Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 7
PETITIONER:
OM PRAKASH GUPTA ETC.
Vs.
RESPONDENT:
DIG VIJENDRAPAL GUPTA ETC.
DATE OF JUDGMENT05/03/1982
BENCH:
MISRA, R.B. (J)
BENCH:
MISRA, R.B. (J)
KOSHAL, A.D.
ERADI, V. BALAKRISHNA (J)
CITATION:
1982 AIR 1230 1982 SCR (3) 491
1982 SCC (2) 61 1982 SCALE (1)153
CITATOR INFO :
C 1984 SC 87 (18,20)
1985 SC 817 (8)
D 1985 SC 817 (14)
F 1987 SC2284 (4,11,13)
F 1988 SC2031 (9)
1988 SC2164 (8)
E&D 1990 SC 897 (8,9,10,11,14)
D 1991 SC 266 (7)
D 1992 SC1106 (6,10)
ACT:
U.P. Urban Buildings (Regulation of Letting, Rent and
Eviction) Act 1972. S.2 (2) and Expln. I and s. 39.
Applicability of the Act-Act not to apply to building
for a period of ten years from ’date of completion of
construction’.
Date of completion of construction-What is-’Date of
first assessment’ if assessed-’Date of occupation’ when no
record of completion of construction or of assessment.
Interpretation of Statutes-Intention of legislature-To
be ascertained primarily from words used by legislative-
Question of interpretation arises when language ambiguous.
HEADNOTE:
The U.P. Urban Buildings (Regulation of Letting, Rent
and (Eviction) Act, 1972 provided by sub-section (2) of
section 2 that except as provided in the Act, the Act was
not to apply to a building during a period of 10 years from
the date on which its construction was completed.
Explanation I to the sub-section provided that the building
shall be deemed to have been completed on the date on which
completion thereof is reported or otherwise recorded by the
local authorities having jurisdiction, and in case of a
building subject to assessment, the date on which the first
assessment thereof comes into effect, and where the said
dates are different, the earliest of the said date, and in
the absence of any such report, record or assessment, the
date on which it is actually occupied for the first time.
The appellant-tenant was in occupation of a shop from
the 16th June, 1967 and prior to his occupation the shop was
in occupation of another tenant for about a month and a
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 7
half. The first assessment of the shop took place on Ist of
April, 1968. The respondent-landlord filed a suit for the
eviction of the tenant on the ground that the Act did not
apply to the shop and the tenant was liable to eviction.
The Trial Judge finding that the construction of the
shop was completed in the year 1967 and that 10 years having
not elapsed since then, held that the provisions of the Act
did not apply and decreed the suit. The appellant’s
492
petition under section 25 of the Provincial Small Causes
Courts Act was dismissed. In his revision petition to the
High Court under section 115 of the Civil Procedure Code the
appellant contended that the date of occupation should be
taken to be the date of completion of the construction of
the shop and not the date of first assessment. The High
Court overruled the contention and held that the
construction of the shop would be deemed to have been
completed on 1st of April, 1968 the date of the first
assessment and ten years not having elapsed, the Act would
not be applicable to the building and dismissed the revision
petition.
In the appeal to this Court it was contended on behalf
of the appellant: (1) that by virtue of sub-section (2) of
section 2, the Act would be applicable to the shop in
question and that the exemption created by the sub-section
did not embrace buildings constructed prior to the
commencement of the Act and (2) that the building should be
deemed to have been constructed on the date of occupation on
16th June, 1967 and not on the date of the first assessment.
and that the appellant was entitled to the benefit of
section 39 of the Act.
Dismissing the appeal,
^
HELD: 1(i) The suit was rightly decreed by the Courts
below. The Act had no application and the appellant could
not be given the benefit of section 39. [498 G-H]
(ii) Primarily, the language employed is the
determining factor of the intention of the legislature. The
first and primary rule of construction is that the intention
of the legislature must be found in the words used by the
legislature itself. The question of interpretation arises
only when the language is ambiguous and, therefore capable
of two interpretations. [497 F]
(iii) The language of sub-section (2) of section 2 of
the Act is explict and unambiguous and is not capable of two
interpretations. [497 G]
In the absence of any ambiguity there is no question of
taking any external aid for the interpretation of the sub-
section. The sub-section contemplates that the Act shall not
apply to a building during a period of 10 years from the
date on which its construction is completed. It no where
says that the building should have been constructed after
the enforcement of the Act and to interpret it in such a way
would be to add words to the sub-section, which is not
permissible. [497 D-F]
2 (i) Explanation I makes it abundantly clear that the
date of occupation would be taken to be the date of
completion of the construction only when there is no report
or record of the completion of the construction or no
assessment thereof. If there is an assessment, as in the
instant case it will be the date of the first assessment
which will be deemed to be the date of completion of the
construction. The building had not therefore become more
than ten years’s old on the date when the revision came to
be decided by the High Court and consequently there was no
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 7
question of giving the benefit of section 39 of the Act to
the appellant. [498 D-F]
493
(ii) In order to attract section 39 the suit must be
pending on the date of the commencement of the Act which
was 15th of July, 1972. [498 F]
In the instant case the suit was filed on 23rd of March
1974 long after the commencement of the Act. [498 F]
(iii) In view of sub-section (2) of section 2, the Act
is not applicable to a building which has not a standing of
ten years. If the Act itself was not applicable, it would be
absurd to say that section 39 thereof would be applicable.
[498 G]
Rattan Lal Shinghal v. Smt. Murti Devi (1980)4 S.C.C.
258 and Ram Saroop Rai v. Lilavati (1980) 3 S.C.C. 452,
over-ruled.
JUDGMENT:
CIVIL APPELLATE JURISDICTION: Civil Appeal No. 1314 of
1978.
Appeal by special leave from the judgment and order
dated the 23rd March, 1978 of the Allahabad High Court in
Civil Revision No. 1906 for 1976.
WITH
CIVIL APPEAL No. 2436 OF 1981
Appeal by special leave from the judgment and order
dated the 20th August, 1981 of the Allahabad High Court in
Civil Writ Petition No. 6909 of 1979.
AND
CIVIL APPEAL No. 1710 OF 1981
From the judgment and Decree dated the 13th March, 1981
of the Allahabad High Court in Writ Petition No. 6167 of
1979.
AND
SPECIAL LEAVE PETITION (CIVIL) NO. 3573 OF 1979
494
From the judgment and order dated the 3rd January, 1979
of the Allahabad High Court in Civil Revision No. 3714 of
1978.
G.L.Sanghi, Mrs. A. Verma and D.N. Mishra for the
Appellant in CA. No. 1314 of 1978.
J.P. Goyal, S.Markandeya and C.K.Ratnaparkhi for the
Respondent in CA. 1314 of 1978.
A.K. Srivastava for the Appellant in CA. 1710/80.
R.B. Mehrotra for Respondent in CA. 1710/80.
Pramod Swarup and Mrs. S. Markandeya for the appellant
in CA. 2436 of 1980.
S.N. Kacker and K.K Gupta for the Respondent in CA.
2436 of 1980.
P.R.Mridul, Praveen Jain and K.B. Rohatgi for the
Petitioner in SLP (Civil) No. 3573 of 1979
R.H. Dhebar for the Respondent.
The Judgment of the Court was delivered by
MISRA J. The first two appeals by special leave and the
third by certificate and the special leave petition raise a
common question of law and, therefore, we propose to dispose
of them by a common judgment.
The pattern of facts in all these cases is similar. We,
therefore set out the facts of Civil Appeal No. 1314 of 1978
to bring out the point for consideration in these matters.
The appellant Om Prakash Gupta is a tenant of a shop on
a monthly rent of Rs. 150/-.The respondent-landlord filed a
suit for the eviction of the tenant on the ground that the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 4 of 7
U.P. Urban Buildings (Regulation of Letting, Rent and
Eviction) Act, 1972 (Act 13 of 1972 and hereinafter referred
to as ’the Act’) did not apply to the shop and the tenant
was liable to eviction. The Judge, Small Causes Court,
Mainpuri decreed the suit on the finding inter alia that the
construction of the shop in suit was completed in the year
1967 and
495
that ten years having not elapsed since then, the provisions
of the Act did not apply to the case. The defendant went up
in revision under section 25 of the Provincial Small Causes
Courts Act against the judgment and decree of the trial
Court but the same was substantially dismissed. The
defendant thereupon filed a revision under section 115 of
the Civil Procedure Code in the High Court which came up for
hearing before a learned Single Judge who remitted the
following issue to the trial court:
"On what date was the construction of the building
in dispute completed within the meaning of section 2
(2) of the U.P. Urban Buildings (Regulation of Letting,
Rent and Eviction) Act, 1972, and deemed to have been
completed as contemplated by Explanation I (a)
thereto."
The Judge Small Causes Court by his order dated 26th of
November 1977 returned the following finding:
"The construction of the disputed shop will be
deemed to have been completed on the date of the first
assessment i.e. 1.4.68 within the meaning of section 2
(2) of the U.P. Urban Buildings Act, 1972."
The finding returned by the trial court was sought to
be challenged on behalf of the tenant on the ground that the
date of occupation should be taken to be the date of
completion of the construction of the shop and not the date
of the first assessment. In Tilak Raj v. Sardar Devendra
Singh,(1) a learned Single Judge of the same High Court had
the occasion to consider section 2 (2) of the Act. He held:
"It is apparent from this provision that for
purposes of this Act, a building is to be deemed to be
constructed, if it is subject to assessment, on the
date with effect from which the first assessment is
made. It is immaterial whether the building was
constructed actually prior to that date or it had come
into occupation prior to that date. The law recognised
for the purposes of this Act, the date of assessment as
the date of the completion of the building. There is
thus no error in the judgment of the court below."
496
The learned Single Judge before whom the revision in
the instant case came up for hearing doubted the correctness
of the above decision. He, therefore, referred the case to a
Division Bench.
There is no dispute that the first assessment of the
shop took place on 1st of April, 1968. It is also not in
dispute that the shop in question was occupied by the
defendant on 16th of June, 1967, and prior to his occupation
the shop was in occupation of another tenant for about a
month and a half. The appellant sought the benefit of
section 39 of the Act on the ground that if the date of
occupation was taken to be the date of the completion of the
construction of the shop, then ten years having elapsed
during the pendency of the revision before the High Court,
the Act would be applicable. The Division Bench, however,
over-ruled the contention of the appellant and held that the
construction of the shop in question would be deemed to have
been completed on 1st of April 1968 and, therefore, the Act
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 5 of 7
would not be applicable to the building till the date of the
decision of the revision on March 23, 1968. The defendant
undaunted by the failure came to this Court to challenge the
judgment of the High Court.
Mr. G.L. Sanghi, senior counsel. appearing for the
appellant strongly contended that on a correct
interpretation of sub-section (2) of section 2, the Act
would be applicable to the shop in question. It would be
appropriate at this stage to extract sub-section (2) of
section 2 of the Act insofar as it is material for the
purposes of the case:
"Except as provided in sub-section (5) of section
12, sub-section (1-A) of section 21, sub-section (2) of
section 24, sections 24A, 24B, 24C or sub-section (3)
of section 29, nothing in this Act shall apply to a
building during a period of ten years from the date on
which its construction is completed:
Explanation I. For the purposes of this sub-
section:
(a) the construction of a building shall be
deemed to have been completed on the date on
which the completion thereof is reported to
or otherwise recorded by the local authority
having jurisdiction and in the case of a
building subject to assessment the date on
which the first assessment thereof
497
comes into effect, and where the said dates
are different, the earliest of the said
dates, and in the absence of any such report,
record or assessment, the date on which it is
actually occupied (not including occupation
merely for the purposes of supervising the
construction or guarding the building under
construction) for the first time :.."
The precise contention on behalf of the appellant is
that the exemption created by this sub-section does not
embrace buildings constructed prior to the enforcement of
the Act. In support of his contention, Mr. Sanghi, relied
upon Rattan Lal Shinghal v. Smt. Murti Devi.(1) The same
contention was raised by him in that case also and a
Division Bench of this Court accepted the contention and
held that Act 13 of 1972 was prospective and applied only to
buildings brought into being de novo after the Act came into
force. In that case there is no discussion except this bald
observation. This Court in a subsequent case Ram Saroop Rai
v. Lilavati(2) held to the contrary. It is on this account
that the present appeals were referred to a larger Bench.
There is no ambiguity in the language of sub-section (2) of
section 2 and in the absence of any ambiguity there is no
question of taking any external aid for the interpretation
of the sub-section. In plain words the sub-section
contemplates that the Act shall not apply to a building
during a period of ten years from the date on which its
construction is completed. It nowhere says that the building
should have been constructed after the enforcement of the
Act and to interpret it in the way the learned counsel for
the appellant seeks to interpret it, we would be adding
words to the sub-section, which is not permissible.
Primarily the language employed is the determining factor of
the intention of the legislature. The first and primary rule
of construction is that the intention of the legislature
must be found in the words used by the legislature itself.
The question of interpretation arises only when the language
is ambiguous and, therefore, capable of two interpretations.
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 6 of 7
In the present case the language of sub-section (2) of
section 2 of the Act is explicit and unambiguous and it is
not capable of two interpretations.
498
As a second limb to the first argument, it is contended
that the building will be deemed to have been constructed on
the date of occupation on 16th of June, 1967 and not on the
date of the first assessment, and that if this be so, the
appellant would be entitled to the benefit of section 39 of
the Act on the date when the revision came to be decided by
the High Court on 23rd of March, 1978. In order to
appreciate this argument it will be expedient to refer to
Explanation I to sub-section (2) of section 2 which has
already been extracted. Explanation I provides that the
building shall be deemed to have been completed on the date
on which completion thereof is reported to or otherwise
recorded by the local authorities having jurisdiction, and
in case of a building subject to assessment the date on
which the first assessment thereof comes into effect and
where the said dates are different, the earliest of the said
dates, and in the absence of any such report, record or
assessment, the date on which it is actually occupied for
the first time. A perusal of Explanation I makes it
abundantly clear that the date of occupation would be taken
to be the date of completion of the construction only when
there is no report or record of the completion of the
construction or no assessment, thereof. If there is an
assessment, as in the present case it is, it will be the
date of the first assessment which will be deemed to be the
date of completion of the construction and in that view of
the matter the building had not become more than ten years’
old on the date when the revision came to be decided by the
High Court, and therefore there was no question of giving
the benefit of section 39 of the Act to the appellant.
Further, in order to attract section 39 the suit must
be pending on the date of commencement of the Act which is
15th of July, 1972 but the suit giving rise to the present
appeal was filed on 23rd of March, 1974 long after the
commencement of the Act. There is yet another reason why
section 39 will have no application to the present case. In
view of sub-section (2) of section 2 of the Act the Act is
not applicable to a building which has not a standing of ten
years and if the Act itself was not applicable, it would be
absurd to say that section 39 thereof would be applicable.
Considered from any angle the Act has no application to the
present case and the appellant could not be given the
benefit of section 39. The suit has, therefore, been rightly
decreed by the courts below.
We find no force in either of the contentions raised by
Mr. Sanghi. The counsel for the appellants in the other
appeals and
499
the petitioner in the special leave petition, adopted the
arguments of Mr. Sanghi.
For the foregoing discussion the appeals and the
special leave petition are dismissed. There shall, however,
be no order as to costs.
We, however, direct that the order of eviction in each
case shall not be executed before 30th of June, 1982 on
condition that each of the appellants in the appeals and the
petitioner in the special leave petition files an
undertaking in this Court within four weeks from today to
the following effect:
1. that he will hand over vacant and peaceful
possession of the suit premises to the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 7 of 7
landlord-respondent on or before 30th of
June, 1982;
2. that he will pay to the respondent arrears of
rent, if any, within a month from today;
3. that he will pay to the respondent future
compensation for use and occupation of the
suit premises for each calendar month by the
10th of the succeeding month; and
4. that he will not induct any other person in
the suit premises as a sub-tenant or licensee
or in any other capacity whatsoever.
We further direct that in default of compliance with
any one or more of the conditions of the undertaking or if
the undertaking is not filed within the stipulated time, the
decree of eviction shall become executable forthwith.
N.V.K. Appeal dismissed.
500