Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 6
PETITIONER:
P.M. PAUL
Vs.
RESPONDENT:
UNION OF INDIA
DATE OF JUDGMENT16/01/1989
BENCH:
MUKHARJI, SABYASACHI (J)
BENCH:
MUKHARJI, SABYASACHI (J)
RANGNATHAN, S.
CITATION:
1989 AIR 1034 1989 SCR (1) 115
1989 SCC Supl. (1) 368 JT 1989 (1) 299
1989 SCALE (1)221
ACT:
Arbitration Act 1940: Sections 14, 17, 30 and
33--Award-Setting aside of--Whether arbitrator has miscon-
ducted himself or proceedings--Adjudicating upon matter not
subject matter of adjudication-Legal misconduct.
HEADNOTE:
The appellant, a contractor entered into a contract with
the respondent for the construction of a building. The
contract consisted of two phases. The date of commencement
of both the phases was March 10, 1979, the date of comple-
tion of Phase I was June 9, 1980 and that of Phase II was
November 9, 1980. Dispute arose about the handing over of
the site. The appellant’s case was that the site was not
handed over as stipulated and consequently the work could
not either be commenced or completed as stipulated. The
respondent asserted that the appellant had abandoned the
work and committed a breach of contract. This was negated by
the appellant.
As the contract provided for settlement of disputes by
an arbitrator, the appellant filed a suit for the appoint-
ment of an arbitrator.
The matter came up in appeal to this Court, and one of
its former Judges was appointed as an arbitrator. The Arbi-
trator entered upon the reference, examined the documents,
heard the parties, considered the evidence, and made an
award after inspecting the sites.
The respondent aggrieved by the award filed a petition
and contested the same. It was contended that the arbitrator
had travelled beyond his jurisdiction in awarding a sum of
Rs.2 lakhs as escalation cost and charges in respect of
claim I.
Disposing of the Civil Miscellaneous Petition the Court,
HELD: 1. It is well-settled that an award can only be
set aside under section 30 of the Arbitration Act, if the
Arbitrator has misconducted himself or the proceeding.
[121C-D]
116
2. Adjudicating upon a matter which is not the subject-
matter of adjudication, is a legal misconduct for the
Arbitrator. [121D]
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 6
3. Escalation is a normal incident arising out of gap of
time in this inflationary age in performing any contract.
[121F]
In the instant case, the dispute that was referred to
the arbitrator was, as to who was responsible for the delay,
what are the repercussions of the delay in completion of the
building, and how to apportion the consequences of the
responsibility. After discussing the evidence and the sub-
mission of the parties to the contract, the arbitrator,
found that it was evident that there was escalation and,
therefore, he came to the conclusion that it was reasonable
to allow 20% of the compensation under claim I, he accord-
ingly allowed the same. This was a matter which was within
the jurisdiction of the arbitrator, and the arbitrator had
not misconducted himself in awarding the amount as he has
done. [121D-E, G-H; 122A]
4. Once It was found that the arbitrator had jurisdic-
tion to find that there was delay In execution of the con-
tract due to the conduct of the respondent, the respondent
was liable for the consequences of the delay, namely, in-
crease in prices. [122C-D]
JUDGMENT:
CIVIL APPELLATE JURISDICTION:: Civil Miscellaneous
Petition No. 265 19 of 1988.
IN
Civil Appeal No. 2632 of 1987.
From the Judgment and Order dated 10.6.1985 of the
Kerala High Court in W.P. No. 210 of 1985 in O.P. No. 897 of
1984.
Mrs. Baby Krishnan for the Appellant.
A.K. Srivastava and C.V.S. Rao for the Respondent.
The Judgment of the Court was delivered by
SABYASACHI MUKHARJI, J. This is an application for
making the award dated 17th February, 1988 passed by Mr V.
Khalid, a former Judge of this Court, in a dispute referred
to him by this Court’s order dated 6th October, 1987, final
and to give consequential directions thereupon.
117
On 7th April, 1979 there was a contract for construction
of the building in question. The contract consisted of two
phases. The date of commencement of both the phases was 10th
March, 1979: the date of completion of phase-l was 9th June,
1980 and for phase-Il 9th November, 1980. The dispute arose
about the handing over of the site. According to the appel-
lant, the site was not handed over to him as agreed upon and
therefore, the work could not either be commenced or com-
pleted as stipulated. He, therefore, accused the respondent
of obstructionist tactics also. According to the respondent,
however, the claims put forward by the appellant were imagi-
nary excuses to gain time and that he put forward various
demands for extension of time and for payment of compensa-
tion to which he was not entitled.
Clause 70 of the general conditions of the contract
provided for settlement of disputes by arbitration. The
appellant resorted to this clause and addressed a letter
dated 13th September, 1980 to the Chief Engineer, South West
Zone, Cochin, informing him that if the said disputes were
not settled to his satisfaction within 15 days from the date
of receipt of the notice, he would be taking appropriate
steps to refer the disputes to arbitration in accordance
with the said clause. This request of the appellant was
turned down by the Chief Engineer, as according to him, work
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 6
was in progress and the question of granting reasonable
extension of time was under examination. Dissatisfied with
this, the appellant took the matter to the Engineer-in-Chief
by his letter dated 14th October, 1980 calling upon him to
appoint an Engineer Officer as the sole arbitrator to adju-
dicate upon the disputes between the parties. This request
was not acceded to. The relationship between the parties
became strained.
The respondent asserted that the appellant had abandoned
the work and committed breach of contract. Thereafter, the
appellant vide a notice dated 4th October, 1982 called upon
the Engineer-in-Chief to appoint an Engineer Officer as the
sole arbitrator. After further correspondence, the
Engineer-in-Chief by his letter dated 9.6.1983 appointed one
Mr. K.C.S. Rao, Chief Engineer, Poona Zone, as the arbitra-
tor in respect of the disputes. Mr Rao, it is asserted,
entered into reference. The appellant asserted that Mr Rao
was incompetent to function as arbitrator for it was he who
had terminated the contract when he was officiating as the
Chief Engineer of Sought West Zone.
Aggrieved by this appointment, he filed a suit in the
Court of Subordinate Judge, Cochin, seeking leave to revoke
the authority of the appointed arbitrator under section 5 of
the Arbitration Act.
118
(hereinafter referred to as ’the Act’), and for appointment
of another person as arbitrator under section 12 of the Act.
It is not necessary to set out the various stages of litiga-
tion thereafter. Ultimately, the matter came to this Court
and by an order passed by this Court on 25th August, 1987 in
Civil Appeal No. 2632/87, it was observed as follows :--
"Having regard to the facts and circumstances
of the case, we are of the opinion that all
the disputes mentioned in the Paper Book be
arbitrated by a former retired Judge of this
Court. We accordingly appoint Mr. Justice v.
Khalid (Retd.) a former Judge of this Court,
as the Arbitrator. The Arbitrator will decide
his remuneration as he thinks fit and the
parties will pay the same in equal shares. The
parties will also bear the costs and charges
of holding the proceedings including the
remuneration and other assistance of Stenogra-
phers etc. Councel for both the parties have
no objection to the aforesaid order. The
learned Arbitrator will enter into reference
within a fortnight from the receipt of the
copy of the order and will make the award
within four months thereafter. Costs of the
parties in the Arbitration proceedings will
abide by the decision of the Arbitrator".
The arbitrator entered upon the reference, examined the
documents, heard the parties and considered the evidence. He
made his award after inspecting the sites on 20th December,
1987 and 21st January, 1988. The claims of the appellants
contractor were as follows:
"1. On account of losses caused due to increase in prices of
materials and cost of labour and transport during the
extended period of contract from 9.6.80 work for
under phase I and from 9.11.80 for work under
phase-II.
5,47,612.15
2. On Account of work done under the contract including
fully executed and partly executed items at the origi-
nally agreed rates and for the cost of materials lying at
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 4 of 6
site and taken over by the Department as well as for the
value of machinery, tools and plants lying over the site
and taken over by Department.
7,27,095.01
3. On account of losses caused due to added and infructuous
expenditure on overheads, establishments, and
119
supervision during the extended period of contract upto
3.12.81, the date of termination. 1,28,864.00
4. On account of losses caused by way of gains prevented
due to unlawful repudiation of the contract by the Depart-
ment and the consequent termination of the contract by the
contractor. 1,04,424.58
5. (a) Release of Bank Guarantee for Rs. 1,25.000 (Bank
Guarantee No. G/19/80 dated 28.4.80 issued by the State Bank
of India, Willingdon Island, Conchin-3).
(b) Refund of the retention amounts recovered by the
Department from the Running Account Bills. Amount not
indicated
6.Interest on all the amounts due and payable. @18% PA from
9.12.81 till
actual date
of payment or
realisation".
The claims on behalf of the respondent, were as under:
"1. Excess cost which had to be borne by the Department
19,16,198.82 on account of the defaults of the contractor
and subsequent cancellation of the contract after adjusting
other amounts due from the contractor under this contract.
2. Cost of reference to Arbitration 7,000.00"
The arbitrator by his award asked the respondent to pay
the following:
"(a) On claim No. I, a sum of Rs.2,00,216.18
with interest at 10% from 9.12.1981 till the
date of this Award.
(b) On claim No. 11, a sum of Rs.2,47,269.69
with interest at 10% from 9.12.1981 till the
date of this Award.
(c) Claim No. III--Disallowed.
(d) Claim No. IV--Disallowed.
(e) On claim No. V(a), the respondent is
directed to
120
refund the Bank Guarantee sum of Rs. 1,25,000
to the Cliamant with interest at 10% from the
date of the encashment till the date of this
Award.
II. The remuneration of the Arbitrator is
Rs.75,000. Rs.50,000 has already been deposit-
ed. The claimant and the Respondent are di-
rected to. remit the balance equally (Rs.
12,5000 each) to the Arbitrator to his Madras
address by Account payee Draft within two
weeks of receipt of the notice under Section
14 of the Arbitration Act, 1940.
11I. The respondent is directed to pay to
the Claimant by way of cost Rs. 17,500 to-
wards Arbitrator’s remuneration
and Rs. 10,000 towards Advocates’ fees and
cost.
IV. The respondent is directed to suffer their
cost.
V. The counter claims preferred by the Re-
spondent against the Claimant are disallowed."
A petition was filed on behalf of the respondent, where-
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 5 of 6
in it was stated as follows:
"Regarding petitioner’s claim No. 1, in the
absence of any escalation clause, it is not
permissible to the Arbitrator to grant any
escalation price as sought by the petitioner.
On the other hand, if the work is not complet-
ed within the specified time, he has got right
to ask for extension of time. Failure to grant
extension of time, the contractor can claim
difference of prices. That is not the case
here. Extension of time was granted and the
Arbitrator after considering the contentions
put-forth before him has granted 20% of the
escalation price which is not in accordance
with the terms of the contract. Though the
term of the contract envisages that the entire
site should be handed over in-time for comple-
tion of the work entrusted to him as referred
to above in civil works before starting of the
work, the contractor is required to put up
some preliminary work like construction of
temporary store sheds, temporary office which
requires sometime and within that time if the
other area or the site is not handed over the
contractor has got grievances to complain
against the Department. Further, by not hand-
ing over the site how much damage or loss is
sustained has not been
121
apprised off. Therefore, it is submitted that
Claim No. 1 of the Contractor should have been
considered as outside the scope of the con-
tract and hence the arbitrator has exceeded
his jurisdiction."
Mr Ashok Srivastava, counsel appearing for the Union of
India, submitted before us that this is a reasoned award and
the learned arbitrator had granted a sum of Rs.2 lakhs as
escalation charges and costs. Mr Srivastava tried to urge
that the right to get escalation charges and costs in the
absence of escalation clause was not a matter referred to
the arbitrator. In other words, it was urged that the arbi-
trator had travelled beyond his jurisdiction in awarding the
escalation cost and charges. It is difficult to accept this
objection for reason more than one.
It is well-settled that an award can only be set aside
under section 30 of the Act, which enjoins that an award of
an arbitrator/umpire can be set aside, inter alia, if he has
misconducted himself or the proceeding. Adjudicating upon a
matter which is not the subject-matter of adjudication, is a
legal misconduct for the arbitrator. The dispute that was
referred to the arbitrator was, as to who is responsible for
the delay, what are the repercussions of the delay in com-
pletion of the building and how to apportion the conse-
quences of the responsibility. In the objections filed on
behalf of the respondent, it has been stated that if the
work was not completed within the stipulated time the party
has got a right for extention of time. On failure to grant
extension of time, it has been asserted, the contractor can
claim difference in prices.
In the instant case, it is asserted that the extension
of time was granted and the arbitrator has granted 20% of
the escalation cost. Escalation is a normal incident arising
out of gap of time in this inflationary age in performing
any contract. The arbitrator has held that there was delay,
and he has further referred to this aspect in his award. The
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 6 of 6
arbitrator has noted that Claim I related to the losses
caused due to increase in prices of materials and cost of
labour and transport during the extended period of contract
from 9.5. 1980 for the work under phase I, and from 9.11.80
for the work under phase II. The total amount shown was
Rs.5,47,618.50. After discussing the evidence and the sub-
missions the arbitrator found that it was evident that there
was escalation and, therefore, he came to the conclusion
that it was reasonable to allow 20% of the compensation
under Claim I, he has accordingly allowed the same. This was
a matter which was within the jurisdiction of the arbitrator
and, hence, the arbitrator had not mis-
122
conducted himself in awarding the amount as he has done.
It was submitted that if the contract work was not
completed within the stipulated time which it appears, was
not done then the contractor has got a right to ask for
extension of time, and he could claim difference in price.
This is precisely what he has done and has obtained a por-
tion of the claim in the award. It was submitted on behalf
of the Union of India that failure to complete the contract
was not the case. Hence, there was no substance in the
objections raised. Furthermore, in the objections raised, it
must be within the time provided for the application under
section 30 i.e., 30 days during which the objection was not
specifically taken, we are of the opinion that there is no
substance in this objection sought to be raised in opposi-
tion to the award. Once it was found that the arbitrator had
jurisdiction to find that there was delay in execution of
the contract due to the conduct of the respondent, the
respondent was liable for the consequences of the delay,
namely, increase in prices. Therefore, the arbitrator had
jurisdiction to go into this question. He has gone into that
question and has awarded as he did.
Claim I is not outside the purview of the contract. It
arises as an incident of the contract and the arbitrator had
jurisdiction. In that view of the matter the objections
raised against the award, cannot be sustained. No other
objection was urged before us. The award, therefore, must be
made the rule of the Court and there will be a decree in
terms of the award, and the respondent is directed to pay
Rs. 17,500 as the arbitrator’s remuneration and Rs. 10,000
as advocates’ fees and costs.
The Civil Miscellaneous Petition is disposed of accordingly.
N.V.K. Petition disposed of.
123