Full Judgment Text
REPORTABLE
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
| .3415 O | |||||
|---|---|---|---|---|---|
| F 2007<br>…Appell | |||||
| Oil & Natural Gas Corporation Ltd.<br>Versus<br>Western Geco international Ltd.<br>J U D G M E N T<br>T.S. THAKUR, J.<br>1. This appeal arises out of an order d<br>2006 passed by a Division Bench of t | |||||
Judicature at Bombay whereby OSA No.24 of 2006 filed by
JUDGMENT
the appellant-Corporation has been partly allowed and the
order passed by a single bench of the High Court in
Arbitration Petition No.203 of 2005 affirmed with the
modification that award of pendente lite and future interest
by the Arbitral Tribunal shall stand deleted.
2. The appellant-Corporation is engaged in the business of
drilling and exploration of oil and natural gases. In
1
Page 1
November, 1999, the appellant invited offers for technical
upgradation of Seismic Survey Vessel, M.V. Sagar Sandhani
(hereinafter referred to as the “ Vessel ”) with a view to
modernising the same. According to the tender conditions,
one of the main items of equipment required for upgradation
of the Vessel was “Streamers” fitted with hydrophones. The
specifications, however, did not stipulate the national origin
of such hydrophones.
3. In response to the tender notice respondent-M/s
Western Geco International Ltd., submitted a bid offering to
supply Nessie 4 streamers equipped with “Geopoint”
Hydrophones of U.S. origin. The appellant’s case is that the
term relating to supply of such Geopoint Hydrophones
JUDGMENT
formed a material part of the offer made by the respondent-
company in whose favour the appellant-Corporation
eventually awarded a contract in terms of its letter dated
th th
10 October, 2000 duly accepted by the respondent on 25
October, 2000. The Vessel was resultantly handed over to
th
the respondent on 10 April, 2001 for carrying on the
proposed modernisation and upgradation work. A formal
2
Page 2
contract was in due course executed between the parties on
th
18 June, 2001.
4. It is common ground that “Geopoint” Hydrophones of
U.S. origin were in terms of the contract fitted in the vessel
and test trials of the same conducted. Even so the vessel
th
could not be delivered back to the appellant on 9 July,
2001, the due date for that purpose, because of some
problem which the respondent encountered in obtaining
licence from the U.S. authorities for sale of such
hydrophones. The appellant-Corporation asserts that the
respondent had for the first time made an application to the
st
U.S. authorities for issuance of a licence as late as on 1
August, 2001 i.e. nearly a month after the due date for
JUDGMENT
delivery of the vessel back to the Corporation. No formal
rejection of the request for a license was according to the
Corporation communicated to it as the matter appeared to
be under some kind of negotiations between the respondent
and the authorities in U.S.
5. The respondent’s case per contra is that it continued its
efforts to obtain a licence only to be informed by its sources
3
Page 3
in the US that the latter was likely to impose certain onerous
conditions one of which could be that US made hydrophones
can be used only on loan basis that too for a short duration
of 24 months only. Respondent’s further case is that its
source in US had informed it that the US authorities were
not likely to grant a licence to sell hydrophones to India. Be
that as it may while the matter was pending with the
th
Defence Department, a massive terrorist attack on 11
September, 2001 shook America. The respondent’s hope of
getting a licence for sale of US made hydrophones receded
further with this unexpected development. The respondent
accordingly informed the appellant-Corporation about the
new development and pleading force majeure the
respondent informed the appellant-Corporation of the
JUDGMENT
former’s inability to equip the vessel with U.S. made
hydrophones. The appellant-Corporation refuted the
th
invocation of force Majeure by its letter dated 20
September, 2001 and informed the respondent that since
the field season was starting shortly any further delay in the
delivery of the vessel would adversely affect its operation.
The respondent on its part started looking for and offering
4
Page 4
alternatives to the U.S. made hydrophones and argued with
the appellant-Corporation that since origin of the
hydrophones was not indicated in the bid documents it was
testing replacement by M-2 US Geo Spectrum Hydrophones
made in Canada at its Norway facilities to check their
suitability which exercise the respondent hoped to complete
th
by 27 September, 2001. The respondent informed the
appellant-Corporation that if the Corporation accepted the
replacement, those hydrophones could be substituted for the
US hydrophones within a short time.
6. The appellant-Corporation was, however, in no mood to
accept a substitute for the contracted hydrophones. It was
on the contrary keen to have US made hydrophones fitted
JUDGMENT
on the vessel. The Corporation, therefore, required the
respondent to continue its efforts to secure a licence from
the US Government in which direction the appellant-
Corporation on its own moved the concerned Ministry in
Government of India to secure a licence. Further information
and details in respect of the proposed Canadian
hydrophones was all the same called for by the Corporation
5
Page 5
from the respondent. Since, however, the efforts to secure a
licence from US Government were making no progress, the
respondent sought approval of the appellant-Corporation to
remove the US hydrophones from the vessel and transfer
them to their repair facility in Singapore to facilitate
replacement by the Canadian made hydrophones. The
th
respondent also wrote a detailed letter dated 10 October,
2001 to the appellant-Corporation informing the latter that
the US government was not likely to grant a licence and that
it had withdrawn the application made for that purpose to
prevent a denial. What is important is that by letter dated
th
16 October, 2001 the respondent clearly stated that it was
not in a position to deliver the vessel with streamers
containing the Geopoint Hydrophones of US make. This
JUDGMENT
st
letter was followed by letter dated 21 October, 2001
addressed to the appellant-Corporation with a request to
permit removal of US hydrophones and replacement of
Canadian hydrophones which had been extensively tested
1999 in connection with supply of Seismic Survey Vessel
delivered to NOIC for the Iran project. Further information
required by the appellant-Corporation was also supplied by
6
Page 6
th
the respondent by its letter dated 24 October, 2001 with a
request to the Corporation to approve the proposed
replacement. The respondent also agreed to give additional
warranty of one year for the replaced hydrophones. By
th
another letter dated 13 November, 2001 the respondent
assured the appellant-Corporation that if the latter agreed to
the replacement proposal there would be no financial
implications and the additional cost involved in fixing the
Canadian hydrophones would also be borne by the
respondent.
rd
7. It was only on 23 March, 2002 that the respondent
conditionally agreed to the proposed replacement of the US
made hydrophones by those made in Canada. One of the
JUDGMENT
conditions imposed for the replacement by the appellant-
Corporation was the right to recover liquidated damages as
per Clause 16 and for excess engagement of vessel as per
Clause 14 of the subject contract. The replacement
accordingly took place and the Vessel eventually delivered
th
back to the Corporation with Canadian hydrophones on 6
th
May, 2002. On 24 May, 2002, a formal amendment to the
7
Page 7
contract was also effected to record the substitution of the
US hydrophones by those made in Canada.
8. With the upgradation and modernisation work
completed as per the amended contract, the respondent
raised invoices for payment due to it but realised that the
appellant-Corporation had deducted from its dues a sum of
US $ 5,114,300.98 towards excess engagement charges in
terms of Clause 14 of the contract. By another letter dated
th
20 August, 2002, the appellant-Corporation further
deducted a sum of US $ 410,641.20 based on a change in
tax law applicable at 4.8% followed by a deduction of a sum
of US $ 80,530.10 based on correction for price charges
inclusive of income tax at 4.8%. These deductions gave rise
JUDGMENT
to disputes which were referred for adjudication to an
arbitral tribunal comprising three former Chief Justices of
India before whom the respondent claimed a sum of US $
7,327,610.68 towards principal dues plus US $1,205,564.13
th
by way of interest for the period from 20 August, 2003 to
th
15 November, 2003 totalling US $ 8,533,174,81 with
8
Page 8
interest pendent lite at 12% p.a. from the date of the filing
of the claim till the award at the same rate.
9. The appellant-Corporation stoutly contested the claim
made against it and alleged that hydrophones being an
important component, the respondent had not only offered
to fit US made hydrophones in the streamer section of the
Vessel but actually fitted the same. The appellant’s case was
that the claimant having contracted to supply US made
hydrophones was legally obliged to handover the Vessel duly
filled with such hydrophones within the stipulated period of
th
90 days which expired on 9 July, 2001. The appellant’s
further case was that the requirement of a licence was first
mentioned by the respondent when letter dated July 9, 2001
JUDGMENT
was delivered to the appellant’s representative on board the
vessel at Singapore in an attempt to explain the
respondent’s failure to hand over the vessel on the due date.
The appellant-Corporation asserted that the respondent had
not even applied for a licence till then and had simply asked
for an extension of time. It was only when the appellant-
Corporation asked the respondent to specify on a realistic
9
Page 9
basis, the period for which extension was being demanded
th
that the respondent had by letter dated 26 July, 2001
stated that according to their understanding the licence will
be issued towards the first week of September, 2001. Since
time was the essence of the contract between the parties,
the respondent’s failure to return the vessel duly upgraded
within 9 months from the date of Letter of Acceptance or 90
th
days from the delivery of the vessel i.e. on or before 9 July,
2001 was a clear breach of its contractual obligation
rendering the respondent liable to payment of liquidated
damages and for excess engagement of the vessel, argued
the appellant-Corporation.
10. The Corporation also disputed the invocation of force
JUDGMENT
majeure clause in the fact situation of the case especially
when securing of a licence for the equipment was not a part
of the contract between the parties, it being the sole
responsibility of the respondent to determine the type and
make of hydrophones. The terrorist attack on the twin
towers was, according to the appellant-Corporation a post-
contractual period issue as the date of the delivery of the
10
Page 10
vessel under the contract had since long expired by the time
the attack took place. It was also contended that the delay
in the completion of the contract was entirely attributable to
the respondent who when called upon by the appellant-
Corporation to submit the performance report of the M-2
hydrophones used in Seismic Survey Vessel PEJWAK
suggested that the appellant-Corporation should obtain the
same directly from NIOC forcing the appellant-Corporation
to send a representative to Oslo to verify the parameters of
the M-2 hydrophones at their own expense. It was asserted
that once the respondent informed the appellant-Corporation
that the US department of Commerce had finally rejected
the licence, the appellant-Corporation was left with no
alternative except to agree to the replacement of the US
JUDGMENT
made hydrophones by Canadian M-2 hydrophones resulting
th
in the delivery of the vessel back to the Corporation on 6
May, 2002 after considerable delay.
11. On the pleadings of the parties the Arbitral Tribunal
framed the following issues for determination:
11
Page 11
(1) Was the national origin of hydrophones used in the Nessie-4
streamers, a material term of the contact between the parties?
(2) Was the respondent justified in refusing to allow substitution of
the Canadian M-2 hydrophones for the US Geopoint
hydrophones?
(3) Was the claimant’s declaration of force majeure justified under
the terms of the contract?
(4) Whether there was any delay in the performance of the contact?
(5) If the answer to point No.4 is in the affirmative, who is
responsible for such delay?
(6) If the answer to point No.4 is in the affirmative, whether the
Claimant is entitled to damages?
(7) Whether the respondent was entitled to adjust the sum of US $
491,000 out of the sum payable, in whole or in part, as alleged
in para 30 of the statement?
(8) Is respondent entitled to both Liquidated Damages and Excess
Engagement charges for the same periods of time under the
provisions of the Contract?
JUDGMENT
12. In the award which the Tribunal made and published
Issue No. 1 was answered in the negative holding that since
the choice of the hydrophones was left to the bidders
subject to the equipment meeting the specifications
prescribed for the purpose and since the stipulations did not
indicate the make or the country of origin of the
12
Page 12
hydrophones, the national origin of such hydrophones was
not a material term of the contract between the parties.
13. Issue No. 2 was, however, answered by the Tribunal in
the affirmative, who took the view that once the respondent
had made the choice and contracted to supply hydrophones
made in the U.S. the appellant-Corporation was entitled to
insist on the supply of the contracted equipment. The
arbitrators further held that once the respondent had
informed the appellant that the option of U.S. made
hydrophones was closed, the later was not justified in
insisting that the request for a license with the U.S.
authorities should be pursued further. The arbitral tribunal
decided Issue No.3 against the respondent holding that none
JUDGMENT
of the events mentioned in the contract had taken place and
since the parties to the contract did not belong to U.S., the
force majeure clause could not have been validly invoked by
the respondent.
14. Dealing with the question of delay in the performance
of the contract and its consequences covered by Issue Nos.
4 to 8, the Arbitrators held that the respondent-claimant had
13
Page 13
completed the performance of the contractual obligations
within the stipulated time frame and would have but for the
U.S. licence requirement delivered the vessel to the
appellant on July 9, 2001 in which event there would have
been no necessity to invoke the force majeure clause or to
seek extension of time or to offer the Canadian
hydrophones. Even so the fact remained that the respondent
had not delivered the vessel back to the appellant-
Corporation on time. The Tribunal then examined whether
the respondent was responsible for the entire delay between
th
July 9, 2001 and 6 May 2002 when the vessel was actually
returned. The Tribunal rejected the contention on behalf of
the respondent that extension of time for completing the
contracted works had the effect of waiving the rights vested
JUDGMENT
in the appellant under clause 14 and 16 of the contract. The
Tribunal held that waiver ought to be express or the fact
situation must be necessary implication manifest an
intention to waive. Mere extension of time did not signify
waiver of the rights flowing from clause 15 and 16 of the
contract, observed the Arbitral Tribunal. Having said so the
Tribunal held that since the respondent had informally
14
Page 14
intimated to the appellant Corporation as early as on
October 24, 2001 that it did not desire to pursue the request
for a licence with the U.S. authorities any further and since
th
by a letter dated 25 October 2001 the final particulars in
regard to the Canadian hydrophones were duly supplied,
allowing some time to the respondent to take a decision, the
delay post October 21, 2001 could not be attributed to the
respondent. That finding, observed the Tribunal, did not
impact the amount deducted by the respondent towards
liquidated damages as the capping provision limited to 10%
was less than the sum payable for the delay upto October
31, 2001. As regards excess engagement charges the
Arbitrators held that except for the period commencing
November 1, 2001 to March 22, 2002 the appellant
JUDGMENT
Corporation was justified in making deductions for the rest
of the period from the claim of the respondent. The
Arbitrators held that the deductions in relation to the period
from November 1, 2001 to March 22, 2002 amounting to
US$ 2,445,246.54 were wrongly made by the appellant-
Corporation which amount the respondent was entitled to
15
Page 15
get from the appellant together with interest at the rate
indicated in the award.
15. As regards deductions based on change of tax law or
non payment of taxes under the Indian Law, the Tribunal
held that the same were not permissible in the facts and
circumstances of the case especially when the contracted
work was to be executed and completed at the ship repair
unit of the respondent claimant in Singapore and so was the
handing over of the completed vessel to the appellant-
Corporation. No part of the work having been undertaken
outside Singapore no deduction could be made on account of
non-payment of any tax. The Arbitrators held that since no
taxes were attracted under the Indian Income Tax Act the
JUDGMENT
price could not include the said tax component. The
Arbitrators accordingly held that deductions made on two
counts, being of US $ 410,641.20 and US $ 80,530.10 were
also unjustified and unwarranted by law or contract.
16. Aggrieved by the award made by the Arbitral Tribunal,
the appellant Corporation preferred a petition under Section
34 of the Arbitration and Conciliation Act, 1996 which failed
16
Page 16
and was dismissed by a Single Judge of the High Court but
was allowed in part in O.S.A No. 241 of 2006 by the Division
Bench of the High Court to the extent of deleting pendente
lite in future interest from the award made by the Tribunal.
Before the Division Bench, a three-fold submission was
urged on behalf of the appellant-Corporation. Firstly, it was
contended that the Tribunal had fallen in error in holding
th st
that the delay between 14 September 2001 and 21 March
2002 was not attributable to the respondent company.
Secondly, it was contended that the Arbitral Tribunal was
not right in holding that the deductions made by the
appellant towards taxes was not legally permissible. Thirdly
it was contended that the award by the Arbitral Tribunal for
the pendente lite and future interest was not justified. While
JUDGMENT
the Division Bench rejected the first two contentions the
respondent appears to have made a statement before the
High Court waiving pendente lite interest and agreeing to
the modification of the award to that extent. The High Court
held that the Arbitral Tribunal’s findings to the effect that
th st
the delay between 16 October and 21 March 2002 is not
attributable to the respondent, was based on the
17
Page 17
consideration of the material placed before the Arbitral
Tribunal which called for no interference. So also deductions
towards payment of taxes were, according to the High
Court, rightly disallowed by the Arbitrators.
17. The present appeal assails the correctness of the Award
of the Arbitral Tribunal and the orders passed by the High
Court as noticed in the beginning of this order.
18. We have heard learned counsel for the parties at length
who have taken us through the award made by the Arbitral
Tribunal, provisions of the contract executed between the
parties and the correspondence exchanged between
them. There is no denying the fact that there was delay in
JUDGMENT
the return of the vessel to the Corporation after
upgradation. In terms of the contractual time schedule the
th
vessel ought to have returned to the Corporation by 9 July
2001 which was instead returned to the Corporation only on
th
6 May 2002 i.e. after a delay of 9 months and 28 days.
Who is responsible for this delay is the essence of the
dispute between the parties. According to the appellant-
18
Page 18
Corporation the delay is entirely attributable to the
respondent while according to the respondent the delay is
attributable to the appellant. The Arbitrators have after
examining the material placed before them recorded a
th
finding to the effect that the delay between 10 July 2001
st
and 31 March 2001 was entirely attributable to the
respondent. That finding was not challenged by the
respondent before the High Court nor is it under challenge
before us. The Arbitrators have on the basis of the finding
recorded by them allowed to the appellant-Corporation
excess engagement charges under clause 14 besides
liquidated damages under clause 16 of the Contract
executed between the parties. But for the period between
st nd
1 November, 2001 and 22 March, 2002 which comes to 4
JUDGMENT
months and 22 days the Arbitrators have found the delay to
be attributable to the appellant-Corporation. Deduction
made by the Corporation in regard to this period has been
faulted by the arbitrators and the amount directed to be
released in favour of the respondent-Company. The award
deals with this period and the amount deducted for the same
in the following words:
19
Page 19
“In the result we are of the opinion that except for
the period from November 1, 2001 to March 23, 2002
for which deduction has been made from the
Claimant’s invoices, no exception can be taken for
the rest of the deduction made from the claim of the
Claimant. The deduction in relation to the period
from November 1, 2001 to March 22, 2002 (4 months
+ 22 days) works out to a sum of US $ 2,445,246.53
which the Claimant would be entitled to from the
Respondent together with interest at the rate of
indicated hereafter”.
st
19. The above period of 4 months and 22 days between 1
nd
November, 2001 and 22 March, 2002, in our opinion,
comprises four separate intervals. The first of these four
st th
intervals is the period between 1 November, 2001 and 26
November, 2001 which period was taken by the appellant-
Corporation to take a final decision whether or not an
application should be made to the U.S authorities for the
issue of a licence. The second interval comprises time taken
JUDGMENT
by the respondent-claimant to make an application between
th th
27 November, 2001 and 7 January, 2002, both days
inclusive. The application for grant of a license was filed by
th
the respondent only on 8 January, 2002. The third interval
th
comprises time taken by the U.S Authorities between 8
th
January, 2002 and 7 March, 2002 to formally decline the
issue of a license for sale of US made hydrophones to India.
20
Page 20
The fourth interval comprises time taken by the respondent-
claimant to convey the decision of the U.S Authorities
th st
between 8 March, 2002 and 21 March, 2002. It is common
ground that while the U.S Authorities had rejected the
th
request for grant of a license on 8 March, 2002, the said
rejection was conveyed to the appellant-corporation only on
nd
22 March, 2002.
20. From the findings of the fact recorded by the
arbitrators with which we see no reason to interfere or
disagree, it is evident, that the appellant-corporation was
solely responsible for the delay in taking a decision in the
th th
matter between 24 October, 2001 and 26 November,
2001. The arbitrators have found and, in our opinion,
JUDGMENT
rightly so that the respondent-claimant had by its letter
th
dated 24 October, 2001 clearly informed the appellant that
there was no use pursuing the matter with the U.S.
Authorities any further. Even particulars regarding Canadian
hydrophones were supplied to the appellant in terms of a
th
letter dated 25 October, 2001. The arbitrators have held
that delay in taking a decision whether or not any formal
21
Page 21
application should be made and a formal rejection obtained
by the respondent was attributable only to the appellant-
Corporation. There is, in our opinion, no legal flaw, infirmity
or perversity in that finding which we hereby affirm.
Deduction made by the appellant-Corporation for the First
st
interval that comprises period between 1 November, 2001
th
and 25 November, 2001, both days inclusive, cannot,
therefore, be sustained and the arbitral award to that extent
cannot be faulted.
21. That brings us to the second interval comprising period
th
between 26 November, 2001-the date when the appellant-
Corporation issued instructions for making of a formal
th
application for the grant of a license and 8 January, 2002-
JUDGMENT
when such an application was actually made by the
th
respondent-company. This period reckoned from 27
th
November, 2001 to 7 January, 2002 works out to 42 (Forty
two) days which must be attributed to the respondent-
claimant, who could and indeed ought to have acted
diligently and with reasonable despatch in the matter
instead of taking the same easy, and if we may say so
22
Page 22
somewhat reluctantly. We cannot help saying with utmost
respect at our command for the eminence and erudition of
the distinguished jurists comprising the Arbitral Tribunal that
the tribunal failed to appreciate this aspect hence fell in a
palpable error leading to miscarriage of justice. The test
adopted by the Tribunal for holding the appellant-
Corporation responsible for delay ought to have been applied
to the respondent as well for its failure to take action in the
right earnest instead of sitting over the matter leading to
detention of the vessel for a period more than what was
absolutely necessary.
th th
22. The period between 8 January, 2002 and 8 March,
2002 comprising the third interval during which the U.S.
JUDGMENT
authorities decided the application for the grant of a license
has been rightly counted against the appellant-Corporation
as it was at the instance of the Corporation that a formal
application was made. The time spent by the U.S.
authorities for disposal of the request could not in the facts
and circumstances be attributed to or counted against the
respondent-claimant who had advised the appellant against
23
Page 23
any such move. The arbitral Tribunal, therefore rightly held
that deduction for this period was not justified.
23. That leaves us with the fourth and the last interval
th nd
comprising the period between 8 March, 2002 and 22
March, 2002 when the rejection of the application was
conveyed to the appellant-Corporation. There is, in our
opinion, no valid reason why this period should not be
counted against the respondent, who could and indeed
should have conveyed the rejection to the appellant-
Corporation forthwith, instead of taking nearly two weeks to
do so. To sum up; the period of 4 months and 22 days which
the arbitrators have attributed to the appellant-Corporation
shall have to be reduced by 42 days comprising the first
JUDGMENT
interval and 14 days comprising the fourth making a total of
56 days. Resultantly, deduction made by the appellant-
Corporation for 56 days referred to above deserve to be
affirmed, and the award made by the arbitrators modified to
that extent. It follows that the amount awarded to the
respondent-Company shall on a proportionate basis, stand
reduced.
24
Page 24
24. We may at this stage deal with the contention urged on
behalf of the respondent that the jurisdiction of the Court to
set aside an arbitral award being limited to grounds set out
in Section 34 of the Arbitration and Conciliation Act, 1996,
this Court ought not to interfere with the same. It was
contended that none of the grounds on which a Court is
authorised to interfere with an arbitral award are present in
the case at hand. Alternatively, it was contended that even if
a contrary view is possible on the facts proved before the
Arbitral Tribunal, the Court cannot, in the absence of any
compelling reason, interfere with the view taken by the
Arbitrators as if it was sitting in appeal over the award made
by the Tribunal. Section 34 of the Arbitration and
JUDGMENT
Conciliation Act, 1996 reads :
“34. Application for setting aside arbitral award.—(1)
Recourse to a court against an arbitral award may be
made only by an application for setting aside such
award in accordance with sub-section (2) and sub-
section (3).
(2) An arbitral award may be set aside by the court
only if—
(a) the party making the application furnishes proof
that—
(i) a party was under some incapacity, or
(ii) the arbitration agreement is not valid under the
law to which the parties have subjected it or, failing
25
Page 25
any indication thereon, under the law for the time
being in force; or
(iii) the party making the application was not given
proper notice of the appointment of an arbitrator or
of the arbitral proceedings or was otherwise unable
to present his case; or
(iv) the arbitral award deals with a dispute not
contemplated by or not falling within the terms of
the submission to arbitration, or it contains decisions
on matters beyond the scope of the submission to
arbitration:
Provided that, if the decisions on matters submitted
to arbitration can be separated from those not so
submitted, only that part of the arbitral award which
contains decisions on matters not submitted to
arbitration may be set aside; or
(v) the composition of the Arbitral Tribunal or the
arbitral procedure was not in accordance with the
agreement of the parties, unless such agreement
was in conflict with a provision of this Part from
which the parties cannot derogate, or, failing such
agreement, was not in accordance with this Part; or
(b) the court finds that—
(i) the subject-matter of the dispute is not capable
of settlement by arbitration under the law for the
time being in force, or
(ii) the arbitral award is in conflict with the public
policy of India.
Explanation.—Without prejudice to the generality of
sub-clause (ii), it is hereby declared, for the
avoidance of any doubt, that an award is in conflict
with the public policy of India if the making of the
award was induced or affected by fraud or corruption
or was in violation of Section 75 or Section 81.”
JUDGMENT
25. It is true that none of the grounds enumerated under
Section 34(2)(a) were set up before the High Court to assail
the arbitral award. What was all the same urged before the
High Court and so also before us was that the award made
by the arbitrators was in conflict with the “public policy of
26
Page 26
India” a ground recognised under Section 34(2)(b)(ii)
(supra). The expression “Public Policy of India” fell for
interpretation before this Court in ONGC Ltd. v. Saw Pipes
Ltd. (2003) 5 SCC 705 and was, after a comprehensive
review of the case law on the subject, explained in para 31
of the decision in the following words:
“ 31. Therefore, in our view, the phrase “public policy
of India” used in Section 34 in context is required to
be given a wider meaning. It can be stated that the
concept of public policy connotes some matter which
concerns public good and the public interest. What is
for public good or in public interest or what would be
injurious or harmful to the public good or public
interest has varied from time to time. However, the
award which is, on the face of it, patently in violation
of statutory provisions cannot be said to be in public
interest. Such award/judgment/decision is likely to
adversely affect the administration of justice. Hence,
in our view in addition to narrower meaning given to
10
the term “public policy” in Renusagar case it is
required to be held that the award could be set aside
if it is patently illegal. The result would be — award
could be set aside if it is contrary to:
(a) fundamental policy of Indian law; or
(b) the interest of India; or
(c) justice or morality, or
JUDGMENT
(d) in addition, if it is patently illegal.
Illegality must go to the root of the matter and if the
illegality is of trivial nature it cannot be held that
award is against the public policy. Award could also
be set aside if it is so unfair and unreasonable that it
shocks the conscience of the court. Such award is
opposed to public policy and is required to be
adjudged void.”
27
Page 27
26. What then would constitute the ‘ Fundamental policy of
Indian Law’ is the question. The decision in Saw Pipes Ltd.
(supra) does not elaborate that aspect. Even so, the
expression must, in our opinion, include all such
fundamental principles as providing a basis for
administration of justice and enforcement of law in this
country. Without meaning to exhaustively enumerate the
purport of the expression “ Fundamental Policy of Indian
Law” , we may refer to three distinct and fundamental juristic
principles that must necessarily be understood as a part and
parcel of the Fundamental Policy of Indian law. The first
and foremost is the principle that in every determination
whether by a Court or other authority that affects the rights
of a citizen or leads to any civil consequences, the Court or
JUDGMENT
authority concerned is bound to adopt what is in legal
parlance called a ‘judicial approach ’ in the matter. The duty
to adopt a judicial approach arises from the very nature of
the power exercised by the Court or the authority does not
have to be separately or additionally enjoined upon the fora
concerned. What must be remembered is that the
importance of Judicial approach in judicial and quasi judicial
28
Page 28
determination lies in the fact so long as the Court, Tribunal
or the authority exercising powers that affect the rights or
obligations of the parties before them shows fidelity to
judicial approach, they cannot act in an arbitrary, capricious
or whimsical manner. Judicial approach ensures that the
authority acts bonafide and deals with the subject in a fair,
reasonable and objective manner and that its decision is not
actuated by any extraneous consideration. Judicial approach
in that sense acts as a check against flaws and faults that
can render the decision of a Court, Tribunal or Authority
vulnerable to challenge. In Ridge v. Baldwin [1963 2 All
,
ER 66] the House of Lords was considering the question
whether a Watch Committee in exercising its authority under
Section 191 of the Municipal Corporations Act, 1882 was
JUDGMENT
required to act judicially. The majority decision was that it
had to act judicially and since the order of dismissal was
passed without furnishing to the appellant a specific charge,
it was a nullity. Dealing with the appellant’s contention that
the Watch Committee had to act judicially, Lord Reid relied
upon the following observations made by Atkin L.J. in [1924]
1 KB at pp. 206,207:
29
Page 29
“Wherever any body of persons having legal authority
to determine questions affecting the rights of
subjects, and having the duty to act judicially, act in
excess of their legal authority, they are subject to the
controlling jurisdiction of the King’s Bench Division
exercised in these writs.”
27. The view taken by Lord Reid was relied upon by a
Constitution Bench of this Court in A.C. Companies Ltd vs.
P.N. Sharma and Anr . (AIR 1965 SC 1595) where
Gajendragadkar, C.J. speaking for the Court observed :
“ In other words, according to Lord Reid’s judgment,
the necessity to follow judicial procedure and
observe the principles of natural justice, flows from
the nature of the decision which the watch
committee had been authorised to reach under
S.191(4). It would thus be seen that the area where
the principles of natural justice have to be followed
and judicial approach has to be adopted, has
become wider and consequently, the horizon of writ
jurisdiction has been extended in a corresponding
measure. In dealing with questions as to whether
any impugned orders could be revised under A. 226
of our Constitution, the test prescribed by Lord Reid
in this judgment may afford considerable
assistance.”
JUDGMENT
28. Equally important and indeed fundamental to the policy
of Indian law is the principle that a Court and so also a
quasi-judicial authority must, while determining the rights
and obligations of parties before it, do so in accordance with
the principles of natural justice. Besides the celebrated ‘ audi
alteram partem’ rule one of the facets of the principles of
30
Page 30
natural justice is that the Court/authority deciding the
matter must apply its mind to the attendant facts and
circumstances while taking a view one way or the other.
Non-application of mind is a defect that is fatal to any
adjudication. Application of mind is best demonstrated by
disclosure of the mind and disclosure of mind is best done
by recording reasons in support of the decision which the
Court or authority is taking. The requirement that an
adjudicatory authority must apply its mind is, in that view,
so deeply embedded in our jurisprudence that it can be
described as a fundamental policy of Indian Law.
29. No less important is the principle now recognised as a
salutary juristic fundamental in administrative law that a
JUDGMENT
decision which is perverse or so irrational that no reasonable
person would have arrived at the same will not be sustained
in a Court of law. Perversity or irrationality of decisions is
tested on the touchstone of Wednesbury’s principle of
reasonableness. Decisions that fall short of the standards of
reasonableness are open to challenge in a Court of law often
31
Page 31
in writ jurisdiction of the Superior courts but no less in
statutory processes where ever the same are available.
30. It is neither necessary nor proper for us to attempt an
exhaustive enumeration of what would constitute the
fundamental policy of Indian law nor is it possible to place
the expression in the straitjacket of a definition. What is
important in the context of the case at hand is that if on
facts proved before them the arbitrators fail to draw an
inference which ought to have been drawn or if they have
drawn an inference which is on the face of it, untenable
resulting in miscarriage of justice, the adjudication even
when made by an arbitral tribunal that enjoys considerable
latitude and play at the joints in making awards will be open
JUDGMENT
to challenge and may be cast away or modified depending
upon whether the offending part is or is not severable from
the rest.
31. Inasmuch as the arbitrators clubbed the entire period
th st
between 16 October, 2001 and 21 March, 2002 for
purposes of holding the appellant-Corporation responsible
for the delay, they committed an error resulting in
32
Page 32
miscarriage of justice apart from the fact that they failed to
appreciate and draw inferences that logically flow from such
proved facts. We have, therefore, no hesitation in rejecting
the contention urged on behalf of the respondent that the
arbitral award should not despite the infirmities pointed out
by us be disturbed.
32. That brings us to the last submission that deduction on
account of taxes not paid should have been allowed by the
respondent-arbitral tribunal. The Tribunal has, in our
opinion, correctly held that no part of the work was
undertaken outside Singapore which was to be executed on
a turnkey basis for a price that was pre-determined. The
arbitrators have, in our opinion, rightly held that no taxes
JUDGMENT
were payable under the Indian Income tax Act so as to
entitle the Corporation to deduct any amount on that
account by reason of non-payment of such taxes. The
challenge to the award to that extent must fail and is,
hereby, rejected.
33. In the result, we allow this appeal but only to the
extent that out of the period of 4 months and 22 days which
33
Page 33
the arbitrators have attributed to the appellant-Corporation
a period of 56 days comprising 42 days of the first interval
and 14 days of the second referred to in the judgment shall
be reduced. Resultantly, deductions made by the appellant-
Corporation for the said period of 56 days shall stand
affirmed and the award made by the arbitrators modified to
that extent with a proportionate reduction in the amount
payable to the respondent. No costs.
…......………………………….…..…J.
(T.S. THAKUR)
.…………………………..……………..J.
(C. NAGAPPAN)
..…………………………..…………….J.
(ADARSH KUMAR GOEL)
New Delhi
September 4, 2014
JUDGMENT
34
Page 34