Full Judgment Text
REPORTABLE
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NOS. 677-678 OF 2021
MAHARASHTRA STATE ELECTRICITY
DISTRIBUTION COMPANY LIMITED ...APPELLANT(S)
VERSUS
ADANI POWER MAHARASHTRA
LIMITED AND ANOTHER ...RESPONDENT(S)
J U D G M E N T
B.R. GAVAI, J.
1. The present appeals challenge the judgment and order
th
dated 28 September 2020 passed by the Appellate Tribunal
for Electricity (hereinafter referred to as ‘APTEL’), in cross
appeals being Appeal No. 116 of 2019, filed by Maharashtra
State Electricity Distribution Company Limited (hereinafter
referred to as ‘MSEDCL’), the appellant herein, and Appeal
No. 155 of 2019, filed by ADANI Power Maharashtra Limited
Signature Not Verified
(hereinafter referred to as ‘APML’), respondent No. 1 herein,
Digitally signed by
Narendra Prasad
Date: 2023.04.20
11:59:45 IST
Reason:
th
thereby challenging the order dated 7 February 2019,
1
passed by Maharashtra Electricity Regulatory Commission
(hereinafter referred to as ‘MERC’).
2. The facts, in brief, giving rise to the present appeals are
as under:
APML and MSEDCL had entered into four long term
Power Project Agreements (hereinafter referred to as ‘PPA’)
th
dated (a) 8 September, 2008 for 1320 MW (hereinafter
st
referred to as ‘1320 MW PPA’); (b) 31 March, 2010 for 1200
th
MW (hereinafter referred to as ‘1200 MW PPA’); (c) 9 August,
2010 for 120 MW (hereinafter referred to as ‘120 MW PPA’)
th
and (d)16 February, 2013 for 440 MW (hereinafter referred
to as ‘440 MW PPA’), pursuant to the competitive bidding
process conducted by MSEDCL.
3. APML, being aggrieved by the Change in Law on
account of the Ministry of Coal bringing into force the New
Coal Distribution Policy, 2013 (hereinafter referred to as
‘NCDP, 2013’), which revised the arrangements prescribed
under New Coal Distribution Policy, 2007 (hereinafter
referred to as ‘NCDP, 2007’) for supply of coal, had filed a
petition being Case No. 189 of 2013, seeking compensation
2
in Tariff on account of Change in Law under the PPAs before
MERC. Finally, in the light of the judgment of this Court in
the case of Energy Watchdog v. Central Electricity
1
Regulatory Commission and Others , the said petition,
after being remanded by the APTEL, was heard afresh by the
MERC.
th
4. Vide order dated 7 March, 2018, the MERC allowed
the claims of APML on account of Change in Law due to
changes brought about by NCDP, 2013. APML, thereafter,
preferred a review petition, being Review Petition No. 167 of
2018 seeking extension of Change in Law relief for domestic
coal shortfall beyond March, 2017 on account of changes
introduced by the Scheme for Harnessing and Allocating
Koyala (Coal) Transparently in India (hereinafter referred to
as ‘SHAKTI Policy’) which had been released by the Ministry
nd
of Power on 22 May, 2017. As per Clause 6.1 of the SHAKTI
Policy, the Appropriate Commission was required to consider
the cost of imported/market based e-auction coal procured
for making up the shortfall in the domestic coal for pass-
through.
1 (2017) 14 SCC 80
3
5. The MERC dismissed the said review petition. However,
liberty was granted to APML to file a fresh petition to seek
extension of Change in Law relief for domestic coal shortfall
beyond March, 2017 in view of the introduction of the
SHAKTI Policy. Subsequently, APML filed a fresh petition,
being Case No. 290 of 2018, before the MERC seeking relief
in support of Change of Law under the respective PPAs for
non-availability/short supply of domestic coal under SHAKTI
Policy after March, 2017.
th
6. The MERC, vide its order dated 7 February 2019,
allowed the petition and granted relief for Change in Law due
to the promulgation of SHAKTI Policy. However, the relief was
directed to be computed on the same methodology and
th
parameters as approved by the MERC vide its order dated 7
March, 2018. Cross appeals were filed before the APTEL by
APML and MSEDCL against the aforesaid order.
7. The learned APTEL framed the following five issues for
adjudication :
“ Issue No.1:- Whether introduction SHAKTI Policy
does not amount to Change in Law
under the PPAs entered into
between APML and MSEDCL and
4
whether APML has not provided
notice of such Change in Law to
the Respondent MSEDCL.
Issue No.2:- Whether the MERC is correct in
holding that for the purpose of
Change in Law compensation,
shortfall in domestic coal shall be
limited to a maximum of 25% of
ACQ after the introduction of
SHAKTI Policy.
Issue No.3:-
(a) whether the MERC was correct
in holding that the SHR submitted
by the Appellant in its bid or SHR
and Auxiliary Consumption norms
specified for new generating
stations under the MYT
Regulations, 2011, whichever is
superior shall form the basis for
computing Change in Law
compensation under the PPAs?
(b) Whether the MERC was correct
in holding that the reference GCV
of domestic coal supplied by CIL
shall be the middle value of GCV
range of assured coal grade in
LoA/PSA/MoU and not the GCV
as received?
Issue No.4:- Whether the MERC was justified in
directing APML to provide advance
intimation of impact on energy
charge by using alternate coal for
the purpose of Merit Order
Despatch?
Issue No.5:- Whether the Respondent MSEDCL
is justified in contesting APML’s
entitlement to Carrying Cost.”
th
8. The APTEL, vide judgment and order dated 28
September 2020, answered the issues as under:
5
“15.1 Issue No.1:- We hold that the introduction of
SHAKTI POLICY amounts to change in law and
all the ingredients of change in law are:, duly
met under the respective PPAs. The impugned
order is therefore affirmed on this issue.
Issue No.2:-
15.2 We hold that findings in the
impugned order relating to the issue of
restricting the quantum of shortfall in
domestic coal to a maximum of 25% are
against the basic principles of restitution I
under the change in law provisions of the
PPAs.
15.3 Issue No.3:- In line with our judgment dated
14.09.2020 in Appeal No.182 of 2019, we hold
that the change in law compensation shall be
calculated based on the SHR specified in the
MERC MYT Regulations, 2011 or the actual
SHR whichever is lower and actual GCV of coal
as received as the plant site.
15.4 Issue No.4:- We find that the directions issued
by the State Commission regarding advance
intimation requirement is not consistent with
normal Rules of MOD preparation and also
does not provide a level playing field for IPPs.
15.5 Issue No.5:- We find that allowance of carrying
cost is a settled position of law and the State
Commission has already allowed the same to
the Appellant, APML.”
9. Consequently, the APTEL dismissed the appeal
preferred by MSEDCL and allowed the appeal preferred by
APML. Hence, MSEDCL has preferred the present appeals.
10. We have heard Shri Gopal Jain, learned Senior Counsel
appearing on behalf of the appellant-MSEDCL and Dr.
6
Abhishek Manu Singhvi, learned Senior Counsel appearing
on behalf of respondent No. 1–APML.
11. Shri Jain submitted that the SHAKTI Policy (Part-B)
restores the position as covered by NCDP 2007. He,
therefore, submits that, since under the SHAKTI Policy there
is 100% assured coal supply, then there is no question of
APML being compensated on account of shortfall in coal
supply. He submits that SHAKTI Policy is in continuation of
NCDP 2007. However, this has not been taken into
consideration by the learned APTEL.
12.
Shri Jain further submits that both APTEL and MERC
have failed to take into consideration that APML had not
complied with the condition of serving a mandatory notice to
MSEDCL for Change in Law under Article 13.3.2 of the 1320
MW PPA.
13. Dr. Singhvi, on the contrary, submits that
undisputedly, SHAKTI Policy would amount to Change in
Law. He submits that there is a concurrent finding of fact by
both APTEL and MERC that SHAKTI Policy is a Change in
Law event.
7
14. Dr. Singhvi further submits that there is also a
concurrent finding by APTEL and MERC on the issue of
mandatory notice. He submits that unless these findings are
found to be perverse or are based on extraneous
consideration, it will not be permissible for this Court to
interfere with the same.
15. When the batch of appeals was being heard, it was
agreed between all the parties that this Court should first
decide Civil Appeal No. 684 of 2021 ( Maharashtra State
Electricity Distribution Company Limited (MSEDCL) v.
2
ADANI Power Maharashtra Limited (APML) and Others )
and Civil Appeal No. 6927 of 2021 ( MSEDCL v. GMR Warora
Energy Ltd. and Others ) inasmuch as three of the issues
involved in all the appeals were common. It was submitted
that those two appeals could be decided by deciding the three
common issues. However, insofar as the other appeals are
concerned, in addition to the three common issues, certain
additional issues were also involved.
16. The said three common issues are thus:
2 2023 SCC OnLine 233
8
| (i) Whether Change in Law relief on account of NCDP<br>2013 should be on ‘actuals’ viz. as against 100% of<br>normative coal requirement assured in terms of<br>NCDP 2007 OR restricted to trigger levels in NCDP<br>2013 viz. 65%, 65%, 67% and 75% of Assured Coal<br>Quantity (ACQ)? | |
|---|---|
| (ii) Whether for computing Change in Law relief, the<br>operating parameters be considered on ‘actuals’<br>OR as per technical information submitted in bid? | |
| (iii) Whether Change in Law relief compensation to be<br>granted from 1st April 2013 (start of Financial Year)<br>or 31st July 2013 (date of NCDP 2013)? | |
| 17. Vide the judgment and order dated 3rd March 2023 in<br>the case of MSEDCL v. APML and Others (supra), this Court<br>decided those two appeals after considering the aforesaid<br>three issues. | |
| 18. The first issue was answered by this Court, holding that<br>the Change in Law relief for domestic coal shortfall should be<br>on ‘actuals’ i.e. as against 100% of normative coal<br>requirement assured in terms of NCDP, 2007. Insofar as the |
9
second issue is concerned, it was held that the Station Heat
Rate (SHR) and Auxiliary consumption should be considered
as per the Regulations or actual, whichever is lower. The
third issue was answered by holding that the Start date for
st
the Change in Law event for the NCDP, 2013 is 1 April 2013.
19. Insofar as Issue Nos. 2 and 3 as framed by the APTEL
are concerned, the same stand squarely covered by the
judgment of this Court in the case of MSEDCL v. APML and
Others (supra). The remaining three issues, which are
required to be considered in the present appeals, are thus:
“ Issue No.1:- Whether introduction SHAKTI Policy
does not amount to Change in Law
under the PPAs entered into
between APML and MSEDCL and
whether APML has not provided
notice of such Change in Law to
the Respondent MSEDCL.
Issue No. 2:- .....
Issue No. 3:- …………
Issue No. 4:- Whether the MERC was justified in
directing APML to provide advance
intimation of impact on energy
charge by using alternate coal for
the purpose of Merit Order
Despatch?
Issue No. 5:- Whether the Respondent MSEDCL is
justified in contesting APML’s
entitlement to Carrying cost.”
10
20. We will first consider the question as to whether the
SHAKTI Policy would amount to Change in Law.
21. It will be apposite to refer to some relevant parts of the
judgment of this Court in the case of Energy Watchdog
(supra), which read thus:
| “ | 50. | ……Even otherwise, from a reading of Clause | ||
|---|---|---|---|---|
| 13, it is clear that Clause 13.1.1 is in four different | ||||
| parts. The first part speaks of enacted laws; the | ||||
| second speaks of interpretation of such laws by | ||||
| courts or other instrumentalities; the third speaks | ||||
| of changes in consents, approvals or licences which | ||||
| result in change in cost of the business of selling | ||||
| electricity; and the fourth refers to any change in | ||||
| the declared law of the land for the project, cost of | ||||
| implementation of resettlement and rehabilitation or | ||||
| cost of implementing the environmental | ||||
| management plan. “Competent court” in Clause | ||||
| 13.1.2 is defined as meaning only the judicial | ||||
| system of India. |
| 56. | However, insofar as the applicability of Clause | |
|---|---|---|
| 13 to a change in Indian law is concerned, the | ||
| respondents are on firm ground. It will be seen that | ||
| under Clause 13.1.1 if there is a change in any | ||
| consent, approval or licence available or obtained | ||
| for the project, otherwise than for the default of the | ||
| seller, which results in any change in any cost of | ||
| the business of selling electricity, then the said | ||
| seller will be governed under Clause 13.1.1. It is | ||
| clear from a reading of the Resolution dated 21-6- | ||
| 2013, which resulted in the letter of 31-7-2013, | ||
| issued by the Ministry of Power, that the earlier coal | ||
| distribution policy contained in the letter dated 18- | ||
| 3-2007 stands modified as the Government has now | ||
| approved a revised arrangement for supply of coal. |
11
| It has been decided that, seeing the overall domestic | |
|---|---|
| availability and the likely requirement of power | |
| projects, the power projects will only be entitled to a | |
| certain percentage of what was earlier | |
| allowable……” |
22. It can thus be seen that this Court has held that if there
is a Change in any consent, approval or licence available or
obtained for the project, otherwise than for the default of the
seller, which results in any change in any cost of the
business of selling electricity, then the said seller will be
governed under Clause 13.1.1 of the PPA. As already
discussed hereinabove, this Court has consistently held that
| modification to NCDP 2007 by the communication dated 31 | st |
|---|
July 2013 would amount to Change in Law and the
generating companies would be entitled to compensation on
account of such Change in Law. Undisputedly, SHAKTI
Policy also reduces the ACQ as was assured under the 2007
NCDP. Consequently, SHAKTI Policy will also have to be held
to be Change in Law.
23. A three-Judges Bench of this Court in the case of
Jaipur Vidyut Vitaran Nigam Limited and Others v.
12
3
ADANI Power Rajasthan Limited and Another
, has also
considered the effect of SHAKTI Policy and held that the
seller would be entitled to the benefit occurring on account of
SHAKTI Policy. As such, the contention that SHAKTI Policy
does not amount to Change in Law is without substance.
| 24. Following the judgments in the case of Energy<br>Watchdog (supra) and ADANI Power Rajasthan Limited<br>(supra), this Court, in the case of MSEDCL v. APML and<br>Others (supra), observed thus: | ||
|---|---|---|
| “130. The MoP, thereafter, addressed a<br>communication dated 31st July 2013 to the<br>Secretary, CERC specifically pointing out the<br>decision of the CCEA to the effect that the higher<br>cost of imported coal was to be considered for pass-<br>through as per the modalities suggested by CERC.<br>The communication states that, as per the decision<br>of the Government, the higher cost of<br>import/market based e-auction coal will have to be<br>considered for being made a pass-through on a case<br>to case basis by CERC/SERC to the extent of<br>shortfall in the quantity indicated in the LoA/FSA. | ||
| 131. The Tariff Policy dated 28th January 2016<br>issued by the MoP in paragraph 6.1 also specifically<br>notes this position and states that, in case of<br>reduced quantity of domestic coal supplied by CIL<br>vis-à-vis the assured quantity or quantity indicated<br>in LoA/FSA, the cost of imported/market based e-<br>auction coal procured for making up the shortfall |
3 2020 SCC OnLine SC 697
13
shall be considered for being made a pass-through
by the Appropriate Commission.
132. Undisputedly, in the case of Energy
Watchdog (supra) as well as in Adani Rajasthan
case (supra) this Court has held that on account of
the Change in Law, the generating companies were
entitled to compensation so as to restore the party
to the same economic position as if such Change in
Law had not occurred. Had the Change in Law not
occurred, the generating companies would have
been entitled to the supply as assured by the
CIL/Coal Companies under the FSA.
133. It is contended by the DISCOMS that in the
case of Energy Watchdog (supra), this Court has
specifically held that the doctrine of force
majeure was not applicable if there was an
unexpected rise in the price of coal and, as such, it
will not absolve the generating companies from
performing their part of the contract. It is submitted
that when the bidders submitted their bids, this
was a risk they knowingly took. We find the said
submission to be without substance. The generators
are not claiming compensation on the basis of rise
in price of coal or on the ground of force
majeure. Their claims, in fact, are on the basis of
the Change in Law, which this Court, in the case
of Energy Watchdog (supra) as well as in Adani
Rajasthan case (supra), has upheld on the ground
of Change in Law.
134. The contention of the DISCOMS that the Adani
Rajasthan case (supra) is not applicable to the facts
of the present case inasmuch as in Adani Rajasthan
case (supra), the State of Rajasthan had assured
100% coal supply and that it was not a case of FSA,
is, in our considered view, without substance. In the
present case also, the NCDP 2007 had assured
100% fuel/coal supply of the normative value.
14
135. The restitutionary principle has been stated by
this Court in the case of Uttar Haryana Bijli Vitran
Nigam Limited (UHBVNL) (supra) thus:
10.
“ Article 13.2 is an in-built
restitutionary principle which
compensates the party affected by such
change in law and which must restore,
through monthly tariff payments, the
affected party to the same economic
position as if such change in law has not
occurred. This would mean that by this
clause a fiction is created, and the party
has to be put in the same economic
position as if such change in law has not
occurred i.e. the party must be given the
benefit of restitution as understood in
civil law. ………….””
25. As such the restitution principle, as has been
consistently applied by this Court on account of Change in
Law, will also be applicable on account of change occurring
due to the introduction of SHAKTI Policy.
26. The contention of the appellant that the SHAKTI Policy
brings back the position of NCDP 2007 and assures 100%
coal supply, is not factually correct. A perusal of the SHAKTI
Policy would reveal that SHAKTI Policy assures 70% of ACQ
as against 100% in 2007 NCDP.
15
| 27. In that view of the matter, we find that the contention<br>that SHAKTI Policy restores the position of 2007 NCDP is<br>factually incorrect. | ||
|---|---|---|
| 28. Insofar as Change in Law Notice is concerned, the<br>APTEL, in its judgment and order, observed thus: | ||
| “13.7 We have considered the submissions made by<br>APML vis-a-vis the fni dings in the impugned order.<br>It is relevant to note that no submission to the<br>contrary has been advanced by the Respondent,<br>MSEDCL on this issue. In the Impugned Order,<br>MERC appears to have expanded the intent of<br>Change in Law notice as a means of intimation to<br>the buyer of power that on account of intended use<br>of alternate coal, the cost of power is likely to<br>increase and then the distribution licensee may<br>decide to not schedule such costly power. Firstly, no<br>such intent can be deciphered from the provisions<br>of the PPA which require a change in law notice to<br>be given to the procurers. MERC has not deliberated<br>upon how this regime will impact the<br>implementation of change in law provision in other<br>scenarios. For example, if there is a change in rates<br>of taxes or duties, which entitles the generator to<br>seek change in law relief, can it still be said that the<br>procurer should be intimated about the impact of<br>such changes in taxes or duties to enable them to<br>decide whether to schedule power or not. In our<br>view, this does not appear to be the intent of change<br>in law notice to the procurers under the PPAs. This<br>is for the simple reason that whether there will be<br>impact on MSEDCL would be known only after<br>MERC decides the change in law claim. Until such<br>time notice given by sellers merely to intimate the<br>occurrence of change in law event, in our view, will |
16
| not influence decisions related to scheduling of<br>power on merit order principles. In any event in far<br>as preparation of MOD stack is concerned, the<br>normal practice is to prepare MOD on the basis of<br>the energy charge bill of (n-1)th or (n-2)th month is<br>taken into account in the order of precedence.<br>Therefore, the impact of a regular or consistent<br>usage of alternate coal will in anyway be reflected in<br>the MOD stack, albeit with the lag of one or two<br>months.” | ||
|---|---|---|
| 29. The aforesaid finding of APTEL cannot be said to be<br>perverse or based on extraneous consideration or in<br>contravention of any of the statutory provisions. | ||
| 30. That leaves us with the issue with regard to Carrying<br>Cost. | ||
| 31. In the case of ADANI Power Limited v. Central<br>Electricity Regulatory Commission4, the CERC had come<br>to a conclusion that there was no provision in the PPA for<br>payment of Carrying Cost for the period from the date of the<br>Change in Law event till the date of approval by the<br>Commission. As such, the Commission had rejected the<br>prayer of the generating company to grant carrying Cost on<br>restitutionary principles from the date of Change in Law till |
4 2018 SCC OnLine APTEL 5
17
the date of decision. The APTEL, while reversing the
judgment of the CERC and allowing the Carrying Cost, had
observed thus:
“ 29. To our mind such adjustment in the tariff is
nothing less then re-determination of the existing
tariff.
x. Further, the provisions of Article 13.2
i.e. restoring the Appellant to the same
economic position as if Change in Law
has not occurred is in consonance with
the principle of ‘restitution’ i.e.
restoration of some specific thing to its
rightful status. Hence, in view of the
provisions of the PPA, the principle of
restitution and judgement of the Hon'ble
Supreme Court in case of Indian Council
for Enviro-Legal Action v. Union of India ,
we are of the considered opinion that the
Appellant is eligible for Carrying Cost
arising out of approval of the Change in
Law events from the effective date of
Change in Law till the approval of the
said event by appropriate authority. It is
also observed that the Gujarat Bid-01
PPA have no provision for restoration to
the same economic position as if Change
in Law has not occurred. Accordingly,
this decision of allowing Carrying Cost
will not be applicable to the Gujarat Bid-
01 PPA.”
32. The same came to be challenged before this Court in the
case of Uttar Haryana Bijli Vitran Nigam Limited
(UHBVNL) and another v. Adani Power Limited and
18
| Others5. The court rejected the same and upheld the order<br>of APTEL. As such, the contention in this regard needs to be<br>rejected. | ||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 33. This Court, in the case of MSEDCL v. APML and Others<br>(supra), after considering the relevant provisions under the<br>Electricity Act, 2003 with regard to appointment,<br>qualifications and Members of the CEA, CERC and the<br>learned APTEL, held that these bodies are bodies consisting<br>of experts in the field. After considering various judgments<br>on the issue, this Court observed thus: | ||||||||||||||||||
| “ | 123. | Recently, the Constitution Bench of this | ||||||||||||||||
| Court in the case of | Vivek Narayan | |||||||||||||||||
| Sharma | v. | Union of India | has held that the | |||||||||||||||
| Courts should be slow in interfering with the | ||||||||||||||||||
| decisions taken by the experts in the fei ld and | ||||||||||||||||||
| unless it is found that the expert bodies have | ||||||||||||||||||
| failed to take into consideration the mandatory | ||||||||||||||||||
| statutory provisions or the decisions taken are | ||||||||||||||||||
| based on extraneous considerations or they | ||||||||||||||||||
| are | ex facie | arbitrary and illegal, it will not be | ||||||||||||||||
| appropriate for this Court to substitute its | ||||||||||||||||||
| views with that of the expert bodies.” | ||||||||||||||||||
| 34. In our view, the view taken by the APTEL cannot be said<br>to be a view taken in ignorance of the mandatory statutory |
5 (2019) 5 SCC 325
19
provisions nor can it be said that it is based on extraneous
considerations. The view also cannot be said to be ex-facie
arbitrary or illegal. As such, in our view, no interference
would be warranted in the present appeals.
35.
In the result, the appeals are dismissed. Pending
application(s), if any, shall stand disposed of. No costs.
…..….......................J.
[B.R. GAVAI]
…….........................J.
[VIKRAM NATH]
NEW DELHI;
APRIL 20, 2023.
20