LASHKARIA CONSTRUCTION PVT. LTD. AND ANR. vs. STATE OF MAHARASHTRA AND ANR.

Case Type: N/A

Date of Judgment: 03-12-2015

Preview image for LASHKARIA CONSTRUCTION PVT. LTD. AND ANR. vs. STATE OF MAHARASHTRA AND ANR.

Full Judgment Text


wp-741-2013


IN THE HIGH COURT OF JUDICATURE AT BOMBAY
ORDINARY ORIGINAL CIVIL JURISDICTION
WRIT PETITION  NO.741 OF 2013
1 Lashkaria Construction Pvt. Ltd. ]
a Private limited company incorporated ]
under the provisions of Companies Act, ]
1961, having its office at 102, Diamond ]
Apartment, Near Techweb Centre, New ]
Link Road, Jogeshwari (West), Mumbai. ]
2 Mr. Mohd. Hasam Yasin Lashkaria ]
Director of Lashkaria Construction Pvt. Ltd. ]
having his office at 102, Diamond ]
Apartment, Near Techweb Centre, New ]
Link Road, Jogeshwari (West), Mumbai. ]  .. Petitioners.
V/s.
1 State of Maharashtra ]
2 The Principal Secretary, Housing ]
Department, Gov. of Maharashtra, ]
having his office at Mantralaya, Mumbai. ]
3 Slum Rehabilitation Authority ]
an Authority, constituted under the  ]
provisions of Slum Act, having its  ]
office at Administrative Building,  ]
Prof. Anant Kanekar Marg,  ]
Bandra (E), Mumbai 400 051. ]  .. Respondents.
Mr. Arif Bookwala, Sr. Advocate with Mr. S. G. Surana for the Petitioner.
Mr. D. J. Khambatta, Advocate General with Mr. Milind More, Addl. G.P., 
for Respondent Nos. 1 and 2.
Mr. V. D. Patil, for Respondent No.3.
CORAM:  MOHIT S. SHAH, C.J.  &
      M.S.SANKLECHA,J.
          RESERVED ON:  9 JANUARY 2015.
PRONOUNCED ON :  12 MARCH 2015.
S.R.JOSHI 1 of 17
::: Uploaded on - 13/03/2015 ::: Downloaded on - 26/06/2024 07:30:45 :::

wp-741-2013

Per Court:­
This Petition under Article 226 of the Constitution of India 
challenges the order dated 24 April 2012 of the State Government.  The 
impugned order cancels the Circular dated 12 November 2010 issued by 
the Slum Rehabilitation Authority (SRA), State Government letter dated 5 
October 2010 being a direction under Section 3K(i) of the Maharashtra 
Slum Areas (Improvement, Clearance and Development) Act, 1971 (the 
Act) and Letter of Intent (LOI) dated 23 November 2010 issued by the 
Chief Executive Officer, Slum Rehabilitation Authority (SRA) issued in 
favour of the Petitioner.
2 Briefly, the facts leading to this Petition are as under:­
rd
(a) On 23  July, 2007, the State Government adopted a new housing
policy for township development within the State Maharashtra. The 
objective of the housing policy was to ensure re­development of
slums by adopting a cluster approach in a time bound manner with
a view to improve the health standards and  living conditions of the
slum dwellers.
th
(b)   In the light of the above policy, on 6  February, 2010, the Petitioner
submitted a proposal to the SRA for cluster development/ special
township development project under Section 3K of the Slum Act.
The SRA in turn, sought necessary directions from the Government
of  Maharashtra  under  Section  3K  of  the  Slum Act  apropos  the
proposal submitted by the Petitioner.  
(c) On 5 October 2010, the State Government accepted / approved
S.R.JOSHI 2 of 17
::: Uploaded on - 13/03/2015 ::: Downloaded on - 26/06/2024 07:30:45 :::

wp-741-2013

Petitioner's proposal for cluster development and issued directives
to the SRA under Section 3K of the Slum Act.
(d) On 16 October 2010, the SRA sought clarification from the State
Government   whether   the   consent   of   the   70%   of   the   slum
dwellers   should   be   obtained   sector­wise.   The   Government   of
Maharashtra by its communication dated 11 November 2010 inter
alia directed the SRA to exercise its discretion in deciding whether 
to obtain consent of 70% slum dwellers either sector­wise or for the 
land being developed as a whole. On 12 November 2010, the SRA 
issued circular No.119 inter alia, providing for obtaining consent of 
the slum dwellers sector­wise.
(e) On 22 November 2010, the SRA informed the Petitioner to pay land 
premium   of   Rs.349.44   Crores   being   25%   of   the   land   cost.
Consequent to the above, on 23 November 2010, the Petitioner paid 
a sum of Rs.52.42 Crores by way of part payment of the land
premium.
(f) Consequent to the above, the SRA issued LOI to the Petitioner on 23
November   2010   in   respect   of   its   proposal   for   cluster   re­
development on 5.13 lakh sq. mtrs of land in Village Malwani,  
Malad in Mumbai.
(g) On 7 May 2011, as directed by the State Government on 6 May
2011, the SRA cancelled LOI dated 23 November 2010 issued to the 
Petitioner without issuing any show cause notice. Being   aggrieved,
the Petitioner filed Writ Petition No.1230 of  2011 in this Court.
 
S.R.JOSHI 3 of 17
::: Uploaded on - 13/03/2015 ::: Downloaded on - 26/06/2024 07:30:45 :::

wp-741-2013

By an order dated 30 November 2011 passed in Writ Petition
No.1230 of 2010, the orders of the State Government dated 6 May
2011 and of the SRA dated 7 May 2011 were set aide.  However,
liberty was given to the State of Maharashtra to take appropriate
action if it so desires only after following the principles of natural
justice i.e. issue show cause notice to the Petitioner.
(h) Consequent to the above, on 10 February 2012 a show cause notice
was issued to the Petitioner, seeking to cancel the LOI dated 23
November 2010 and the circular No.119 dated 12 November 2011
issued   by   the   SRA.   The   Petitioners'   responded   to   the   notice.
However, by the impugned order dated 24 April 2012, show cause
notice was confirmed, resulting in cancellation of the LOI dated 23
November   2010   and   circular   No.119   dated   12   November   2010
issued by the SRA, as a consequence of directions dated 5 October 
2010 issued by the State Government, was also cancelled.
3 It is the Petitioner's contention that the issues arising in this 
Petition are no longer res integra in view of the  judgment of this Court in 
Writ Petition No.1165 of 2012 (M/s. Sterling Buildcon Pvt. Ltd. & another 
V/s. State of Maharashtra and Others) rendered on 24 September 2013. It 
is submitted that this Court in M/s. Sterling Buildcon (supra) had set 
 
aside an order dated 24 April 2012 passed by the State Government.  This 
resulted in Government directives dated 8 October 2010, Circular dated 
12 November 2010 of SRA and provisional LOI dated 7 December, 2010 
issued in favour of M/s. Sterling Buildcon (supra) being upheld. It is 
submitted that on the above ground alone, the Petition be allowed. 
S.R.JOSHI 4 of 17
::: Uploaded on - 13/03/2015 ::: Downloaded on - 26/06/2024 07:30:45 :::

wp-741-2013

4 This is not a  case where a common impugned order had been 
issued   in   case   of   M/s.   Sterling   Buildcon   (supra)   and   the   Petitioner. 
Although, the impugned orders are both dated 24 April 2012, they are in 
fact two different orders – one in case of the Petitioner and the other in 
case of M/s. Sterling Buildcon. In these circumstances, it may not be 
appropriate to apply the decision of this Court in M/s. Sterling Buildcon 
(supra) without comparing the facts in both the cases.
5 In support of its submission that the facts in its case are 
identical to the facts of M/s. Sterling Buildcon (supra), the Petitioner 
highlighted the following facts:­
(a) Both   the   Petitioner   and   M/s.   Sterling   Buildcon   had   submitted
similar   proposal   to   the   State   Government   and   SRA   for   cluster
development;
(b) The directives given by the State Government to the SRA under
Section 3K(i) of the Slum Act dated 5 October 2010 in respect of
the Petitioner and dated 8 October 2010 in respect of  M/s. Sterling
Buildcon  are similar;
(c) The circular No.119 dated 12 November 2010 issued by the SRA
was a general circular applicable to both i.e. M/s. Steling Buildcon
and the Petitioner;
(d) On the basis of the above, an LOI was issued by the SRA to the
Petitioner on 23 November 2010 and on 7 December 2010 to M/s. 
Sterling Buildcon;
(e) Thereafter,   show   cause   notices   were   issued   by   the   State
S.R.JOSHI 5 of 17
::: Uploaded on - 13/03/2015 ::: Downloaded on - 26/06/2024 07:30:45 :::

wp-741-2013

Government dated 10 February 2012  to the Petitioner and dated 
2 March 2012 to M/s. Sterling Buildcon. Both the notices were  
identical, calling upon the parties to show cause as to why LOI  
issued should not be cancelled and also why the Circular No.119
issued by the SRA should not be cancelled.  This was essentially on
the   ground   that   the   SRA   Circular   was   contrary   to   the   State
Government   directions   dated   5   October   2010   in   case   of   the
Petitioner and    dated 8  October  2010  in  case  of  M/s. Sterling
Buildcon ; and
(f) The impugned order dated 24 April 2012  by the State Government
on the show cause notice issued to the Petitioner was on the same
date i.e.  24 April 2012 when the order was passed in case of M/s. 
Sterling Buildcon. The impugned order canceling the LOI   dated
23 November, 2010 issued by the SRA, the Circular No.119 dated
12   November   2010   issued   by   the   SRA   as   well   as   the   State
Government letter dated 5 October 2010 in the case of Petitioner.
This impugned order is submitted, is identical to the order passed
in the case of M/s. Sterling Buildcon. 
In the above facts, it is contended that the order of this Court 
rendered on 24 September 2013 in case of M/s. Sterling Buildcon (supra) 
applies to the facts of the present case and the Petition be allowed.
6 The aforesaid submission is opposed by the State Government 
on the ground that there are fundamental differences in the facts in this 
Petition   from   that   existing   in   M/s.   Sterling   Buildcon.   The   State 
Government   pointed   out   the   following   distinguishing   features   in   the 
present case which would warrant the Petition not being entertained:­
S.R.JOSHI 6 of 17
::: Uploaded on - 13/03/2015 ::: Downloaded on - 26/06/2024 07:30:45 :::

wp-741-2013

(a) In       M/s.   Sterling     Buildcon,   the   Petitioner   had   obtained  
written consent of 3839 slum dwellers out of 7000 slum dwellers
covering   in   area   of   1,89,470.50   sq.   mtrs.     Further,   1470   slum
dwellers   had   shown   their   willingness   to   appoint   M/s.   Sterling
Buildcon (supra) for re­ development.  Thus, 71% of the 7000 slum 
dwellers had given their consent for re­development.  As against the 
above, the Petitioner have been able to obtain consent of only 1286
slum dwellers out of 17000 slum dwellers.  Although, the Petitioner
do claim that a further 1871 slum dwellers have  given   consent   to
the   Petitioner   being   the   developer,   no   evidence   of   the   same   is
forthcoming.  
(b) The ownership/ development rights over the land in case of the
Petitioner   is   with   Maharashtra   Housing   Area   &   Development
Authority (MHADA) and Municipal Corporation of Greater Mumbai. 
As   against   the   above,   M/s.   Sterling   Buildcon   has
ownership/development rights over almost 50% of the  land   which
is part of its cluster development ; 
(c) Consequent to the passing of the impugned order dated 24 April
2012, the Petitioner had accepted the amount of Rs.52.41 Crores
being the premium amount paid by it as a refund.   On the other
hand, in the case of M/s. Sterling Buildcon (supra), the refund of
land premium was not accepted by it and it continued to be  with
the SRA; and
(d) Further, the Petitioners have been changing  the time within which
the requisite consent of slum dwellers would be obtained from the
S.R.JOSHI 7 of 17
::: Uploaded on - 13/03/2015 ::: Downloaded on - 26/06/2024 07:30:45 :::

wp-741-2013

slum dwellers.  To begin with a few  weeks   time   on   6   February
2010 to obtain consent of the slum­dweller's society and thereafter 
to obtain consent of slum dwellers, a reasonable time is originally 
sought   during   adjudication   proceedings   which   is   thereafter  
extended to about 18 months in the  impugned order and about two 
years  before this Court.  This conduct   itself   dis­entitles   them   to
any relief in writ jurisdiction.
In view of the above, it is submitted that the facts in the 
present case are completely different from that existing in M/s. Sterling 
(supra) and in view of the above differences, it is clear that the Petitioner 
is not in a position to comply with the LOI dated 23 November 2010 and 
the directions dated 5 October 2010 passed under Section 3(k) of the 
Slum Act.  Therefore, the benefit of this Court's decision in M/s. Sterling 
Buildcon (supra) should not be extended to the Petitioner.
7 As  against  the  above,   it   was  contended  on  behalf  of  the 
Petitioner that the above distinctions as made out are of no consequence 
and it is submitted as under:­
(a) The Petitioner has obtained consent of about 30 to 35% of the
17000 slum dwellers.   In any case, the consent is required to be
filed/   submitted   after   Annexure   II   has   been   issued   by   the
Competent Authority as held in M/s. Sterling Buildcon (supra) by
the Court.  This stage has not yet been reached.  Therefore,  at this
stage, the aforesaid   distinction sought to be made in the facts is
immaterial;
(b) So far as ownership of land is concerned, it does not make any
S.R.JOSHI 8 of 17
::: Uploaded on - 13/03/2015 ::: Downloaded on - 26/06/2024 07:30:45 :::

wp-741-2013

difference to the requirement of obtaining  the consent of the slum
dwellers.  Thus, the distinction is of no consequence; and
(c) The refund of land premium of Rs.52.41 Crores was accepted by the
Petitioner as a consequence of the impugned order. However, the
Petitioners are ready to furnish an undertaking to pay the amounts
as directed   by this Court.   This taking of refund cannot be held
against the Petitioner as it is consequence of the impugned order.  It 
is the impugned order which is a subject matter of challenge before
this Court.  
8 It is not disputed that this Court in its decision rendered in 
M/s. Sterling Buildcon (supra) on 24 September 2013 while allowing the 
Petition had factored in the following distinguishing features pointed out 
by the State. In particular, at paragraph 47, it was observed as under:­
There is no dispute about the fact that the petitioner has 
already obtained consent of 3749 slum dwellers out of 7000 
slum dwellers in the slum spread over 1.89 lacs sq. mtrs., out of  
which for almost 88000 sq. mtrs. of land the petitioner has 
acquired   ownership/development   rights.   The   petitioner,   thus, 
has obtained consent of almost 55% of all the slum dwellers. 
Out of the remaining slum dwellers, about 1149 slum dwellers, 
are   such   who   have   already   expressed   their   willingness   and  
desire   for   redevelopment,   but   they   had   earlier   submitted 
proposals   through   other   developers,   which   proposals   have 
already been rejected by the SRA as far back in January 2012.  
Thus, more than 70% of the slum dwellers have expressed their  
readiness and willingness for redevelopment and are keen to 
obtain rehab tenements.   The petitioner was given LOI on 7 
December 2010 for providing not only 4900 rehab tenements 
to the eligible slum dwellers, each tenement admeasuring 269 
sq.ft. but similar tenements to about 1846   project affected  
persons. Both these rehab tenements  to  the  slum  dwellers and 
projected affected persons are to be provided by the petitioner 
S.R.JOSHI 9 of 17
::: Uploaded on - 13/03/2015 ::: Downloaded on - 26/06/2024 07:30:45 :::

wp-741-2013

free of cost. Besides the petitioner is to provide free of cost 
primary school building, secondary school building and college 
building, library, health center, fire station, police chowky, office 
buildings   and   Municipal   staff   quarters   to   Municipal  
Corporation and MHADA with built­up area of about 25,000 
sq. mtrs. besides providing roads, playgrounds and recreation 
areas over 48,000 sq. mtrs, of land.
Besides, the petitioner is going to pay amount of 
premium of about 92.91 crore approximately, out of which the 
petitioner has already paid amount of premium of about 13.94 
crore approximately being the first installment of 15% of the  
amount of premium as per the Government circular dated 2 
July 2010. The amount is still lying with the SRA   and the 
petitioner has not withdrawn the same, though offered by SRA 
under the impugned order dated 24 April 2012. It is in the 
background of the aforesaid facts that we have considered issues 
raised in the petition. 
Besides, also the fact that almost 50% of the land belonged to the 
Petitioner  ­ M/s. Sterling Buildcon and consequently, had a prior claim for 
slum redevelopment on the land belonging to it (see para 17 (i) of the 
judgment dated 24 September 2013 in M/s. Sterling Buildcon).   In the 
present facts, all the aforesaid  factors which weighed with the Court in 
allowing the Petition in M/s. Sterling Buildcon (supra) are not present. 
However, although the above factors were taken into consideration, we 
have to examine the law laid down in the above decision and whether the 
same is fact specific or generally applicable. 
9 Let us first consider the first objection – viz: the Petitioner 
does not have the requisite consent of the slum dwellers as possessed by 
the Petitioner in M/s. Sterling Buildcon (supra). The contention of the 
Petitioner that in any case, the occasion to submit the consent of the slum 
dwellers has not yet arisen, for the reason that it is only after annexure II 
S.R.JOSHI 10 of 17
::: Uploaded on - 13/03/2015 ::: Downloaded on - 26/06/2024 07:30:45 :::

wp-741-2013

has been issued by the competent authority would that occasion arise. 
This Court in M/s. Sterling Buildcon (supra) had negatived the contention 
of the State that the Petitioner is required to obtain consent of 70% of the 
eligible slum dwellers before obtaining annexure II and has observed in 
paragraphs 38 to 42 of judgment dated 24 September 2013 as under:­
38:­ The   contention   of   the   State   Government   that   the 
petitioner should have been required to obtain consent of 70% 
of the eligible  slum dwellers before obtaining annexure 2 flies 
in the face of the Government's own Directive dated 8 October 
2010, wherein the Government specifically directed as under:
“2.17:­  It will be mandatory for the developer 
M/s. Sterling Buildcon Pvt. Ltd. to obtain consent of 
70% eligible slum holders within a period of 1 year 
from the date of receipt of Annexure 2 for the present 
scheme at Mauje Borla, Tal. Chembur and to enter 
into individual agreements with eligible beneficiaries 
and to start the   work of the scheme failing which  
said project may be reviewed at Govt. level.”
(emphasis supplied)
39:­  It is necessary to note that at the hearing learned Advocate 
General proceeded on the basis of the aforesaid translation of  
clause 2.17 of the Government approval dated 8 October 2010, 
original of which is in Marathi. In fact, in the other matter 
raising somewhat similar controversy being Writ Petition 741 
of 2013, when a similar clause 2.17 came up for consideration, 
learned Advocate General objected to the translation furnished 
by that petitioner and the learned Advocate General submitted  
that the correct translation of clause 2.17   in the said writ  
petition is as under:
2.17  For SRA Scheme at at village Malwani 
M/s.Lashkaria  Construction Pvt.Ltd. is appointed 
developer in principle. It will be mandatory for the 
developer in the proposed scheme after the date of 
obtaining Annexure II within one year to obtain 
S.R.JOSHI 11 of 17
::: Uploaded on - 13/03/2015 ::: Downloaded on - 26/06/2024 07:30:45 :::

wp-741-2013

70%   individual   consent  of   the   eligible   slum 
dwellers and enter into individual agreements and 
accordingly commence work. If the developer fails 
to do so the Government will review the scheme at  
the State Government level.”
(emphasis supplied)
40:­  Hence on the question of alleged default on the part of the 
petitioner,   it   is   clear   that   the   time   limit   to   obtain   70% 
individual consent of eligible dwellers is one year from the date 
of obtaining Annexure 2 from the Competent Authority i.e. 
certification of Annexure 2 by the Competent Authority after  
the developer submits the draft Annexure 2, as provided in 
guidelines. This certification is admittedly not done even in 
respect   of   draft   Annexure   2   submitted   by   the   petitioner   in 
respect of 3489 slum dwellers even before the impugned order 
was passed. 
It is clarified that the finding that the consent of 70% of  
the eligible slum dwellers is required to be given within one  
year   from   the   date   of   certification   of   Annexure   2   by   the  
Competent   Authority   is   only   applicable   to   the   Township 
Development Scheme (and not to individual slum rehabilitation 
scheme) in view of special directives of the State Government 
under section 3K(1) of the Slum Act.
41:­  It is necessary to note that Clause 2.17 by itself does not 
prescribe   any   time   limit   for   the   petitioner   to   submit   draft 
Annexure   2   to   the   Competent   Authority.   Learned   Advocate 
General would however submit that merely because clause 2.17  
of the Government Directive does not prescribe any time limit, 
it does not mean that the draft Annexure 2 can be submitted at 
any point of time, but it must be submitted within reasonable  
time. 
42:­  Even after accepting the above submission, we cannot over 
look the fact that the provisional LOI was issued by SRA on 7  
December 2010 and even before expiry of six months, the State 
Government exparte cancelled the provisional LOI and all the 
approvals granted in favour of the petitioner. The petitioner, 
S.R.JOSHI 12 of 17
::: Uploaded on - 13/03/2015 ::: Downloaded on - 26/06/2024 07:30:45 :::

wp-741-2013

therefore, has not been given an opportunity to submit the draft 
Annexure 2  of eligible slum dwellers within reasonable time. 
There is considerable substance in the submission of the learned 
counsel for the petitioner. Once SRA cancelled the LOI on 7 May  
2011 and thereafter there has been litigation and subsequent 
order   dated   24   April   2012   of   the   State   Government,   the 
petitioner has not been able to obtain any further consent and 
therefore the petitioner needs to be given at least further six 
months time to submit the draft Annexure 2 of other slum 
dwellers, without obtaining their consent at this stage.”
Therefore, the failure of the Petitioner to obtain consent of 70% 
eligible slum dwellers or more at this stage could not result in cancellation 
of the LOI dated 23 November 2010, Circular dated 12 November 2010 
issued by the SRA and State Government letter dated 5 October 2010 as 
held in the impugned order. 
10 So far as the second distinction sought to be made by the 
State is concerned namely the ownership/ development rights over almost 
50% of the land belonged to the Petitioner in the case of M/s. Sterling 
Buildcon (supra) while this is not so in the present case. The ownership of 
land   and/or   development   rights   over   the   land   in   respect   of   a   slum 
rehabilitation   area   certainly   puts   the   party   who   owns   it   in   a   better 
position. This in view of the provisions of the Slum Act which provides 
that   the   owner   of   the   land   would   have   a   prior   claim   for   slum 
redevelopment of its land. This Court in M/s. Sterling Buildcon (supra) 
had taken a view that it may not be in the best interest of all to set the 
clock   back   as   the   Petitioner   therein   had   certainly   a   prior   claim   to 
redevelop in respect of over 50% of the land to be developed under 
cluster redevelopment. In this case, the Petitioner does not make any such 
claim. However, there is no requirement that for the purposes of cluster 
S.R.JOSHI 13 of 17
::: Uploaded on - 13/03/2015 ::: Downloaded on - 26/06/2024 07:30:45 :::

wp-741-2013

development, atleast 50% of the land must be owned by the Developer. 
This factor by itself cannot dis­entitle the Petitioner from participating in 
cluster development as there is no such requirement in the SRA Circular 
as well as the State Government directives dated 5 October 2010. 
11 However, it is submitted by the State Government that in any 
event the conduct of the Petitioners dis­entitles the Petitioner to any relief 
in these proceedings as set out herein below:
(a)  It is emphasized that the area of this Cluster Development is huge/
mamoth i.e. 5.13 lakh sq. mtr.  In  view of the decision of this Court
in  Awdesh Tiwari v/s. Chief Executive Officer 2006 (4) Mah. Law 
Journal 282  – once a developer submits a proposal then the person
concerned   has   a   monopoly   and   others   are   prevented   from
submitting proposal for redevelopment of the land in issue. Thus,
in such circumstances, it is expected of the applicant of the project
for cluster development to be candid  and  forthright. It is not   open
to  an  applicant to  make  loose statements and, thereafter go back 
on     the     same,   bringing     the   entire   project   to   peril   or
unreasonably delay it. In this case, the Petitioner on 6 February
2010   had   promised   to   produce   the   requisite   consent   of   the  
remaining slum dwellers­society within a few weeks. Thereafter,
during adjudication proceedings, the Petitioner originally sought a 
reasonable time to obtain the requisite consent of slum dwellers and 
thereafter stated that it would obtain the consent within 18 months 
while  before us the Petitioner states that it will obtain the consent 
of requisite slum dwellers within two years from the date of the  
order of this Court ; and
S.R.JOSHI 14 of 17
::: Uploaded on - 13/03/2015 ::: Downloaded on - 26/06/2024 07:30:45 :::

wp-741-2013

(b) The Petitioner has taken the refund of the premium paid by it on
passing of the impugned order, while the Petitioner in M/s. Sterling 
Buildcon (supra), had not accepted the refund of the land premium
which had been paid. It continued to be with SRA. This is the factor 
which   would   indicate   the   Petitioner   in   M/s.   Sterling   Buildcon
(supra) was involved in the project by not taking the refund while
challenging the order.  In this case, the Petitioner took the refund
immediately after the passing of the impugned order dated 24 April 
2012 and are   now taking the chance of getting the impugned  
orders quashed.
12 We find considerable substance in the aforesaid submissions 
made  by the learned Advocate General.  As per the settled position, writ 
jurisdiction   is   discretionary.   The   writ   remedy   is   an   extra   ordinary 
prerogative remedy which is not to be exercised by this Court merely 
because, the Petitioner has shown some illegality in the impugned order. 
In fact, the Supreme Court in  State of Maharashtra v/s. Prabhu 1994 
(2) SCC 481  in paragraph 4 has observed as under:­
4:­ Even   assuming   that   construction   placed   by   the   High 
Court   and   vehemently   defended   by   the   learned   Counsel   for 
respondent is correct should the High Court have interfered 
with   the   order   of   Government   in   exercise   of   its   equity  
jurisdiction.  The distinction between writs issued as a matter of 
right such as habeas corpus and those issued in exercise of 
discretion such as certiorari and mandamus are well known 
and explained in countless decisions given by   this Court and 
English Courts. It is  not necessary to recount them. The High 
Courts exercise control over Government functioning and ensure 
obedience of rules and law by enforcing proper, fair and just 
performance of duty. Where the Government or any authority 
passes an order which is contrary to rules or law it becomes  
amenable   to   correction   by   the   courts   in   exercise   of   writ 
jurisdiction.  But one of the principles inherent in it is that the 
S.R.JOSHI 15 of 17
::: Uploaded on - 13/03/2015 ::: Downloaded on - 26/06/2024 07:30:45 :::

wp-741-2013

exercise of power should be for the sake of  justice. One of the 
yardstick for it is if the quashing of the order results in greater 
harm   to   the   society   then   the   court   may   restrain   from 
exercising13 the power.”
The   project   in   hand   is   for   rehabilitation   of   about   17000   slum 
dwellers. The Petitioner has not been stead fast with regard to the time 
required for obtaining requisite consent of slum dwellers.  Initially, it was 
a reasonable time and thereafter within 18 months during adjudication 
proceedings and now at the hearing before us that the Petitioner states 
that it would require 2 years time to obtain consent of 70%  of the slum 
dwellers. Soon after passing of the impugned order on 24 April 2012, the 
Petitioner also took the refund of the deposit of Rs.52.41 Crores. Thus, 
without putting the deposit amount of Rs.52.41 Crores at stake, unlike 
M/s. Sterling Buildcon (supra), as indicted above, the Petitioner has kept 
cluster development of the lands as large as 5.13 lakh sq. mtrs in limbo. 
Without having  made  any  progress  in implementation  of  the  project, 
without   anything   at   stake   and   without   any   equity   in   its   favour   the 
Petitioner wants restoration of all the orders, conferring on the Petitioner 
the monopoly to redevelop 5.13 lakh sq. mtrs. of land with no ownership 
rights over the same (albeit with liability to rehabilitate 17,000 slum 
dwellers on the site). In such extra ordinary circumstances and in these 
peculiar   facts,   we   will   not   exercise   our   extra   ordinary   discretionary 
jurisdiction in favour of the Petitioner.  
13 For the aforesaid reasons, the   Petition is dismissed . Since 
the Writ Petition is disposed of, Chamber Summons No.109 of 2013 for 
intervention does not survive and the same is disposed of as infructuous.
(M.S.SANKLECHA,J.) CHIEF JUSTICE
S.R.JOSHI 16 of 17
::: Uploaded on - 13/03/2015 ::: Downloaded on - 26/06/2024 07:30:45 :::

wp-741-2013

After the judgment is pronounced, the learned Counsel for 
the Petitioners pray that  the  ad­interim  stay  granted  by  order  dated 
24 April 2013 of this Court be continued for twelve weeks to enable the 
Petitioners to move the Apex Court in accordance with law.  The learned 
Counsel   for   the   Respondents   opposes   the   same.   In   the   facts   and 
circumstances, since the ad­interim relief has been operative since 24 
April 2013, the same shall be continued for a period of eight weeks from 
today. 
CHIEF JUSTICE
(M.S.SANKLECHA,J.)
    
S.R.JOSHI 17 of 17
::: Uploaded on - 13/03/2015 ::: Downloaded on - 26/06/2024 07:30:45 :::