Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 5
PETITIONER:
LAKSHMICHAND & BALCHAND
Vs.
RESPONDENT:
STATE OF ANDHRA PRADESH
DATE OF JUDGMENT05/11/1986
BENCH:
PATHAK, R.S.
BENCH:
PATHAK, R.S.
OZA, G.L. (J)
CITATION:
1987 AIR 20 1987 SCR (1) 108
1987 SCC (1) 19 JT 1986 785
1986 SCALE (2)725
ACT:
Civil Procedure Code, 1908--Order 21, Rule 18---Power of
the Court to allow set off--When is a claim rounded on
doctrine of equitable set off.
HEADNOTE:
The appellant-contractor entered into two agreements
with the respondent State for carrying out certain road
repairing works. Clause 68 of the agreement provided for
preparation of the final bill of the contractor after taking
into account amounts received by him earlier, while clause
71 permitted the State to retain or deduct money due under
the contract from an amount due to the contractor under any
other contract. While the work was in progress the contrac-
tor made certain claims in respect of loss suffered on
account of delay, escalation of rates and other heads. The
arbitrator held the contractor entitled to Rs.99 lacs. The
civil court refused to pass a decree in terms of the award.
The High Court on appeal allowed the claim to the extent of
Rs.16 lacs together with interest. The contractor claimed
recovery of decretal amount with interest in terms of the
award and cost of execution proceedings. The respondent
State contested the claim contending that a sum of Rs.22
lacs was recoverable from the appellant and claimed adjust-
ment against the amount due under the decree. The Executing
Court held the respondent State entitled to set off.
In the revision petition before the High Court it was
contended for the appellant that the respondent State was
not entitled to set off in execution proceedings, and that
the sum of which adjustment was sought consisted of (a) an
amount claimed by respondent State as due to it upon prepa-
ration of the final bill in respect of the contracts covered
by the award, and (b) an amount claimed by the respondent
State under a separate contract on the ground that the
appellant had committed a breach of that contract. The High
Court having regard to cl. 68 of the agreement found the
respondent State entitled to set off so far as the first
claim was concerned. It justified the second claim also by
reference to cl. 71 of the contract but held that adjustment
claimed could not be made against the decretal amount but
must await determination upon the arbitration.
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 5
109
In this appeal by special leave it was contended that
Order 21, Rule 18 of the Code of Civil Procedure, under
which a set off can be claimed, does not apply in terms to
the present case.
Allowing the appeal in part, the Court,
HELD: 1. The Court has the power to allow a set off in
certain circumstances even in cases which do not strictly
fail within the terms of Order 21, Rule 18 of the Code of
Civil Procedure. [112B]
Bhoganadham Seshaiah v. Budhi Veerabhadrayya (died) &
Ors., AIR 1972 Andhra Pradesh 134, approved.
2. The respondent State’s claim to adjustment of the
amount due to it upon the preparation of the final bill is
covered by cl. 68 of the contract. What was awarded to the
contractor under the decree was an amount relating to a part
only of the work entrusted to him. The contract was still in
the process of execution. Any amount claimed by him for such
work was subject to a final settlement of account on the
preparation of the final bill. The fight to payment depended
on the terms of the contract. Any payment made while the
contract was still being worked out was in the nature of a
provisional payment. It was always subject to adjustment
against amounts found due on preparation of the final bill.
Such adjustment was implied in the very terms of the con-
tract. The High Court was, therefore, right in holding that
the amount claimed by the State Government on this count was
entitled to be set off against the decretal amount claimed
by the contractor. [112C E]
3.1 The claim to adjustment of the amount claimed on
breach of another contract is rounded in the doctrine of
equitable set off but there is no evidence on record to
bring the case within the operation of the doctrine. It is
not a case where cross demands rise out of the same transac-
tion, or the demands are so connected in their nature and
circumstances that they can he looked upon as part of one
transaction. [112F G]
3.2 The benefit of cl. 71 of the contract can be claimed
only if the amount sought to. he retained is an ascertained
sum, an amount which can be readily adjusted against the
amount payable under the other contract. In the instant
case, the amount sought to be adjusted had yet to be deter-
mined as a liability against the contractor. The decision of
the High Court cannot, therefore, he sustained. [112GH,
113A]
JUDGMENT:
CIVIL APPELLATE JURISDICTION: Civil Appeal No. 4083 of
1986
110
From the judgment and order dated 13.4.1984 of the
Andhra Pradesh High Court in C.R.P. No. 3072 of 1983.
Dr. Y.S. Chitale, G.N. Narayan and N. Nittar for the Appel-
lant.
T.S. Krishnamurthy Iyer, T.V.S.N. Chaff and Ms. V.
Grover for the Respondent;
The Order of the Court was delivered by
PATHAK, J. This appeal is directed against the judgment
and order of the High Court of Andhra Pradesh disposing of a
revision petition filed by the Appellant in execution pro-
ceedings.
The Appellant is a contractor, who entered into two
agreements with the Government of the State of Andhra Pra-
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 5
desh for providing B.T. Macadam wearing coat and seal coat
along two stretches of the Hyderabad-Vijayawada National
Highway. While the work was in progress, the contractor made
certain claims in respect of the loss suffered on account of
delay, escalation of rates and other heads. The claims were
referred to arbitration. On September 4, 1979 the Arbitrator
held the contractor entitled to a sum of Rs.99,00,000 under
five heads of claim. The contractor applied to the Civil
Court for making the award a rule of the Court while the
State Government prayed for setting aside the entire award.
The Civil Court set aside the award and refused to pass a
decree in terms of the award. The contractor-appealed to the
High Court, and on April 19, 1982 the High Court allowed the
appeal to the extent of one of the claims only, the claim
being for loss of profit in the sum of Rs. 16,00,000 togeth-
er with interest. The appeal was dismissed in respect of the
other heads of claim.
For the realisation of the amount due under the decree
the contractor filed Execution Petition No. 48 of 1982
before the V Additional Judge, City Civil Court, Hyderabad
claiming recovery of Rs. 16,00,000 towards the decretal
amount, Rs.7,80,000 towards interest in terms of the award
up to the date of the execution petition and Rs.8,691 to-
wards costs of the Execution Petition. The State Government
filed objections, contending inter alia that a sum of
Rs.22,91,332 was recoverable by it from the contractor and
claimed adjustment against the amount due to the contractor
under the said decree. It urged that after adjusting the
amount due to the State Government the balance payable to
the contractor would stand reduced to Rs.76,667. This sum
111
together with the other deposits of the contractor with the
Government and refundable to him, viz. Rs.3,92,236 was
deposited in the Executing Court. The contractor withdrew
the amount without prejudice to his rights to contest the
adjustment. The Executing Court held that the State Govern-
ment was entitled to set off the amounts claimed by it, and
accordingly adjourned the Execution Petition for further
proceedings.
The contractor filed a revision petition before the High
Court and contended that the State Government was not enti-
tled to claim adjustment in execution proceedings. It was
pointed out that the sum of Rs.22,91,332 of which adjustment
was sought by the State Government against the amount for
which the contractor had taken out execution, consisted of
(a) an amount of Rs.10,21,800 claimed by the State Govern-
ment as due to it upon the preparation of the final bill in
respect of the contracts covered by the award and (b) an
amount of Rs. 12,69,532 claimed by the State Government
under a separate contract on the ground that the contractor
had committed a breach of that contract. The contractor
disputed both claims. He contended that the final bill in
respect of the earlier contract had been prepared in his
absence and that he challenged the inclusion of several
items in that bill. In regard to the latter amount he urged
that he was not guilty of any breach of contract.
The High Court has found that so far as the first claim
to adjustment was concerned the State Government was justi-
fied in making it because the arbitration was effected while
the work was still in progress and the contract was in the
process of execution by the contractor, and having regard to
clause 68 of the agreement final payment had to be made to
the contractor after taking into account the amount which
had been received by him earlier. The second claim to ad-
justment was made by the State Government under another
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 4 of 5
contract, and the High Court justified that claim by refer-
ence to clause 71 of that contract, which permitted the
Government to retain or deduct money due under the contract
from an amount due to the contractor under any other con-
tract. However, it held that the adjustments claimed by the
State Government could not be made against the decretal
amount but must await determination upon due arbitration.
Learned counsel for the Appellant contends before us
that the State Government is not entitled to a set off at
all because, he says, a set off can be claimed only under
Order 21 Rule 18 of the Code of Civil Procedure and that
provision does not apply in terms to the present
112
case. Learned counsel for the respondent urges, on the other
hand, that the power of the Court extends to granting an
equitable set off in appropriate cases, and the High Court
was therefore justified in making the order which it did.
We have no doubt that in certain cases the Court has the
power to allow a set off even in cases which do not strictly
fall within the terms of Order 21 Rule 18 of the Code. A
Full Bench of the Andhra Pradesh High Court has discussed
the matter in Bhoganadham Seshaiah v. Budhi Veerabhadrayya
(died) and Others, AIR [1972] Andhra Pradesh 134 and has
examined at some length the circumstances in which such set
off may be granted. The facts before us, however, call for a
somewhat different consideration. So far as the first claim
to adjustment is concerned, the matter is covered by clause
68 of the contract. What was awarded to the contractor under
the decree was an amount relating to a part only of the work
entrusted to him. The contract was still in the process of
execution. Any amount claimed by him for such work was
subject to a final settlement of account on the preparation
of the final bill. The right to payment depended on the
terms of the contract. Any payment made while the contract
was still being worked out was in the nature of a provision-
al payment. It was always subject to adjustment against
amounts found due against the contractor on preparation of
the final bill. Such adjustment was implied in the very
terms of the contract. Therefore, in regard to the adjust-
ment claimed by the State Government on the first count the
High Court is right, in our opinion, in holding that the
amount claimed by the State Government, as determined on
arbitration, was entitled to a set off against the decretal
amount claimed by the contractor, and that payment of the
decretal amount was to be subject to such adjustment.
In regard to the claim to adjustment on the second count
the position is more controversial. The claim is rounded in
the doctrine of equitable set off, but we do not find evi-
dence before us to bring the case within the operation of
the doctrine. It is not a case where cross demands rise out
of the same transaction or the demands are so connected in
their nature and circumstances that they can be looked upon
as part of one transaction. Nor can assistance be derived
from clause 71. The benefit of that provision can be claimed
only if the amount sought to be retained is an ascertained
sum, an amount which can be readily adjusted against the
amount payable under the other contract. Here, the amount
sought to be adjusted has yet to be determined as a liabili-
ty against the contractor. It has been disputed by the
appellant. Accordingly, clause 71 cannot be invoked. In the
result, the decision
113
of me High Court in respect of the adjustment of Rs.
12,69,532 cannot be sustained.
In the circumstances, the appeal is allowed in part, the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 5 of 5
judgment and order of the High Court is modified in so far
that while the adjustment claimed by the State Government on
the basis of the final bill relating to the contract covered
by the award is maintained, the direction in respect of the
adjustment of the claim made under the other contract is set
aside. The parties will bear their own costs.
P.S.S. Appeal al-
lowed.
114