Full Judgment Text
1
REPORTABLE
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NOS.2174-2175 OF 2012
SHAKUNTALA YADAV AND OTHERS Appellant(s)
Versus
STATE OF HARYANA AND OTHERS Respondent(s)
W I T H
CIVIL APPEAL NOS. 2176-2177 OF 2012
SHAKUNTALA YADAV AND OTHERS Appellant(s)
Versus
STATE OF HARYANA AND OTHERS Respondent(s)
J U D G M E N T
JUDGMENT
KURIAN, J.
1. We have heard learned counsel for the parties.
2. The appellants are aggrieved since their request
for release of 1.23 acres of land falling in Khasra
No. 23/8/1, 8/2, 9/2, 12/2 and 13/1 in village
Sahaul, Tehsil and District Gurgaon and .25 acres of
Page 1
2
land falling I Khasra No. 23/10/1 in the same village
has been rejected.
3. Placing reliance on the letter of the Finance
Minister of Haryana, for releasing lands coming under
Lal Dora, the appellants approached the High Powered
Committee. It appears that the High Powered
Committee turned down the request on the ground that
possession of the property had already been taken,
pursuant to Award passed on 12.3.2004 and that the
same had already been handed over to Haryana Urban
Development Authority (in short 'the HUDA'). That
decision of the High Powered Committee was challenged
before the High Court leading to the impugned
judgments.
4. The High Court endorsed the view taken by the
JUDGMENT
High Powered Committee and has held that once the
acquired land has already been taken possession of,
there is no question of release under Section 48 of
the Land Acquisition Act, 1894 (in short 'the Act').
5. Learned counsel appearing for the State sought to
establish that the land had already been taken
possession of, by inviting our attention to the order
passed by the High Powered Committee on 28.3.2008,
wherein it is stated as
Page 2
3
follows :-
“8. In fact the petitioner had two
pockets of land measuring 1.23 acres
falling in Khasra No. 23/8/1, 8/2, 9/2,
12/2, 13/1 and 0.25 acres falling in
Khasra No. 23/10/1. The applicants had
applied for change of land use of these
khasra numbers for setting up of
information technology unit on 5.12.2005
in the office of Director, Town and
Country Planning. The said application
was returned vide No. G-1721-AD(B)-
2006/9881 dated 21,4,2006 mentioning that
the applied land is under acquisition and
the applicants were asked to get the land
released and then apply for change of land
use permission. The land is already
acquired and HUDA has taken a possession
of land of other land owners vide Rapat
Rojnamcha dated 12.3.2004. It was also
informed by Chief Town Planner (HUDA) that
HUDA has planned industrial plots on this
land and allotted 11 No. such plots. It
was noted that land of the applicant is
lying vacant. Since as mentioned above
the land is awarded, possession of the
adjoining land stands taken and also
stands allotted by HUDA, therefore, the
land of the petitioner mentioned in CWP
No. 10294/2004 and 14669 of 2005 cannot be
considered for release.”
JUDGMENT
6. We find it difficult to appreciate the contention
of the learned counsel for the State, that the High
Powered Committee had taken note of the fact of
taking possession. On the other hand, what is
revealed from the order is that the lands which were
taken possession and handed over to HUDA was that of
other land owners. The stand in the counter
affidavit is not clear on the aspect of taking
possession. On the other hand, the appellants assert
Page 3
4
that they have never been dispossessed from the land.
th
7. In the above circumstances, this Court on 7
July, 2010 passed the following order :-
“Learned counsel for the petitioners
submits that in pursuance of the orders of
the Finance Minister of Haryana, issued in
the year 1981, two acres of land of Lal Dora
on all four sides of the lands in Village
Sarhaul, Tehsil and District Gurgaon was
left free from acquisition and this has been
confirmed by the Land Acquisition Officer,
Urban Estate, Gurgaon, Haryana by letter
dated 2.3.2005 and by the District Town
Planner Enforcement, Gurgaon in his letter
dated 9.6.2006 addressed to Millennium
Industries Private Limited who are
neighbours of petitioners. He also submits
that on the basis of the said direction, the
land of Millennium Industries Private
Limited has been left out of acquisition.
It is submitted that the land of the
petitioners also falls within the two acres
area around the village as in the case of
Millennium Industries Private Limited but
the High Powered Committee (HPC) has
erroneously refused to leave out the land of
the petitioners.
In view of the said submissions, issue
notice. Status quo regarding possession.”
JUDGMENT
8. Thereafter it is seen that the matters were
adjourned from time to time, to 13.9.2010, 9.11.2010,
22.2.2011, 30.3.2011, 4.5.2011 all before the
Registrar and on 22.7.2011 before the Court.
Thereafter, on 26.8.2011, this Court passed a
specific order that the counter affidavit was vague
on the aspect of Lal Dora and Millennium Industries
Private Limited, specifically referring to in the
Page 4
5
th
order dated 7 July, 2010. The order dated 26.8.2011
reads as follows :-
“We find that the counter affidavit
filed on behalf of respondents 1 to 3 does
not deal with the submission that was
recorded by this Court in the order dated
7.7.2010.
At this stage, learned counsel for the
respondents submitted that an additional
affidavit with reference to the order dated
7.7.2010 will be filed.
Finally, adjourned by four weeks.”
9. On 23.9.2011, since time was sought for
additional affidavit, a detailed order was passed,
which reads as follows :-
“By order dated 7.7.2010, we had noted
the submission of the petitioner that on the
orders of the Finance Minister of Haryana,
issued in the year 1981, two acres of land of
Lal Dora on all four sides in village
Sarhaul, Tehsil and District Gurgaon was left
free from acquisition and this has been
confirmed by the Land Acquisition Officer,
Urban Estate, Gurgaon, Haryana by letter
dated 2.3.2005 and by the District Town
Planning and Enforcement by letter dated
9.6.2006. The contention of the petitioner
was that on that ground the lands of
Millennium Industries Private Limited who are
neighbours of petitioners were left out of
acquisition, but their land, which is
similarly situated, has not been left out.
JUDGMENT
In the counter filed, this issue was not
dealt with and consequently on 26.8.2011,
when we drew the attention to this fact, the
learned counsel for the respondent submitted
that an additional affidavit will be filed.
But the said additional affidavit has not
been filed. Learned counsel for respondents
1 to 3 again seeks time. We find no reason
to grant further time. However, finally four
weeks' time is granted to file an additional
affidavit subject to deposit of Rs.2500/- as
costs with the Supreme Court Legal Services
Page 5
6
Committee and producing acknowledgment within
that period.
List thereafter.”
10. Despite the State being put on cost for filing
additional affidavit, it was noted by this Court when
the matter was taken up thereafter on 21.11.2011,
that the additional affidavit had not been filed.
Hence four weeks' more time was granted and the
matter came up before this Court again on 3.1.2012.
It was noted that neither the cost was deposited nor
the affidavit filed. Therefore, this Court imposed a
further cost of Rs.5000/- and gave one more
opportunity, by way of last indulgence, to file the
additional affidavit. Yet the additional affidavit
th
was not filed and therefore, on 10 February, 2012,
this Court passed the following order :-
“Right of the respondents to file
additional affidavit is closed.
JUDGMENT
Delay condoned in filing special leave
petitions.
Leave granted.
List the matters for hearing at an
early date.
In the meanwhile, interim order to
continue.”
11. We have extensively referred to the background of
the case before this Court only to indicate that
there was no assistance on the two crucial aspects
Page 6
7
which are actually pivotal for a decision in the
case.
12. The High Court, unfortunately, has gone only on
one tangent that the land having vested with the
Government on operation of Section 16 of the Act, the
request for release under Section 48 cannot be
considered. An attempt for review, when the
appellants pointed out the instance of Millennium
Industries Private Limited, in similar circumstances,
was also turned down, without going into those
aspects, by passing a cryptic order.
13. There being no Rojnama to show that the physical
possession had already been taken, nor any pleadings
in that regard, we find it difficult to appreciate
the submission made by the learned counsel for the
JUDGMENT
State that the possession had already been taken and
handed over to HUDA. Unless the property is taken
possession of, in accordance with law, there arises
no question of handing over the property to HUDA.
Symbolic possession, as has been held by this Court
in (2012) 1 SCC 792 titled as Raghbir Singh Sehrawat
versus State of Haryana and others, will not serve
the purpose .
14. In case the land of the appellants is in Lal
Page 7
8
Dora, we find no reason to deny, a similar treatment
as has been granted to Millennium Industries Private
Limited. However, on the pleadings available before
this Court, we find it difficult to arrive at a
definite conclusion in that regard. Therefore, we
deem it just and proper to remand the matter to the
High Powered Committee.
15. In the above circumstances, the appeals are
allowed, the impugned orders passed by the High Court
are set aside. The impugned order passed by the High
Powered Committee is also set aside. The request
made by the appellants for release of their land are
remanded to respondent No.3 – High Powered Committee
for consideration afresh.
16. We make it clear that the request of the
JUDGMENT
appellants shall not be turned down, on the ground of
operation of Section 16 of the Act. In case it is
found that the land is in Lal Dora, they shall also
be granted similar treatment, as has been given to
Millennium Industries Private Limited.
17. The orders, as above, shall be passed
expeditiously by Respondent No.3 – High Powered
Committee, at any rate, within a period of three
months from the date of production of copy of this
Page 8
9
judgment. In the event of any delay beyond the said
period, the members of the Committee shall be
personally liable for costs to the tune of Rs.500/-
(rupees five hundred only) each per day.
18. Till orders are passed, as above, the interim
orders passed by this Court to maintain status quo,
with regard to possession, will continue to operate.
19. No order as to costs.
........................J.
(KURIAN JOSEPH)
........................J.
(ROHINTON FALI NARIMAN)
New Delhi,
March 09, 2016
JUDGMENT
Page 9
10
ITEM NO.106 COURT NO.10 SECTION IV
S U P R E M E C O U R T O F I N D I A
RECORD OF PROCEEDINGS
Civil Appeal No(s). 2174-2175/2012
SHAKUNTALA YADAV & ORS. Appellant(s)
VERSUS
STATE OF HARYANA & ORS. Respondent(s)
(with appln. (s) for permission to urge addl. grounds)
WITH
C.A. No. 2176-2177/2012
Date : 09/03/2016 These appeals were called on for hearing today.
CORAM :
HON'BLE MR. JUSTICE KURIAN JOSEPH
HON'BLE MR. JUSTICE ROHINTON FALI NARIMAN
For Appellant(s)
Mr. Diljit Singh Ahluwalia, Adv.
Mr. Amarjit Singh Bedi,Adv.
Md. Asfar Heyat Wasi, Adv.
For Respondent(s)
Mr. Rahul Verma, AAG
Mr. Sanjay Kumar Visen,Adv.
UPON hearing the counsel the Court made the following
O R D E R
JUDGMENT
These appeals are allowed in terms of the signed
reportable judgment.
Pending applications, if any, stand disposed of.
[RENU DIWAN] [SUKHBIR PAUL KAUR]
COURT MASTER A.R.-CUM-P.S.
(Signed reportable judgment is placed on the file)
Page 10