CPI I INDIA LTD. vs. BPTP LTD AND ORS.

Case Type: Original Misc Petition

Date of Judgment: 10-03-2012

Preview image for CPI I INDIA LTD. vs. BPTP LTD AND ORS.

Full Judgment Text


IN THE HIGH COURT OF DELHI AT NEW DELHI
( Reportable )
O.M.P. 577 of 2012 & I.A. Nos. 12593 and 15657 of 2012
CPI INDIA I LTD ..... Petitioner
Through: Mr. Rajiv Nayar, Senior Advocate
with Ms. Bindi Dave, Mr. Amit
Sethi, Mr. Sameer Pandit and
Mr. Aman Raj Gandhi, Advocates.
Versus
BPTP LTD AND ORS. ..... Respondents
Through: Mr. Dushyant Dave and Mr. Sandeep
Sethi, Senior Advocates with
Mr. Hardeep Sachdeva,
Mr. Rudreshwar Singh, Mr. Kamal
Shankar, Mr. R. Poddar and
Mr. Ravi Bhasin, Advocates.
CORAM: JUSTICE S. MURALIDHAR
O R D E R
03.10.2012
1. By this petition under Section 9 of the Arbitration and Conciliation
Act, 1996 (‘Act’), CPI India I Limited (‘CPI’), a company organized
under the laws of Mauritius and having its registered office address at
Ebene in Mauritius, has sought interim reliefs against BPTP Ltd.
(‘BPTP’) (Respondent No. 1), an Indian company , and twenty-four other
Respondents in relation to the disputes that have arisen between CPI and
the Respondents from the Share Subscription Agreement (‘SSA’) dated
th th
10 August 2007; Shareholders’ Agreement (‘SHA’) dated 10 August
th
2007 as further amended by the Amendment Agreement dated 9 July
2008 (‘Agreement’) and a Memorandum of Understanding (‘MoU’)
th
dated 19 December 2009 entered into between CPI and the
Respondents.
O.M.P. No. 577 of 2012 Page 1 of 19

2. The background to the present petition is that the Respondents 2 and 3
are the Promoters of BPTP, Respondent No. 1. An SSA was entered into
between CPI, Respondents 2 and 3 (referred to as ‘Promoters’), BPTP
(referred to as the “Company”) as well as other existing shareholders of
BPTP whose names were listed out in Schedule-I to the Agreement (and
who are arrayed as Respondents 4 to 25 in this petition). In the SSA, CPI
was described as “a property investor desirous of making investments in
the Indian real estate sector.” The recitals to the SSA stated that the
Promoters who are engaged in the business of real estate construction and
development, along with the other existing shareholders, collectively held
100% of the issued share capital of BPTP, “a real estate development
company engaged in residential and commercial real estate development
projects”. The current real estate projects of BPTP were set out in
Schedule-II of the SSA.
3. The SSA stated that the Promoters as well as BPTP represented to CPI
that BPTP would make its best efforts to complete the listing of its shares
under qualified and initial public offer (‘QIPO’) within twenty-four
th
months of the Closing Date as defined in Clause 5.1 of the SSA, i.e., 18
August 2007. CPI subscribed to 13,551,971 Equity Shares for the sum of
Rs. 300 crores and 22,500,000 Preference Shares for a total amount of
Rs. 22.50 crores.
4. In terms of Clause 4.2 of the SHA executed on the same date, it was
agreed that the proceeds of CPI’s subscription of shares would be utilized
by BPTP only for foreign direct investment (‘FDI’) compliant real estate
projects, hotels, hospitals and special economic zones, and to fund capital
expenditures and/or land acquisitions for the purpose of expanding the
business of BPTP in relation to such FDI compliant real estate projects
etc. Under Clause 4.8 of the SHA, the parties acknowledged their intent
O.M.P. No. 577 of 2012 Page 2 of 19

to pursue a QIPO to be closed within twenty four months after the
Closing Date.
5. Clause 4.10 of the SHA provided for “Swap Option”. Inter alia , it was
stated that in the event BPTP failed to achieve a QIPO within twenty-four
months following the Closing Date, CPI, shall within six months from
the expiry of the said twenty four months period, have the option (the
‘Swap Option’) to require upon demand that:
“(i) the Company (or the Promoters) establish one or more
special purpose project companies (each, a “Project
Company” and, collectively, the “Project Companies” ) as set
out in Clauses 4.10.4 and 4.10.5 below,
(ii) the Project Company(s) issue to the Investor a number of
Shares in the Project Company(ies) as per the shareholding set
out in Clause 4.10.4,
(iii) the Company transfer assets to the Project Company(s) in
accordance with Clause 4.10.4, with any cost of such transfers
(including stamp duty, if any) to be borne solely by the Project
Company(s) (provided that the Company shall be responsible
for capital gains taxes, if any, involved in connection with such
transfer of assets) and
(iv) the Company or the Promoter (or a Promoter SPV) shall
buy back the Investor Shares in the Company pursuant to
Clause 4.10.7. Notwithstanding the forgoing, the Investor shall
be entitled to exercise the Swap Option at any time prior to the
expiry of twenty four (24) months under the provisions of
Clause 11.3.5 and Clause 11.4.2.”
6. The manner of issuing Swap Option was set out in Clause 4.10.3 of
the SHA. CPI was entitled to select the projects under the Swap Option
within thirty days from receipt of the Company Fair Market Value from
the Auditor by giving a written notice to BPTP and the Promoters. A
separate Project Company was to be formed in respect of each of the
projects. CPI and BPTP were to hold shares in each of the Project
O.M.P. No. 577 of 2012 Page 3 of 19

Company(s) in the ratio of 49.99:50.01. Under Clause 4.10.5, CPI was to
infuse fresh funds and subscribe/purchase such shares of the Project
Company(s) for the acquisition of 49.99% shareholding in such projects.
7. Clause 4.10.13 of the SHA provided that in the event that the failure to
implement the Swap Option was attributable to BPTP or the Promoters
then CPI “shall have the right to require (on a joint and several basis
against the Promoters), at any time upon demand, that the Promoters
purchase the Investor Shares in accordance with the mechanics set forth
in Clause 11.3”. In the event that the failure to implement the Swap
Option was attributable directly to the failure of CPI to use its reasonable
efforts to complete such Swap Option, including but not limited to
infusion of fresh funds, then CPI would not be entitled to require the
Promoters to purchase CPI’s shares. The said Clause further provided as
under:
“In the event the Swap Option is not implemented within six (6)
months of the date of receipt of the Swap Option Notice for any
reason, the Investor shall have the right to require the Company to
sell the Project(s) selected by it under the Swap Option, in
accordance with Clause 4.10.16. This right shall be valid for a
period of thirty (30) days from the expiry of the said six (6) month
period in the preceding sentence.”
8. Under Clause 8.15 of the SHA, no major decision could be taken in
connection with BPTP by a Resolution or at any meeting with respect to
the matters listed out thereunder “without the affirmative vote of the
Investor Director”, i.e., CPI. The matters listed out included:
“(a) Amendments to the articles of association or any
constitutional documents, except as may be required for the
QIPO;
(f) Incurrence of indebtedness over Rs.100 crores, not
specifically approved in the annual AOP;
O.M.P. No. 577 of 2012 Page 4 of 19

(h) Deviations from the AOP in terms of new project site
acquisitions where the land cost is greater than Rs.150 crores,
financings beyond Rs.100 crores, major capital expenditures
beyond Rs.50 crores, selection of construction contractors
(other than listed names in the AOP for value exceeding Rs.50
crores) and branding of projects other than under the “BPTP”
brand;
(i) Entering into any new line of business;
(j) Sale, lease, license, mortgage or otherwise subject to lien or
dispose of substantially all of the properties or assets of the
Company”
9. In terms of Clause 4.10 SHA read with Clause 3 of Amendment
th
Agreement No. 1 dated 9 July 2008, CPI initiated its Swap Option right
th th
by a notice dated 9 July 2008. Subsequently on 9 January 2009, CPI
delivered the Swap Option Notice to BPTP as well as the Promoters’
Group. With the six months’ period provided in Clause 4.10.13 having
th th
expired on 8 July 2009, CPI by its Notice dated 6 August 2009
exercised the Sale Right in terms of the said Clause. At this stage, the
th
parties held further negotiations and an MoU was entered into on 19
December 2009 in terms of which, as set out in Preamble Clause (D), it
was agreed as under:
“(D) Without prejudice to the exercise of the Sale Right by the
Investor, the Parties have agreed, subject to the terms of this MoU,
to postpone/ suspend the implementation of the Sale Right for a
period of time up to the IPO Deadline (as hereinafter defined) in
order to give the Company time to complete a QIPO. If on or prior
to the IPO Deadline, the Company has completed the QIPO and
the shares of the Company are listed on the Exchange, then the
Sale Right shall not be implemented by the Investor and this MoU
shall stand terminated. To facilitate the Sale Right, the Parties have
agreed upon a mechanism which shall maximize the revenues
generated upon the sale of the Selected Projects (as hereinafter
defined).”
10. The selected projects referred to hereinabove were set out in Schedule
O.M.P. No. 577 of 2012 Page 5 of 19

A as under:
“SCHEDULE A
SELECTED PROJECTS
Sr.
No.
Name of
City Type Sector Area Average
CPI
Share
CPI’s
BPTP
BPTP’s
Project
In
Valuation
Avg.
Share
Avg.
(acres) INR m (%) Valuation (%) Valuation
1 Project P
Faridabad Group
Housing
75 18.506 831.80 57.99% 482.36 42.01% 349.44
(Resort)
2 Project A Faridabad Group
Housing
83 17.669 708.61 55.99% 396.75 44.01% 311.86
3 Project G Faridabad Group
Housing
83 18.013 722.15 50.00% 361.08 50.00% 361.08
4 Project H Faridabad Group
Housing
83 7.013 288.02 50.00% 144.01 50.00% 144.01
5 Project M Faridabad Group
Housing
80 10.630 441.08 55.99% 246.96 44.01% 194.12
6 Project G Gurgaon Group
Housing
106 21.956 1035.33 50.00% 517.67 50.00% 517.67
7 Project A
Gurgaon Group
Housing
37D 13.000 674.49 58.00% 391.20 42.00% 283.29
(Park
Serene)
8 Project Y Gurgaon Group
Housing
102 27.431 2,552.44 50.00% 1,276.22 50.00% 1,276.22
Total 134.217 7,253.92 3,816.25 3,437.67”
11. The ‘absolute trigger events’ were set out in Clause 4.4 of the MoU.
One of this was BPTP having failed to successfully implement the QIPO
by the IPO Deadline. Clause 10 of the MoU provided for distribution of
sale proceeds. The proceeds from the sale/transfer of each of the selected
projects were to be deposited directly into an Escrow Account which was
to be in the name of BPTP and was to be operated upon by the escrow
agent thereunder only upon receipt of joint written instructions from
BPTP and CPI. Under Clause 10.2 of the MoU, all proceeds generated
th
after the effective date, i.e., 19 December 2009 from the pre-sales by
BPTP or any units located on any of the selected projects was to be
deposited into the escrow account. Further “after the Effective Date, any
construction or pre-sales of any units on any of the Selected Projects shall
be made subject to and in accordance with the mutual agreement in
O.M.P. No. 577 of 2012 Page 6 of 19

writing between the Company and the Investor”.
12. Under Clause 10.3(a) of the MoU, the sale proceeds were to be
distributed to CPI and BPTP in the ownership percentage ratio set forth
in Schedule A. Under Clause 10.3(b) of the MoU, CPI’s portion had to
be paid to it “by way of immediate buy back of the Investor Shares by the
Company upon the sale of each Selected Project and shall be completed
within ten (10) Business Days from the time that the Sale Proceeds for
each Selected Project are deposited into the Escrow Account”. Under
Clause 10.3(c) of the MoU, it was provided that in the event that the
Reserve Bank of India (‘RBI’) or any governmental authority determines
the buy-back price of the shares of CPI at a price lower than that arrived
at under Clause 10.3(b) then BPTP and the Promoter Group would still
be obligated to pay CPI the difference in CPI Portion through a suitable
tax effective mechanism.
13. Clause 12 of the MoU set out the ‘representations and warranties’.
Under Clause 12.2(d), it was represented by BPTP that “other than the
Selected Projects mentioned in Schedule H, the necessary development
licenses have been obtained for all other Selected Projects....”.
14. Admittedly, the QIPO was not achieved as was agreed under the
MoU. According to CPI, BPTP immediately became liable to implement
the sale of Selected Projects and CPI was entitled to have its share of the
proceeds distributed to it in accordance with the MoU. CPI stated that
BPTP and the Promoters had “without any just cause intentionally and in
breach of the MoU and the SHA failed to take further steps to implement
the sale of the Selected Projects till date”.
15. The present petition in para 7.4(f)(ii) lists out the alleged breaches
O.M.P. No. 577 of 2012 Page 7 of 19

and defaults committed by the Respondents. This includes unauthorised
raising of the debts by the Respondents without the Investor Director’s
approval. In particular, it is pointed out that a meeting of the Board of
th
Directors of BPTP was held on 29 June 2012 and the Respondents
proceeded to approve incurrence of the following debts, without CPI’s
Directors approval:
“(i) Term loan from Syndicate Bank for Rs.90 crores,
(ii) Corporate loan of Rs.125 crores from IFCI Limited; and
(iii) raising fresh debt of upto Rs.730 crores.”
th
16. It was further averred by CPI that on 9 November 2011, i.e., five
days after receiving the default notice from CPI, the Respondents
unilaterally addressed a letter to RBI requesting for an opinion on the
validity of certain provisions of the Agreements without disclosing the
full information pertaining to CPI’s investments in BPTP. RBI had by a
th
letter dated 12 December 2011 given a brief response advising BPTP to
th
be guided by its Instructions dated 24 October 2011 as was advised to it
in a similar case earlier.
th th
17. By letters dated 25 April 2012 and 8 June 2012, BPTP had taken
the stand that the rights and remedies available to CPI under the
Agreements were not enforceable in law. CPI alleges that these letters
were attempts at avoiding BPTP’s obligations towards CPI and to
illegally extinguish its remedies. The other grievances include creation of
encumbrances on the Selected Projects, the unauthorised passing of
resolutions and unauthorised use of proceeds from the sale of
development rights.
th
18. In the above circumstances, the present petition was filed and on 4
July 2012 the following order was passed by this Court in the presence of
O.M.P. No. 577 of 2012 Page 8 of 19

counsel for the Respondents:
“1. Notice. Mr. Kamal Shankar, learned counsel accepts notice on
behalf of the Respondents.
2. During the course of the arguments it has been agreed by
learned Senior counsel for the Respondents, on instructions, that
within the next week, a meeting will he held between the
representatives of Respondent No. 1 BPTP Limited and the
Petitioner CPI India Limited to examine what alternative options
can be explored including reworking the shareholders agreement
which is the subject matter of the present petition. Respondent No.
1 will disclose to the Petitioner the exact amounts of statutory and
government dues which are to be paid by Respondent No. 1. The
Petitioner will also be informed as to which unencumbered
properties/assets of Respondent No. 1 company will be earmarked
to secure the investment made by the Petitioner thus far. It is made
clear that this would be without prejudice to rights and contentions
of either party.
th
3. List on 26 July 2012.
4. Till the next date of hearing, Respondent No. 1 will not give
effect to the Resolution passed by the Board of Directors of
th
Respondent No. 1 at the meeting held on 29 June 2012. It is
clarified that none of the ‘Selected Projects’ the list of which is at
page 138 of the documents volume, shall be sold, alienated or
otherwise encumbered by Respondent No. 1 till the next date.
5. Order be given dasti under signature of the Court Master.”
19. BPTP filed I.A. No. 12593 of 2012 for modification of the
th th
aforementioned order dated 4 July 2012. On 17 July 2012, the
following order was passed in the said application:
“1. Issue notice.
2. Mr. Amit Sethi, Advocate accepts notice on behalf of the
Petitioner.
3. It is stated by Mr. Mukul Rohtagi, learned senior counsel for the
Petitioner ( sic BPTP) that without prejudice to the rights and
contentions of the Respondents, the Respondents are prepared to
offer as security to the Petitioner two of its unencumbered
O.M.P. No. 577 of 2012 Page 9 of 19

properties, the valuation report in respect of which has been
enclosed with the application. He further states that the Petitioner
can carry out inspection of the title documents of both the
properties on a mutually convenient date and time. The
Respondents are also prepared to answer any other queries that the
Petitioners may have in respect of the said two properties.
4. It is directed that the Petitioners will be permitted to inspect the
th
title documents of the properties offered on 18 July 2012 at 3.00
p.m. at the office of the Respondents.
5. The original title deeds in respect of these two unencumbered
properties shall be produced by the Respondents on the next date
of hearing.
rd
6. List on 23 July 2012.”
th
20. Thereafter on 25 July 2012 after hearing the submissions of the
counsel for the parties, the following order was passed:
“1. Mr. Harish Salve, learned senior counsel appearing for the
Respondents states that a further affidavit will be filed within two
days with copies to the other side explaining the circumstances
under which the Respondents are pressing for being permitted to
avail of the loan of Rs.125 crores from the IFCI. He states that the
affidavit will also indicate the current status of the eight properties
listed in Schedule A to the Memorandum of Understanding
th
(‘MoU’) dated 19 December 2009.
2. Mr. Rajiv Nayyar, learned senior counsel for the Petitioner
states that the Petitioner will file a reply to the said affidavit before
the next date of hearing.
th
3. List on 29 August 2012.
O.M.P. No.577 of 2012
4. The parties are agreed that the eight properties listed in
Schedule-A to the MoU can be evaluated by Cushman &
Wakefield (India) Pvt. Ltd., registered office at B-6/8, Commercial
Complex, Opp. Deer Park, Safdarjung Enclave, New Delhi-110029
th
and also at 14 Floor/II, Block-C, Building No.8, DLF Cyber City,
Gurgaon-122022. A request will be made to the said valuers today
itself jointly by both the parties. The fees of the valuer will be
shared equally by both the parties. The Court requests the valuers
O.M.P. No. 577 of 2012 Page 10 of 19

to submit their report not later than four weeks from today. The
Respondents will provide complete details of the eight properties
to the valuers to enable them to properly assess their present value.
th
5. The next date of 26 July 2012 is cancelled.
th
6. List on 29 August 2012.
7. Interim orders to continue.
8. Copy of this order be given Dasti.”
st
21. On 1 August 2012, the following order was passed in I.A. No.
13887 of 2012, an application filed by the Respondents, for directions:
“1. Learned Senior counsel for the parties have been heard.
2. Without prejudice to the rights and contentions of the Petitioner,
the four projects/properties of Respondent No.1-Company, viz.,
Project M, Project H, Project Q and Project D listed in Annexure
‘A’ to this application will, in addition to the properties asked to be
th
evaluated in the earlier order dated 25 July 2012, also be
evaluated by the same firm, i.e. Cushman and Wakefield (India)
th
Pvt. Ltd in terms of the order passed by this Court on 25 July
2012.
3. The application stands disposed of in the above terms.”
22. Subsequent to the above orders, M/s Cushman & Wakefield (India)
nd
Pvt. Ltd. [‘Cushman & Wakefield’], have filed their Report dated 22
th
August 2012 as further revised on 28 August 2012. They have also
submitted a valuation report in respect of the four further land parcels
st
which were permitted to be evaluated by the order dated 1 August 2012
passed by the Court.
23. One other subsequent development is that a three-Member arbitral
Tribunal (‘arbitral Tribunal’) has been constituted for adjudicating the
disputes between the parties. It is stated that the said arbitral Tribunal
O.M.P. No. 577 of 2012 Page 11 of 19

th
has already held its first sitting on 29 September 2012.
24. This Court has heard the submissions of Mr. Rajiv Nayar, learned
Senior counsel appearing for CPI and Mr. Dushyant Dave and Mr.
Sandeep Sethi, learned Senior counsel appearing for the Respondents.
25. At the outset, it requires to be noted that the parameters governing
grant of interim reliefs in an application under Section 9 of the Act are
more or less the same as those governing an application for interim
injunction under Order XXXIX of the Code of Civil Procedure, 1908
(‘CPC’). The three basic parameters that require to be considered are the
existence of a prima facie case; the balance of convenience and the
irreparable hardship that might result from the grant or refusal of the
interim relief as prayed for in the petition.
26. In Wander Ltd. v. Antox India (P) Ltd. 1990 (2) Arb.LR 399 (SC) ,
the Supreme Court observed as under (Arb.LR @ p.401):
“5. Usually, the prayer for grant of an interlocutory injunction is at
a stage when the existence of the legal right asserted by the
plaintiff and its alleged violation are both contested and uncertain
and remain uncertain till they are established at the trial on
evidence. The court, at this stage, acts on certain well settled
principles of administration of this form of interlocutory remedy
which is both temporary and discretionary. The object of the
interlocutory injunction, it is stated is to protect the plaintiff
against injury by violation of his rights for which he could not
adequately be compensated in damages recoverable in the action if
the uncertainty were resolved in his favour at the trial. The need
for such protection must be weighed against the corresponding
need of the defendant to be protected against injury resulting from
his having been prevented from exercising his own legal rights for
which he could not be adequately compensated. The court must
weigh one need against another and determine where the "balance
of convenience lies". The interlocutory remedy is intended to
preserve in status quo , the rights of parties which may appear on a
prima facie . The court also, in restraining a defendant from
O.M.P. No. 577 of 2012 Page 12 of 19

exercising what he considers his legal right but what the plaintiff
would like to be prevented, puts into the scales, as a relevant
consideration whether the defendant has yet to commence his
enterprise or whether he has already been doing so in which latter
case considerations somewhat different from those that apply to a
case where the defendant is yet to commence his enterprise, are
attracted.”
27. In Colgate Palmolive (India) Ltd. v. Hindustan Lever Ltd. (1999) 7
SCC 1 , it was held as under (SCC @ p.13-14):
“24. We, however, think it fit to note herein below certain specific
considerations in the matter of grant of interlocutory injunction, the
basic being-non-expression of opinion as to the merits of the
matter by the Court, since the issue of grant of injunction usually,
is at the earliest possible stage so far as the time frame is
concerned. The other considerations which ought to weigh with the
Court hearing the application or petition for the grant of
injunctions are as below:
(i) Extent of damages being an adequate remedy;
(ii) Protect the plaintiffs interest for violation of his rights though
however having regard to the injury that may be suffered by the
defendants by reason therefor;
(iii) The court while dealing with the matter ought not to ignore the
factum of strength of one party's case being stronger than the
other’s;
(iv) No fixed rules or notions ought to be had in the matter of grant
of injunction but on the facts and circumstances of each case - the
relief being kept flexible;
(v) The issue is to be looked from the point of view as to whether
on refusal of the injunction the plaintiff would suffer irreparable
loss and injury keeping in view the strength of the parties’ case;
(vi) Balance of convenience or inconvenience ought to be
considered as an important requirement even if there is a serious
question or prima facie case in support of the grant;
O.M.P. No. 577 of 2012 Page 13 of 19

(vii) Whether the grant of refusal of injunction will adversely
affect the interest of general public which can or cannot be
compensated otherwise.”
28. The issue that requires to be first addressed is whether CPI has made
out a prima facie case for continuation of the interim order passed by this
th
Court on 4 July 2012 till such time the arbitral Tribunal passes an order
on any application that may be filed by either party under Section 17 of
the Act. What is not in dispute is that CPI has over five years ago
invested over Rs. 322.5 crores in the shares of BPTP. Till date it has had
no return on the said investment. CPI’s investment was not a simpliciter
subscription of shares of BPTP. It was governed by elaborate conditions
in the SSA, the SHA (as amended) and later the MoU. While BPTP may
now want to contend that the SSA, the SHA and the MoU may be void
and therefore unenforceable the fact remains that BPTP has not rescinded
any of the said agreements or the MoU. Further, it has had the benefit of
FDI under those agreements and the MoU. The clauses of the documents
referred to hereinbefore demonstrated that there was an expectation that
BPTP would be able to roll out a QIPO within an assured time frame,
failing which CPI could exercise the Swap Option and thereafter bring
the Selected Projects to sale. Although extensive arguments were
advanced on behalf of the Respondents as to who should be held liable
for the QIPO not taking place, that is a question that should be properly
raised before and addressed by the arbitral Tribunal. At this stage, it is
sufficient for the Court to note the factual position that such QIPO has in
fact not taken place. The MoU spells out the consequences of the QIPO
not taking place. The MoU does state that the Selected Projects would be
available to be brought to sale at the instance of CPI as per its choice and
the sale proceeds would be placed in an escrow account to be operated
under the joint instructions of CPI and BPTP.
O.M.P. No. 577 of 2012 Page 14 of 19

29. The exercise of having the Selected Projects evaluated by Cushman
& Wakefield was basically to ascertain what the current market value of
those assets might be. The executive summary produced by Cushman
and Wakefield in relation to those Selected Projects indicates that their
present market values are at an aggregate of around Rs.387 crores subject
of course to qualifying statements regarding the unlicensed projects, ,
which are expected to fetch much less than licensed projects. Likewise
the valuation report in relation to the four additional Projects states that
their aggregate market value is around Rs. 390 crores. This is again
subject to the caveat regarding the unlicensed projects.
30. In response to a query from the Court whether in the market value
indicated in the above executive summaries in the reports prepared by
Cushman and Wakefield are reflective of the possibility of the said
properties fetching the stated prices if immediately brought to sale, the
response of learned Senior counsel for Respondents was that the current
market scenario in the real estate sector was not encouraging. It was
unlikely that there might be many buyers forthcoming to pay the
aforementioned market value if the properties were put up for sale.
31. From the reports of Cushman and Wakefield it is apparent that in
relation to two of the Selected Projects, i.e., Project A (Park Serene) and
Project M (Park Arena), BPTP has not only raised constructions, but has
also been selling the units to individual flat buyers. It is pointed out by
learned Senior counsel appearing for CPI that the amounts collected so
far from the purchasers by BPTP in relation to both Project M and
Project A are approximately Rs. 213 crores. CPI has filed I.A. No. 15657
of 2012 insisting that BPTP should be asked to deposit the said sum of
Rs. 213 crores in an escrow account. CPI alleges that sale of units in both
the Projects A and M have been undertaken by BPTP without the consent
O.M.P. No. 577 of 2012 Page 15 of 19

of CPI as mandated in the MoU. BPTP states that it did inform CPI that it
was going ahead with the sale of units in both those Projects and there
was an implied consent.
32. At this stage, it is not possible for the Court to come to a definite
conclusion on the above submissions regarding Projects A and M.
However, in the absence of a specific letter of consent from CPI, it does
prima facie appear that BPTP was in breach of its obligation to obtain the
consent of CPI to the sale of units in Projects A and M.
33. All the above facts when collectively assessed do indicate that CPI
has made out a prima facie case for continuation of the interim order in
its favour till such time the arbitral Tribunal passed an order on an
application that may be filed by either party under Section 17 of the Act.
34. It was earnestly pleaded on behalf of BPTP that the balance of
convenience was in favour of the modification of at least the first part of
th
the interim order dated 4 July 2012 which stayed the implementation of
th
the decisions taken at the Board Meeting held on 29 June 2012. It was
submitted that BPTP has sixty ongoing projects, has an annual turnover
of over Rs. 1500 crores and nearly 700 employees. Further, BPTP was
facing a liquidity crunch and the interim order was starving BPTP of the
possible borrowings from financial institutions. In particular, a reference
is made to a loan of Rs. 125 crores sanctioned by IFCI which BPTP says
has not been able to be availed of by it because of the interim order
passed by the Court. BPTP submits that in lieu of the vacation of the first
th
part of the interim order dated 4 July 2012 it is willing to place four
additional properties, which have also been evaluated by Cushman &
Wakefield, as unencumbered security with CPI so as to meet any possible
claims that CPI might have against it. It is submitted that the collective
O.M.P. No. 577 of 2012 Page 16 of 19

value of the six of the Selected Projects (minus Project A and Project M)
together with the four additional projects would be more than sufficient
to meet CPI’s entire claims which in any event have not yet been
formally made before the arbitral Tribunal.
35. Learned Senior counsel appearing for CPI, on instructions, stated that
CPI would not be willing to accept four additional properties three of
which in any event are unlicensed. It is stated that even among the
Selected Projects it now transpires that the warranties given by BPTP in
its MoU were false. The report of Cushman & Wakefield reveals that
among the Selected Projects, Projects G and H in Sector 83 are
unlicensed, and only five acres in Project Y in Sector 102 and 14.79 acres
in Project G in Sector 106 are licensed. In respect of four additional
projects being offered, three are unlicensed. It is pointed out that with
the real estate market admittedly not encouraging, the furnishing of
further properties as security would hardly be sufficient to meet CPI’s
claims. CPI, a foreign investor, after investing over Rs. 300 crores in
BPTP and waiting for over five years is faced with a situation where
there is neither a QIPO nor the prospect of any of the Selected Projects
being brought immediately to sale.
36. As regards the prayer that BPTP should be asked to deposit Rs. 213
crores that it has collected through sale of units in Projects A and M in an
escrow account, it appears to the Court from the submissions made by
learned Senior counsel for BPTP that the amounts so collected have
already been utilized in construction activity in Projects A and M
themselves. BPTP says that it would not be able to deposit any sum,
leave alone Rs. 213 crore, even in a separate account that will be subject
to the interim or final Award that the arbitral Tribunal might pass. It was
stated by learned Senior counsel for BPTP that it might not be prepared
O.M.P. No. 577 of 2012 Page 17 of 19

even to sell one parcel of those properties rightaway to generate some
cash which could be placed in a separate account.
37. The Court would like to observe that BPTP’s contention regarding
the legality of the SSA, the SHA and the MoU in light of the Foreign
Exchange Management Act, 1999 and RBI’s circulars can be raised
before and be addressed by the arbitral Tribunal. At this stage, the prayer
of CPI that the sale proceeds of the projects should be deposited in an
escrow account does not per se violate any requirement of the RBI.
However, in the light of BPTP’s expression of its inability to deposit any
sum in an escrow account, the only order that the Court is prepared to
pass at this stage is to require BPTP to keep a complete account of all the
monies collected by it thus far through sale of units in Projects A and M
and furnish such accounts, including the appropriation of the monies so
collected, to CPI within a period of two weeks from today. Subject to
further orders that may be passed by the arbitral Tribunal, BPTP will
cease further activities as regards Projects A and M and maintain status
quo in relation to the Selected Projects. It is clarified that it would be
open to BPTP to place before the arbitral Tribunal any further proposal in
support of its plea for modification or variation of this order. Such
proposal would be then considered on its merits by the arbitral Tribunal.
38. In the circumstances, and particularly in light of the repeated
submissions made by counsel for both parties that the real estate market
is not very encouraging at the present stage, it does appear that the
balance of convenience in continuing the interim orders passed by this
th
Court on 4 July 2012 at this stage is in favour of CPI and not BPTP.
39. On the aspect of irreversible hardship, the Court at this stage is
th
satisfied that if the interim order passed by it on 4 July 2012 is not
O.M.P. No. 577 of 2012 Page 18 of 19

continued in the manner indicated hereinafter, CPI would be subjected to
irreversible hardship which hardship outweighs the possible hardship that
BPTP will be subjected to in the facts and circumstances of the case.
40. It is clarified that the observations in this order are tentative and not
intended to influence any order that may be passed by the arbitral
Tribunal.
41. In conclusion, it is directed as under:
th
(i) The interim order passed by this Court on 4 July 2012 is
directed to continue till such time the arbitral Tribunal passes
an order, including by way of modification or variation of this
order, in accordance with law in an application that may be
filed by either party under Section 17 of the Act.
(ii) BPTP will furnish to CPI, within two weeks from today, the
accounts of the monies collected by it by sale of units in
Projects A and M, including the manner of disbursing of such
monies collected by it. Till further orders that may be passed by
the arbitral Tribunal, BPTP will cease further activity in
relation to Projects A and M and maintain status quo in relation
to the Selected Projects.
(iii) It will be open to the parties to rely on the pleadings, documents
and reports forming part of the record of the present petition in
the arbitral proceedings.
42. The petition and all pending applications are disposed of in the above
terms but with no order as to costs.
S. MURALIDHAR, J
OCTOBER 3, 2012 / akg
O.M.P. No. 577 of 2012 Page 19 of 19