Full Judgment Text
REPORTABLE
IN THE SUPREME COURT OF INDIA
2024 INSC 628
CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NOs. 9781-9782 of 2024
@ SLP (C) Nos. 8128 -8129 of 2021
PAM DEVELOPMENTS PRIVATE LIMITED ...APPELLANT(S)
VERSUS
THE STATE OF WEST BENGAL & ANR. …RESPONDENT(S)
J U D G M E N T
PAMIDIGHANTAM SRI NARASIMHA, J .
1. Leave granted.
2. State of West Bengal, respondent herein, issued a notice
inviting tenders on 08.09.2010, for the widening and
strengthening of Egra Bajkul road under the Tamluk Highway
Division in Purbo Medinipur District and accepted appellant’s
offer, leading to grant of a Work Order for the project to be
completed within 18 months from 23.12.2010. The project got
delayed by about five months, but the work was completed by
Signature Not Verified
09.11.2012.
Digitally signed by
Indu Marwah
Date: 2024.08.23
18:35:25 IST
Reason:
1
3. The appellant raised a bill for Rs. 77,85,290 and that was in
addition to seven other claims under different heads, owing to
alleged delays on part of the Respondent. As the respondent denied
any liability, the dispute was referred to Arbitration for resolution.
4. The Arbitrator gave his award on 30.01.2018, holding the
respondents are liable to the tune of Rs.1,37,25,252, with interest.
There were seven claims. Claim no. 1 related to loss of business,
with respect to which Rs. 3,87,530 was awarded; claim no. 2
related to uneconomic utilization of plant and machinery, with
respect to which Rs. 61,22,000 was awarded and claim no. 3
related to labour charges for uneconomical stoppage of work, with
respect to which Rs.5,80,500 was awarded; claim no. 4 related to
interest on delayed payment of running account bills and escalation
bill
for which the Arbitrator awarded Rs. 54,84,024; claim no. 5
related to escalation with respect to which Rs.11,51,198 was
granted; and claim 6 related to interest on the sum awarded , with
respect to which interest @12% p.a. was awarded from 12.04.2016
to 30.01.2018 and @ 9.25% p.a. post award interest till date of
actual payment. Finally claim no.7 pertained to costs and the
Arbitrator awarded 4 lakhs to the appellant, being the successful
party.
2
4.1. The Respondents challenged the award under Section 34 of
1
the Arbitration and Conciliation Act, 1996 and it was allowed in
part by the District Judge setting aside claim no. 1 for loss of
business , since the same had never been claimed by the appellant
and was thus beyond the Arbitrator’s jurisdiction. Claim no. 2 for
uneconomic utilization of plant and machinery was also set aside
because the Arbitrator didn’t account for the loss of 135 days at
the behest of the appellant while determining the alleged 200 days
of ‘wasted machine’.
4.2. Aggrieved by the decision of the District Judge, the appellant
filed an appeal under Section 37 of the Act against the order setting
aside the award on claims 1 and 2. On the other hand, the
Respondent filed a cross appeal seeking setting aside of the rest of
the claims as well. By the order impugned before us, the Calcutta
High Court exercising jurisdiction under Section 37 of the Act set
aside claim no.1 as well as claim nos. 3 and 4, but restored the
Award with respect to claim no.2. However, while retaining claim
no. 5 as it is, the High Court slightly modified claim no. 6 relating
to pre-reference interest.
1
Hereinafter referred to as the ‘Act’.
3
5. A comprehensive table of the claims and the decision in the
Award, Section 34 and Section 37 jurisdiction is as follows –
| Claim no. | Arbitral Award | Section 34 | Section 37 |
|---|---|---|---|
| 1. Loss of<br>business | Awarded<br>Rs.3,87,530. | Award Set aside,<br>because it was never<br>claimed by the<br>appellant and was<br>the basis for<br>granting of-site<br>expenses. | Affirmed the<br>decision of<br>District judge. |
| 2. Uneconomic<br>utilization of<br>plant and<br>machinery | Awarded Rs.<br>61,22,000 for<br>deploying plant<br>and machinery<br>on all 200 wasted<br>days as required<br>under the<br>Contract. | Award set aside, as<br>Arbitrator did not<br>account for wastage<br>of 135 days by the<br>appellant itself. | Awarded claim<br>no. 2, thereby<br>reversing<br>decision by the<br>District Judge. |
| 3. Labour<br>Charges for<br>uneconomical<br>stoppage of<br>work | Arbitrator<br>granted 3% of the<br>contract amount<br>Rs.5,80,500/- as<br>per the Hudson’s<br>formula. | Award upheld by the<br>District Court. | Set aside,<br>because it is<br>contrary to the<br>Special Terms<br>and Conditions<br>of the Contract. |
| 4. Interest on<br>delayed<br>payment of<br>Running<br>Account Bills<br>and Escalation<br>Bills | Awarded Rs.<br>54,84,024/- on<br>the ground of<br>interest on<br>blocked capital<br>(when amount | Award upheld by the<br>District Court. | Set aside<br>because<br>monthly bills<br>raised by<br>appellants were<br>paid without<br>delay. As per |
4
| exceeded Rs.1<br>crore) @12% pa. | clauses 7-9, no<br>claim for<br>interest arises. | ||
|---|---|---|---|
| 5. Escalation<br>Bill | Awarded<br>Rs.11,51,198/-<br>as respondent<br>has already paid<br>part of such<br>amount. The<br>claimant is<br>entitled to the<br>balance. | Award upheld by the<br>District Court. | Affirmed the<br>Award and<br>decision of the<br>District Judge. |
| 6. Interest | Arbitrator<br>awarded interest<br>@12% on amount<br>of claims w.e.f<br>12.04.2016 to the<br>date of Award and<br>further interest<br>@9.25% p.a. from<br>date of award till<br>actual payment. | Award upheld by the<br>District Judge. | Modified. Only<br>interest pendent<br>lite and post<br>award payable.<br>No interest for<br>pre-reference<br>period. |
| 7. Cost | Awarded Rs.4<br>Lakhs towards<br>legal and<br>administrative<br>expenses. |
6. Mr. Saurav Agarwal, counsel for the appellant, confined his
submissions to claim no. 3, 4 and 6 awarded by the Arbitrator and
5
upheld by the District Judge but set aside/modified by the High
Court. We will deal with each of these claims.
7. Re claim no. 3: This claim relating to loss caused due to idle
labour, machinery, etc.
7.1. On this count, the Arbitrator accepted the claim of loss on
the ground of on-site establishment ‘as permissible’ to the extent
of 3% of the contract amount by the Hudson’s formula for expenses
of engineers, supervisors, etc. It was his considered view that the
appellant maintained such an establishment to execute the work
and the same has not been disputed by the Respondent. Therefore,
he awarded claim no. 3 in favour of the appellant for Rs.5,80,500.
7.2. The challenge to the Award made by the Respondent was
dismissed by the District Judge under Section 34, holding that the
findings of the Arbitrator cannot be held to be irrational, insensible
or unrealistic and also that they are not in conflict with public
policy. We may state at this very stage that this common reasoning
of the District Court while upholding the Award for claim nos. 3,
4, 5 and 6. The standard reasoning of the District Court for these
claims is as follows:
“I have gone through the observation of the learned
Arbitrator in respect of claim Nos. 3, 4, 5 and 6. On
meticulous scrutiny of the award with reference to the
documents produced by the parties to the ease, I find that
6
the reasons and findings given by the learned Arbitrator
cannot be said to be irrational, insensible or unrealistic. In
fact, award in respect of claim Nos. 3, 4, 5 & 6 cannot be
said to be.in conflict with the public policy of India even by
stretch of Imagination. On the other hand, it is apparent that
cogent and acceptable reasons have been furnished by the
learned Arbitrator in respect of these four heads of claims
(claim Nos. 3 to 6). The award in respect of such four claims
does not call for any interference.”
7.3. While exercising jurisdiction under Section 37, the High
Court examined the relevant clauses of the contract and held the
claim is impermissible under the contractual provisions. They are
extracted herein below for ready reference.
''SPECIAL TERMS AND CONDITIONS
CONDITION IN EXTENDED PERIOD
As Clause 4 of W.B.F. 2908 or Clause 5 of W.B.F. No.2911
(ii) as the case may be when an extension of time for
completion of work is authorised by the Engineer-In-Charge,
it will be taken for granted that the validity of the contract
is extended automatically upon the extended period with all
terms and conditions rates, etc. remaining unaltered, i.e. the
tender is revalidated upon the extended period.
EXTENSION OF TIME
For cogent reasons over which the contractor will have no
control and which will retard the· progress, extension of time
for the period lost will be granted on receipt of application
from the contractor before the expiry date of contract. No
claim whatsoever for idle labour, additional establishment,
cost of materials and labour and hire charges of tools &
Plants etc. would be entertained under any circumstances.
The contractor should consider the above factor while
quoting this rate. Applications for such extension of time
should be submitted by the contractor in the manner
indicated in Clause 5 of the printed form of W.B.F. No. 2911
(ii).
IDLE LABOUR Whatever the reasons may be no claim or idle
labour, enhancement of labour rate additional
establishment cost, cost of TOLL and hire and labour
charges of tools and plants Railway freight etc. would be
entertained under any circumstances."
7
7.4. Mr. Saurav Agarwal submitted that the High Court under
Section 37 ignored the plausible view of the Arbitrator, as upheld
under Section 34, and substituted it with its own reasoning.
7.5. This submission is persuasive, but the contract clauses
speak for themselves. In fact, High Court did what the Arbitrator
should have done. Examine what the contract provides. This is
not even a matter of interpretation. It is the duty of every Arbitral
Tribunal and Court alike and without exception, for contract is the
foundation of the legal relationship. Having considered the above
referred clauses in the Contract the High Court came to the
conclusion that awarding any amount towards idle, machinery,
etc. is prohibited under the ‘Special Terms and Conditions’ of the
Contract. The Arbitrator did not even refer to the contractual
provisions and the District Court dismissed the objections under
Section 34 with a standard phrase as extracted hereinabove. High
Court exercising jurisdiction under Section 37 did its duty and we
are of the opinion that the conclusions of the High Court are
correct and cannot be interfered with.
8. Re claim no. 4: This claim relates to interest on delayed
payment of running account bills.
8
8.1. The Arbitrator held that the Claimant is entitled to receive
compensation for any loss and/or damage of capital which arose
naturally from breach or which parties knew to be likely to arise
from breach. Payments on running account bills is guided by
clause 7 of the Contract and there is no prohibition in the contract
regarding payment of interest on the ‘blocked capital’. Therefore,
holding that the injured party ought to be placed in the same
financial position he would have been but for the other party’s
fault, the Arbitrator awarded interest on delayed payments at the
rate of 12% p.a., which was quantified to Rs. 54,84,024. As
indicated above, the District Court upheld the Award.
8.2. The relevant portion of the Award is as follows:-
“ 23.1… As the claimant is entitled to payment of R/A bills
when the amount is Rs. 1 crore and above, I accept the
statements/calculation made by the claimant vide
Statement submitted before the arbitral tribunal for Rs.
82,26,036/-. In compliance of direction issued by MOM no.
21 dated 24.7.2017, based on work value of Rs. one crore.
Such statement giving all details covering the criteria of bill
value of Rs. 1 crore was served to respondent and there was
no comment on such statement whatsoever. Payment of
R/A bills is guided only by the provision under clause 7 with
amendment thereon. Claimant claimed interest @ 18% p.a.
which is not allowed. I restrict rate of interest @ 12% p.a.
only and thereby the admissible amount of the claim stands
at Rs. 54,84,024/- [Rs. 82,26,036 ÷ 18 X 12]
23.2 The claimant notified loss of interest during the
execution period under Interest Act (vide annexure-K, page
109, Annexure-m page-112, annexure-O, page 115, annex.-
R1, page-119 & 122 with claimant’s document). Moreover,
such payment is out of the written contract for executed
9
quantities. There is no prohibition in the contract for
payment of interest on blocked capital. The claimant is
otherwise entitled to receive payment on account of interest
on blocked capital. Such principle of law is laid down in the
case of Secretary, Irrigation Department Government of
Orissa Vs. G.C. Ray reported in (1992) 1 SCC 508. The
claimant is entitled to receive compensation for any loss or
damage and/or blockage of capital which arose naturally
from the breach or which the parties knew to be likely to
arrive from such breach. The injured party is to be placed in
the same financial position, as he would have been in, if the
other party had duly carried out the contract, i.e., to place
the injured party in the same position if the contract has
been performed. I award Rs. 54,84,024/- only.”
8.3. Mr. Saurav Agarwal submitted that the payments became
due when the gross amount of work done exceeded Rs.1 crore,
therefore the delay was to be accounted for from this date. The
error, he submits is because the High Court relied on chart
submitted by the respondents, unlike the Arbitrator and the
District judge who relied on appellant’s chart.
8.4. High Court exercising jurisdiction under Section 37 merely
recounted the dates on which the bills were raised, and the
payments made. Thereafter High Court formulated certain
questions, which it felt that the Arbitrator and the District Judge
should have answered, but failed to hold any discussion on such
questions. In this view of the matter, the High Court proceeded to
set aside Award of claim no. 4. The relevant portion of the High
Court Judgment is as follows:-
10
“ The learned Arbitrator proceeded on the basis of the
statement submitted by the appellant that there was
delay in the payment of these bills. The unpaid running
account bills were described as “blocked capital”. He
viewed the delay in receiving “this blocked capital” as
“loss and damage” to the appellant and granted Rs.
54,84,024/- on that reasoning, as “interest”.
The learned Judge upheld this award. It is challenged
by the respondent. The respondent relies on Clauses
7, 8 and 9 of the contract by which monthly bills had
to be raised by the appellant on the measurement
made. These payments against the monthly running
account bills were to be treated as advance under
Clause 7. Payment could have been made only when
the gross amount exceeded Rs. 1 crore. According to
the respondent no bill was raised by the appellant.
According to the statement of claim of the appellant,
th
the first bill for Rs. 1,32,91,180/- was prepared on 29
th
August, 2011 and paid on or about 30 August 2011.
th
Similarly, the second was prepared on 7 February,
th
2012 and paid on 9 February, 2012. The third and
fourth bills for Rs. 1,28,23,488/- and Rs.
th
1,30,90,000/- respectively were prepared on 5
th
March, 2012 and paid between 30 March, 2012 and
th
20 June, 2012. The fifth bill for Rs. 3,14,82,214/-
th th
was prepared on 6 July, 2012 and paid between 24
st
July, 2012 and 1 October, 2012. The sixth bill was
th th
raised on 5 July, 2012 and paid between 6 July,
st
2012 and 1 October, 2012. The work was completed
th
on 9 November, 2012.
What the learned Arbitrator did not determine were the
following:
a) Who was responsible for non-preparation of the RA bill
within time?
b) Which of the RA bill claims of the appellant were to be
treated as advance under the above clause of the
contract?
c) Was any notice under the Interest Act, 1978 issued by
the appellant and to what effect?
d) For what amount and for which period the claim for
interest was being entertained and granted by him?
From the above narration of facts it appears that the
bills were paid soon after they were prepared. In that
case there could not have been any claim for interest.
If a claim for interest has been made for running
account bill below one crore, under the said terms it is
11
to be treated as a claim for interest for unpaid advance.
No right to claim interest arose.
Now, unless these facts were established by the
appellant and discussed by the learned Arbitrator to
show that there was delay in the preparation of the
bills by the respondent, that those bills were over one
crore and not be treated as advance and that the right
to obtain payment thereof arose on their due
submission and service of a notice under the Interest
Act, 1978, the award of interest could not be justified.
Total absence of discussion of these facts signifies that
the learned Arbitrator completely failed to exercise its
jurisdiction…. ”
8.5. The conclusion of the High Court, “ that it appears that the
bills were paid soon after they were prepared ” or that, “ in that case
there could not have been any claim for interest ” cannot qualify as
grounds for interference under Section 37. Equally, the approach
of the High Court in holding that the Arbitrator neither established
nor discussed the questions posed by it is not a ground to set aside
the Award. The reasoning of the Arbitrator is reflected in that
portion of the Award extracted hereinabove and we see nothing
perverse in it. Nor such conclusion is against our public policy.
The scope of Section 37 is enunciated in many decisions of this
Court, and we apply the principles laid down therein to the facts
of the present case.
8.6. For these reasons, we set aside the judgment of the High
Court in relation to claim no. 4 and restore the Award and thereby
the judgment of the District Court upholding the Award.
12
9. Re claim no. 6: This claim relates to Interest
9.1. Arbitrator awarded interest @12% on sum awarded from
12.04.2016, which is the date when appellant claimed breach of
contract, to 30.01.2018, which is the date of the Award, and
further interest @ 9.25% p.a. from date of Award till actual
payment. This was confirmed by the District Judge under Section
34.
9.2. High Court held that the contract between the parties
prohibits grant of pre-reference interest and therefore interest
could not have been granted for this period. As per the High Court,
as the Arbitrator could have granted interest only for pendent lite
and post award, the Award was modified directing - pendente lite
interest @12% p.a. from 03.08.2016 till date of award i.e.
30.01.2018, along with post award interest @ 9.25% p.a.
9.3. The learned counsel for the appellants has submitted that
the award for interest is within the domain of the Arbitrator under
Section 31(7) and ought not to be substituted by courts under
Section 34 or 37.
9.4. Section 31(7) of the Act determines the grant of interest. The
relevant provision is extracted hereunder for ready reference.
13
“ 31. Form and contents of arbitral award.—
(7) (a) Unless otherwise agreed by the parties, where and in so
far as an arbitral award is for the payment of money, the arbitral
tribunal may include in the sum for which the award is made
interest, at such rate as it deems reasonable, on the whole or any
part of the money, for the whole or any part of the period between
the date on which the cause of action arose and the date on
which the award is made.
(b) A sum directed to be paid by an arbitral award shall, unless
the award otherwise directs, carry interest at the rate of two per
cent higher than the current rate of interest prevalent on the date
of award, from the date of award to the date of payment.
Explanation.—The expression “current rate of interest”
shall have the same meaning as assigned to it under clause (b)
of section 2 of the Interest Act, 1978 (14 of 1978).”
9.5. The power of the Arbitrator to grant pre-reference interest,
pendente lite interest, and post-award interest under Section 31(7)
of the Act is fairly well-settled. The judicial determinations also
highlight the difference in the position of law under the Arbitration
Act, 1940. The following propositions can be summarised from a
survey of these cases:
I. Under the Arbitration Act, 1940, there was no specific
provision that empowered an Arbitrator to grant interest.
However, through judicial pronouncements, this Court has
affirmed the power of the Arbitrator to grant pre-reference,
pendente lite , and post-award interest on the rationale that a
person who has been deprived of the use of money to which
he is legitimately entitled has a right to be compensated for
14
2
the same. When the agreement does not prohibit the grant
of interest and a party claims interest, it is presumed that
interest is an implied term of the agreement, and therefore,
3
the Arbitrator has the power to decide the same.
II. Under the 1940 Act, this Court has adopted a strict
construction of contractual clauses that prohibit the grant of
interest and has held that the Arbitrator has the power to
award interest unless there is an express, specific provision
4
that excludes the jurisdiction of the Arbitrator from
5
awarding interest for the dispute in question .
III. Under the 1996 Act, the power of the Arbitrator to grant
interest is governed by the statutory provision in Section
31(7). This provision has two parts. Under sub-section (a), the
Arbitrator can award interest for the period between the date
of cause of action to the date of the award, unless otherwise
2
Secretary, Irrigation Department, Government of Orissa v. G.C. Roy, (1992) 1 SCC 508 , para
43(i). Also see Executive Engineer, Dhenkanal Minor Irrigation Division, Orissa v. N.C.
Budharaj, (2001) 2 SCC 721 ; Union of India v. Krafters Engg. and Leasing (P) Ltd., (2011) 7
SCC 279 .
3
G.C. Roy (supra), paras 43(iv) and 44.
4
Board of Trustees for the Port of Calcutta v. Engineers-de-Space-Age, (1996) 1 SCC 516 , paras
4 and 5; Madnani Construction Corporation Private Limited v. Union of India, (2010) 1 SCC
549 ; Tehri Hydro Development Corporation Ltd. v. Jai Prakash Associates Ltd., (2012) 12 SCC
10 , paras 18-20; Union of India v. Ambica Construction, (2016) 6 SCC 36 (First Ambica
Construction Case); Ambica Construction v. Union of India, (2017) 14 SCC 323 (Second Ambica
Construction Case); Raveechee and Company v. Union of India, (2018) 7 SCC 664 ; Reliance
Cellulose Products Ltd. v. ONGC Ltd., (2018) 9 SCC 266 .
5
State of U.P. v. Harish Chandra and Co., (1999) 1 SCC 63.
15
agreed by the parties . Sub-section (b) provides that unless
the award directs otherwise, the sum directed to be paid by
an arbitral award shall carry interest at the rate of 2% higher
than the current rate of interest, from the date of the award
to the date of payment.
IV. The wording of Section 31(7)(a) marks a departure from
Arbitration Act, 1940 in two ways: first , it does not make an
explicit distinction between pre-reference and pendente lite
interest as both of them are provided for under this sub-
section; second , it sanctifies party autonomy and restricts the
power to grant pre-reference and pendente lite interest the
moment the agreement bars payment of interest, even if it is
6
not a specific bar against the Arbitrator.
V. The power of the Arbitrator to award pre-reference and
pendente lite interest is not restricted when the agreement is
6
Sayeed Ahmed and Company v. State of Uttar Pradesh, (2009) 12 SCC 26 , paras 14, 23, 24;
Union of India v. Saraswat Trading Agency, (2009) 16 SCC 504 ; Sree Kamatchi Amman
Constructions v. The Divisional Railway Manager (Works), Palghat, (2010) 8 SCC 767 , para 19;
Union of India v. Bright Power Projects (India) Pvt Ltd., (2015) 9 SCC 695 , para 13; Reliance
Cellulose Products Ltd (supra), para 24; Jaiprakash Associates Limited v. Tehri Hydro
Development Corporation India Limited, (2019) 17 SCC 786 , paras 13-15; Delhi Airport Metro
Express Private Limited v. Delhi Metro Rail Corporation, (2022) 9 SCC 286 , paras 16-20, 24.
16
7
silent on whether interest can be awarded or does not
8
contain a specific term that prohibits the same .
VI. While pendente lite interest is a matter of procedural law, pre-
9
reference interest is governed by substantive law. Therefore,
the grant of pre-reference interest cannot be sourced solely
in Section 31(7)(a) (which is a procedural law), but must be
based on an agreement between the parties (express or
implied), statutory provision (such as Section 3 of the Interest
10
Act, 1978), or proof of mercantile usage .
9.6. In view of the above, the High Court had no reason to interfere
with the Arbitral Award with respect to grant of pre-reference
interest, since the Contract between parties does not prohibit the
same.
10. Having analysed the reasoning in the Award and the
judgment of the District Judge under Section 34 of the Act and of
the High Court under Section 37 with respect to claim nos. 3, 4
and 6, we;
7
Jaiprakash Associates Limited v. Tehri Hydro Development Corporation India Limited, ( 2019)
17 SCC 786 , para 13.2.
8
Oriental Structural Engineers Private Limited v. State of Kerala, (2021) 6 SCC 150 , paras 15-
18.
9
Central Bank of India v. Ravindra , (2002) 1 SCC 367, para 39 following G.C. Roy (supra),
para 43(v).
10
Central Bank of India Secy./GM, Chennai, Central Coop. Bank Ltd. v. S.
(supra), para 39;
Kamalaveni Sundaram , (2011) 1 SCC 790, para 13.
17
(a) Uphold the decision of the High Court in setting aside the
Award with respect to claim no. 3 and dismiss the Civil
Appeal to this extent.
(b) Allow the appeal and set aside the judgment of the High
Court in so far as it rejected and set aside claim no. 4
awarded by the Arbitrator, as upheld by the District Judge
under Section 34.
(c) Allow the appeal and set aside the judgment of the High
Court in so far as it modified claim no. 6, to the extent of
rejecting pre-reference interest awarded by the Arbitrator,
as upheld by the District Judge under Section 34.
(d) In conclusion, Award of claim no. 3 is set aside and Award
of claim no. 4 is upheld. Under claim no.6, the appellant
will also be entitled to claim pre-reference interest.
11. The Civil Appeal arising out of SLP (C) No. 8128 of 2021 is
allowed in part as indicated hereinabove and Civil Appeal arising
out of SLP (C) No. 8129/2021 stands disposed of accordingly.
Parties shall bear their own costs.
………………………………....J.
[ ]
PAMIDIGHANTAM SRI NARASIMHA
………………………………....J.
[ PANKAJ MITHAL ]
NEW DELHI;
AUGUST 23, 2024.
18