Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 11
PETITIONER:
BOMBAY HOUSING BOARD (NOW THE MAHARASHTRAHOUSING BOARD)
Vs.
RESPONDENT:
KARBHASE NAIK & CO., SHOLAPUR
DATE OF JUDGMENT29/01/1975
BENCH:
MATHEW, KUTTYIL KURIEN
BENCH:
MATHEW, KUTTYIL KURIEN
BHAGWATI, P.N.
UNTWALIA, N.L.
CITATION:
1975 AIR 763 1975 SCR (3) 407
1975 SCC (1) 828
CITATOR INFO :
D 1988 SC1791 (9)
ACT:
The Bombay Housing Board Act (69 of 1948), s. 64--’Anything
done or purporting to have been done in pursuance of the
Act’, Scope of--Breach of contract if comes within
expression.
HEADNOTE:
There was a contract between the State and the respondent,
which after the passing of the Bombay Housing Board Act,
1948, was deemed to have been entered into between the
appellant and the respondent, for the construction of’
buildings by the respondent. Clause 14 of the Contract
provided that where any additional or altered work is
directed to be carried out and no rates are entered in the
Schedule of Rates in the Division, or agreed to, then. the
contractor may, within 7 days of the order, give notice of
the rate he intends to charge. In such a case, the
Engineer-in-charge would be at liberty to cancel the order
if he does not agree to the rate stated by the contractor,
and get the work done by another. Where the Engineer-in
charge has not cancelled the order and the contractor has
commenced work and incurred expenditure, the contractor
shall only be entitled to be paid at such rate as may be
fixed by the Engineer-in-charge, and if the contractor is
dissatisfied, he may raise a dispute about the rate and the
decision of the Superintending Engineer will be final.
Clause 15 provided that the Engineer-in-charge has power to
stop or to reduce the whole of the work specified in the
tender or get it done by another, and the contractor has no
claim to any compensation whatsoever on account of such
stoppage or reduction. But, before the Engineer-in-charge
could stop the work and get it done by another contractor,
he should give the first contractor a written notice. The
contractor shall also have no right under the clause to,
claim any payment or compensation on account of any profit
or advantage which he might have derived from the execution
of the work in full but which he did not derive in
consequence of the full amount of work not having been
carried out, or on account of any loss due to purchase of
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 11
materials or labour recruited by him. The clause further
provides that the contractor shall not also, have any claim
for compensation by reason of any alteration in the original
specification which may involve curtailment of work as
originally contemplated.
The respondent filed a suit claiming a certain sum of money
with respect to certain items and the suit was decreed by
the trial court except with respect to 4 items. The High
Court in appeal. however decreed those items also. They
were : (1) the respondent was ordered to carry out certain
work with respect to the first two items and the respondent
intimated his rate as required by cl. 14. The Engineer-in-
charge did not cancel the order or give the contract for the
extra work to any other contractor, and therefore, the High
Court held that the amount due to the respondent for the
extra work was to be calculated’ on the basis of the rate
specified in the notice; (2) the respondent was assured by
the appellant that the work was to be completed in
accordance with the specifications in the agreement and that
no alteration would be made therein, but-in fact an
alteration was made as a result of which the respondent
became entitled to lesser amount and the High Court held he
was entitled to the difference; and (3) the appellant
represented to the respondent that the appellant would
entrust the respondent with another item of work but
contrary to the representation, got the work done by another
without giving notice in writing to the respondent and
hence, the High Court held that the respondent was entitled
to compensation.
408
In appeal. to this Court, it Was contended; (1) that with
respect to the first items, in view of cl. 14, the
respondent was entitled only to the rate as fixed by the
Engineer-in-charge; (2) with respect to the 3rd item since
the Engineer-in,charge was entitled to change the
specifications, the respondent was not entitled to
compensation in view of Cl. 15; (3) with respect to the 4th
item no notice was necessary before getting the work done by
another contractor; and (4) the suit was barred by
limitation under s. 64 of the Bombay Housing Board Act,
1948, which provides a 6-month period of limitation for any
suit for anything done or purporting to have been done in
pursuance of the Act, because the act of entering into a
contract was an act done in pursuance of the Act. and so a
claim for damages for breach of the contract would come
within the purview two items. [412E-F]
HELD: (1) The High Court was wrong in allowing the claim
on the first two items. [412E-F]
The High Court erred in holding that cl. 14 was
inapplicable. The High ,Court was also wrong in holding
that if the clause was applicable it gave the Engineer-in-
charge an absolute power to fix the rate and that it was
unjust. Until the rates were settled by agreement the
respondent was under no obligation to carry out the
additional or altered work. The respondent could
legitimately have said that in the absence of scheduled
rates in the division for the type of work or an agreement
in regard to the rates, it was not bound to carry out the
additional or altered work. Merely because the Engineer-in-
charge did ,not exercise his liberty to cancel the contract
after receiving notice of the respondent’s rate, it could
not be said that there was a concluded contract ’between the
parties for payment at those rates. The fact that an
express power was given to the Engineer-in-charge by the
clause to cancel the order if he did not agree to the rate
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 11
would not mean that the failure to cancel the order ,would
result in an agreement as to the rate or.rates. In the
absence of some positive act on the part of the Engineer-in-
charge agreeing to the rate, there was no agreement as to
the rate and the respondent was not bound to carry out the
work. The provision regarding fixation of rate by the
Engineer-in-charge and ’by the Superintending Engineer was
intended to cover cases where the notice specifying the rate
was not given by the contractor, or when, even though the
notice was given, the Engineer-in-charge did not cancel the
order in the event of his not agreeing to the rate specified
in the notice and the contractor ,commences work and incurs
expenditure. [412B-E]
(2) The High Court was right in its conclusion with respect
to the 3rd item that cl. 15 had no application and that the
claim was well-founded. The nature of the work was such
that by altering the specification, there was not only no
curtailment of work but there was in fact an increase of
work involving additional cost. [413G]
(3) The observance of the condition as regards the written
notice in cl. 15 was mandatory, and since no such notice was
given the respondent ’was entitled to damages. [414B]
(4) The contract entered into by the Board for construction
of buildings is an act done in pursuance of the provisions
of the Act; and it makes no difference whether the contract
was entered into with the Board or that it was deemed to ’be
entered into with the Board., But the act complained of in
this case by the respondent was the non-payment of the
amount alleged to be due to the respondent on the basis of a
breach of the contract; and that act could not be said to
have been done or purported to have been done in pursuance
of the Act. It could not said that the breach complained of
had any reasonable connection with any duty cast upon the
appellant or its agents by the Act. [415B; 417B]
The Trustees of Port of Bombay v. The Premier Automobiles
Ltd. A.I.R. 1974 S.C. 923, followed.
The Municipal Borough of Ahmedabad v. Jayantilal Cheetalal
Patel, I.L.R. 1947 Bom. 841, approved.
409
Athimannil Muhammad v. The Malabar District Board, I.L.R. 58
Madras 746. and Jalgaon Borough Municipality v. The Khandesh
Spinning and Weaving Mills, Co. Ltd. I.L.R. 1953 Bombay
590, referred to.
JUDGMENT:
CIVIL APPELLATE JURISDICTION : Civil Appeal No. 13 of 1968.
From the judgment and order dated the 29th/30th January,
1963 of the Bombay High Court in First Appeal No. 51 of
1957.
S. T. Desai, D. D. Kango, P. C. Bhartari and K. J. John,
for the appellant.
Sharad Manohar, B. P. Maheshwari, Randhir Jain and Suresh
Sethi, for the respondent
The Judgment of the Court was delivered by
MATHEW, J.-This is an appeal by the defendant on the basis
of a certificate against a decree passed by the High Court
’of Bombay in appeal from a decree in a suit for recovery of
balance of amount due on account of extra construction work
carried out by the plaintiff respondent.
The State of Bombay prepared a scheme for construction of
blocks in Sholapur and invited tenders for the same. The
respondent, a firm, submitted its, tender on 29-7-1948. The
tender was in B-1 form, otherwise known as percentage
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 4 of 11
tender. The tender was accepted on 6-12-1948 by the Labour
Department on behalf of the State of Bombay. The Bombay
Housing Board came into being with the passing of the Bombay
Act 69 of 1948 and under s. 54 of that Act,, the above
contract shall be deemed to, have been entered into with the
Board.
The order to carry out the work was issued to the respondent
by the Housing Commissioner on 15-8-1948. The construction
was to be completed within one year from the date of the
order. The time was extended and the work was actually
completed in March, 1950 and possession was taken by the
appellant some time between 5-5-1950 and 30-5-1950. The
amount paid to the respondent on 30-3-1951 under the final
bill was accepted by it under protest. As the disputes
between the parties in respect of the claims made by the
respondent could not be settled by agreement, the respondent
filed the suit,, claiming under 4 items, namely, A to D, a
sum of Rs. 38,000-8-0.
As we are concerned in this appeal only with the claims
specified in A-3, A-4, C-1 and C-2, it is not necessary to
refer to the contentions of the appellant in respect of the
other items. In regard to the claims in items A-3 and A-4,
the appellant contended that they were for extra works
carried out by the respondent without any agreement as to
the rate to be charged and therefore the respondent was
entitled to have the claim settled on the basis of the
provision in clause 14 of the contract for such works and
that claims in item C-1 and C-2 were not maintainable by
virtue of clause 15 in the contract and that the suit was
barred by limitation.
410
The trial court decreed the suit for a sum of Rs. 2,865-0-0
with proportionate cost and future interest. It dismissed
the claims made under items A-3 A-4, C-1 and C-2.
The respondent filed an appeal before the High Court for the
balance of its claim and the appellant filed a cross appeal.
The High Court decreed the claims in items A-3, A-4, C-1 and
C-2 and the sole question in this appeal is whether the
claims in these items were sustainable in view of clauses 14
and 15 of the contract between the parties and whether there
was evidence to establish them.
The amount claimed in item A-4 was Rs. 8,239 and that was
mainly in respect of the work of filling up of ditches,
etc., which was done by the respondent under the order of
the appellant. The order to carry out this extra work was
given on 7-11-1949. The respondent intimated by notice in
writing, as required by clause 14, the rate for carrying out
the work. The Engineer-in-charge did not exercise his
liberty to cancel the order, or give the contract for the
extra work to any other contractor. The respondent’s case
was that the amount due to it for the extra work under item
A-4 was to be calculated on the basis of the rate specified
in the notice. The appellant contended that in view of
clause 14 of the contract, the respondent was entitled only-
to the rate as fixed by the Engineer-in-charge.
So, the question for consideration in respect of item A-4 is
whether, in view of clause 14 of the contract it was open to
the respondent to make the claim on the basis of the rate
quoted by it in the notice. Clause 14 provides:
Alterations in specifications and designs not
to invalidate contracts--
The Engineer-in-charge shall have power to
make any alterations in, or additions to, the
original specifications, drawings, designs and
instructions that may appear to him to be
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 5 of 11
necessary or advisable during the progress of
the work, and the contractor shall be bound to
carry out the work in accordance with any
instructions in this connection which may be
given to him in writing signed by the
Engineer-in-charge and such alteration shall
not invalidate the contract; and any
additional work which the contractor may be
directed to do in the manner above specified
as part of the work shall be carried out by
the contractor on the same conditions in all
respects on which he agreed to do the main
work, and at the same rates as are specified
in the tender for the main work. And if the
additional or altered work include any class
of work for which no rate is specified in this
contract, then such class of work shall be
carried out at the rates entered in the
Schedule of Rates of the Division or at the
rates mutually agreed upon between the
Engineer-in-charge and the contractor,
whichever are lower. if the additional or
altered work, for which no rate is entered in
411
the Schedule of Rates of the Division, is
ordered to be carried out before the rates are
agreed upon then the contractor shall, within
seven, days of the date of receipt by him of
the order to carry out the work, inform the
Engineer-in-charge of the rate which it is his
intention to charge for such class of work,
and if the Engineer-in-Charge does not agree
to this rate he shall by notice in writing be
at liberty to cancel his order to carry out
such class of work, and arrange to carry it
out in such manner as he may consider
advisable, provided always that if the
contractor shall commence work or incur any
expenditure in regard thereto before the rates
shall have been determined as lastly
hereinbefore mentioned, then in such case he
shall only be entitled to be paid in respect
of the work. carried out or expenditure
incurred by him provide (previous ?) to the
date of the determination of the rate as
aforesaid according to such rate or rates as
shall be fixed by the Engineer-in-charge. In
the event of a dispute, the decision of the
Superintending Engineer of the Circle will be
final."
It is clear from the clause that where any additional or
altered work is directed to be carried out and no rates are
entered in the Schedule of Rates in the Division or agreed
to, then, the contractor may, within seven days of the
order, give notice of the rate he intends to charge. In
such a case, the Engineer-in-charge would be at liberty to
cancel the order if he does not agree to the rate stated by
the contractor and get the work done by any other agency.
Where, however, the Engineer-in-charge has not cancelled the
order for additional or altered work and the contractor has
commenced work and incurred expenditure, the contractor
shall only be entitled to be paid at such rate or rates as
may be fixed by the Engineer-in-charge. In any such case if
the contractor is dissatisfied, he may raise a dispute about
the rate or rates so fixed by the Engineer-in-charge. Where
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 6 of 11
such dispute is raised, the Superintending Engineer will
decide the same and his decision will be final.
We do not think that the respondent was bound to carry out
the additions, and alterations as there was no reply to the
notice stating the rates it intended to charge. But it was
free to commence and complete the work on the basis that
since the rates quoted by it were not accepted, it would be
paid at such rates to be fixed by the Engineer-in-charge and
that if it was dissatisfied with the rate or rates fixed by
the Engineer-in-charge, if could raise a dispute before the
Superintending Engineer and that the time limit for
completion would be extended in all cases of additions or
alterations as stated in the last sub-para of clause 14.
The High Court was of the view that clause 14 had no
application because it thought that the respondent was bound
to carry out the work as directed by the Engineer-in-charge
even when there was no agreement as regards the rate to be
charged for the extra work, as the nature of work in some
cases would be such that if the work was not completed at
the time when the work was to be completed, the cont-
412
ractor would have to do much extra work over and above the
actual work involved. The Court also said that clause 14
gave the Engineer-in-charge an absolute power to fix the
rate and that would be unjust and therefore the Court
decreed in full the amount claimed under items A-3 and A-4.
We think that until the rates were settled by agreement the
respondent was under no obligation to carry out the
additional or altered work. The respondent could
legitimately have said that in the absence of scheduled
rates in the division for the type of work in question or an
agreement in regard to the rates, it was not bound to carry
out the additional or altered work. We are not satisfied
that since the Engineer-in-charge did not exercise his
liberty to cancel the order, there was a concluded contract
between the parties. The failure to cancel the order for
additional or altered work on receipt of the notice speci-
fying the rate would not result in an agreement as to the
rate to be charged. The clause only gave the Engineer-in-
charge the liberty to cancel the order and get the work done
by another contractor. The fact that an express power was
given to the Engineer-in-charge by the clause to cancel the
order if he did not agree to the rate would not mean that
the failure to cancel the order would result in an agreement
as to the rate or rates. The proviso in clause 14 was
intended to cover cases where the notice specifying the rate
was not given by the contractor, or where, even though the
notice was given, the Engineer-in-charge did not cancel the
order in the event of his not agreeing to the rate specified
in the notice. We are of the view that in the absence of
some positive act on the part of the Engineer-in-charge
agreeing to the rate, there was no agreement as to the rate
and that the respondent was not bound to carry out the work.
In this view of the matter, we think that the High Court
went wrong in allowing the claim in item A-4.
The claim under Item A-3 stands on the same footing as the,
claim under item A-4 and, therefore, that claim has also to
be rejected;
The next question is whether the High Court was justified in
decreeing the claims in items C-1 and C-2.
Item C-1 was a claim for Rs. 9,000/-. The respondent’s case
was that there was assurance by the appellant that the work
was to be completed in accordance with the specifications in
the agreement and that no alteration would be made therein.
According to the respondent, as per the specification, it
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 7 of 11
was to do the work with 5" thick R.C.C. slab over B and B-1
type of blocks to cover an area of about 61,000 sq. ft. an,
the rate at which the respondent agreed to do the work was
Rs. 2-15-6 per sq. ft. The further case of the respondent
was that it agreed to do the construction work after
estimating the cost of the entire construction as a whole
and after making a calculation of the profit and loss on
that basis in different items of work and it had sustained
loss because it had to do a different type of work for which
it could make no estimate in anticipation. The order to
carry out the work in the altered form was communicated to
the respondent on 27-1-1949.
413
It protested against it saying that it will have to use
extra quantity of iron and claimed 6 annas extra per sq. ft.
over the rate for 4 1/2" slab which it had given for ’A’
type block. The appellant turned down the demand and the
respondent had to do the work with 4 1/2" R.C.C. slabs over
the area of 24,000 sq. ft. According to the respondent, if
it were to do the work with 5" slab according to the
original specification over the’ area of 24,000 sq. ft., it
would have used 27,000 lbs. of iron as reinforcement and
would have got Rs. 71,250 for the work, but, because of the
reduction in the size of the slab, it was required to put in
44,000 lbs. of reinforcement and was to be paid Rs. 60,000
only. On the other hand, the appellant contended that the
Engineer-in-charge was entitled to change the specification
under the contract and the respondent was not entitled to
claim any damage arising from the change in the nature of
the work and relied upon clause 15 for this purpose. The
High Court held that clause 15 had no application.
We do not think that the High Court was in error. Clause 15
empowers the Engineer-in-charge to step or to reduce the
whole of the work specified in the tender if he thinks it
necessary to do so and the, contractor has no right to claim
any compensation whatsoever on account of such stoppage or
reduction in the work. The clause also provides that the
contractor shall have no right to claim any payment or
compensation on account of any profit or advantage which he
might have derived from the execution of the work in full
but which he did not derive in consequence of the full
amount of the work not having been carried out or on account
of any loss that he may be put to on account of materials
purchased or agreed to be purchased or for unemployment of
labour recruited by him. The clause further provides that
the contractor shall not also have any claim for
compensation by reason of any alteration having been made in
the original specifications, drawings, design or instruction
which may involve curtailment of work as originally
contemplated.
In its evidence, the respondent stated that it put slabs of
4 1/2" thickness in an area measuring 24,000 sq. ft. out of
an area of 61,000 sq. ft. and that it had to put 44,000 lbs.
of reinforcement instead of 27,000 lbs. and so it must be
paid for the extra 17,000 lbs. a sum of Rs. 9,000/-. The
High Court took the view that this involved no reduction or
curtailment in the work and as the alteration involved
additional cost to the respondent, it cannot be said that
there was reduction or curtailment of work. 1n other words,
the High Court was of the view that the nature of the work
was such that there was not only no curtailment of work but
an increase of work involving additional cost. We think the
High Court was right in its conclusion that clause 15 has no
application and that the claim was well founded.
The respondent had claimed Rs. 9,097/- from the appellant in
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 8 of 11
respect of item C-2. In the plaint the respondent stated
that the appellant represented to it that the appellant
would entrust the respondent with the pipeline work
mentioned therein but that the appellant, contrary to
representation, got the work done by another contractor and,
therefore, the respondent was entitled to compensation for
it.
423SCI/75
414
The High Court found that as it was provided in clause 15
that before the Engineer-in-charge could stop the work and
get the work done by another contractor, he should give the.
respondent a written notice and as such a notice was not
given, the respondent was entitled to damage.
We see no reason to think that observance of the condition
as regards the written notice was not mandatory. We see no
force in the argument that the written notice was not
necessary as that was specifically provided for in the
clause.
The last point for consideration is whether the suit was
barred by limitation as it was not brought within six months
of the act complained of.
The High Court was of the view that s. 64 of the Bombay
Housing Board Act, 1948 has no application as the claims
were for damages for breach of contract.
Section 64 provides
"No person shall commence any suit against the
Board or against any officer or servant of the
Board or any person acting under the orders of
the Board, for anything done or purporting to
have been done in pursuance of this Act, with-
out giving the Board, officer, or servant or
person two months’ previous notice in writing
of the intended suit and of the cause thereof,
nor after six months from the date of the act
Complained of."
"And in the case of any such suit for damages,
if tender of sufficient amends shall have been
made before the action was brought, the
plaintiff shall not recover more than the
amounts so tendered and shall pay all costs
incurred by the defendant after such tender."
The appellant submitted that the act of entering into the
contract was an act done or purporting to have been done in
pursuance of the Act and therefore, any claim for money as
damages for breach of the contract by the respondent would
come within the purview of the section.
The Preamble of the Act provides
"Whereas it is expendient to take such
measures, to make such schemes and to carry
out such works as are necessary for the
purpose of dealing with and satisfying the
need of housing accommodation and with that
object in view it is necessary to establish a
Board and to make certain other provisions
hereinafter appearing; It is hereby enacted as
follows."
Section 19 provides that the Board may enter into all such
contracts as it may consider necessary for carrying out the
purposes of the Act. Section 23 (1 ) states that the Board
may incur expenditure and undertake works for framing and
execution of housing schemes. Section 23(2) says that the
government may entrust to the Board the framing
415
and execution of any housing scheme. Therefore, the Board
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 9 of 11
has statutory duty to frame schemes for construction of
houses and execute them. Section 24(f) would also indicate
that the purpose of a scheme is construction of house. In
these circumstances, we think that the contract entered into
the Board for construction of buildings might be an act done
in pursuance to the provisions of the Act. We will also
assume that it makes no difference whether it was deemed to
be entered the contract was or whether it wag deemed to be
entered 54 of the Act. But the question is whether the act
complained of, namely the non-payment of a claim for money
based on breach of contract, was an act done or purporting
to have been done in pursuance of the Act.
There can be no doubt that the act complained of by the
respondent was the non-payment of money as damages or
compensation resulting from an alleged breach of contract.
In The Municipal Borough of Ahmedabad v. Jayantilal
Chhotalal Patel(1) the Court held that when a municipality
has power to enter into a contract under the Municipal
Boroughs Act and the municipality purports to exercise its
power to enforce such contract, any act done in the exercise
of its power to enforce the contract is not in pursuance of
the Act but in pursuance to the contract and, therefore, a
suit brought against the municipality for return of deposit
under a contract to clean the streets was not a suit of the
type described in s. 206 of the Bombay Municipal Boroughs
Act, 1925 which is in pari materia with s. 64 of the Act.
In the course of the judgment, Chagla, J. (as he then was)
observed that what the plaintiff sought to enforce was, the
right which came into existence as a result of the contract
entered into between the plaintiff and the municipality and
not a public duty cast upon the municipality by the statute,
that in forfeiting the deposit, the municipality was not
acting in pursuance to the power given to ’it under statute
but was doing so in pursuance of a power given to it under
the contract and, therefore, the suit to enforce rights
under the contract entered into with the municipality which
the municipality was not under any obligation to enter
into, cannot fall with the ambit of the section. We think
that the decision lays down the law correctly ,and that the
principle deducible from it is applicable to the facts here.
Mr. S. T. Desai referred to the decision of the Madras High
Court in Athimannil Muhammad v. The Malabar District
Board(2) and said that the decision therein would I govern
the instant case. That was a case where a suit was filed
against the District Board more than six months after the
date of the accrual of the cause of action, claiming damages
on the ground that its President improperly cancelled a
contract of lease for one year of the tolls in certain
places, which was stated to have been entered into by the
plaintiff with the Board through its Vice President. The
President in performance of what he thought was his duty
under the Madras Local Boards Act accepted a higher offer by
another person and the necessary consequence of it was
cancellation of the acceptance of the plaintiff’s offer. It
was held that though the distinction between actions on
contract and actions independent of con-
(1) (I.L.R.) 1947 Bom. 841
(2) I.L.R. 58 Madras 746.
416
tract may be convenient enough as a working rule, the real
test to be applied was whether what was complained of was
some act done in pursuance of a statute. Varadachariar, J.
in delivering the judgment of the Court said that the
cancellation of the acceptance of the offer was the
necessary result of what the President thought was his duty
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 10 of 11
in accordance with the terms of the Act as he interpreted
them namely to accept the highest tender and that he did
this on the footing that the Vice President’s acceptance of
the plaintiff’s tender was not in compliance with the Act.
He further said that the right to collect tolls was a
special privilege conferred upon local bodies by- statute
and that they were authorized either to manage the
collection of the tolls themselves or through their own
agency or to lease them out, and that in any case what the
President as representing the Board did in connection with
the leasing out of the right to levy tolls was undoubtedly
an act done in execution of his powers or duties under the
Act.
We need not consider the correctness of this decision as,
even on the assumption that it is correct, it has no
application to the facts here. There the Court found that
the act complained of had reasonable connection with the
discharge of his statutory duty as President or at any rate,
he thought that it was his statutory duty as President to
accept the highest bid. The distinction between an act done
with some semblance of authority or show of right and a
prima facie illegal act in this context has been clearly
pointed out in the decision in Jalgaon Borough Municipality
v. The Khandesh Spinning and Weaving Mills Co. Ltd. (1)
where the question was whether-notice under s.206 ,of the
Bombay Municipal Boroughs Act, 1925, was necessary before
filing a suit to recover a sum of money on the basis of a
contract. The Court held that an act which is Prima facie
illegal is not within the category of acts done or purported
to have been done in pursuance of that Act, and that it is
only an act done under a vestige or semblance of authority
or with some show of a right that would fall within the
category. Bhagwati, J. in the course of his judgment said
that the acts which would fall within the category of those
done or purported to have been done in pursuance of the Act
could only be those which were done under a vestige or
semblance of authority, or with some show of a right and
that the distinction between ultra vires and illegal acts on
the one hand and wrongful acts on the other wrongful in the
sense that they purport to have been done in pursuance of
the Act is that they are intended to have been done in
pursuance of the Act and are done with a vestige or,
semblance of authority or sort of- a right invested in the
party doing those acts.
In The Trustees of Port of Bombay v. The Premier Automobiles
Ltd. (2) section 87 of the Bombay Port Trust Act, 1879,
which is in pari materia with s.64 of the Act fell for
consideration and the question was whether short delivery by
a statutory bailee was something done or purporting to have
been done under the provisions of that Act. In the course
of the judgment, Krishna Iyer, J., speaking for the Court,
(1) I.L.R. (1953) Bombay 590 (2) A.I.R. 1974 S.C. 923
417
said that a suit for damages for breach of contract would
not, attract the section (see para 46 of the judgment).
As we said, the act complained of in this case was the non-
payment of the amount alleged to be due to the respondent on
the-basis of the breach of the contract between the parties.
We do not think that the act complained of could be said to
have been done or purported to have been done in pursuance
of the Act. By no stretch of imagination could it be said
that the breach complained of had any reasonable connection
with any duty cast upon the appellant or its agents by the
Act.
In the result we disallow the claims of the respondent in
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 11 of 11
items A-3 and A-4 set aside the decree of the High Court to
that extent. We affirm the decree of the High Court in
respect of the claims in items C-1 and C-2. The appeal is
allowed to the extent indicated but is dismissed in other
respects. We direct the parties to bear their cost in this
Court.
V.P.S. Appeal allowed in part.
418