Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 14
PETITIONER:
UNION OF INDIA
Vs.
RESPONDENT:
RAMAN IRON FOUNDRY
DATE OF JUDGMENT12/03/1974
BENCH:
BHAGWATI, P.N.
BENCH:
BHAGWATI, P.N.
GOSWAMI, P.K.
CITATION:
1974 AIR 1265 1974 SCR (3) 556
1974 SCC (2) 231
CITATOR INFO :
O 1984 SC 29 (9,13,20,25)
RF 1992 SC 847 (53)
ACT:
Indian Arbitration Act (10 of 1940 s. 41 (b)-Court when can
issue interim in function. Indian Contract Act (9 of 1872),
s. 74-Stipulation of amount of damages in contract-Claim for
damages for branch--If claim for liquidated or unliquidated
damages.
’Sums due,’ meaning of.
HEADNOTE:
A dispute arose regarding the performance of a contract
between the appellant and respondent, each party contending
that the other had committed a breach of the contract and
claiming large sums of money by way of damages. The appel-
lant’s claim was for damages stipulated under cl. 14 of the
contract. The respondent was called upon to pay the amount
claimed and was also informed that on failure to make the
payment the appropriate officer would be authorised to
recover the amount from the pending bills of the respondent
in respect of other contracts under cl. 18 of the Contract.
The respondent thereupon moved the High Court under s. 20 of
the Arbitration Act, 1940, and the claim and counter claim
were referred to arbitration. During the pendency of the
arbitration some amounts became due and payable by the
appellant to the respondent in respect of other contracts
between them. The respondent applied to the High Court for
an injunction restraining the appellant from recovering its
claim for damages from the amounts which had fallen due and
the High Court granted the injunction holding that cl. 18
did not authorise the appellant to appropriate the amounts
of any pending bills of the respondent towards satisfaction
of its claim for damages against the respondent unless such
claim was either admitted by the respondent or adjudicated
upon by the arbitrator or the Court.
Dismissing the appeal to this Court,
HELD : (1) The order of interim injunction cannot be said to
be outside the scope of the High Court’s power under s. 41
(b) of the Arbitration Act. [563D-E]
(a) Section 41 (b) says that the Court shall have, for the
purpose of and in relation to arbitration proceedings, the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 14
same power of making orders in respect of any of the matters
set out in the second schedule as it has for the purpose of
and in relation to any proceedings before the Court and one
of the matters set out in the second Schedule is ’interim
injunction.’ The, Court has therefore power to issue interim
injunction. But such interim injunction can only be for the
purpose of and in relation to arbitration proceedings.The
Court could not therefore make an interim order which,
though ostensibly in form an order of interim injunction, in
substance amounted to a direction to the appellant to pay
the amounts due to the respondent under other contracts.
[562F-563A]
(b) However, in the present case, the order of interim
injunction’ does not expressly or by necessary implication
direct the appellant to pay amounts due to the respondent
under other contracts. The a appellant can still refuse to
pay such amounts if it thinks it has a valid defence and the
only remedy open to the respondent then would be to take
measures in an appropriate forum. No breach of the interim
injunction as such would be involved in non-payment of such
amounts by the appellant to the respondent. The only thing
which the appellant is interdicted from doing is to satisfy
its claim for damages by appropriating such amounts. Such
an order- would be within the power of the court under s. 41
(b), because the claim for damages forms the subject matter
of arbitration proceedings. [563A-D]
(2) The appellant had no right or authority under cl. 18 to
appropriate the amounts of other pending bills of the
respondent, ’in or towards satisfaction of its claim for
damages against the respondent, and so, the High Court has
justified in issuing the interim injunction-. [569G]
557
(a) Though the words"where any claim for the payment of a
sum of money arises" occurring in the opening part of cl. 18
are words of great amplitude, covering even a claim for
damages, it is a well settled rule of interpretation,
applicable alike to instruments as to statutes that the
meaning of ordinary words is to be found not so much in
strict etymological propriety of language nor even in
popular use as in the subject or occasion on which they are
used and the object which is intended to be attained. The
context and collection of a particular expression may show
that it was not intended to be used in the sense which it
ordinarily bears. The words must therefore be read not in
isolation but in the context of the whole clause. [564G-
565B]
(b) The heading of the clause reads "Recovery of sums due".
The heading cannot control the interpretation of a clause if
its meaning is otherwise plain and unambiguous, but it can
be referred to as indicating the general drift of the clause
and affording a key to a better understanding of the
meaning. When there is an obligation to pay a sum of money
at a future date it is a debt owing, but when the obligation
is to pay a sum of money in present, it is a debt due. A
sum due would therefore mean a sum for which there is an
existing obligation to pay in present or in other words
which is presently payable. [565 C-D, G-H]
(c) The language used in the body of the clause also
supports the view that it is with recovery of sums presently
due and payable by the respondent that this clause deals.
The clause is merely intended to provide a mode of a claim
for payment of a sum of money arising out of or under the
contract.’ It therefore postulates a claim for a sum which
is due and payable, that is, presently recoverable and it
may be recovered by the mode therein provided. It is
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 14
difficult to believe that the contracting parties could have
intended that even though a, sum is not due and payable by
the respondent, the appellant should be entitled to recover
it by adopting the mode set out in the clause. Such an
interpretation would mean that as soon as a claim is made by
the appellant, it would immediately become recoverable and
the appellant, under the clause, would be entitled to sell
of the securities of the respondent and appropriate the sale
proceeds in or towards satisfaction of such claim, and in
case that is insufficient, to recover the balance by
appropriating other sums due to the respondent, and if there
is even then a shortfall, to recover it personally from the
respondent. And this consequence would ensue even if the
claim is for a sum which the respondent is under no existing
obligation to pay or which is not presently payable or, is
disputed as regards liability or quantum. It would be more
consonant with reason and good sense to take the view, which
is supported by the language of the clause that it does no
more than merely provide an additional mode of recovery. to
the appellant and that the appellant is entitled to exercise
the right conferred under it only where there is a claim for
a sum which is presently due and payable by the respondent.
The last words of the clause namely, "the contractor shall
on demand pay to the purchaser the balance remaining due",
clearly postulate that the reference in the clause is to a
sum presently due and payable by the respondent to the
appellant. [566B-567B]
(d) It is not legitimate to construe the clause by
reference to a corresponding clause which prevailed in the
earlier standard form of contract where the words were
whenever under the contract any sum of money is
recoverable’. This is not a statute enacted by the
legislature where it can be said that if the legislature has
departed from the language used by it in an earlier
enactment, it would be a fair presumption to make that the
alteration in ,the language was deliberate and was intended
to convey a different meaning’ This is a clause in a
contract and in construing it any reference to a similar or
dissimilar clause in another contract would be irrelevant.
Moreover, on a question of construction of the clause the
mere use of word ’claim’ cannot be a decisive factor. The
clause has to be read as a whole, and so read, it
applies.only where the appellant has a claim for a sum
presently due and payable by the respondent. [567B-G]
(e) In the present case, the claim is for damages for
breach of the contract. The damages claimed are liquidated
damages under cl. 14 of the Contract; but under Indian law
there is no difference in the nature of the claim whether it
be for liquidated damages or for unliquidated damages. Even
if there is a stipulation for liquidated damages a party
complaining of breach of contract can recover
558
only reasonable compensation for the injury sustained by
him, the stipulated amount being merely the outside limit.
The claim in the present case therefore stands on the same
footing as a claim for unliquidated damages. A claim for
unliquidated damages does not give rise to a debt until the
liability is adjudicated upon and damages assessed by an
adjudicatory authority. When there is a breach of contract,
the party who commits the breach does not eo instanti incur
any pecuniary obligation nor does the party complaining of
the breach become entitled to a debt due from the other
party. The only right which the party aggrieved by the
breach has is the right to sue for damages and this is not
an actionable claim. A claim for damages for breach of
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 4 of 14
contract is therefore not a claim for a sum presently due
and payable and the appellant is not entitled, in exercise
of the right conferred upon it under cl. 18, to recover the
amount of such claim by appropriating other sums due to the
respondent. [567H-569G]
Kesoram Industries v. Commissioner of Wealth Tax [1966] 2
S.C.R. 688 followed.
Jones v. Thompson (1858) 27 L. J. , Q. B. 234, Jabed Sheikh
v. Taher Malik 45 Cal. Weekly Notes, 519 and S. Malkha
Singh v. M/s. N. K. Gopala, Krishna Mudaliar 1956 A.I.R.
Pun. 174, referred to.
Iron & Hardware (India) Co. v. Firm Shamlal & Bros. 1954
A.I.R. Bom. 423 approved.
JUDGMENT:
CIVIL APPELLATE JURISDICTION: Civil Appeal No. 1330 of
1973
Appeal by special leave from the Judgment and Order dated
the 22nd January, 1973 of the Delhi High Court in I. A. No.
1854 of 1972 in Suit No. 485 (A) of 1972 and
Civil Appeals Nos. 1224 & 1225 of 1973.
Appeals by special leave from the Judgment and Order dated
the 15th November, 1972 of the Delhi High Court in I. A.
Nos. 846 and 119 of 1972 in Suit No. 158 of 1971.
L. N. Sinha, Solicitor General of India Shyamala pappu &
S. P. Nayar for the appellant (in all the appeals)
D. G. Singhania, M. K. Garg and Shiv Khurana for respon-
dent (in C. A. 1330)
D. D. Sharma for respondent (in C.A.s. 1224-1225)
The Judgment of the Court was delivered by
BHAGWATI, J.-These appeals, raise an interesting question
relating to the interpretation of cl. 18 of the General
Conditions of Contract contained in the Standard Form of
Contract No. D.G.S. & D. 68. That is the standard form in
which contracts are entered into by the Central Purchase
Organisation of the Government of India for purchase of
stores from third parties described as ’contractors and the
question of interpretation which arises for determination
is, therefore, one of some importance, affecting as it does
a large number of people who enter into such contracts with
the Government of India. The facts giving rise to these
appeals follow a common pattern and it would, therefore, be
sufficient if we set out the
559
facts relating to civil appeals Nos. 1221 and 1225 of 1973.
They bring out clearly the point which arises for
consideration in all the three appeals.
The respondent tendered for supply of certain quantity of
foam compound to the appellant and its tender was accepted
by the appellant by acceptance of Tender dated 16th July,
1968. The Acceptance of Tender was subject to the General
Conditions of Contract contained in the Standard Form of
Contract No. D.G.S. & D. 68. The only clauses of the
General Conditions of Contract which are material for our
purpose are cls. 18 and 24 and they read as follows:
"18. RECOVERY OF SUMS DUE
Whenever any claim for the payment of a sum of
money arises out of or under the contrat
against the contractor, the purchaser shall be
entitled to recover such sum by appropriating
in whole or in part, the security, if any,
deposited by the contractor, and for the
purpose aforesaid, shall be entitled to sell
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 5 of 14
and/or realise securities forming the whole or
part of any such security deposit. In the
event of the security being insufficient, the
balance and if no security has been taken from
the contractor, the entire sum recoverable
shall be recovered by appropriating any sum
then due or which at any time thereafter may
become due to the contractor under the
contract or any other contract with the
purchaser or the Government or any person
contracting through the Secretary, if such sum
even be not sufficient to cover the full
amount recoverable, the contractor shall on
demand pay to the purchaser the balance
remaining due.
"24. ARBITRATION
In the event of any question, dispute,or
difference arising under these conditions or
any special conditions of contract, or in
connection with this contract, (except as to
any matters the decision of which is specialty
provided for by these or the special
conditions) the same shall be referred to the
sole arbitration of an Officer in the Ministry
of Law, appointed to be the arbitrator by the
Director General of Supplies & Disposals. It
will be no objection that the arbitrator is a
Government Servant, that he had to deal with
the matters to which the contract relates or
that in the course of his duties as a
Government servant he has expressed views on
all or any of the matters in dispute or
difference. The award of the arbitrator shall
be final and binding on the parties to this
contract.
Work under the contract shag, if reasonably
possible, continue’ during the arbitration
proceedings and no payment due to or payable
by the purchaser shall-be withheld on account
of such proceedings.
560
The performance of this contract ran into difficulties and a
dispute arose between the parties giving rise to claims by
either party against the other. The respondent contended
that the appellant had committed a breach of the contract
and was, therefore, liable to pay to the respondent a sum of
Rs. 2,35,800/- by way of damages. suffered by the respondent
by reason of the breach of the contract. The appellant, on
the other hand, said that it was the respondent who had
committed the breach, of the contract and was liable to pay
to the appellant by way of damages a sum of Rs. 2.28,900/-
under clause 14 of the General Conditions of Contract. The
Assistant Director of Supplies by his letter dated 30th
March, 1971 called upon the respondent to make payment of
the amount of Rs. 2,28,900/and intimated that if the
respondent failed to do so on or before 30th April, 1971,
the Pay and Accounts Officer, New Delhi/Madras would be
authorised to recover the, same from the pending bills of
the respondent in respect of other contracts. This dispute
between the parties being a dispute arising out of the
contract was liable to be settled by arbitration under cl.
24 of the General Conditions of Contract and the respondent,
therefore, filed an application. in the Delhi High Court
under s. 20 of the Indian Arbitration Act for filing the
Arbitration Agreement contained in that clause. The
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 6 of 14
respondent also, at the same time, made an application to
the Delhi High Court for an interim injunction restraining
the appellant from recovering the amount of damages claimed
by it from the pending bills of the respondent. This
application was, however, rejected by the Delhi High Court
on the ground that it was not shown that there were any
pending bills of the respondent at that time out of which
the threatened recovery could be made by the appellant. The
application under s. 20 of the Indian Arbitration Act was
thereafter heard by the Delhi High Court and by an order
dated 5th May, 1972 the Delhi High Court allowed that
application and ordered the arbitration agreement contained
in cl. 24 to be filed and made an order of reference to
arbitration in accordance with the arbitration agreement.
The claim of the respondent against the appellant for Rs.
2,35,800/- and the counter-claim of the appellant against
the respondent for Rs. 2,28,900/- thus became the subject
matter of reference tO arbitration. During the pendency of
the arbitration some amounts became due and payable by the
appellant to the respondent in respect of other contracts
entered into between the parties. In view of the letter
dated 30th March, 1971 the respondent apprehended that the
appellant would appropriate these amounts towards recovery
of the amounts of damages claimed by it even though the
claim for damages was disputed by the respondent and was
pending adjudication before the arbitrator. The respondent,
therefore, made interim Application No. 119 of 1972 to the
Delhi High Court on 17th January, 1972 under s. 41 read with
the Second Schedule to the Indian Arbitration Act, 1940
praying that the status quo should be maintained and the
appellant should be restrained from recovering its claim for
damages from the amounts due and payable by the appellant to
the respondent in respect of the pending bills. How it
appears that this Interim Application No. 119 of 1972 was
made in the Original Application under s. 20 of the Indian
Arbitration Act,
561
1940 and the appellant, therefore, raised a technical
objection that the Original Application under s. 20 having
been disposed of, Interim Application No. 119 of 1972, as
filed, could not be maintained. The respondent, in view of
this technical objection raised on behalf of the appellant,
filed another Interim Application No. 746 of 1972 as an
independent application under s. 41 read with the Second
Schedule to the Indian Arbitration Act, 1940 on 16th May,
1972 praying for the same interim relief as was claimed in
the earlier Interim Application No. 119 of 1972. Both these
interim applications were resisted by the appellant relying
on cl. 18 of the General Conditions of Contract but Mr.
Justice Avadh Bihari of the Delhi High Court, who heard
these interim application, took the view that cl. 18 did not
authorise the appellant to appropriate. the amounts of any
pending bills of the respondent towards satisfaction of its
claim for damages against the respondent, unless such claim
for damages was either admitted by the respondent or
adjudicated upon by arbitration or suit in civil court. The
learned Judge accordingly by an order dated 15th November,
1972 allowed both the interim applications and issued an
interim injunction restraining the appellant "from effecting
recovery of the amounts claimed to be due from- the other
pending bills" of the respondent. The appellant thereupon,
with certificates obtained from the Delhi High Court,
preferred Civil Appeals Nos. 1224 and 1225 of 1973 in this
Court. One appeal was directed against’ the impugned order
in so far it related to Interim Application No. 119 of 1972
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 7 of 14
and the other in so far as it related to Interim Application
No. 846 of 1972. The appellant also preferred Civil Appeal
No. 1330 of 1973 against a similar order passed by the
learned Judge in Interim Application No. 854 of 1972 in the
other case.
There are in the main two grounds on which the learned
Solicitor General, appearing on behalf of the appellant,
challenged the order of Interim injunction made by Mr.
Justice Avadh Bihari
A.The impugned order amounted in effect and substance to an
order directing the appellant to pay the amounts of the
pending bills of the respondent: in respect of the other
contracts and since the question of payment of the amounts
of such pending bills did not form the subject matter of the
reference which was pending before the arbitrator., the
learned Judge had no jurisdiction under s. 41 read with the
Second Schedule to make such an order and the impugned order
was, therefore, outside the scope of his power and hence
invalid.,
B.Clause 18 comes into play when there is a claim for
payment of a sum of money arising out of or under the
contract. It is not necessary that the sum of money must be
due and payable to the purchaser. It is enough if there is
a claim even for damages. Whenever, there is such claim,
the purchaser is given a right under cl. 18 to recover it by
appropriating "any sum then due or which at any time
thereafter
562
may become due to the contractor under the contract" or
under any other contract. The appellant was, therefore, en-
titled to recover the amount of its claim for damages
against the respondent by appropriating the sums which
subsequently became due to the respondent under other
contracts, even though the claim for damages was contested
by the respondent and was pending adjudication before the
arbitrator. No interim injunction could be granted to
prevent the exercise of such right. If interim injunction
were to be granted in a case of this kind as of course
merely on the ground, without anything more, that the claim
for damages is pending adjudication and until it is
determined in favour of the purchaser,’ it should not be
allowed to be recovered by the purchaser out of other sums
due to the contractor, it would render cl. 18 meaningless
and ineffectual and the tight to the purchaser under that
clause would become illusory. of course, it would be open to
the court even in such a case to grant interim injunction,
if it is satisfied that the claim for damages is prima facie
not well founded and the balance of convenience requires
that, Pending adjudication, the purchaser should be
restrained from effecting recovery of the claim for damages
from out of other sums due to the contractor. But here
admittedly neither of these two factors was taken into
consideration by the learned Judges and the order of interim
injunction made by’ him cannot, therefore, be sustained.
We shall proceed to examine these grounds in the order in
which we have set them out.
Re: Ground A.
It was common ground between the parties that the order of.
interim injunction was made by the learned Judge under s. 41
(b) read with the Second Schedule to the Indian Arbitration
Act, 1940. Now s. 41(b) says that the court shall have, for
the purpose of and in relation to arbitration proceedings,
the same , power of making orders in respect of any of the
matters set out in the Second Schedule as it has for the
purpose of and in relation to any proceedings before the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 8 of 14
Court and one of the matters set out in the Second Schedule
is "interim injunction". The Court has, therefore, power
under s.41 (b) read with the Second Schedule to issue
interim injunction, but such interim injunction can only be
"for the purpose of and in relation to arbitration
proceedings". , The arbitration proceedings in the present
case were for determination of the mutual claims of the
appellant and the respondent arising out of the contract
contained in the acceptance of Tender dated 16th July, 1968.
The question whether any amounts were payable by the
appellant to the respondent under other contracts was not
the subject matter of the arbitration proceedings. The
Court obviously could not, there fore, make an interim order
which, though ostensibly in form an order of interim
injunction, in substance amounted to a direction to the
appellant to pay the amounts due to’ the respondent under
other contracts. Such an interim order would clearly not be
for the purpose of or in relation to the arbitration
proceedings as required by
563
s. 41 (b). But here the order of interim injunction made
by the learned judge does not, expressly or by necessary
implication, carry any direction to the appellant to pay the
amounts due to the respondent under other contracts. It is
not only in form but also in substance a negative
injunction. It has no positive content. What it does is
merely to injunct the appellant from recovering, suo moto,
the damages claimed by it from out of other amounts due to
the respondent. It does not direct that the appellant shall
pay such amounts to the respondents. The appellant can
still refuse to pay such amounts if it thinks it has a valid
defence and if the appellant.does so, the only remedy open
to the respondent would be to take measures in an
appropriate forum for recovery of such amounts where it
would be decided whether the appellant is liable to pay such
amounts to the respondent or not. No breach of the order of
interim injunction as such would be involved in non-payment
of such amounts by the appellant to the respondent. The
only thing which the appellant,is interdicted from doing is
to make recovery of its claim for damages by appropriating
such amounts in satisfaction of the claim. ’That is clearly
Within the power of the Court under s. 41 (b) because the
claim for damages forms the subject matter of the
arbitration proceedings and the Court can always say that
until such claim, is adjudicated upon, the appellant shall
be restrained from recovering it by appropriating other
amounts due to the respondent. The order of interim
injunction made by the learned Judge cannot, therefore, be
said to be outside the scope of his power under s. 41 (b)
read with the Second Schedule
Re: Ground B.
That takes us to the second ground of challenge against the
order of interim injunction. This ground of challenge is
based on the proper interpretation of cl. 18. The argument
of the appellant was that what is required for attracting
the applicability of cl. 18 is a mere claim for payment of a
sum of money arising out of or under the contract against
the contractor and it is not necessary that a sum of money
must be actually due and payable from the contractor to the
purchaser. If the purchaser has a claim for payment of a
sum of money against the contractor, he would be entitled to
exercise the right given under cl. 18, even though such
claim may not be for a sum due and payable but pay be for
damages and it may be disputed by the contractor and may not
have been adjudicated upon in a court of law or by
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 9 of 14
arbitration. The purchaser can in such a case recover the
amount of his claim, without resort to a court of law or
arbitration, by appropriating sums due to the contractor
under the same contract or under other contracts, if the
claim of the purchaser is not well founded and the
appropriation made by him is, therefore, unjustified, the
contractor can always institute a suit or arbitration for
recovering the sums due to him which have been wrongly
appropriated by the purchaser and in such suit or
arbitration,the court or the arbitrator, as the case
may be, would examine theclaim against which
appropriation has been made bypurchaser and if the
claim is found to be unsustainable, set at naught the
appropriation and pass a decree or award for the sums due
to the contractor. But the court cannot and should not
restrain the purchaserfrom exercising
564
his right of appropriation merely because the claim against
which appropriation is sought to be made by the purchaser is
disputed by the contractor and is pending adjudication
before a court of law or arbitrator. The court should not
prevent the normal operation of cl. 18 by interfering with
it, unless it appears to the court prima facie that the
claim which is sought to be recovered by appropriation is
not well founded and the balance of convenience lies in
favour of restraining the purchaser from recovering it by
appropriation. The respondent, however, disputed the
validity of this construction placed on cl. 18 by the
appellant and contended that though the words used in the
opening part of cl. 18 are "any claim for the payment of a
sum of money", which are general words of apparently wide
amplitude sufficient to cover even a claim for damages
arising out the contract, a proper construction of the
clause read as a whole clearly suggests that these words are
intended to refer only to a claim for a sum due and payable
and do not take in a claim for damages which is disputed by
the contractor. It is only when a claim for damages is
adjudicated upon by a civil court or an arbitrator and the
breach of the contract is established and the amount of
damages ascertained and decreed that a debt due and payable
comes into existence; till then it is nothing more than a
mere right to sue for damages and it does not fall within
the words of cl. 18. Moreover, cl. 18 merely provides a
mode of recovery and it can have no application where a
claim, even though it be for a sum due and payable, is dis-
puted by the contractor and has to be established in a court
of law or by arbitration: cl. 18 applies only where a claim
is either admitted,or in case of dispute, substantiated by
resort to the judicial process. Therefore, when the
purchaser has a claim for damages which is disputed by the
contractor, the purchaser is not entitled under cl. 18 to
recover the amount of its claim for damages by appropriating
other sums due to the contractor until the claim for damages
is adjudicated upon and culminates in a decree. The
appellant in the present case had consequently no right
under cl. 18 to appropriate sums due to the respondent under
other contracts in satisfaction of its claim for damages
against the respondent, when the claim for damages was
pending adjudication before the arbitrator and the learned
Judge was right in restraining the appellant from doing so
by issuing an interim injunction. These were broadly the
contentions of the parties under this head of challenge and
the question is which of these rival contentions is correct.
It is true that the Words "any claim for the payment of a
sum of money" occurring in the opening part of, cl. 18 are
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 10 of 14
words of great amplitude, wide enough to cover even a claim
for damages, but it is a well settled rule of interpretation
applicable alike to instruments as to statutes that the
meaning of ordinary words is to be found not. so much in
strict etymological propriety of language nor even in
popular use as in the subject or occasion on which they are
used and the object which is intended to be attained. The
context and collocation of a particular expression may show
that it was not intended to be used in the sense which it
ordinarily bears. Language is at best an imperfect medium
of expression and a variety of meanings may often
565
lie in a word or expression. The exact colour and shape of
the meaning of any word or expression should not be
ascertained by reading it in isolation, but it should be
read structurally and in its context, for its meaning may
vary with its contextual setting. We must, therefore, read
the words ’any claim for the payment of a sum of money’
occurring in the opening part of cl. 18 not in isolation but
in the context of the whole clause, for the intention of the
parties is to be gathered not from one part of the clause or
the other but from the clause taken as a whole. It is in
the light of this principle of interpretation that we must
determine whether- the words ’any claim for the payment of a
sum of money’ refer only to a claim for a sum due and
payable which is admitted or in case of disputes,
established in a court of law or by arbitration or they also
include a claim for damages which is disputed by the
contractor.
The first thing that strikes one on looking at cl. 18 is its
heading which reads: "Recovery of Sums Due". It is true that
a heading cannot control the interpretation of a clause
if its meaning is other- wise plain and unambiguous,
but it can certainly be referred to as indicating the
general drift of the clauses and affording a key to a better
understanding of its meaning. The heading of cl. 18 clearly
suggests that this clause is intended to deal with the
subject of recovery of sum due. Now a sum would be due to
the purchaser when there is an existing obligation to pay it
in present. It would be profitable in, this connection to
refer to the concept of a ’debt’, for a sum due is the same
thing as a debt due. The classical definition of ’debt’ is
to be found in Webb v. Stenton (1) where Lindley, L. J.,
said : "a debt is a sum of money which is now payable or
will become payable in the future by reason of a present
obligation". There must be debitum in praesenti; solvendum
maybe in praesenti or in future that is immaterial. There
must be an existing obligation to pay a sum, of money now or
in future. The following passage from the judgment of the
Supreme Court of California in People v. Arguello. (2)
which, was approved by this Court in Kesoram Industries v.
Commissione of Wealth Tax (3) clearly brings out the
essential characteristics of a debt
"Standing alone, the word ’debt,’ is as
applicable to a sum of money which has been
promised at a future day as to a sum now due
and payable. If we wish to distinguish
between the two, we say of the former that it
is. a debt ’owing, and of the latter that it
is debt due."
This passage indicates, that when there is an obligation to
pay a sum of money at a future date, it is a debt owing but
when the obligation, is to pay a sum of money in praesenti,
it is a debt due. A sum due would, therefore, mean a sum
for which there is an existing obligation to pay in
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 11 of 14
praesenti or in other words, which is presently payable..
(2) [1869] 37 Calif. 524
(1) [1883] 11 Q.B.D. 518.
(3) [1966] 2 S.C.R. 688.
566
Recovery-of such sums is the subject matter of cl. 18
according to the heading. That is the dominant idea running
through the entire cl.18.
The language used in the body of cl. 18 also supports the
view that it is with recovery of sums presently due and
payable by the ,contractor to the purchaser that this clause
deals. It may be noted that cl. 18 does not lay down the
substantive rights and obligations of the parties under the
contract. It is merely intended to provide a mode of
recovery of ’ a claim for payment of a sum of money arising
out of or under the contract". It, therefore, postulates a
claim for a sum which is due and payable, that is.
presently recoverable and may be recovered by the mode
therein provided. it is difficult to believe that the
contracting parties could have intended that even though a
sum is not due and payable by the contractor to the
purchaser under the contract, the purchaser should be
entitled to recover it by adopting ,the mode set out in cl.
18. It is important to note that cl. 18 does not -create a
lien on other sums due to the contractor or give to the
purchaser a right to retain such sums until his claim
against the contractor is satisfied.If merely a right of
lien or retention were given to secure payment of a claim,
then even if the claim were for a sum not presently due and
payable, the provision perhaps would not have been so
startling ,or unusual. But here the right given to the
purchaser under. cl. 18 is a right to recover the amount
of his claim by appropriating other sums due to the
contractor and, on the, interpretation of the appellant,
this can be done even if the claim is for a sum which is not
due or payable in praesenti and the purchaser is otherwise
not entitled to recover it. That would indeed be a highly
extra-ordinary result which we would be loathe to
reach in the absence of clear and compelling language. This
interpretation, if accepted, would mean that as soon as a
claim is made by the purchaser, it would immediately become
recoverable and the purchaser would be entitled to sell off
the securities of the contractor and appropriate the sale
proceeds in or towards satisfaction of such claim and in
case that is insufficient, recover the balance by
appropriating other sums due to the contractor and if there
is even then a shortfall, recover it personally from the
contractor, for the last words of cl. 18 provide that
"the contractor shall on demand pay to the purchaser the
balance remaining due". And this consequence would ensue
even if the claim is for a sum which the -contractor is
under no existing obligation to pay or which is not
presently payable or is disputed as regards the existence of
liability or its quantum. A mere making of a claim by the
purchaser would impose a liability on the contractor to
pay it. That surely could -not have been the intention
of the contracting parties. It would be more consonant
with reason and good sense to take the view, which, as
pointed out above, is plainly and indubitably supported by
the language used by the contracting parties, that cl. Is
does no more than merely provide an additional mode of
recovery to the purchaser, and the purchaser is entitled
to exercise the right conferred, under that clause only
where there is a claim for a sum which is presently due and
payable by the contractor. This view, indeed, becomes
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 12 of 14
irresistible
567
when we consider the last words of cl. 18, namely, "the
contractor shall on demand pa to the purchaser the balance
remaining due", which clearly postulate that the
reference in the clause is to a sum presently due and
payable by the contractor to the purchaser, so that, if
any balance remains unrecovered after adopting the special
mode of recovery provided in the clause, such balance must
be paid by the contractor to the purchaser on demand. The
appellant laid great emphasis on the use of the word ’claim’
in the opening part of cl. 18 and contended that the
Standard Form of Contract which was in use prior to the
adoption of the present Standard Form of Contract, cl. 14,
and which corresponded to the present cl. 18, opened with
the words " whenever under this contract any sum of money is
recoverable from and payable by the contractor", but this
formula was deliberately and advisedly altered when the
present Standard Form was introduced and instead, the words
"whenever any claim for the payment of sum of money
arises...." were substituted and this change in phraseology
indicated that in order to attract the applicability of the
present cl. 18 it was not necessary that there should be a
sum due and payable by the contractor to the purchaser but
it was enough if there was a mere claim on the part of the
purchaser for payment of a sum of money by the contractor,
irrespective of whether such sum of money was presently due
and payable or not. This contention is, in our opinion,.
wholly untenable. We do not think it is legitimate to
construe cl. 18 of the contract between the parties by
reference to a corresponding clause which prevailed in an
earlier Standard Form of Contract. This is not a statute
enacted by the Legislature where it can be said that if the
Legislature has departed from the language used by it in
an earlier enactment, it would be a fair presumption to make
that the alteration in the language was deliberate and it
was intended to convey a different meaning. It is a clause
in a contract which we are construing and there, any
reference to a similar or dissimilar clause in another
contract would be irrelevant. The only question before us
is, what does cl. 18 mean and that depends on the plain
interpretation of its language in the context in which it
occurs. Moreover, on a question of construction of cl. 18,
mere use of the word "claim" cannot be a decisive factor.
Cl. 18 has to be read as a whole, each part throwing light
on the other, without any undue emphasis on one word or the
other. We cannot allow our interpretation of cl. 18 to be
hijacked from its true course by the use of a solitary word
such as "claim", but we must arrive at the true meaning of
the clause by construing it in all its parts and in its
proper contextual setting. So viewed, it is clear that cl.
18 applies only where the purchaser has a claim for a sum
presently due and payable by the contractor.
Having discussed the proper interpretation of cl. 18, we may
now turn to consider what is the real nature of the claim
for recovery of which the appellant is seeking to
appropriate the sums due to the respondent under other
contracts: The claim is admittedly one for damages for
breach of the contract between the parties. Now, it is true
that the damages which are claimed are liquidated damages
under cl. 14,
568
but so far as the law in India is concerned, there is no
qualitative difference in the nature of the claim whether it
be for liquidated damages or for unliquidated damages. Sec.
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 13 of 14
74 of the Indian Contract Act eliminates the some-what
elaborate refinements made under the English common law in
distinguishing between stipulations providing for payment of
liquidated damages ’and stipulations in the nature of
penalty. Under the common law a genuine preestimate of
damages by mutual agreement is regarded as a stipulation
naming liquidated damages and binding between the parties a
stipulation in a contract in terrors is a penalty and the
Court refuses to enforce it, awarding to aggrieved party
only reasonable compensation. The Indian Legislature has
sought to cut across the web of rules and presumptions under
the English common law, by enacting a uniform principle
applicable to all stipulations naming amounts to be paid in
case of breach, and stipulations by way of penalty, and
according to this principle, even if there is a stipulation
by way of liquidated damages, a party complaining of breach
of contract can recover only reasonable compensation for the
injury sustained by him, the stipulated amount being merely
the outside limit. It, therefore makes no difference in the
present case that the claim of the appellant is for
liquidated damages. It stands on the same footing as a
claim for unliquidated damages. Now the law is well settled
that a claim for unliquidated damages does not give rise to
a debt until the liability is adjudicated and damages
assessed by a decree or order of a Court or other
adjudicatory authority. When there is a breach of contract,
the party who commits the breach does not eo instanti incur
any pecuniary obligation, nor does the party complaining of
the breach becomes entitled to a debt due from the other
party. The only right which the party aggrieved by the
breach of the contract has is the right to sue for damages.
That is not in actionable claim and this position is made
amply clear by the amendment in s. 6(e) of the Transfer of
Property Act, which provides that a mere right to sue for
damages cannot be transferred. This has always been the law
in England and as far back as 1858 we, find it stated by
Wightman, J., in Jones v. Thompson (1) "Exparte Charles and
several other cases decide that the amount of a verdict in
an action for unliquidated damages is not a debt till
judgment has. been signed".. It was held in this case that a
claim for damages dots not become a debt even after the jury
has returned a verdict in favour of the plaintiff till the
judgment is actually delivered. So also in O’ Driscoll v.
Manchester Insurance Committee,(2) Swinfen Eady, L. J., said
in reference to cases where the claim was for unliquidated
damages "in such cases there is no debt at all until the
verdict of the jury is pronounced assessing the damages and
judgment is given. The same view has also been taken
consistently by different High Courts in India. We may
mention only a few of the decisions, namely, Jabed Sheikh v.
Taher Mallik,(3) S. Malkha Singh v. M/s N. K. Gopala Krishna
Mudaliar(4) and Iron & Hardware (India) Co. v. Firm Shamlal
& Bros.(5)
(1) [1858] 27 L. J. Q.B. 234.
(3) 45 Cal. Weekly Notes, 519.
(2) [1915] 3 K. D. 499.
(4) 1956 A.I.R. Pun. 174.
(5) 1954 A.I.R. Bom. 423.
569
Chagla, C. J. in the last mentioned case, stated the law in
these terms:
" In my opinion it would not be true to say
that a person who commits a breach of the
contract incurs any pecuniary liability, nor
would it be true to say that the other party
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 14 of 14
to the contract who complains of the breach
has any amount due to him from the other
party.
As already stated, the only right which he has
is the right to go to a Court of law and
recover damages. Now, damages are the
compensation which a Court of law gives to a
party for the injury which he has sustained.
But, and this is most important to note, he
does not get damages or compensation by reason
of any existing obligation on the part of the
person who has committed the breach. He gets
compensation as a result of the fiat of the
Court. Therefore, no pecuniary liability
arises till the Court has determined that the
party complaining of the breach is entitled to
damages. Therefore, when damages are
assessed, it would not be true to say that
what the Court is doing is ascertaining a
pecuniary liability which already
existed. The Court in the first place must
decide that the defendant is liable and then
it proceeds to assess what that liability is.
But till that determination there is no
liability at all upon the defendant."
This statement in our view represents the correct legal
position and has our full concurrence. A claim for damages
for breach of contract is, therefore, not a claim for a sum
presently due and payable and the purchaser is not entitled,
in exercise of the right conferred upon it under cl. 18, to
recover the amount of such claim by appropriating other sums
due to the contractor. On this view, it is not necessary
for us to consider the other contention raised on behalf of
the respondent, namely, that on a proper construction of cl.
18, the purchaser is entitled to exercise the right
conferred under that clause only where the claim for payment
of a sum of money is either admitted by the contractor, or
in case of dispute, adjudicated upon by a court or other
adjudicatory authority. We must, therefore, hold that the
appellant had no right or authority under cl. 18 to
appropriate the amounts of other pending bills of the
respondent in or towards satisfaction of its claim for
damages against the respondent and the learned Judge was
justified in issuing an interim Injunction restraining the
appellant from doing so.
We accordingly dismiss the appeals. The appellant in each
appeal will pay the costs of the respondent all throughout,
V.P.S.
Appeals dismissed.
-45Sup.CI/75
570