Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 5
CASE NO.:
Appeal (civil) 7391 of 2001
PETITIONER:
ASIA RESORTS LIMITED
Vs.
RESPONDENT:
USHA BRECO LIMITED
DATE OF JUDGMENT: 30/10/2001
BENCH:
D.P. Mohapatra & K.G. Balakrishnan
JUDGMENT:
BALAKRISHNAN, J.
Leave granted.
The appellant constructed a hotel resort by name Timber Trail
Heights at Bansaar in Himachal Pradesh. This place is at a high altitude of
5000 feet from sea level and in order to ensure a quick access for the
visiting tourists to this resort, the appellant wanted to have a passenger
ropeway system and for that purpose, the appellant entered into a contract
with the respondent, by name, Usha Breco Limited. The respondent
completed the work relating to ropeway system and handed over the same to
the appellant on 27.4.1988. Initially, the ropeway system was being
operated and maintained by the employees of the respondent, but later on the
appellant absorbed those workers as its own employees. According to the
appellant, right from the beginning, the ropeway system was not
functioning well and it did not meet the specification required by the
appellant. The appellant had been making a request to the respondent to
rectify the defects but the latter failed to rectify the same. The appellant also
alleged that the respondent did not cooperate with the appellant for getting
clearance from the Himachal Pradesh Ropeway Inspector. The Inspector did
not approve the ropeway system for the installed capacity. The appellant
alleged that the works undertaken by the respondent were defined in the
annexure to the agreement and as per the agreement, the ropeway system
must have a capacity for carrying on 150 passengers per hour and it was
further stipulated that within 8 hours of operation per day, the total capacity
of passengers must be 1200 per day and according to the appellant, based on
such representation, assurance and agreement, the appellant invested huge
amount for the ropeway system. The appellant later realized that only 800
passengers would be able to reach the destination through the ropeway
system per day and this, according to the appellant, caused heavy financial
loss. The appellant issued a notice to the respondent but the latter did not
accede to their request. Ultimately, on 16.6.1993, the appellant issued a
notice to the respondent intimating that it would be constrained to file a
petition under Section 20 of the Arbitration Act, 1940 (for short the Act).
Clause 15 of the agreement provided for arbitration and the appellant filed a
petition under Section 20 of the Act on 30.11.1993.
The respondent filed a reply contending that the petition filed by the
appellant was barred by limitation. The respondent contended that the
appellant had issued notice on 17.4.1990 through its advocate intimating the
respondent that they would take legal action against them. It was contended
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 5
by the respondent that the petition filed under Section 20 of the Act on
30.11.1993 was more than 3 years after the issuance of notice. The
respondent alleged that the subsequent notice on 16.6.1993 was issued
beyond the period of 3 years from the earlier notice. The respondent also
contended that there was no subsisting agreement between the parties and all
matters relating to the contract were concluded and the minutes also were
recorded on 12.4.1988.
The learned Single Judge before whom the application under Section
20 was filed rejected the contention urged by the respondent herein and held
that the petition under Section 20 was filed in time. The learned Single
Judge was of the view that parties had made correspondence regarding the
disputes till 1993 and therefore, the petition under Section 20 of the Act was
within limitation. The learned Single Judge also observed that a letter
written on 6.4.1993 by the respondent to the appellant would amount to
acknowledgment under Section 18 of the Limitation Act and on that basis
also, the petition for arbitration was held to have been filed within time.
This order was challenged before the Division Bench. After an
elaborate consideration of the whole matter, the Division Bench came to the
conclusion that the petition filed by the appellant under Section 20 of the
Act was barred by limitation and there was no acknowledgment on the part
of the respondent to extend the period of limitation. This judgment of the
Division Bench is challenged before us.
We heard Mr. R.F. Nariman, learned senior Counsel for the appellant
and Dr. A.M. Singhvi, learned senior Counsel for the respondent.
The Counsel for the appellant submitted that the appellant gave notice
on 17.4.1990 to the respondent informing them of the difficulties
encountered by the ropeway system and making a request to rectify the
same. The disputes and differences between the parties arose after
17.4.1990. Thereafter, there was mutual consultation, which lasted up to
1993 until it ultimately failed and then alone the cause of action arose for
filing petition under Section 20 of the Act. It was also argued that the notice
sent on 17.4.1990 was not sent with the intention of initiating arbitration
proceedings, rather the appellant wanted to intimate that they would initiate
criminal action against the respondent.
The Counsel for the respondent, on the other hand, contended that the
appellant issued notice on 17.4.1990 for which a definite reply was given on
17.5.1990 and, therefore, the cause of action, if any, had arisen and the
petition filed after a period of 3 years from that date was barred by
limitation.
The counsel for the appellant argued that in view of the arbitration
clause contained in the agreement, the petition under section 20 of the Act
could be filed only after making a bona fide attempt to resolve the
differences by mutual consultations and according to the appellant, these
mutual consultations continued even after the notice dated 17.4.1990 and by
the notice sent on 16.6.1993 the agreement between the parties was
terminated and the cause of action arose for filing of a petition under Section
20 of the Act.
The arbitration clause contained in the agreement is as follows :
If at any time any question, dispute and difference whatsoever
shall arise between ARL and UBL in relation to or in
connection with this Agreement, both parties agree to resolve
such differences by mutual consultation failing which either
party may give to the other notice in writing of the existence of
such question, dispute or difference and the same shall be
referred for the final determination of a single arbitrator, if
agreed upon or to two arbitrators one to be appointed by ARL
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 5
and another by UBL; or in case of disagreement between the
said two arbitrators to the final arbitration of an Umpire to be
appointed by the said two arbitrators and that the award of the
sole arbitrator or the said Umpire as the case may be shall be
final and binding on both the parties and the said arbitration
proceedings shall be governed by the provisions of the Indian
Arbitration Act, 1940 and the rules thereunder, to be read
together with all statutory amendments or modifications of the
said Act.
It is true that from the above arbitration clause it is clear that parties
should have made an effort to settle the differences by mutual consultations
and only on failure of such attempt steps could have been taken by the
parties for making a reference to the arbitrator, but the notices issued
between the parties hardly give any indication that these mutual
consultations for resolution of differences continued upto 1993. A perusal
of the notice sent by the appellant on 17.4.1990 to the respondent and the
reply received from the latter would show that the cause of action had arisen
for filing of a petition under section 20 of the Act as early as on
17.5.1990. The material portion of the notice sent by the appellant has been
extracted in the impugned judgment. Suffice it to say that in the notice dated
17.4.1990, it is made out in unmistakable terms that the appellant was of the
view that the respondent had committed a serious breach of the
agreement and therefore the respondent was called upon to do the needful
within 30 days from the date of that notice, failing which the appellant
would take legal action against the respondent in court of law. In the
notice, it was stated that the performance of the passenger ropeway was not
to the satisfaction of the appellant and the respondent had supplied the
equipment which was capable of working up to sixty per cent capacity and
that the respondent had charged hundred per cent money. It was also stated
that the appellant had spent Rs.70 lakhs and due to the delay in delivery of
the equipment, the appellant had suffered liquidated damage to the tune of
Rs.3.50 lakhs. The appellant further stated that the project costing Rs.206
lakhs should have been completed in the month of March, 1987, but it was
not ready even in April, 1988 and on that account the appellant had
suffered damage to the extent of Rs.37 lakhs at the construction stage. In
the notice, it was mentioned that the respondent committed the offence of
cheating punishable under section 420 IPC as there was dishonest intention
on the part of the respondent from the very inception of the contract and that
the respondent committed extortion by putting the appellant in fear of not
completing the project. It is, however, pertinent to note that the appellant
did not specifically state in the notice that it would initiate criminal
prosecution against the respondent. The contention of the appellants
counsel that the notice sent by the appellant was not as a prelude to filing of
a petition under section 20 of the Arbitration Act but only to initiate
criminal action, is belied by the absence of such a warning in that notice.
The tenor of the notice dated 17.4.1990 is that the appellant wanted the
respondent to give a final reply in the matter and to settle all claims of the
appellant.
The respondent sent a detailed reply to the notice sent by the appellant
wherein all the allegations were denied. The respondent denied the claim
made by the appellant in its entirety and it was stated that the appellant
issued the notice with a view to delay the payment of about Rs.6 lakhs which
was due to the respondent. The appellant was told in clear terms that the
respondent was not prepared to accede to the claim made by the appellant.
The crucial question is whether any mutual consultation between the
parties to resolve the differences as envisaged under the arbitration clause
had taken place even after the reply sent by the respondent on 17.5.1990.
The appellant would contend that there was further correspondence between
the parties during this interregnum. To substantiate this contention, the
appellant relies on the letter written by the appellant on 24.3.1993 to Usha
Martin Industries Ltd. and also a letter written by the respondent to the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 4 of 5
appellant on 6.4.1993. In the letter dated 24.3.1993, it is stated that We
are looking forward for the implementation of your decision to increase the
capacity of our passenger ropeway system and we assure you that we will
release the payment in your favour as agreed immediately. This letter was,
in fact, not sent to the respondent, but probably to a sister concern of the
respondent. We would assume that it was sent to the respondent as we see
a reply by the respondent on 6.4.1993 on record. In the letter dated
6.4.1993, the respondent makes a complaint that the minutes of the
discussion held on 19th and 20th March, 1993 with the Executive Director of
M/s Usha Martin Industries Ltd. were not properly recorded.
In the absence of any other material, it is difficult to discern whether
this correspondence would amount to any effective mutual consultations
between the parties. The Division Bench has rightly held that these letters
hardly make any acknowledgement under Section 18 of the Limitation Act.
There is not much controversy that the residuary article 137 of the
Limitation Act applies so far as the period of limitation is concerned for an
application under Section 20 of the Arbitration Act, 1940. The residuary
article 181 of the Limitation Act, 1908 was replaced by Article 137 in the
Limitation Act, 1963. Earlier, Article 181 was applicable only in respect of
application to be filed under the Civil Procedure Code. This Article was
replaced by Article 137 in the Limitation Act, 1963 in a modified form. By
insertion of Article 137, it cast a wider net so as to include any application
for which no period of limitation was provided elsewhere in that division.
The third division of the Limitation Act, 1963 deals with various
applications to be filed under various special statutes. The definitions of
applicant and application are also inserted in the Limitation Act, 1963.
Therefore, it is clear that the intention of the legislature was to provide a
residuary article prescribing period of limitation for filing petitions and
applications under the various special laws. This Court in Kerala State
Electricity Board vs. T.P. Kunhaliumma AIR 1997 SC 282 held that
Article 137 would apply to any petition or application filed under any Act to
a civil court and it cannot be confined to applications contemplated by or
under the Code of Civil Procedure. In Major (Retd.) Inder Singh Rekhi
vs. Delhi Development Authority 1998(2) SCC 338; Union of India and
Another vs. M/s. L.K. Ahuja and Co. 1988(3) SCC 76; Steel
Authority of India Ltd. vs. J.C. Budharaja, Government and Mining
Contractor 1999(8) SCC 122; and Union of India and another vs.
M/s. Vijay Construction Co. AIR 1983 Delhi 193, this Court held that the
period of limitation for filing application under Section 20 of the
Arbitration Act, 1940, is as prescribed under Article 137 of the Limitation
Act.
Under Section 20 of the Act, the cause of action for filing an
application may arise whenever a difference has arisen to which the
agreement applies. Regard must be had to the relevant arbitration clause
in the agreement. If any specific terms are used in the arbitration clause, that
would govern the parties as to when a petition for reference of arbitration
shall be filed in Court.
In the instant case, the arbitration clause states that all parties would
resolve such differences by mutual consultation failing which either party
must give to the other notice in writing of the existence of such question,
dispute or difference and the same shall be referred for the final
determination. The appellant issued notice to the respondent and a definite
reply was received by the appellant. It is clear that cause of action for filing
had arisen, the moment the appellant received the reply notice denying the
claims made by the appellant. Therefore, the Division Bench has rightly
held that the application was barred by time.
The appellant herein has filed an application under Section 5 of the
Limitation Act praying that the delay in filing the application under Section
20 of the Act be condoned. Section 5 of the Limitation Act says any appeal
or any application, other than application under any of the provisions of
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 5 of 5
Order XXI of the Code of Civil Procedure, 1908, may be admitted after the
prescribed period, if the appellant or the applicant satisfies the court that he
had sufficient cause for not preferring the appeal or making the application
within such period. The applicant can show sufficient cause for not filing
the application in time. It appears that this Court had no occasion to
consider whether Section 5 of the Limitation Act, 1963 could be applied in
the case of an application to be filed under Section 20 of the Arbitration Act,
1940. The Division Bench of the High Court of Delhi in Union of India
and another vs. M/s. Vijay Construction Co. AIR 1981 Delhi 193 held
that the benefit of Section 5 of the Limitation can be availed by the applicant
for an application under Section 20 of the Arbitration Act. Going by the
provision contained in Section 5 of the Act, we are also of the view that in
an appropriate case the court can extend the benefit of the said Section.
The counsel for the appellant contended that a prayer was made
before the High Court for condoning the delay, if any, but the same was
rejected. As per the Arbitration clause, the disputes between the parties
could be referred to a single arbitrator if agreed to by both the parties but in
case of disagreement both the parties can appoint one arbitrator each and in
case of disagreement between the said two arbitrators there is a provision
that an umpire also could be appointed by the two arbitrators. In the instant
case, the learned Single Judge straightaway appointed the arbitrator.
Though there was a cause of action for the appellant to initiate proceedings
under the Arbitration Act for appointment of an arbitrator, the appellant
failed to do so. The letter written by the respondent on 6.4.1993 indicates
that the respondent had some proposal for consideration.
Having regard to the nature of disputes between the parties, we are of
the view that the delay caused in filing the application by the appellant was
not willful and hence is liable to be condoned. However, in the facts and
circumstances of the case we are also of the view that the delay shall be
liable to be condoned only upon payment of costs. Accordingly, the delay
in filing the application under Section 20 of the Arbitration Act is condoned
on condition that the appellant pays a sum of Rs.20,000/- to the respondent
within a period of one month. The said sum of Rs.20,000/- shall be
deposited with the Registrar General of this Court on or before 1st
December, 2001 and on such deposit the respondent would be at liberty to
withdraw the same. For payment of cost as stated above, the appeal would
stand allowed and the matter would be remitted to the High Court to be
proceeded with in accordance with the provisions of the Arbitration Act,
1940, read with relevant arbitration clause in the agreement between the
parties. In case the appellant fails to deposit the said amount of
Rs.20,000/- within the stipulated period, the appeal would be deemed to
have been dismissed without further reference to the Court.
I.A. Nos. 1 to 4 would stand allowed.
The appeal is disposed of in the aforesaid terms.
J
[ D.P. Mohapatra ]
J
[ K.G. Balakrishnan ]
October 30, 2001.