Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 14
PETITIONER:
GORDHANDAS PURSHOTTAMDAS SONAWALA AND ANOTHER
Vs.
RESPONDENT:
THE EASTERN COTTON COMPANY
DATE OF JUDGMENT:
31/03/1958
BENCH:
BHAGWATI, NATWARLAL H.
BENCH:
BHAGWATI, NATWARLAL H.
KAPUR, J.L.
GAJENDRAGADKAR, P.B.
CITATION:
1958 AIR 713 1959 SCR 346
ACT:
Cotton Contracts-Cotton Association-Statute Providing for
cotton contracts to be in accordance with the by-laws of the
Association -By-laws prescribing Forms of Contract
Substantial compliance with Form Validity of the contracts-
Bombay Cotton Contracts Act,1932 (Bom. IV Of 1932), s.
8(1).
HEADNOTE:
Sub-section (1) of s. 8 of the Bombay Cotton Contracts Act,
1932, provides: " Save as hereinafter provided in this Act,
any contract .... which is entered into after the date on
which this Act comes into operation and which is not in
accordance with the by-laws of any recognized cotton
association shall be void ".
In respect of the transactions in cotton entered into
between the parties, the appellants had to pay the
respondents a sum of money for failure to give delivery of
the cotton bales under the
347
contracts, but the payment was made without prejudice to the
rights and contentions of the parties. Subsequently, the
appellants sued the respondents for recovery of the amount
on the footing that the contracts were void under s. 8(1) of
the Bombay Cotton Contracts Act, 1932, as being not in
accordance with the by-laws of the East India Cotton
Association Ltd., of which both the -parties were members,
in as much as the contract notes did not company with the
terms contained in the official contract form provided by
the by-laws of Association, by reason of the omission to
fill in the blanks relating to measurements and difference
above or below the settlement rate. The respondents
contended that the relevant provisions contained in the
official contract form bad either become obsolete or were
suspended at all material times. The evidence showed that
according to the practice of the trade the parties to the
contract were not tied down to a literal compliance with the
terms contained in the official contract form but were
required to act according to the position as it then
obtained and that it was sufficient if they substantially
complied with the requirements of the contract form :
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 14
Held, that in the circumstances of the case the official
contract form had to be filled in so far as it was
practicable and that the omission to fill in the blanks in
the contract notes did not spell any departure from an
essential or a characteristic part of the contract form;
consequently, the legal effect of the contracts was not in
any manner changed so as to render the contracts void as not
being in accordance with the by-laws of the Association,
within the meaning of s. 8 of the Bombay Cotton Contracts
Act, 1932.
Radhakisson Gopikisson v. Balmukund Ramchandra, (1932) L.
R. 60 I. A. 63, relied on.
JUDGMENT:
CIVIL APPELLATE JURISDICTION: Civil Appeal No. 398 of 1956.
Appeal from the judgment and order dated March 19, 1956, of
the Bombay High Court in Appeal No. 45 of 1955, arising out
of the judgment and order dated March 23, 1956, of the said
High Court in its Ordinary Original Civil. Jurisdiction in
Suit No. 468 of 1951.
M. C. Setalvad, Attorney-General for India, N. P.
Nathwani, J. B. Dadachanji, S. N. Andley and Rameshwar Nath,
for the appellants.
Purshottam Tricumdas, K. K. Desai and I. N. Shroff, for the
respondents.
1958. March 31. The Judgment of the Court was delivered by
348
BHAGWATI J.-This appeal with a certificate of fitness is
directed against the judgment and decree passed by the High
Court,of Judicature at Bombay in appeal from its ordinary
Original Civil Jurisdiction confirming, though on different
grounds, the judgment and decree passed by a single Judge of
that High Court in Suit No. 468 of 1951 instituted by the
appellants (Original Plaintiffs) to recover from the respon-
dents (Original Defendants) a sum of Rs. 1,80,099-8-0 with
interest and costs.
Since the year 1932 the first appellant has been a member of
the East India Cotton Association Ltd., (hereinafter
referred to as " the Association " ) as the sole ’proprietor
of the firm of Messrs. Narrondass Manordass There in after
referred to as "the member firm"). The first appellant
along with other partners carried on business in partnership
in Bombay inter alia as Cotton Merchants and Commission
Agents in the name and style of Messrs. Narrondass
Manordass, the 2nd appellant (hereinafter referred to as "
the partnership firm "). The respondents are a partnership
firm and also a member of the Association.
Between September 23, 1947, and December 10, 1947, the
member firm sold to the respondents 2,300 bales of Broach
Vijay Fine 3/4" Navsari and/or Bardoli 7/8" Cotton for
March/April 1948 Delivery. Out of these 2,300 bales, 1,100
bales were disposed of by means of " Havalas " and in
respect of the remaining 1,200 bales, there were cross-
contracts. In the result when the time for " Delivery "
arrived, sales in respect of 700 bales remained outstanding
and the member firm was liable to give delivery of 700 bales
to the respondents. As however, the member firm failed to
give delivery of the said 700 bales to the respondents,
under the relevant by-laws of the Association, the
respondents " Invoiced Back " these 700 bales to the member
firm on May 3, 1948, and as a result of this " Invoicing
Back " a sum of Rs. 1,07,530-8-0 became due and payable by
the member firm to the respondents and with regard to the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 14
transactions of all the 2,300 bales taken together an
aggregate sum of Rs. 1,79,749-8-0 became due and payable by
the
349
member firm to the respondents. In respect of this sum of
Rs. 1,79,749-8-0, the respondents sent to the member firm
eight separate " Debit Notes " in respect of varying amounts
and finally a consolidated debit note for Rs. 1,79,749-8-0.
It appears that the contract notes in respect of these
transactions had been signed by one Ramanlal Nagindas who
had been employed as a salesman in the Ready Cotton
Department of the partnership firm. The appellants
contended that the said Ramanlal Nagindas had no authority
to enter into the said transactions or to sign contract
notes in respect thereof on behalf of the appellants and
also that the said contracts were not in accordance with the
by-laws of the Association and they therefore denied their
liability in respect of the said transactions. The
partnership firm, however, as the beneficiary under the said
contracts decided to pay the amounts claimed by the respon-
dents without prejudice to the rights and contentions of
both the parties. On May 7, 1948, the said sum of Rs.
1,79,748-8-0 was paid by the partnership firm and was
received by the respondents in terms of the letter addressed
by the respondents on the said date:-
"The payment is made by you and accepted by us without
prejudice to the rights and contentions of both the parties
in respect thereof. "
A further sum of Rs. 350 being the amount of penalty for the
alleged failure to tender the aforesaid 700 bales of the
said contracts of Broach/Vijay March/April 1948 Delivery,
was also paid by the partnership firm to the respondents on
June 6, 1948, without prejudice to their aforesaid
contentions.
The said Ramanlal Nagindas had entered into similar
transactions with several other merchants and some of them
claimed arbitration under by-law 38-A of the Association.
Petitions were thereupon filed by the member firm in the
High Court at Bombay being Petitions Nos. A/51, A/52, A/55
and A/56 of 1949 under s. 33 of the Indian Arbitration Act
inter alia for a declaration that there existed no valid and
enforceable arbitration agreement between the parties. Mr.
Justice Shah delivered judgment in the said petitions
350
on August 20, 1950, holding inter alia that the said
contracts were void as being not in accordance with the by-
laws of the Association and allowed those petitions. The
respondents to the petitions thereupon filed petitions under
Art. 136 of the Constitution for special leave to appeal to
this Court against the said judgment of Mr. Justice Shah.
These petitions were, however, dismissed by this Court on or
about April 6, 1951.
The appellants thereafter by their attorney’s letter dated
May 2, 1951, called upon the respondents to return the said
sum of I-Is. 1,80,099-8-0 (being the aggregate of the said
two sums of Rs. 1,79,749-8-0 and Rs. 350.) with interest
thereon at the rate of 6 per cent. per annum. The
respondents failed and neglected to pay to the appellants
the said sum or any part thereof with the result that on May
7, 1951, the appellants filed the suit against the
respondents for repayment to them of the said sum with
interest and costs.
In the plaint as filed the appellants averred that the said
contracts were void under the Bombay Cotton Contracts Act,
1932, as being not in accordance with the by-laws of the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 4 of 14
Association inter alia in the following respects: (1) The
contract notes produced by the respondents omitted to state
the difference of Rs......... above or below the settlement
rate of hedge contracts for the purpose of periodical
settlements as required by by-laws 139 and 141; and (2) no
provision was made in any of the aforesaid contract notes
with regard to the measurement of bales as required by the
official form for delivery contracts prescribed in bylaw 80.
The respondents in their written statement contended that
there was no by-law which required any person to agree upon
any difference above or below the settlement rate of hedge
contracts for the purpose of periodical settlements and to
state the same. They further contended that the relative
provisions contained in the official contract form had
become obsolete as at all material times there were no hedge
contracts bearing different numbers and in practice the said
contracts were not put through periodical settlements.
351
They also contended that at all material times there was no
by law which required any person to agree upon any specific
measurements in respect of the bales agreed to be purchased
inasmuch as the operation of by-law 101 in regard thereto
had been suspended by the Board since November 30, 1942.
After the suit reached hearing the appellants amended the
plaint by averring that by reason of the said payments
having been made by them and accepted by the respondents
without prejudice to the rights and contentions of both the
parties there was an implied agreement between them that in
the event of the appellant’s establishing that they were not
bound to pay the said sums to the respondents and that the
respondents were not entitled to the payment thereof the
respondents would repay or return the same to the
appellants. This plea was traversed by the respondents in
the supplemental written statement which they filed.
The learned trial Judge followed the judgment of Mr. Justice
Shah and held that the omission of the clause regarding
measurement in the contract notes did not alter the
character or legal effect of the contracts. He similarly
held that the omission of any reference in the contracts to
the amount of difference above or below the settlement rate
of hedge contracts in the last term of the contract notes
rendered the contracts void. He however was of the opinion
that there was no implied agreement between the parties of
the nature alleged by the appellants and that the payment
made by appellants to the respondents was voluntary and
therefore dismissed the appellants’ suit with costs.
The appellants preferred ail, appeal against this decision
and the appellate Court dismissed the appeal and confirmed
the decree passed by the learned trial Judge, though on
different grounds. The appellate Court agreed with the
learned trial Judge that the omission of the term regarding
measurement in the contract notes did not affect the
character or legal affect of the contracts. In regard to
the omission to fill-up the difference above or below the
settlement rate
352
fixed for the hedge contracts in the last clause of the
contract notes, however, the appellate Court was of the
opinion that there was no obligation on the parties to agree
to add or deduct the difference above or below the
settlement rate as contended by the appellants. If the
parties did agree then the contract form provided that the
agreement should be set out therein. If, however, they did
not agree then the first part of cl. (2) of by law 141 would
come into play and the settlement of the delivery contract
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 5 of 14
would go through on the basis of the settlement rate of the
hedge contract. The omission to fill-up the difference was
thus of no consequence and did not invalidate the contracts.
The appellate Court also differed from the trial Judge on
the question of the implied agreement and held that if the
appellants succeeded in establishing that the respondents
were not entitled to receive the payments the respondents
were bound to repay the sums paid by the appellants to them.
In view, however, of the conclusion reached that the
contracts were not void, the appellate Court dismissed the
appeal.
The -provisions of the Bombay Cotton Contracts Act, 1932
(Bom. IV of 1932) and the by-laws of the Association which
fall to be considered by us may now be referred to:-
Section 8(1) (Bombay Cotton Contracts Act, 1932):
" Save as hereinafter provided in this Act, any contract
(whether either party thereto is a member of a recognized
cotton association or not) which is entered into after the
date on which this Act comes into operation and which is not
in accordance with the by-laws of any recognized cotton
association shall be void."
By-law 80 of the Association:-
" Forward contracts between members how made: -Delivery
Contracts between members shall be made on the official form
given in the Appendix. Hedge contracts between members may
be verbal or in writing and when in writing shall be in one
or other of the forms given in the Appendix. Whether verbal
or written all contracts shall be subject to the by-laws,
353
provided that in the case of Delivery Contracts By-laws 149
to 163 inclusive shall not apply.
The specimen of the official contracts form in triplicate as
used in 1947-48 (Vide Exhibit " D ") contained the following
terms amongst others:-
No. Contract Note
From Brokers
To Messrs.......................
We have this day bought by your order and for your account
subject to the By-laws of the East India Cotton Association
Ltd. From Messrs......(...) bales of Cotton at Rs.. per
candy, delivered in Bombay in full pressed bales.
Measurement... tons/per 100 bales.
(For delivery contracts only). for the purpose of periodical
settlement of this contract we agree to a difference of
Rs... above/below the settlement rate of hedge contract No.
Remarks... Bombay...194
No. Contract Note
From Brokers
To Messrs............................
We have this day sold by your order and for your account
subject to the By laws of the East India Cotton Association
Ltd. To Messrs...(..) bales of... Cotton... at Rs.. per
candy, delivered in Bombay in full pressed bales.
Measurement... tons/per 100 bales.
(For delivery contracts only). For the purpose of
periodical settlement of this contract we agree to a differ-
ence of Rs ... above/below the settlement rate of hedge con-
tract No.
Remarks ... Bombay ... 194
The contract notes which are rendered between the member
firm and the respondents, however, contained no term as to
measurement and so far as the last clause was concerned the
blanks in regard to the difference of Rs...above or below
the settlement rate of hedge contract No.... were not filled
in.
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 6 of 14
The relevant by-laws in connection with these two terms
contained in the official contract form were by law 101, and
by laws 139 and 141:--
By-law: 101.
Claims for excess measurement.
In respect of all Forward Contracts, measurement
45
354
shall approximate 13-1/2 tons per 50 bales provided that in
respect of Forward Contracts, other than Hedge Contracts,
the parties may agree upon any other measurement. In all
Forward Contracts, for any port the rate or rates of freight
for any excess measurement over 13-1/2 tons per 50 bales
shall be fixed by the Board from time to time and unless
otherwise fixed the rate for such excess for all ports shall
be Rs. 15 per ton in respect of each lot of 50 bales
measuring more than 13-1/2 tons but not more than 14-1/2
tons and in respect of each lot of 50 bales measuring more
than 14-1/2 tons Rs. 35 per ton for any excess over 13-1/2
tons.
No allowance for excess measurement shall be payable by the
seller:-
(a) unless the buyer has given to the seller reasonable
notice fixing an appointment for measurement, or
(b) unless the buyer submits a claim to the seller within 6
weeks after the complete lot has been weighed over.
The Board shall have power from time to time and at any time
to suspend the operation of this Bylaw as regards
measurements.
By-law: 139.
"Settlement Days. All Delivery Contracts other than those
excepted under By-laws 136 and Hedge Contracts shall be
subject to periodical settlements through the Clearing House
and in every case the parties to the contract must be
members of the Association. Settlements of differences due
on open contracts and of other liabilities to be settled
through the Clearing House shall be made once weekly on days
which shall be fixed by the Board and notified in a calendar
to be published annually.
The day on which Balance Sheets are required to be submitted
to the Clearing House shall be known as Settlement Day."
By-law: 141.
Settlement rates.-(1) For the purpose of these settlements,
settlement prices for all positions of the Hedge Contract
shall be fixed by the Board on or about the third working
day immediately preceding Settlement
355
Day. The prices so fixed shall be I P. M. prices on the day
of fixation.
(2)In the case of Delivery Contracts, the settlement price
of the Hedge Contract shall be the basis for the periodical
settlement. Such allowances as shall be agreed upon by the
parties in their contract to cover any difference, between
the cotton contracted -for and the cotton which is the basis
of the Hedge Contract shall be added to or deducted from the
said settlement price. In the case of contracts for
descriptions which are not tenderable against the Hedge
Contract the parties may either agree in their contract upon
an allowance above or below the Hedge Contract for the
purpose of their periodical settlement or may apply to the
Board to fix settlement rates.
...........................................................
The only question for our determination in this appeal is
whether the contracts between the parties were not in
accordance with the by-laws of the Association and therefore
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 7 of 14
void. There is no doubt that all the contracts were subject
to the by-laws of the Association. The question still
remains whether they were in accordance with the by-laws
because if they were not in accordance with those by-laws
they would be void. The expression " not in accordance with
" has been the subject of judicial interpretation in
Radhakisson Gopikisson v. Balmukund Ramchandra (1). Their
Lordships of the Privy Council there held that the form
prescribed was not a stereotyped one and that literal
compliance with it was not essential. The only thing
required was that the contract notes must contain all the
terms and conditions set out in the form in order to comply
with it. Their Lordships were of the opinion that
substantial compliance with the form would be enough and if
such sufficient compliance with the by-laws was found in a
particular case that would save the contracts from being
declared void as not being in accordance with the by-laws.
It was, however, urged on behalf of the appellants that by-
law 80 prescribes the form in which the contracts were to be
entered into and all the terms and
(1) (1932) L.R. 60 I.A. 63.
356
conditions incorporated in the official contract form had to
be strictly complied with, that the omission of the term as
to measurement as also the omission to fill in the blanks in
regard to difference of Rs...... above or below the
settlement rate of hedge contract No. ..................
were such departures from the form prescribed as would
render the contracts void because it could not be then said
that there was sufficient compliance with the statutory
form. Reliance was placed in support of this contention on
Burchell v. Thompson (1), Ex-parte Stanford, In re Barber
(2), Thomas v. Kelly (3) and Parsons v. Brand & Cols v.
Dickson (4). The principle emerging from these decisions
was enunciated to be that if the document executed by and
between the parties departed from a characteristic part of
the form prescribed or made a difference in the legal effect
of the instrument, it would not be in accordance with the
form and would therefore be void. It would all depend upon
the materiality of the -particular term which is
incorporated in the form. If the non-compliance with the
requirements of the form were such as to make the document
something else by reason of a characteristic part of the
form not being followed or the document would lose some
legal effect which it would have had if the proper words had
been inserted therein, it cannot be said that there is sub-
stantial compliance with the statutory form.
Considering the term as to measurement in this light, it
appears that the same had its basis in the requirements of
the trade in regard to the pressing of the bales. The bales
which were the subject-matter of these forward delivery
contracts were either meant for transport within the country
or export outside the country. The bales were to be fully
pressed so as to occupy the minimum space either in
transport by rail or by steamer and initially they were
bound with hoops. The baling hoops were however difficult
to obtain from Japan and therefore the bales came to be
bound with ropes made of cotton, jute coir and hemp. The
bales thus bound otherwise than with hoops
(1) [1920] 2 K. B. 80.
(3) (1888) 13 App. Cas. 506.(2) (1886) 17 Q.B.D. 259.
(4) (1890) 25 Q.B.D. 110,
357
occupied more space and difficulties were encountered by the
merchants because of their being obliged to pay -extra
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 8 of 14
insurance and freight charges in respect of such bales. Not
only did the railways charge more for the transport of such
bales, the shipping companies also did so and the insurance
companies charged higher rates for insurance because the
bales were not pressed in a manner which would minimise the
risks of insurance. All these factors brought about a
situation creating difficulties between the purchasers and
the sellers of cotton and these difficulties had to be
resolved by the Association. by law 101 had proceeded on the
basis of cotton bales being bound with hoops, the
approximate measurement in tons as agreed and understood in
the trade being, 13-1/2 tons per 50 bales. That was the
standard measurement. It was open however to the parties to
agree upon any other measurement. If any measurement other
than the standard measurement was agreed to, an adjustment
had to be made by reason of such difference in measurement
and by-law 101 provided that certain amount therein
specified had got to be paid by the seller to the purchaser
as and by way of allowance for such excess measurement.
Towards October, 1942, the situation in regard to the baling
hoops deteriorated so much that it was thought desirable
that bales bound with ropes should be permitted to be
tendered under the by-laws of the Association and that the
operation of by-law 101 as regards measurements should be
suspended. There were heavy fluctuations in the prices of
the materials permitted to be used, and it was therefore
thought advisable to fix certain allowances from time to
time or before the beginning of the delivery periods taking
into consideration the extra insurance and freight charges,
if any, in respect of such bales. A sub-committee appointed
by the Association made a report in this behalf on October
29, 1942, and on November 20 1942, the Board of Directors of
the Association passed a resolution approving the
recommendations of the subcommittee with this modification
that the allowance to be prescribed in the price of bales
bound with ropes
358
as against the price of bales bound with hoops as provided
in by-laws 96 and 119, be fixed before the commencement of
the season and not be altered from time to time. The Board
of Directors issued a notice on November 30, 1942,
suspending the operation of bylaw 101 as regards the
measurement until further notice.
The position as it obtained at the time when the suit
contracts were entered into was that by-law 101 as regards
measurement had been suspended and there was no necessity so
far as the by-laws went to make any mention in the contracts
in regard to the same. If the claim for excess measurement
had not to be entertained, it was not at all necessary to
mention the measurement in the contract forms and there
would be substantial compliance with the contract form, even
though no measurement was mentioned therein, the very basis
for the mention of such measurement having disappeared.
It was, however, urged on behalf of the appellants that
measurement was an essential part of the description of the
goods sold and the suspension of by-law 101 made it all the
more necessary that the measurement should be specified in
the contract form itself. The standard measurement which
had been mentioned in by-law 101 had disappeared and it
would therefore be necessary to mention in the contract form
what was the measurement on the basis of which the price of
the contract had been fixed by and between the parties. If
the bales actually tendered measured more in weight than
what was actually agreed upon, the purchaser would be
entitled to obtain from the seller an allowance for such
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 9 of 14
excess measurement and that was the reason why it was
necessary after the suspension of by-law 101 to mention the
agreed measurement between the parties.
This argument however ignores the fact that simultaneously
with the suspension of the operation of the by-law 101, by-
laws 96 and 119 which referred to forward and hedge
contracts respectively were altered and provision was made
therein to incorporate measures consequent upon the tender
of bales bound with ropes
359
in place of bales bound with hoops. The consequences of
such tenders were worked out in the by-laws as thus amended
and allowances in the price of bales bound with ropes as
against the price of bales bound with hoops were also
provided for. These allowances were in accordance with the
resolution of the Board dated November 20, 1942, to be fixed
before the commencement of the season and if such allowances
were provided for there was nothing further to be done in
regard to the difference in measurement, if any. If the
situation which obtained after November 20, 1942, provided
for a tender of bales bound with ropes instead of bales
bound with hoops in fulfilment of the contracts entered into
between the parties, that was well known to all the members
of the Association and it was open to them while fixing the
prices themselves to take count of the extra charges for
insurance and freight which would be payable by the
purchaser in the event of bales bound with ropes being
tendered instead of bales bound with hoops. It, therefore,
follows that the omission to mention the measurements in the
contract notes did not render the contracts not in
accordance with the by-laws. There was no such by-law in
operation at the time and even otherwise there was no need
whatever to incorporate in the contract notes any term as to
measurement. It could not therefore be said that there was
any departure from an essential or a characteristic part of
the contract form or that the legal effect of the contracts
was changed so as to invalidate the same.
When we come to the term in regard to the differences of
Rs............... above or below the settlement rate of
hedge contract No............... we find that that had
reference to periodical settlements of contracts through the
clearing house. In accordance with bylaw 139 all delivery
contracts other than those excepted under by-law 136 and
hedge contracts were subject to periodical settlements
through the Clearing House which settlements had to be made
once weekly on days fixed by the Board. If the contracts
had got to go through the clearing house in this manner it
was necessary also that settlement rates should be fixed
360
and by-law 141(1) provided that settlement prices for all
positions of the hedge contract should be fixed by the
Board. The settlement prices thus fixed were to be taken as
the basis for the periodical settlement of delivery
contracts and it was further provided in bylaw 141(2) that
such allowance as shall be agreed upon by the parties in
their contracts to cover any difference between the cotton
contracted for and the cotton which was the basis of the
hedge contract shall be added to or deducted from the said
settlement prices. This was the basis of the provision
contained in the relevant term of the contract form. In the
case of contracts for descriptions not renderable against
the hedge contract it was open to the parties either to
agree upon an allowance above or below the hedge contract or
they would make an application to the Board to fix the
settlement rates. Whenever there was an agreement in this
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 10 of 14
behalf the parties were to mention the difference thus
agreed into the contract form and the periodical settlements
of delivery contracts were to be effected on that basis.
The question arises as to whether the parties were bound to
enter into any such agreement at the time they entered into
the contracts. It was contended on behalf of the appellants
that such an agreement was necessary because it would
otherwise involve the parties into payment of large sums of
money on the settlement day next after the day of the
contract. The hedge contracts appertained to cotton of the
lowest average and if the quality of cotton which was the
subject-matter of the contract between the parties was, as
was usual, of a higher variety, it would involve the payment
of large amounts by way of differences on the next
settlement day, which certainly would not be within the
contemplation of the contracting parties. If that was so,
the parties would agree to a difference between the rates of
the cotton contracted for and the cotton which was the basis
of the hedge contract and this difference above or below
would serve to minimize the incidence of such payment on the
next settlement day. It was, therefore, submitted that it
was incumbent on the parties when entering into a contract
to
361
fill-in this term as to differences. If they agreed upon
such differences the blank had to be filled-in accordingly;
but even though they did not agree upon any such
differences, it was necessary for them to mention in the
contract form that the difference above or below the rate of
the hedge contract agreed upon by them was nil.
It was contended on the other hand on behalf of the
respondent that there was no obligation on the parties
entering into the contract to fill in that term. If they
agreed upon the difference all well and good but if they did
not agree upon the difference, the first part of by-law
141(2) stepped in and the consequences had to be worked out
as if there was no agreement and the differences had to be
paid on the settlement day next ensuing on the basis of the
difference between the contract rates and rates of hedge
contract, even though it may involve a payment of a
substantial amount all at once. According to this
submission, in the case of contracts for descriptions
tenderable againt the hedge contract two positions arose:
viz., (1) parties to the contract may not agree to any
difference in which case it would not be necessary to fill
in that term in the contract note or (2) they may agree to
the difference in which event the difference would be
mentioned in the contract note. In the case of contracts
for descriptions which were not renderable against the hedge
contract three positions would arise, viz., (1) the parties
may not agree upon any difference in which event it would
not be necessary to fill in the term as to difference in the
contract notes; (2) the parties may agree upon such
difference and that would have to be mentioned in the
contract notes or (3) the parties could apply to the Board
to fix the settlement rates.
It appears that the contention urged on behalf of the
appellants would be more in consonance with business idea,-,
because no business man would think of immediately forking
out a large sum of money on the next ensuing settlement day.
It would be tantamount to paying the price of the goods or a
substantial part thereof long before the due date of
delivery ever
46
362
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 11 of 14
arrived. While recognizing the necessity of arriving at an
agreement in this manner we are, however, not impressed with
the argument that in the event of no such agreement as to
the difference having been reached it would even so be
necessary to mention in the contract note that the
difference agreed upon was nil. When the parties entered
into the transactions all the terms and conditions of the
contract would certainly be negotiated and agreed upon
between them. It would be open to them, in view of the by-
laws above referred to, to agree upon the difference above
or below the settlement rate of hedge contracts for the
purpose of facilitating the settlements through the clearing
house. But if no such difference above or below the
settlement rate of hedge contracts were agreed upon between
the parties, it would not necessarily follow that the word
nil had got to be mentioned in the contract notes. The very
fact that no difference above or below the settlement rate
of hedge contracts was agreed upon in the manner
contemplated would be enough to spell out an agreement that
no such difference was to be computed in arriving at the
settlement rates in respect of these contracts. If that was
the true position it would be Superfluous to write the word
" nil " as contended for by the appellants and the
consequences, of such non mention would be the same as if
the difference agreed upon was nil. By-law 141 (2) could
then be worked out without any difficulty and the settlement
rates in the case of delivery contracts would be fixed on
the basis of the settlement price of the hedge contracts
taking into account the facts that there was either no
difference which was agreed upon or that the difference
agreed upon was a specific one which was mentioned in the
contract notes.
It was however pointed out on behalf of the respondents that
the official contract form contained the expression "
above/below the settlement rate of hedge contract
No......... Even though this may have been in consonance
with the position as it obtained when the hedge contracts of
five different varieties were in vogue, involving the
specification of hedge contracts as Nos. I to 5, that
position substantially chanced
363
when hedge contracts of these 5 varieties were abolished and
in their place and stead was substitute, a hedge contract
called the 1. C. C. The five varieties of hedge contracts
were also for different deliveries which did not necessarily
coincide one with the other and these contracts were not on
the market all at one time, With the result that it would be
necessary if the requirements of the contract form had to be
complied with to fill in the blank not only by describing
the hedge contract number, whether it was one or the other
of the numbers I to 5 but also the particular hedge contract
of a particular delivery. Even if it may be assumed that
the blank to be filled in in this behalf required a mention
not only of the hedge contract No but also of a particular
delivery thereof, all that went by the board when the I. C.
C. was substituted in place of the hedge contract Nos. I to
5. The old contract form which had been prescribed by by-law
80 was continued without any change being effected therein
by virtue of such substitution and if at all the parties to
a contract were to fulfill the requirements of the contract
form, it would be necessary for them to strike out the
words " hedge contract No and put in their place and stead
the word " 1. C. C. " Even there the 1. C. C. appertained to
different deliveries which were not on the market all at one
time. The months of delivery were nowhere required to be
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 12 of 14
filled in in the contract form, whether the contract form
required the parties to have regard to the hedge contract No
or the I. C. C., and to that extent, it can be said that the
parties were expected to rely upon their commonsense and the
practice of the trade as to what particular delivery was
contemplated when the contracts were entered into between
them.
All this goes to show that the parties to the contract were
not tied down to a literal compliance with the terms
contained in the official contract form but were required to
act according to the position as it then obtained and if
they substantially complied with the requirements of the
contract form that was enough. If the hedge contract No was
not in vogue in the
364
market they need not conform to that provision in the
official contract form but could make the necessary changes
in accordance with the type of hedge contract which was then
in vogue. Similarly, they would have to record in the
contract form the agreement reached between them in regard
to the difference of Rs...... above or below the settlement
rate of the hedge contract No...... if they came to a
particular agreement in that behalf. if, however, no such
agreement was reached between the parties-and here the
effect of no agreement having been arrived at in regard to
such difference would be the same as if the agreement
between them was that the difference was to be nil-no
mention need be made of such difference in the contract
form. The result of either of the two latter positions
would be that if the contracts were to pass through the
Clearing House the settlement rates would be determined on
the basis of the settlement price of the hedge contract
fixed by the Board for those various settlements and the
parties would have to pay to or receive from one another the
differences calculated on the difference between the
contract rates and those settlement rates.
The whole of this discussion, however, is academic by reason
of the fact that in practice delivery contracts were not put
through any periodical settlements and at all material times
the operation of this term in the official contract form’
had become obsolete. This position was not disputed on
behalf of the appellants and their counsel stated before the
Court that he did not wish to dispute the fact that delivery
contracts were at no time submitted to periodical settle-
ments in the Association. The effect of this procedure
being adopted in the Association was tacitly to suspend the
operation of these by-laws as to periodical settlements in
respect of delivery contracts and it would be superfluous,
nay absurd, on the part of the business people entering into
contracts subject to the by-laws of the Association to
incorporate in the contract form provisions which had become
obsolete. If the contracts were not to pass through the
periodical settlements in the Clearing House no question
would
365
ever arise of settlement rates requiring to be fixed, much
less of the basis of such settlement rates being determined,
or of the difference of Rs...... above or below the
settlement rate of hedge contracts being ever agreed upon
between the parties. If under those circumstances, the
parties did not fill in those blanks which required to be
filled in in the official contract form on the basis of by-
laws 139 and 141 being in operation, it could not be said
that they had failed to substantially comply with the
requirements of the official contract form. The official
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 13 of 14
contract form had to be filled in so far as it was
practicable. The operation of these by-laws was in effect
suspended and by the tacit understanding of the trade they
were to be treated as if they did not exist. It could not
therefore be urged that the parties were put to the
necessity of agreeing to such differences, if having regard
to the circumstances that prevailed, it was impracticable to
do so and if these blanks were not filled in as originally
contemplated the contract notes could certainly not be
impeached as being not in accordance with the by-laws of the
Association.
It was, however, urged on behalf of the appellants that if
the parties to the contracts intended not to comply with the
requirements of by-laws 139 and 141 that would by itself
vitiate the contracts because in that event the contracts
would certainly be not in accordance with the by-laws of the
Association. The parties in that event intended to
perpetrate an illegality at the very inception of the
contracts and the contracts were therefore void. There is
considerable force in this argument but we do not feel
called upon to consider the same in view of the fact that
that was not the ground on which the validity of the suit
contract was challenged in the plaint.
We are therefore of the opinion that the omission to fill in
those blanks in the contract notes did not spell any
departure from an essential or a characteristic part of the
contract form nor was the legal effect of the contracts in
any manner changed thereby rendering the contracts void
within the meaning of s. 8 of the Bombay Cotton Contracts
Act, 1932.
366
Both these grounds of attack against the validity of the
contracts in question therefore fail and we are of the
opinion that the contracts entered into between the
appellant,-, and the respondents were not void as alleged.
The appellants were therefore not entitled to recover from
the respondents the said sum of Rs. 1,80,099-8-0 or any part
thereof as alleged or at all and we are of the opinion that
the appellate Court was right in rejecting the appellants’
claim.
We cannot part with this appeal without observing that the
whole difficulty has been created by reason of the
Association not having made the necessary alterations in the
contract form in accordance, with the situation as it
obtained. from time to time. When by-law 101 was suspended
in operation the Association ought to have deleted the term
as to measurement from the contract form. When the by-laws
139 and 141 were virtually abrogated by reason of the
delivery contracts not being subjected to periodical
settlements in the Clearing House, the Association ought to
have similarly deleted the last clause from the official
contract form which required the difference of Rs above or
below the settlement rates of hedge contract No to be
filled-in by the parties. Equally untenable west he
retention of the expression " Hedge Contract No when the
five different varies of hedge contracts were abolished
and one hedge contract named 1. C. C. was substituted
therefor. We fully endorse the observations made by the
appellate Court in the course of its judgment:-
" We have had occasion to point out in the past how badly
the by-laws of the East India Cotton Association are drafted
and how clumsily the forms also settled, and the present
form is an illustration of what we have had occasion to say
in the past."
The manner in which the official contract form which had
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 14 of 14
been settled when the by-laws of the Association came first
to be promulgated has been retained in its pristine glory in
spite of the various changes made in the operation of the
by-laws and the practice of the trade only enhances the
difficulties of the parties and enables the parties who are
so minded to raise all
367
sorts of disputes tenable or otherwise in order to avoid
their liability in respect of the transactions effected by
them in the Association. It may be hoped that the
Association will take effective steps to bring the official
contract form in conformity with the bylaw,% in operation
from time to time and the practice of the trade prevailing
in the Association.
The result therefore is that this appeal fails and must
stand dismissed with costs throughout.
Appeal dismissed.