Full Judgment Text
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NO. 5952 OF 2002
Uttarakhand Power Corporation Ltd. and another … Appellants
Versus
ASP Sealing Products Ltd. … Respondent
J U D G M E N T
G.S. Singhvi, J.
1. Whether the respondent, who was a consumer of electricity supplied
by Uttar Pradesh State Electricity Board [for short, “the Board”]
(predecessor of appellant No.1 herein) is liable to pay minimum charges in
st
terms of second proviso to para 11 of agreement dated 21 September,
1998 read with Clause 17 (ii) of the Electricity Supply (Consumers)
Regulations, 1984 [for short, “the Regulations”] after disconnection of the
2
supply of electricity is the question which arises for consideration in this
appeal.
2. The respondent had set up a factory at Rudrapur, District Udham
Singh Nagar, which now forms part of the State of Uttarakhand for
manufacture of PVC and EPDM rubber profiles for automobile vehicles. In
1990, the Board sanctioned electric connection of 400 KVA load for the
respondent’s factory. Thereafter, as per the requirement of the
Regulations, the respondent entered into an agreement with the Board.
th
On 12 February, 1997, the respondent applied for an additional load of
200 KVA, which was duly sanctioned. As a sequel to this, fresh agreement
was executed between the parties for the total load of 600 KVA. After one
year and seven months, the respondent approached the Board for
reduction of load from 600 KVA to 250 KVA. The competent authority of
the Board accepted the respondent’s request, who then executed another
st
agreement dated 21 September, 1998.
3. In May 1999, the supply of electricity to the respondent’s factory
was discontinued at the latter’s request. After five months, the concerned
Executive Engineer sent communication on 5.10.1999 to the respondent
requiring it to pay Rs.6,13,592/- towards minimum charges for six months.
3
This was followed by notice dated 4.5.2000 and recovery certificate dated
4.8.2000 issued under Sections 3 and 5 respectively of the U.P.
Government Electricity Undertakings (Recovery of Dues) Act, 1958 [for
short, “the 1958 Act”].
4. The respondent challenged the demand of minimum charges in Civil
Miscellaneous Writ Petition No.511 (M/B) of 2001 by contending that being
an old consumer, it was not liable to pay minimum charges after
disconnection of the supply of electricity. The Board contested the writ
st
petition and pleaded that in terms of agreement dated 21 September,
1998 and the Regulations framed under Section 49 read with Section 79
of the Electricity (Supply) Act, 1948 [for short, “the 1948 Act”], the
respondent is bound to pay minimum charges for the period of six months
counted from the date of disconnection.
5. By the impugned order, a Division Bench of the High Court quashed
the demand of minimum charges by observing that Clause 17 of the
Regulations is not applicable to the respondent’s case because the initial
guarantee period of two years had ended long ago. The Division Bench
also held that the demand of minimum charges cannot be raised after
disconnection of the supply of electricity.
4
6. Shri Pradeep Misra, learned counsel for the appellants argued that
the High Court committed an error by entertaining the writ petition
ignoring that an equally efficacious alternative remedy was available to the
respondent by way of arbitration in terms of para 16 of agreement dated
st
21 September, 1998. He further argued that in view of second proviso to
st
para 11 of agreement dated 21 September, 1998 and Clause 17(ii) of the
Regulations, the respondent is bound to pay minimum charges for the
period of six months despite the fact that supply of electricity was
disconnected sometime in May 1999. Learned counsel then submitted that
the High Court’s view on the issue of applicability of Clause 17 of the
Regulations to the respondent’s case is ex facie erroneous and is liable to
st
be upset because in terms of para 6 of agreement dated 21 September,
1998 read with para (C) thereof, the date of commencement of supply was
st
21 September, 1998 and by May 1999, a period of less than one year had
been completed. Learned counsel argued that with the execution of fresh
agreement, the respondent lost its status as an old consumer and in terms
of Clause 17(ii) of the Regulations, it is liable to pay the minimum charges.
7. Ms. Neeru Vaid, learned counsel for the respondent submitted that
her client should not be non-suited on the specious ground of availability
of alternative remedy because no argument on this issue was made before
5
the High Court. She emphasized that minimum charges are levied in lieu
of the actual investment made by the licensee in laying infrastructure for
supply of electricity to the consumer and argued that the High Court did
not commit any error by quashing the demand of minimum charges
because the Board did not provide additional infrastructure for supply of
electricity with reduced load of 250 KVA.
8. We have considered the respective submissions. In our opinion, the
respondent cannot be non-suited on the ground of availability of
alternative remedy of arbitration, because even though, an objection to
this effect was taken in the written statement filed on behalf of the Board,
no such argument appears to have been made before the High Court. In
any case, at this belated stage, we do not find any justification to non-suit
the respondent on the ground that it did not avail the alternative remedy
of arbitration.
9. We shall now deal with the question posed in the opening paragraph
of this order. For this purpose, it will be profitable to notice the relevant
st
provisions of agreement dated 21 September, 1998 and Clauses 10(b)
and 17(i) and (ii) of the Regulations.
6
st
Agreement dated 21 September, 1998
6. `Date of commencement of supply’ means the date
mentioned in Para (C) hereunder and if no such date is
mentioned then the date of actual connection of Consumer’s
installation or the date of expiry of a period of one month
from the date of intimation to the consumer about the
availability of power after completion of the arrangements
required to connect his installation whichever is earlier.
C. AND WHEREAS this agreement shall be deemed to have
st
been effective from the 21 day of September One thousand
nine hundred ninety eight which date shall be construed as
the date of commencement of supply under this agreement.
11. This agreement shall subject herein before provided be
and remain in force for two years from the date of
commencement of supply (hereinafter / called the initial
period of supply) and thereafter from year to year basis on
the terms and conditions herein contained.
Provided that either party shall be at liberty to
determine this agreement at any time after the expiration of
the initial period of supply on giving one month’s notice in
writing of such intention, and on the expiration of such notice
this agreement shall absolutely cease and determine, but
without prejudice to the rights and remedies if any, of either
party, which may have accrued or arisen hereunder in the
meantime.
Provided further that if the consumer ceases taking
supply of electrical energy due to any reason, he shall be
liable to pay to the supplier necessary charges as per
provision made in the regulation framed by the supplier under
Sections 49 and 79 of Electricity (Supply) Act, 1948.
17(a). In case of shifting of the connections, change or
addition of process, the consumer hereby covenants that for
all purposes he shall be deemed as old registered consumer of
the supplier and the supplier shall treat him accordingly.
7
(b) In case of reduction/addition of loads, the consumer hereby
covenants that for all the purposes he shall be deemed as old
registered consumer—the supplier having taken supply for
different loads before execution of this agreement. The
supplier shall treat him accordingly.
Regulations
10(b) Application for reduction of load .– If a consumer, in
whose name the service is connected, wishes to have
his contracted load reduced, he shall submit an
application thereof, giving full particular of reduction of
load required by him. The reduction in the contracted
load of various categories of power consumers on such
an application shall be allowed by the Supplier on the
terms and conditions detailed below, after completion of
necessary formalities by the consumer, which are
subject to revision by the Supplier from time to time.
(i) xxx
(ii) xxx
(iii) xxx
(iv) The existing agreement will stand terminated with effect from
the date of allowing reduction in load and the consumer will
be required to sign a fresh agreement for the reduced load
effective from the date of allowing reduction of load.
17. Agreement. – (i) The consumer shall enter into a formal
declaration/agreement for a minimum period of two years for
taking electrical energy before release of supply. After expiry
of the above period of two years, the declaration/agreement
will continue on year to year basis on the same terms and
conditions unless terminated in accordance with the provisions
of the declaration/agreements.
All consumers shall execute declaration/agreements governing
supply of energy in the form prescribed by the Board from
time to time.
8
(ii) If the supply to a consumer is disconnected on request or
in default before compulsory period of two years is over,
he shall be liable for payment of minimum charge for the
remaining period by which it falls short of two years or for
the period of six months from the date of disconnection
whichever is less, together with the estimated expenditure
on the erection and demolition of the sub-station and the
line (not paid by the consumer) actually dismantled due to
the disconnection, together with the estimated expenditure
on the cartage of the salvaged materials to stores and the
cost of unsalvaged materials plus 15% supervision charges
on the labour and cartage only.
(emphasis supplied)
st
10. A conjoint reading of various paragraphs of agreement dated 21
September, 1998 and the Regulations extracted hereinabove show that
before release of supply, every consumer is required to enter into a
declaration/agreement for taking electrical energy for minimum period of
two years. This period of two years is counted from the date of
commencement of supply and is treated as initial period of supply. After
expiry of two years, the declaration/agreement continues on year to year
basis on the same terms and conditions unless terminated by either party.
In terms of para 17 of the agreement, the consumer is treated as old
registered consumer of the supplier if there is shifting of connection,
change or addition of process or addition or reduction of load. Clause
10(b) of the Regulations lays down that if the consumer applies for
reduction of the contracted load and the same is sanctioned by the
9
competent authority, the existing agreement automatically ceases to exist
and the consumer is required to sign a fresh agreement for the reduced
load effective from the date of allowing such reduction. Clause 17(ii) of
the Regulations lays down that if before expiry of the compulsory period of
two years, supply is disconnected at the instance of the consumer or on
account of default in payment of charges for the energy supplied by the
licensee, then the consumer shall have to pay minimum charges for the
remaining period or for six months from the date of disconnection,
whichever is less. This clause also obligates the consumer to pay
estimated expenditure on the erection and demolition of the sub-station
and the line actually dismantled due to the disconnection, together with
the estimated expenditure on the cartage of the salvaged materials to
stores and the cost of unsalvaged materials plus 15% supervision charges
on the labour and cartage.
11. From what we have noted above, it is clear that if a consumer
applies for reduction of the contracted load, then the existing agreement
stands automatically terminated with effect from the date of allowing
reduction in load and the consumer is required to execute fresh agreement
for the reduced load. If the supply of electricity is disconnected at the
consumer’s request or on account of default in payment of the electricity
10
charges before expiry of two years period specified in the agreement and
the Regulations, then the consumer is bound to pay minimum charges for
the remaining period or for six months counted from the date of
disconnection, whichever is less.
12. There is no dispute between the parties that after sanction of
electric connection with a load of 400 KVA, the respondent entered into an
agreement with the Board as per the requirement of the Regulations. It is
also not in dispute that fresh agreements were entered into between the
th
parties on 12 February, 1997 when the load was increased from 400 KVA
st
to 600 KVA and again on 21 September, 1998 when the load was reduced
from 600 KVA to 250 KVA. The period of two years for which the Board
was required to supply electricity to the respondent with a load of 250 KVA
st
commenced from 21 September, 1998. The said period would have
th
ended on 20 September, 2000 and if the respondent had not applied for
disconnection, the Board would have supplied electricity to respondent’s
factory till that date in accordance with the terms and conditions
st
enumerated in agreement dated 21 September, 1998 and the
Regulations. However, the fact of the matter is that just after nine months
of execution of fresh agreement, a request was made on behalf of the
respondent for disconnection of the supply of electricity and the same was
11
accepted by the competent authority of the Board. As a consequence,
supply of electricity to the respondent’s factory was discontinued in May,
1999. Therefore, in terms of second proviso to para 11 of the agreement
and Clause 17(ii) of the Regulations, the respondent became liable to pay
minimum charges and we do not find any illegality in the action of the
Board to create the demand of minimum charges.
13. The reasons assigned by the High Court for quashing the demand
created by the Board are ex facie untenable. A reading of the order under
challenge shows that the High Court decided the writ petition by assuming
that the respondent had completed initial guarantee period of two years
and Clause 17 of the Regulations is not applicable to its case. In the
process, the High Court not only omitted to consider the fact that the
st
respondent had executed fresh agreement dated 21 September, 1998
and in terms thereof the period of two years commenced from the date of
agreement, but also misconstrued Clause 17 of the Regulations, sub-
clause (ii) whereof unequivocally lays down that if the supply of electricity
is disconnected at the instance of the consumer, the latter is liable to pay
minimum charges for the remaining period of the agreement or for six
months, whichever is less. The High Court also failed to note that the
supply of electricity was disconnected at the respondent’s request within
12
st
nine months of agreement dated 21 September, 1998. Therefore, the
impugned order is liable to be set aside.
14. The argument of the respondent’s counsel that the demand of
minimum charges could not have been created against her client because
no additional infrastructure was laid for supply of electricity at a reduced
load of 250 KVA sounds attractive but the same cannot be accepted
because the respondent did not challenge the vires of the Regulations or
st
the terms of agreement dated 21 September, 1998.
15. Before concluding, we may also notice the judgment of this Court in
Bihar State Electricity Board, Patna and others v. M/s. Green
Rubber Industries and others (1990) 1 SCC 731. In that case, a two-
Judge Bench considered a question whether in terms of the agreement
entered into between the Board and the consumer, the latter is liable to
pay minimum guarantee charges irrespective of consumption of electricity
and held:
“ It is true that the agreement is in a standard form of
contract. The standard clauses of this contract have been
settled over the years and have been widely adopted because
experience shows that they facilitate the supply of electric
energy. Lord Diplock has observed: “If fairness or
reasonableness were relevant to their enforceability the fact
that they are widely used by parties whose bargaining power
is fairly matched would raise a strong presumption that their
13
terms are fair and reasonable.” Schroeder (A.) Music
Publishing Co. Ltd. v. Macaulay. In such contracts a standard
form enables the supplier to say: “If you want these goods or
services at all, these are the only terms on which they are
available. Take it or leave it.” It is a type of contract on which
the conditions are fixed by one of the parties in advance and
are open to acceptance by anyone. The contract, which
frequently contains many conditions is presented for
acceptance and is not open to discussion. It is settled law that
a person who signs a document which contains contractual
terms is normally bound by them even though he has not
read them, even though he is ignorant of the precise legal
effect. In view of clause 4 having formed one of the
stipulations in the contract along with others it cannot be said
to be nudum pactum and the maxim nudum pactum ex quo
non oritur actio does not apply. Considered by the test of
reasonableness it cannot be said to be unreasonable inasmuch
as the supply of electricity to a consumer involves incurring of
overhead installation expenses by the Board which do not
vary with the quantity of electricity consumed and the
installation has to be continued irrespective of whether the
energy is consumed or not until the agreement comes to an
end. Every contract is to be considered with reference to its
object and the whole of its terms and accordingly the whole
context must be considered in endeavouring to collect the
intention of the parties, even though the immediate object of
enquiry is the meaning of an isolated clause. This agreement
with the stipulation of minimum guaranteed charges cannot
be held to be ultra vires on the ground that it is incompatible
with the statutory duty. Differences between this contractual
element and the statutory duty have to be observed. A supply
agreement to a consumer makes his relation with the Board
mainly contractual, where the basis of supply is held to be
statutory rather than contractual. In cases where such
agreements are made the terms are supposed to have been
negotiated between the consumer and the Board, and unless
specifically assigned, the agreement normally would have
affected the consumer with whom it is made, as was held in
Northern Ontario Power Co. Ltd. v. La Roche Mines Ltd.”
16. In the result, the appeal is allowed and the impugned order is set
aside. As a corollary, the demand of minimum charges created by the
predecessor of appellant No.1 is upheld and the writ petition filed by the
14
respondent is dismissed. The appellant shall now be entitled to encash the
bank guarantee furnished by the respondent in terms of interim orders
th th
dated 13 September, 2002 and 5 December, 2003 passed by this Court.
……………………….J.
[ G.S. Singhvi ]
………..……………….J.
[ Dr. B.S. Chauhan ]
New Delhi
September 08, 2008.