1
REPORTABLE
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NO. 3984 OF 2019
| NEPA LIMITED THROUGH ITS SENIOR<br>MANAGER (LEGAL) | ..... | APPELLANT |
|---|
| | |
| VERSUS | | |
| | |
| MANOJ KUMAR AGRAWAL | ..... | RESPONDENT |
J U D G M E N T
SANJIV KHANNA, J.
1.
By award dated 14.04.2000, the appellant, M/s Nepa Limited,
was held liable to pay Rs. 14,49,300/- to the respondent,
Manoj Kumar Agrawal. The amount was towards refund of the
balance security deposit, which was made by Manoj Kumar
Agrawal in terms of the agreement dated 25.10.1996. The award
had stipulated that Rs. 14,49,300/- would carry an interest @
the rate of 18% per annum from the date of the award, till
payment.
2. It is an accepted case that the appellant paid an amount of
Rs. 1,50,000/- to the respondent on 22.10.2001. It is also
undisputed that this payment would be adjusted/set-off against
the interest, and not from the principal amount of the award,
i.e., Rs.14,49,300/-.
3.
The objections filed by the appellant under Section 34 of the
Signature Not Verified
Digitally signed by
NIRMALA NEGI
Date: 2022.12.17
11:53:19 IST
Reason:
1
Arbitration and Conciliation Act, 1996 were dismissed on
28.02.2001.
1 For short, the “Act”.
2
4.
The appellant had thereupon preferred an appeal under Section
37 of the Act before the Division Bench of the High Court. On
30.10.2001, the Division Bench passed an order whereby, on the
appellant depositing 50% of the awarded amount within ten days
from the date of the order before the executing court, the
execution proceedings for the balance amount were to remain
stayed. The respondent was entitled to withdraw the deposited
amount after furnishing personal undertaking for restitution
of the amount if he is so directed, within three months from
the date of the final disposal of the appeal. The
direction/order attaching the properties of the appellant was
to continue.
5.
Pursuant to the interim order, the appellant had deposited Rs.
7,78,280/- on 05.11.2001. On 08.11.2001, the respondent
withdrew Rs.7,78,280/-, after furnishing personal undertaking
in terms of the order dated 30.10.2001.
6.
The appeal preferred by the appellant under Section 37 of the
Act was dismissed by the Division Bench on 02.02.2012.
7.
It may be stated here that the respondent had also challenged
the award by filing objections under Section 34 of the Act,
which were dismissed. Thereupon, the respondent had filed an
appeal under Section 37 of the Act which was also dismissed.
It is stated by the respondent, who appears in-person, that
both the appellant and the respondent had preferred a special
leave petition before this Court, which were dismissed.
8. Learned counsel appearing for the appellant accepts that the
3
payment of Rs.7,78,280/-, which was withdrawn by the
respondent on 08.11.2001, would be first adjusted/set-off
against the interest element payable in terms of the decree,
which in this case, is the award. The balance amount would be
set off/adjusted towards the principal amount payable. To this
extent also, there is no dispute.
9.
The dispute before us is whether the respondent is entitled to
interest @ the rate of 18% as per the award on the principal
amount of Rs. 14,49,300/- till the decision of the appeal
under Section 37 of the Act on 02.02.2012, or interest @ the
2
rate of 18% is payable on the net principal amount after the
set-off/adjustment of interest due on 08.11.2001 from
Rs.7,78,280/- which was withdrawn by the respondent on
08.11.2001.
10.
On 01.08.2012, the respondent had filed an application for
recovery of amount of Rs. 3,97,382/- along with the interest.
On 18.08.2012, the respondent had filed another application
stating and claiming that he was entitled to interest on
Rs.14,06,259/-, i.e., the principal amount awarded along with
the 18% interest till the decision of the appeal under Section
| 37 of the Act, which was decided on 02.02.2012. | 3 |
|---|
| The executing court | vide | order dated 05.10.2012 held that the |
|---|
respondent is entitled to decree in the sum of Rs. 3,97,382/-
2
See paragraph 25 below. As per calculations made by the appellant vide Annexure
‘A’ to this judgment the net principal amount payable is Rs. 9,13,483/-. As per
the calculations made by the respondent vide Annexure ‘B’ to this judgment the
net principal amount payable is Rs.9,30,300/-.
3 It appears that some payments were made by the appellants post dismissal of
their appeal under Section 37 of the Act on 02.02.2012. Therefore, the figures
mentioned do not tally with awarded amount etc.
4
along with the interest @ the rate of 18% per annum.
12.
The appellant paid an amount of Rs. 4,15,629/- on 31.10.2012.
The payment was computed on the basis of the order passed by
the executing court quantifying the decree amount as Rs.
3,97,382/- and included interest payable on the said amount.
13.
Aggrieved, the respondent preferred a civil revision before
the High Court of Madhya Pradesh at Jabalpur, which had been
| allowed by the impugned order dated 19.06.2017, | inter alia |
|---|
holding that in terms of Order XXI, Rule 1, sub-rules (4) and
| (5) | 4 | of the Code of Civil Procedure, 1908 | 5 | , the appellant |
|---|
having failed to give notice for deposit of amount of Rs.
7,78,280/-, the respondent would be entitled to interest @ the
rate of 18% per annum, even on the sum of Rs. 7,78,280/-,
which was withdrawn by him, till the decision of the appeal
under Section 37 of the Act, on 02.02.2012.
14. In our opinion, the judgment of the High Court is
unsustainable and contrary to the law. In the present case, it
is accepted and admitted position that the respondent had
withdrawn amount of Rs. 7,78,280/-, which had been deposited
by the appellant, on 08.11.2001. In this background, the
question of notice in terms of sub-rule(4) to Rule 1 to Order
| XXI of the CPC becomes irrelevant. In | Gurpreet Singh | v. | Union |
|---|
4 Order XXI – Execution of Decrees and Orders –
1. Modes of paying money under decree. –
xx xx xx
(4) On any amount paid under clause (a) or clause (c) of sub-rule
(1), interest, if any, shall cease to run from the date of service of
the notice referred to in sub-rule (2).
(5) On any amount paid under clause ()b) of sub-rule (1), interest,
if any, shall cease to run from the date of such payment.
xx xx xx”
5 For short, ‘CPC’
5
| of India, | (2006) 8 SCC 457, a five Judges Bench of this Court |
|---|
had examined Rule 1 to Order XXI of the CPC, post the
substitution by Act No. 4 of 1976, and observed that the
effect of the substitution is that upon deposit of the
decretal amount in the court and giving notice thereof to the
decree holder, there would be cessation of interest from the
date of notice to the decree holder of such deposit. Rule 1 to
Order XXI of the CPC also postulates payment by the judgment
debtor to the decree holder by other specified modes, namely,
by postal money order, bank or by payment evidenced in
writing, in which case the interest ceases to run from the
date money is tendered. The legislative intent clearly, is
that the interest would cease on the principal amount paid by
the judgment debtor to the decree holder. Issue of notice is
to enable the decree holder to withdraw the amount deposited.
Therefore, when the deposited amount is withdrawn and gets
credited in the account of the decree holder, he is not
entitled to interest on the deposited amount, even when there
is failure on the part of the judgment debtor to issue notice
of deposit. In absence of notice, the interest would cease to
run from the date when the amount is transferred/credited in
the account of the decree holder. If notice is issued,
interest ceases to run from the date of service of notice.
15.
In the present case, order dated 30.10.2001 was passed in the
presence of the parties including the respondent. Thereupon,
the appellant had deposited Rs. 7,78,280/- before the
6
executing court on 05.11.2001. The respondent had notice of
the deposit and accordingly had withdrawn the said amount,
i.e., Rs. 7,78,280/- on 08.11.2001.
16.
The respondent, who appears in-person, has relied on the
| judgments of this Court in | P.S.L. Ramanathan Chettiar and |
|---|
| Others. vs. O.R.M.P.R.M. Ramanathan Chettiar | , |
|---|
and the decision dated 13.02.2020 in C.A. No. 3867 of 2010,
Delhi Development Authority through its Vice Chairman vs. Bhai
Sardar Singh and Sons , to submit that the order dated
30.10.2001 being conditional and the withdrawal of Rs.
7,78,280/- being in terms of the conditional order i.e., on
furnishing of personal undertaking given by the respondent,
the direction for payment of interest @ the rate of 18% on
Rs.7,78,280/- would continue till the decision of the appeal
under Section 37 of the Act on 02.02.2012. It is only then
that the complete title and the payment got vested in the
respondent.
17.
In our opinion, the submission made is fallacious and is
| contrary to law. In | Ramanathan | (supra), the amount which was |
|---|
deposited by the judgment-debtor was not withdrawn by the
| decree holder. The judgment in | Ramanathan | (supra) in paragraph |
|---|
| 12 thereof, specifically states that | “on principle, it appears |
|---|
to us that the facts of a judgment-debtor’s depositing a sum
in court to purchase peace by way of stay of execution of the
decree on terms that the decree holder can draw it out on
furnishing security, does not pass title to the money to the
7
decree holder. He can if he likes take the money out in terms
of the order, but so long as he does not do it, there is
nothing to prevent the judgment-debtor from taking it out by
furnishing another security, say, immovable property, if the
court allows him to do so and on his losing the appeal putting
the decretal amount in court in terms of Order XXI Rule 1 of
the CPC in satisfaction of the decree”. The aforesaid
narration makes it clear that this was not a case in which the
decree holder had withdrawn the money. The penultimate
paragraph of this judgment records that the deposit made was
not unconditional, and that the decree holder was not free to
withdraw the amount whenever he likes even before the disposal
of the appeal. In order to do so, he had to give security in
terms of the order, which he did not furnish. It may be noted
that this judgment is prior to the substitution of Rule 1 to
Order XXI of the CPC by Act No. 104 of 1976 with effect from
| In the decision of this Court in | Delhi Development Authority |
|---|
| (supra), | the money deposited by the Delhi Development |
|---|
Authority in the court was not withdrawn by the contractor
Bhai Sardar Singh and Sons. In fact, an application was filed
by Bhai Sardar Singh and Sons to permit them to withdraw the
money, but they were not permitted to do so. In this
background, it was held that the deposit was not payment in
terms of Rule 1 to Order XXI of the CPC. Under the Arbitration
6
Whether the amendment has the effect of substitution of the principle
enunciated in Ramanathan’s case ( supra ), need not be examined in this decision.
8
Act, 1940, the award can be executed after the award is made
Rule of the Court. Therefore, an award under the Arbitration
| Act, 1940 | per se | was not a decree of the Court. Under the |
|---|
provisions of the Act, i.e., the Act, 1996, an award is a
decree of the Court and is executable, unless objections are
| filed under Section 34 of the Act. | 7 | |
|---|
19.
In the present case, objections under Section 34 of the Act
were filed and dismissed on 28.02.2001. Thereupon, the award
was executable.
20.
In Delhi Development Authority ( supra ), on the aspect of
liability of Delhi Development Authority to pay interest on
the deposit made in court for failure to issue written notice,
it was held that it was not necessary. The reason was that the
decree holder was aware of the deposit made by the judgment
debtor. Therefore, the decree holder cannot be permitted to
urge and plead that he was served a notice of the deposit.
Accordingly, the decree holder, it was held, was not entitled
to interest post the decision, even when the judgment debtor
had not served any formal notice as required under sub-rule
(4) to Rule 1 to Order XXI of the CPC.
21. In the present case, the appellate court, on the appeal
preferred under Section 37 of the Act did grant stay, subject
to the condition that the appellant would deposit 50% of the
| 7 | Post substitution by Act No.3 of 2016 with retrospective effect from 23 | | rd |
|---|
| October 2015, the legal position has undergone change. | | Section 36 as it stood | |
“36. Enforcement. – Where the time for making an application to set aside
the arbitral award under section 34 has expired, or such application having been
made, it has been refused, the award shall be enforced under the Code of Civil
Procedure, 1908 (5 of 1908) in the same manner as if it were a decree of the
Court.”
9
amount. Rs. 7,78.280/- was deposited by the appellant on
05.11.2001. The stay, therefore, only operated for the balance
amount. On the balance amount, certainly, the appellant would
be liable to pay interest @ the rate of 18% per annum till the
date of actual payment. However, on Rs.7,78,280/- paid, after
adjusting/appropriating payment due on the interest accrued,
on the balance principal amount paid to the respondent,
interest would not be payable.
| 22. | | The respondent has relied on the principle that the interim |
|---|
order merges into the final order. In Civil Appeal No. 2417 of
| 2022, decided on 25.03.2022, titled | State of Uttar Pradesh |
|---|
| through Secretary and Ors. | v. | Prem Chopra | , this Court had |
|---|
| referred to an earlier decision in | State of Rajasthan | v. | J.K.S |
|---|
| Synthetics and Anr. | , (2011) 12 SCC 518, wherein it has been |
|---|
observed that where a stay is granted by way of interim order
on dismissal of the writ petition or vacation of the interim
order, the beneficiary of the interim order shall have to pay
interest on the amount withheld or not paid by him by virtue
of the interim order. The aforesaid observations, in fact,
support the appellant and not the respondent. The observations
hold that the person liable to make payment would have to pay
the principal amount along with the interest which is
specified in the contract or the statute as he had enjoyed
benefit of the stay order. The interest is payable only on
the amount that is not paid. It will be incongruous to hold
that the person would be liable to pay interest even in
respect of the amount, which has been paid and handed over to
10
the decree holder.
| This Court in | Raunaq International Limited | v. | I.V.R. |
|---|
| Construction Limited and Others | , (1999) 1 SCC 492, has |
|---|
observed that the parties, at whose instance, interim orders
are obtained, should be made accountable for the consequences
of the interim order. These observations obviously are
relevant in the context of the present case to the extent that
the appellant is liable to pay interest @ the rate of 18% per
annum on the amount which was not paid to the respondent.
However, the amount which was withdrawn and paid to the
respondent, no interest liability would occur and would be
payable.
24.
The respondent submits that the payment of Rs. 7,78,280/-
being conditional, the respondent would have been under an
obligation to refund the said amount in case the appellant had
succeeded in the appeal under Section 37 of the Act, 1996.
This argument does not impress, as in the event the appellant
had succeeded in their appeal, the entire amount paid would
have been refundable. The undertaking was not onerous, and was
to operate only if the amount of Rs. 7,78,280/- was not
refunded by the respondent. The respondent had obviously used
and utilized the money. The appellant did not have any right
on the money paid to the respondent, who could use it in a
manner and way he wanted. There was no charge. Money is
fungible and would have gotten mixed up with the other amounts
available with the respondent. Right to restitution would not
11
make the payment conditional. Interest has been
jurisprudentially defined as the price paid for money
borrowed, or retained, or not paid to the person to whom it is
due, generally expressed as a percentage of amount in one
year. It is in the nature of the compensation allowed by law
or fixed by parties, for use or forbearance or damage for its
8
detention. In the context of the present case, interest would
be the compensation payable by the appellant to the
respondent, for the retention or deprivation of use of money.
Therefore, once the money was paid to the respondent, interest
as compensation for deprivation of use of money will not
9
arise.
25. In view of the aforesaid reasons, we allow the present appeal
and set aside the impugned order dated 19.06.2017, whereby the
appellant had been directed to pay interest @ the rate of 18%
per annum on Rs.14,49,300/- from the date of the award till
the date of decision of the appeal under Section 37 of the Act
on 02.02.2012. We hold that the appellant would be liable to
| pay interest @ the rate of 18% on Rs.9,13,483.00/9,30,300.00 | 10 |
|---|
(the exact amount to be calculated and determined by the
executing court) with effect from 08.11.2001 till the payment
8
Hyder Consulting (UK) Ltd. v. State of Orissa , (2015) 2 SCC 189, as quoted in
Webster’s Third New International Dictionary and Corpus Juris Secondum.
9
We have not examined and decided the issue either way – whether interest would
be payable on the amount withdrawn in case withdrawal is on conditions like
furnishing bank guarantee etc.
10 We have taken the figures from the calculations made by appellant – M/s Nepa
Limited, which is enclosed as Annexure ‘A’ and by Manoj Kumar Agarwal –
respondent, which is enclosed as Annexure ‘B’ to this judgment. As per the
appellant, the principal amount due and payable is Rs.9,13,483/-. However, as per
the respondent, the principal amount due and payable is Rs. 9,30,300/-. The
difference is only Rs.17,000/-, albeit, the correct computation would be made by
the executing court.
12
was/is made.
26.
Learned counsel for the appellant has submitted that they have
made over-payment and our attention is drawn to annexure (P-
12), which shows that they have paid total amount of Rs.
56,70,096/-. We would not like to go into the said aspect, as
this would relate to computation and calculations. The
appellant is entitled to invoke Section 144 of the CPC and
take recourse to appropriate remedies available to him in law,
in case over-payment had been made to the respondent.
27.
The appeal is allowed in the aforesaid terms.
28. Pending application(s), if any, shall stand disposed of.
..................J.
(SANJIV KHANNA)
..................J.
(SUDHANSHU DHULIA)
NEW DELHI.
DECEMBER 08, 2022.
ps
13
Annexure ‘A’
Sheet of Calculation of Interest by NEPA Limited Through its Senior Manager (Legal)
– Appellant
| S. No. | Particular | Amount (in INR) | |
|---|
| A. | Principal Amount as per the Award dated<br>14.04.2000 | 14,49,300/- | |
| B. | Rate of Interest @18% | For an year:<br>2,60,874 | Per day<br>714.72 |
| C. | Interest till 22.10.2001 | 3,96,313 | |
| D. | Amount paid on 22.10.2001 (@ pg 175) | (1,50,000) | |
| E. | Balance Interest | 2,46,313 (C-D) | |
| F. | Interest till 08.11.2001 (Date of withdrawal of<br>50% Awarded amount by the Respondent) | 12,150 | |
| G. | Total | 2,58,463 (E+F) | |
| H. | 50% of Amount deposited on 08.11.2001 | 7,78,280 | |
| I. | Adjusted towards interest | (2,58,640) | |
| J. | Adjusted towards principal | 5,19,817 (H-I) | |
| K. | New Principal as on 08.11.2001 | 9,13,483 | |
14
Annexure ‘B’
Sheet of Calculation of Interest by Manoj Kumar Agrawal – Respondent
| S. No. | Particular | Amount (in INR) | |
|---|
| A. | Principal Amount as per the Award dated<br>14.04.2000 | 14,49,300/- | |
| B. | Rate of Interest @18% | - | - |
| C. | Interest till 22.10.2001 | 3,97,028 | |
| D. | Amount paid on 22.10.2001 (@ pg 175) | (1,50,000) | |
| E. | Balance Interest | 2,47,028 (C-D) | |
| F. | Interest till 08.11.2001 (Date of withdrawal of<br>50% Awarded amount by the Respondent) | 12,150 | |
| G. | Total | 2,59,178 (E+F) | |
| H. | 50% of Amount deposited on 08.11.2001 | 7,78,280 | |
| I. | Adjusted towards interest | (2,59,178) | |
| J. | Adjusted towards principal | 5,19,102 (H-I) | |
| K. | New Principal as on 08.11.2001 | 9,30,300 | |