful not to be influenced by the considerations
of cause of action which are germane in suit and the scope
and ambit of the said jurisdiction must be determined on the
plain terms of the article without being inhibited by any a
priori considerations. The learned Judge in the same
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 30 of 41
decision had also indicated that the very object of Article
131 seems to be that there should be a Forum, which could
resolve such disputes between two States or the State and
the Union and that forum should be the highest Court in the
land so that the final adjudication of disputes could be
achieved speedily and expeditiously without either party
having to embark on a long tortuous and time consuming
journey through a hierarchy of Courts. Mr. Andhyarujina
also relied upon the observations of Bhagwati J in the
aforesaid case to the effect:
What article 131 requires is that the dispute must be
one which involves a question on which the existence or
extent of legal right depends. The article does not say
that the legal right must be of the plaintiff. It may be of
the plaintiff or of the defendant. What is necessary is
that the existence or extent of the legal right must be in
issue in the dispute between the parties. We cannot
construe Article 131 as confined to cases where the dispute
relates to the existence or extent of the legal right of the
plaintiff, for to do so, would be to read words in the
article which are not there. It seems that because the mode
of proceeding provided in Part III of the Supreme Court
Rules for bringing a dispute before the Supreme Court under
Article 131 is a suit, that we are unconsciously influenced
to import the notion of cause of action, which is germane
in a suit, in the interpretation of Article 131 and to read
this article as limited only to cases where some legal right
of the plaintiff is infringed and consequently, it has a
cause of action against the defendant. But it must be
remembered that there is no reference to a suit or cause of
action in Article 131 and that article confers jurisdiction
on the Supreme Court with reference to the character of the
dispute which may be brought before it for adjudication.
The requirement of cause of action, which is so necessary
in a suit, cannot, therefore, be imported while construing
the scope and ambit of Art. 131.
The learned counsel Mr. Andhyarujina, also relied
upon the observations of Bhagwati J in the said decision to
the following effect:-
What has, therefore, to be seen in order to determine
the applicability of Art.131 is whether there is any
relational legal matter involving a right, liberty, power or
immunity qua the parties to the dispute. If there is, the
suit would be maintainable, but not otherwise.
Reliance was also placed on the observations of
Chandrachud J, in the self same case, which may be extracted
herein under:-
By the very terms of the article, therefore, the sole
condition which is required to be satisfied for invoking the
original jurisdiction of this Court is that the dispute
between the parties referred to in clauses (a) to (c) must
involve a question on which the existence or extent of a
legal right depends. Chandrachud J also had categorically
stated:-
I consider that the Constitution has purposefully
conferred on this, Court a jurisdiction which is untrammeled
by considerations which fetter the jurisdiction of a Court
of first instance, which entertains and tries suits of a
civil nature. The very nature of the dispute arising under
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 31 of 41
Article 131 is different, both in form and substance, from
the nature of claims which require adjudication in ordinary
suits.
Mr. Andhyarujina, also referred to the comments of
Mr. Seervai in his book, wherein the author has said that
it is reasonable to hold that the court has power to resolve
the whole dispute, unless its power is limited by express
words or by necessary implications and the Supreme Court
would have the power to give whatever reliefs are necessary
for enforcement of a legal right claimed in the suit, if
such legal right is established. Mr. Andhyarujina also
contended that once the grievance of the State of
Maharashtra having brought forth before the Supreme Court in
a pending proceeding under Article 131 of the Constitution,
the jurisdiction having been invoked by the State of Andhra
Pradesh, the Court has ample power under Article 142 of the
Constitution and for doing complete justice between the
parties, the Court would not be bound by the provisions of
any procedure and can make a departure of the same. It is
in this context, reliance was placed on the observations
made by the Supreme Court in the case of Delhi Judicial
Services vs. State of Gujarat, 1991(4) SCC 406, whereunder
this Court has observed as follows:-
No enactment made by Central or State legislature can
limit or restrict the power of this Court under Article 142
of the Constitution, though while exercising power under
Article 142 of the Constitution, the Court must take into
consideration the statutory provisions regulating the matter
in dispute. What would be the need of complete justice in
a cause or matter would depend upon the facts and
circumstances of each case and while exercising that power
the Court would take into consideration the express
provisions of a substantive statute. Once this Court has
taken seisin of a case, cause or matter, it has power to
pass any order or issue direction as may be necessary to do
complete justice in the matter.
Mr. Andhyarujina submitted that the likelihood of
submergence within the State of Maharashtra on account of
height of dam at Almatti being raised to 524.256 meters, was
disclosed only during the pendency of the present suit and
the State of Karnataka itself in its letter dated 10th of
August, 1998 had communicated to the State of Maharashtra
that the State need not approach the Court of law on this
issue as the matter can be resolved amicably. According to
the learned counsel, the State of Karnataka too agreed to
carry out actual field surveys and calculations to determine
the extent of submergence under the directions of Central
Water Commission in its meeting dated 22.2.1999 and those
studies are still under progress and further the Supreme
Court itself had passed an order of status quo relating to
the height of Almatti Dam by order dated 2.11.1998 and
consequently, the State of Maharashtra never thought it fit
to file an independent suit, invoking the jurisdiction of
the Court under Article 131. But the State of Karnataka
having obtained the liberty from this Honble Court to
proceed further with the installation of the assembly of the
gates by order dated 4.11.1998 and the said State of
Karnataka refusing to give an undertaking to the State of
Maharashtra not to raise the height of the Almatti Dam
beyond the present level of 509 meters, the State of
Maharashtra was compelled to put forth its grievance on the
question of likely submergence of its territory and has
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 32 of 41
prayed for the relief of injunction against the State of
Karnatka for raising the dam height up to 524.256 meters.
Mr. Andhyarujina also submitted that the exact extent of
area to be submerged in the event the Almatti Dam is allowed
to be constructed upto 524.256 meters, has not yet been
ascertained and surveys are still on, but there cannot be
any doubt that a large scale of the area within the State of
Maharashtra would get submerged. Mr. Nariman, the learned
senior counsel, appearing for the State of Karnataka did not
seriously dispute the right of a co-defendant like State of
Maharashtra to put forth the grievances so as to get relief
against another co-defendant, though he undoubtedly,
submitted that in the event, the State of Maharashtra was
allowed to have the additional written statement and an
adjudication of the additional issues framed, the State of
Karnataka should have been given an opportunity, putting
forth its case. He however contended that the dispute
relating to submergence of territory of Maharashtra on
account of the height of the dam at Almatti being raised to
524.256 meters, cannot be a matter of adjudication in a suit
under Article 131, since the State of Maharashtra had not
raised the dispute before the tribunal itself, even though
the Project Report submitted by the State of Karnataka
before the tribunal indicated the height of the dam at
524.256 meters. According to Mr. Nariman, such a dispute
would be a fresh water dispute and would not be a part of
adjudicated dispute and as such under Article 131 of the
Constitution this dispute cannot be entertained and decided
upon by this Court. Mr. Nariman also contended that the
materials on record do not establish or do not help the
Court to come to a positive finding that in the event, the
Almatti Dam is raised to 524.256 meters, a large extent of
the State of Maharashtra would get submerged inasmuch as the
submergence, if any and the flow back, if any, would be in
the river itself and not any territory beyond the river.
Mr. Nariman further urged that the State of Maharashtra did
anticipate submurgence of its territory as would appear from
its stand before the tribunal which is apparent from
paragraph 6.3.1(k) of Exh. MRK-1. It is true, according to
the learned counsel that the tribunal did not consider the
said question but after the Original Report was submitted,
Maharashtra could have filed an application under Section
5(3) of the Act, seeking clarifications on the question of
submergence but, that was not admittedly done, which would
indicate that it had no grievance on the question of
submergence. Having examined the rival contentions on this
issue, we have no hesitation to hold that the issue must be
answered against the State of Maharashtra.
It is no doubt true that the jurisdiction of the Court
in a suit under Article 131 of the Constitution is quite
wide, which is apparent from the language used in the said
article and as has been interpreted by this Court in the two
cases already referred to (see 1978 (2) SCR 1 and 1978 (1)
SCR 64). It is also true that Article 142 confers wide
powers on this Court to do complete justice between the
parties and the Court can pass any order or issue any
direction that may be necessary, but at the same time,
within the meaning of Article 131, the dispute that has been
raised in the present suit is between the State of Andhra
Pradesh and State of Karnataka and question, therefore,
would be whether it involve any existence or extent of a
legal right of such dispute. In answering such a dispute,
it may be difficult to entertain a further dispute on the
question of submergence as raised by the State of
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 33 of 41
Maharashtra, a co-defendant. But in view of the stand taken
by Mr. Nariman, without further delving into the matter and
without expressing any final opinion, whether such a stand,
as the one taken by Maharashtra is possible for being
adjudicated upon, we would examine the merits of the said
contention. A bare perusal of the report of the tribunal
setting out the facts as found by it and giving its decision
on the matters referred to it as per Exh.PK1 as well as the
Further Report of the said tribunal, giving explanation to
the application for clarifications filed by the different
States, as per Exh. PK2, we find that the question of
submergence within the territory of the State of Maharashtra
on account of Almatti Dam in the State of Karnataka has not
at all been discussed nor any opinion has been expressed
thereon. The tribunal having given its decision on the
question of sharing of the water in river Krishna on enbloc
allocation basis, if the user of such water in a particular
way, becomes detrimental to another State, then such a
grievance would be a fresh dispute within the meaning of
Section 2(C) read with Section 3 of the Act and it cannot be
held to be an adjudicated dispute of the tribunal. We have
already indicated that it is only an adjudicated dispute
between the States on which a decision has been given by a
tribunal constituted under Section 4 of the Act by the
Government of India, can be a subject matter of a suit under
Article 131, if there is any breach in implementation of the
said decision of the tribunal. But a dispute between the
two states in relation to the said Inter- State river
arising out of the user of the water by one State would be a
fresh water dispute and as such would be barred under
Article 262 read with Section 11 of the Inter-State Water
Disputes Act, 1956. The question of submergence of land
pursuant to the user of water in respect of an Inter-State
river allocated in favour of a particular State is
inextricably connected with the allocation of water itself
and the present grievance of the State of Maharashtra would
be a complaint on account of an executive action of the
State of Karnataka within the meaning of Section 3(A) and
also would be a water dispute within the ambit of Section
2(C) and, therefore, it would not be appropriate for this
Court to entertain and examine and answer the same. We do
appreciate the concern of the State of Maharashtra, when it
comes to its knowledge that there would be large-scale
inundation and submergence of its territory if the height of
Almatti Dam is allowed to be raised to 524.256 meters, as
per the latest Project Report of the State of Karnataka, but
such concern of the State of Maharashtra alone would not be
sufficient for this Court to decide the matter and issue any
order of injunction as prayed for in the additional written
statement filed by the State of Maharashtra and on the other
hand, it would be a matter for being agitated upon before a
tribunal to be constituted by the Govt. of India in the
event, a complaint is made to that effect by the State of
Maharashtra. We also do not find sufficient materials in
this proceeding before us to enable this Court to come to a
positive conclusion as to what would be the effect on the
question of submergence, if the height of the dam at Almatti
is allowed to be constructed up to 524.256 meters inasmuch
as, according to the State of Maharashtra, the joint surveys
are still on. It is too well settled that no Court can
issue an order of mandatory injunction on mere apprehension
without positive datas about the adverse effects being
placed and without any definite conclusion on the question
of irreparable injury and balance of convenience. Then
again, while allowing a particular State to use the water of
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 34 of 41
an inter- State river, if the manner of such user really
submerges some land in some other State, then the question
has to be gone into as to what would be the amount of
compensation and how the question of rehabilitation of those
persons within the submerged area can be dealt with which
really is an aspect of the doctrine of equitable
apportionment and all these can be gone into, if a complaint
regarding the same is made and the Government of India
appoints a tribunal for the said purpose. But these things
cannot be gone into, in a suit filed under Article 131 as a
part of implementation of an adjudicated dispute of a
tribunal. It is also surprising to note that even though
the Original Project Report of 1970 in relation to Almatti
Dam had been produced before the tribunal, which was
adjudicating the disputes raised by different States, yet
the State of Maharashtra never thought of the question of
submergence and never attempted to get that question decided
upon. In the aforesaid premises, howsoever wide the power
of the Court under Article 142 of the Constitution may be,
we do not think it proper to entertain the question of
submergence, raised by the State of Maharashtra in its
additional written statement and decide the question of
injunction, in relation to the height of Almatti Dam on that
basis. Issue 9 (c) is accordingly decided against the State
of Maharashtra.
It would also be appropriate to notice at this stage
another argument advanced by Mr. Andhyarujina, the learned
senior counsel appearing for the State of Maharashtra, to
the effect that in view of Clause XV of the decision of the
Tribunal each State is entitled to use water allocated in
their favour within its boundary, the moment by user of such
water by one State, any territory of another State get
submerged then it would be a violation of the decision of
the Tribunal contained in Clause XV, and therefore, the said
State should be injuncted from such user. Clause XV of the
decision reads thus:-
Nothing in the order of this Tribunal shall impair
the right or power or authority of any State to regulate
within its boundaries the use of water, or to enjoy the
benefit of water within that State in a manner not in
consistent with the order of this Tribunal.
The aforesaid Clause does not in any way interfere
with the rights of a State from using the water allocated by
the Tribunal within its boundaries nor is this Clause
capable of being construed that if any submergence is caused
in any other State by such user, then the user becomes in
consistent with any order of the Tribunal. Mr.
Andhyarujinas entire argument is based upon the expression
regulate within its boundary but that expression applies
to the use of water or enjoys benefits of water within that
State. Since the question of submergence of any other State
by the user of water by another State allocated in its
favour is not a subject matter of adjudication by the
Tribunal and in fact the Tribunal has not expressed any
opinion on the same it would be difficult for us to hold
that submergence ipso facto even if admitted to be any
within the State of Maharashtra by user of water by the
State of Karnataka at Almatti can be held to be in
consistent with the order of Tribunal. In this view of the
matter we are unable to accept the submission of Mr.
Andhyarujina, learned senior counsel appearing for the State
of Maharashtra that the user of water by the State of
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 35 of 41
Karnataka by constructing a Dam at Almatti is in consistent
with Clause XV of the decision of Tribunal. Issue 9(C),
therefore, is answered against the State of Maharashtra.
ISSUE NO. 10
The aforesaid issue has been framed in view of the
averments made in paragraph 68 of the plaint. In the
aforesaid paragraph of the plaint the plaintiff has
indicated the figure in terms of acreage of land planned to
be irrigated by different projects and excess utilisation of
the water beyond the allocation made by the Tribunal in
respect of different projects. The plaintiff obviously is
under a misconception that in the decision of the Tribunal
there has been a projectwise allocation of water in respect
of different projects in different States. We have already
considered the matter at length and have come to the
conclusison that the allocation was made enbloc and not
projectwise and as such, the question that construction of
oversized reservoir at Almatti is contrary to the decision
of the Tribunal does not arise. Besides Clause VII of the
decision of the Tribunal indicates as to how use of water in
a water year will be measured and it stipulates that while
use shall be measured by the extent of depletion of the
waters of the river Krishna in any manner whatsoever
including losses of water by evaporation and other natural
causes from man made reservoirs and other works without
deducting the quantity of water which may return after such
use to the river, but so far as water stored in any
reservoir across any stream of the Krishna river system is
concerned, storage shall not of itself be reckoned as
depletion of the water of the stream except to the extent of
the losses of water from evaporation and other natural
causes from such reservoir. The water diverted from such
reservoir for its own use, however, has to be reckoned as
use by that State in the water year. In view of this
decision of the Tribunal assuming the State of Karnataka has
the potentiality of storage of water at Almatti, in the
absence of any materials placed by the plaintiff to indicate
as to any diversion from such reservoir by the State of
Karnataka for its own use, it is not possible to come to a
conclusion that there has been a violation of the decision
of the Tribunal by the State of Karnataka by having
potentiality of storage of water at Almatti, as contended by
the plaintiffs counsel. It is in this connection it is
worthwhile to notice that after submission of the report and
the decision in the year 1973 as per Exhibit PK-1 the
Government of India had filed the application for
clarification which was registered as Reference No. 1 of
1974 by the Tribunal and Clarification 1(b) was to the
following effect :-
While the Tribunal have laid down restriction on the
use of water in certain sub-basins as well as the total use
by each State, there may be locations where huydro power
generation (within the basin) may be feasible at exclusively
hydro-sites or at sites for multi-purpose projects. At such
sites, part of the waters allocated to the States, as also
water which is to flow down to other States could be used
for power generation either at a single power station or in
a series of power stations. The Tribunal may kindly give
guidance as to whether such use of water for power
generation within the Krishna basin is permitted even though
such use may exceed the limits of consumptive use specified
by the Tribunal for each State or sub- basin or reach, and
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 36 of 41
if so, under what conditions and safeguards.
The State of Andhra Pradesh to the aforesaid
application for clarification submitted two Notes Nos. 9
and 10 before the Tribunal on 7th May, 1975 and 8th May,
1975. In this note it was specifically pleaded that the
Tribunal may be pleased to explain that the Upper State have
no right to store water in excess of share allocated to them
and in a manner which will affect the right of the State of
Andhra Pradesh in the dependable flow. Several grounds had
been advanced by the State of Andhra Pradesh as to why such
guidance is needed, particularly when under Scheme A
allocation there has been no express provision for sharing
of deficiency. The Tribunal considered the same and
ultimately noted in its further report under Exhibit PK-2
that the State of Andhra Pradesh withdrew the said note and
consequently no ground for any further clarification. A
note having been submitted by the State of Andhra Pradesh
seeking a clarification for fixation of a limit in the
matter of storage of water by the upper riparian States and
then ultimately having withdrawn the same the present
grievance that construction of large sized Dam at Almatti by
the State of Karnataka would adversely affect the State of
Andhra Pradesh and its right could be infringed is devoid of
any substance. The issue is accordingly answered against
the plaintiff.
ISSUES NO. 11 & 12 :
These two issues center round the same question as to
whether there was any specific allocation or utilisation at
Upper Krishna Project and whether providing for irrigation
under Almatti Canal is contrary to the decision of the
Tribunal since no allocation for irrigation has been made
thereunder. We have already discussed the relevant
materials placed by the State of Andhra Pradesh as well as
the decision of the Tribunal and we have come to the
conclusion that the plaintiff the State of Andhra Pradesh,
has utterly failed to establish that infact there was any
specific allocation by the Tribunal in respect of Upper
Krishna Project or the Almatti Reservoir and on the other
hand, the allocation was enbloc making it clear and
unambiguous that States can utilise the quantity of water
allocated in their favour within their territory. This
being the position we have no hesitation to answer these two
issues against the plaintiff State Andhra Pradesh and we
hold that the plaintiff has failed to produce any materials
in support of the aforesaid two issues. These two issues
accordingly are answered against the plaintiff.
ISSUE NO.13
So far as this issue is concerned the question of
entitlement of the State of Karnataka to reallocate or
re-adjust utilisation under UKP or any other project
unilaterally does not arise at all. If the Tribunal would
have made any projectwise allocation and would have
restricted the user of water under UKP to any particular
quantity then the question of re-allocation by the State of
Karntaka on its own would have arisen but the Tribunal not
having made any allocation in respect of the Upper Krishna
Project which includes Almatti and having made an enbloc
allocation so long as the total user by the State of
Karnataka does not exceed the enbloc allocation in its
favour it cannot be said that there has been any violation
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 37 of 41
by the State of Karnataka by planning to use any particular
quantity of water at Almatti. Then again the question of
getting concurrence of other riparian States, as has been
raised by the State of Andhra Pradesh is wholly
misconceived. Neither there exists any law which compels
any State to get the concurrence of other riparian States
whenever it uses water in respect of inter-State river nor
the decision of the Tribunal which allocates the water in
the Krishna Basin on the basis of 75% dependability which
figure was in turn arrived at by an agreement of parties
puts any condition to have the concurrence of other riparian
State. In this view of the matter without further dilating
on this issue, we answer the same against the plaintiff.
ISSUE NO. 14
The aforesaid issue has been raised on the hypothesis
that the Union of India is going to sanction different
projects within the State of Karnataka which are in
violation of the decision of Krishna Water Disputes
Tribunal. As has been indicated earlier, so far as the
Upper Krishna Project is concerned, the Government of India
has approved the Dam height at crest level of 509 meters.
The subsequent revised project submitted by the State of
Karnataka in 1993 and re- submitted in 1996 are still under
consideration and no final decision has been taken thereon.
The Union of India in its counter affidavit has
categorically refuted the allegations made by the State of
Andhra Pradesh in this regard and on the other hand, it has
been averred that State of Andhra Pradesh is going ahead
with some project not sanctioned by the Union Government.
In course of hearing Mr. Ganguli, learned Senior counsel
appearing for the State of Andhra Pradesh, has not produced
any materials in support of the aforesaid stand pertaining
to issue no. 14. We, therefore, decide the said issue
against the plaintiff.
ISSUE NO.15
The aforesaid issue has been framed on the allegation
of the plaintiff that the State of Karnataka is likely to
execute the Upper Krishna Stage II multipurpose project
without getting the environmental clearance under the
Environment Protection Act as well as in violation of the
Notification issued by the Central Government in exercise of
its power under the same Act and the Rules made thereunder.
Under Article 256 of the Constitution it is an obligation
for the States to exercise their power ensuring compliance
with laws made by Parliament and even it enables the Union
Government to give such direction to a State as may be
necessary for that purpose. In a federal structure like
ours, the Constitution itself maintains balance by
distributing powers between the Centre and the States and by
conferring power on the Central Government to regulate and
to issue directions whenever necessary. The several
provisions of the Constitution have been tested in the last
50 years and there is no reason to conceive that any State
will force ahead with its project concerning user of water
in respect of Inter State reservoir without getting the
sanction/concurrence of the Appropriate Authorities and
without compliance with the relevant statutes or laws made
by the Parliament. It is a common knowledge that the large
scale projects planned by each of these States, are
submitted to the Planning Commission for its approval and
for getting financial assistance. Such projects are then
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 38 of 41
examined by different authorities and it is only after
getting approval of the Planning Commission the same is
submitted to the appropriate departments of the Government
of India where again all the formalities are scrutinised and
final sanction or permission is granted. So far as user of
water in respect of an Inter State Reservoir is concerned,
the plans are also examined by the Central Water Commission,
who is an expert body and the views given by such Commission
also is taken into consideration by the Government of India.
This being the entire gamut of procedure we really fail to
understand on what basis the State of Andhra Pradesh has
made the allegation and the issue has been struck in that
respect. Needless to mention that every such projects
whether being executed in the State of Maharashtra or
Karnataka or Andhra Pradesh must be approved by the
appropriate authority of the Government of India and
necessarily, therefore, before any approval is accorded, the
project must be found to have complied with all the relevant
laws dealing with the matter. It has not been placed before
us that the State of Karnataka has carried out any project
in contravention of the provisions of any particular law
made by Parliament or in contravention of any direction
issued by the Government of India. This issue accordingly,
in our opinion, is pre-mature. But we hasten to add that
all the projects of different States concerning user of
water available to them in respect of an Inter State River
must be duly sanctioned by the Appropriate Authorities of
the Government of India after proper scanning and it is only
then the State would be entitled to carry out the same. The
issue is answered accordingly.
ISSUE NO.16
If the issue in question is examined in relation to
the construction of Almatti Dam, which in fact is the bone
of contention in the suit itself, we have not been able to
find out as to how the State of Andhra Pradesh has been or
would be adversely affected or what would be the
consequences thereon. When a plaintiff wants to seek a
relief of injunction by the action or inaction of the
defendant on the ground that such action or inaction has
been grossly detrimental to the interest of the plaintiff
State and has infringed the rights of the plaintiff State
then in such a case it is obligatory for the plaintiff to
put materials on record and establish the necessary
ingredients to enable the Court to come to the conclusion
that by such action or inaction of the defendant the
plaintiff has suffered irreparable damages . When we
examine the averments in the plaint as well as the documents
sought to be relied upon by the plaintiff on this score, we
find that there exists no materials on the basis of which it
is possible for a Court to come to a conclusion that on
account of the construction of Almatti Dam within the State
of Karnataka the lower riparian State the plaintiff has
been adversely affected or is likely to be adversely
affected. The complaint and grievance of the plaintiff
State is rather imaginary than real and on the records of
this proceedings no materials have been put forth to enable
the Court to come to a conclusion on the question of
so-called adverse effect on the State of Andhra Pradesh on
account of the construction of Dam at Almatti. Mr.
Ganguli, learned Senior Counsel appearing for the State of
Andhra Pradesh referred to the written memorandum furnished
to the Committee by the State of Karnataka wherein the said
State had unequivocally admitted that the additional storage
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 39 of 41
in Almatti will cause a temporary reduction in quantum of
flows going to Andhra Pradesh for a period of about three
months during August to October which is made good later on.
According to the learned counsel since those three months
are vital for the crops in the State of Andhra Pradesh the
State will sustain irreparable damages and, as such on the
admission of the State of Karnataka a finding could be
arrived at. At the outset we must state that the written
memorandum furnished by the State of Karnataka cannot be
read in isolation by spinning out a particular sentence and
must be read as a whole. Thus read we do not find any
admission on the part of the State of Karnataka indicating
any reduction of flows to the State of Andhra Pradesh. Mr.
Ganguli also pointed out to Clause XV of Scheme B
whereunder the Tribunal itself had come to the conclusion
about the possibility of water shortage and had empowered
the concerned authority to make necessary adjustment. But
what has been stated thereunder is in relation to the
adoption of Scheme B which has not been possible on
account of lack of sincerity of the State of Andhra Pradesh
and even thereunder the Krishna Valley Authority has been
empowered as often as it thinks fit to determine the
quantity of water which is likely to fall to the share of
each State and adjust the uses of the authorities in such a
matter so that by the end of water year each State is
enable, as far as practicable, use the water according to
their share. We need not further examine this aspect
particularly when Scheme B has not been operative so far
and even this Court has refused to issue any mandatory
injunction for adoption of Scheme B in OS 1 of 1997 filed
by the State of Karnataka. In the aforesaid premises, we do
not have enough materials to come to the conclusion that the
construction of Almatti Dam by the State of Karnataka has in
any way affected or likely to affect the State of Andhra
Pradesh in any manner and consequently the said issue must
be answered against the plaintiff.
ISSUE NO. 17 - Under this issue, the question that
arises for consideration is whether by the decision of the
Krishna Water Disputes Tribunal, only 5.00 TMC was awarded
for utilisation at Hippargi. While answering Issue No. 3,
we have already held that the tribunal only made enbloc
allocation and not any specific allocation for specific
projects, excepting those mentioned in Clause (IX) and under
Clause (IX) so far as Hippargi is concerned, coming under K2
sub-basin, the same does not find mention therein. In this
view of the matter, the said issue is answered against the
plaintiff.
ISSUE NO. 18- The aforesaid issue has been framed on
the basis of averments made in paragraph 66(v) and paragraph
68(b) item No. 4. The averment in paragraph 66(v) is on
the basis of Newspaper Report and the averment made in
paragraph 68(b) item No. 4 is the own estimation of State
of Andhra Pradesh. Defendant No. 1- State of Karnataka
denies the contents of the averments in the plaint vide
paragraph No. 12.88 and paragraph No. 12.111. The counsel
appearing for the State of Andhra Pradesh also did not place
any material in support of the aforesaid issue in course of
the arguments and the averments in the plaint having been
denied in the written statement, the issue in question must
be answered against the plaintiff.
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 40 of 41
ISSUE NO. 19- Though, the plaintiff-State of Andhra
Pradesh on its own estimation, has made an averment in
paragraph 68(b) to the effect that the plan utilisation by
the State of Karnataka in K2 sub-basin is 428.75 TMC on the
basis of which the aforesaid issue has been framed, but no
positive datas have been placed before us to come to the
aforesaid conclusion. On the other hand, the State of
Karnataka in its written statement has asserted that under
Upper Krishna Project, the utilisation would be to the tune
of 173 TMC and this is apparent from several documents
placed before the tribunal as well as in this proceeding In
this view of the matter, we answer this issue by holding
that the plaintiff has failed to establish that the
cumulative utilisation in K2 sub-basin of the State of
Karnataka would be to the tune of 428.75 TMC. At any rate,
since we have already held that the allocation was enbloc
and there is no restriction for utilisation in K2 sub-basin
in the decision of the tribunal. The issue really does not
survive for consideration. The issue is answered
accordingly.
ISSUE NO. 20- This issue relates to the decision of
the tribunal in Clause (IX), under which Clause,
restrictions have been put to the extent indicated
thereunder. But the State of Andhra Pradesh has not been
able to establish the allegation made in this regard nor
even the counsel, appearing for the State has made any
submission thereon. During the course of hearing of the
suit, on behalf of the State of Andhra Pradesh, written
submissions had been filed and even after the close of the
hearing, the State of Andhra Pradesh has filed a written
submission on 15th of March, 2000, in which also, there has
been no mention about the alleged violation in sub-basin
K-6, K-8 and K-9. We, therefore, answer this issue by
holding that the plaintiff has failed to establish the same
and the issue is answered against the plaintiff accordingly.
ISSUE NO. 21-
This issue relates to utilisation of water under
Almatti. In paragraph 66(iii), the plaintiff has made the
averment, which has been denied and explained in the written
statement by the State of Karnataka vide paragraph 12.85 and
the State of Karnataka further averred that the entire
utilisation at Almatti is within its allocable share and no
injury is caused to the State of Andhra Pradesh thereunder.
Since, we have already held that under the decision of the
tribunal, the allocation was enbloc and not project-wise,
even if it is held that utilisation under Almatti would be
of the order of 91 TMC, as claimed, the same would not
violate the decision of the tribunal. That apart, we do not
have any positive material, on the basis of which, it can be
said that the utilisation under Almatti would be of the
order of 91 TMC. The issue is answered accordingly.
In course of arguments Mr. Ganguli, the learned
Senior counsel for the State of Andhra Pradesh had raised a
contention that the State of Karnataka to frustrate any
decree to be passed by this Court injuncting the defendant
no.1 from raising the construction of the Dam at Almatti at
a height of 524.256 has already incorporated an autonomous
body, called Krishna Bhagya Jala Nigam Limited (KBJNL)and
the State Government has divested itself of all powers
relating to the construction of Dam at Almatti with the
aforesaid Nigam and this has been designedly made so that
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 41 of 41
any order or decree for injunction would not be binding.
Since this argument had been advanced towards the concluding
stage and there was no assertion in the plaint in this
regard, nor any issue had been struck by the Court, the
State of Karnataka had been permitted to file an affidavit
indicating the correct state of affairs in relation to the
constitution of KBJNL and to allay or apprehension in the
minds of the plaintiff State. An affidavit had been filed
by the Secretary to the Government of Karnataka, Irrigation
Department, who has also been nominated as Director of
KBJNL, the said nomination having been made under Article
147(c) of the Articles of Association of the Companies. It
has been categorically stated in the said affidavit that for
facilitation of mobilising funds and providing sufficient
funds to complete irrigation projects the constitution of
KBJNL has been constituted with the sole idea to complete
the works of Upper Krishna Projects by 2000AD. This company
is a Government Company which has been established with an
approval of the Cabinet in the State of Karnataka by its
decision dated 6th May, 1994 and the Chief Minister of the
State of Karnataka is the Chairman of the Company whereas
Deputy Chief Minister is the Vice- Chairman of the Board of
Directors. All the Subscribers to the Memorandum are
Government Officials and it has been declared to be a
Government Company. The Memorandum of Articles of
Association have been exhibited as Exhibited PAP 210. The
affidavit has given the details as to how the State
Government retains full control over KBJNL and on going
through the said affidavit we have no hesitation to come to
the conclusion that the apprehension of the plaintiff State
is wholly mis-conceived and devoid of any substance.
In view of our conclusions drawn on different issues,
it is not possible for the Court to grant the relief of
permanent mandatory injunction, so far as construction of
the Dam at Almatti is concerned as well as the reliefs
sought for in paragraphs (b) to (k). But at the same time,
we make it clear that there is no bar for raising the height
of the Dam at Almatti upto 519.6 meters subject to getting
clearance from the Appropriate Authority of the Central
Government and any other Statutory Authority, required under
law. The question of raising the height upto 524.256 meters
at Almatti could be appropriately gone into by a Tribunal,
to be appointed by the Central Government, on being
approached by any of the three riparian States and such
Tribunal could also go into the question of apprehension of
submergence within the territory of the State of Maharashtra
and give its decision thereon, in the event the height of
the Dam at Almatti is allowed to be raised upto 524.256
meters. The Tribunal would also be entitled to go into the
question of reallocation of the water in river Krishna
basin, if new datas are produced by the States on the basis
of improved method of gazing.
The suit is disposed of accordingly. There will be no
order as to costs.