Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 7
PETITIONER:
LARSEN & TOUBRO LIMITED
Vs.
RESPONDENT:
MAHARASHTRA STATEELECTRICITY BOARD & ORS.
DATE OF JUDGMENT13/09/1995
BENCH:
VERMA, JAGDISH SARAN (J)
BENCH:
VERMA, JAGDISH SARAN (J)
PARIPOORNAN, K.S.(J)
CITATION:
1996 AIR 334 1995 SCC (6) 68
JT 1995 (7) 18 1995 SCALE (5)342
ACT:
HEADNOTE:
JUDGMENT:
J U D G M E N T
PARIPOORNAN, J.
Leave granted.
The appellant, petitioner in arbitration petition Lodg.
No.240/94 in the High Court of Judicature at Bombay,
initiated under Section 41 of the Arbitration Act, has filed
this appeal by special leave against the order passed by
N.D. Vyas,J. dated 20.10.1994. The appellant’s prayer for
injunction against the first respondent (Maharashtra State
Electricity Board) from invoking or claiming or demanding or
releasing any amount whatsoever under certain bank
guarantees given by respondent Nos, 2 to 5 was dismissed by
the aforesaid order by the learned Judge. Respondent Nos. 1
to 5 in the arbitration petition Lodg. No. 240/94 as also in
this appeal are - (1) Maharashtra State Electricity Board,
Bombay, (2) Standard Chartered Bank, branch Bombay, (3)
Grindlays Bank p.l.c., branch Bombay, (4) Citi Bank, N.A.,
branch Bombay and (5) Bank of Baroda, branch Bombay.
The first respondent invited tenders for supply and
commission of Coal Handling Plant. The appellant’s tender,
which was accepted, culminated in a contract, executed
between the parties, dated 9.3.1989. The value of the
contract was Rs. 61,11,07,200/-. The appellant furnished the
following five Bank Guarantees :
Name of No of the Bank Nature of Amount of Last
the Bank Guarantee the Bank the Bank extended
Guarantee Guarantee date.
in Rs.
------------------------------------------------------------
1. Standard 529/88/153 Security 5,50,30,000 31.5.94
Chartered against
Bank/Respondent advance
No. 2 payment
2. ANZ 1101/88/384/G Performance 6,17,28,000 31.3.95
Grindlays
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 7
Bank, PLC
Respondent
No. 3.
3.Citi Bank, 26247 Partial 2,72,39,850 19.11.94
N.A. release
Respondent of reten-
No. 4 tion money
4. Bank of 73/309 Security 6,13,40,978 26.9.94
Baroda, against
Respondent liquidated
No. 5 damage
5. Standard 529/92/380 Partial 1,12,00,000 31.12.94
Chartered release of
Bank retention
Respondent money
No. 2.
------------------------------------------------------------
(Vol.II page 4 of Paper Book)
The completion of the Plant seems to have been delayed. The
parties are blaming each other for the delay. After taking
the trial and performance test, the Plant was taken over by
the first respondent on 10.6.1994. On the same day a take-
over certificate was also issued. It is seen that earlier on
29.3.1994, the appellant lodged its claim. The first
respondent denied the claims so made. They did not make any
counter-claim then. On 4.6.1994, the appellant invoked the
arbitration clause as per the contract. A meeting of the
Arbitrators took place on 14.9.1994. The Arbitrators gave
certain directions. In pursuance thereto the appellant filed
its claim on 30.9.1994. The Arbitrators gave time to the
first respondent to file their counter claim on or before
30.11.1994. In the mean-while on 1.10.1994 the first
respondent invoked all the Bank Guarantees except Guarantee
No. 2 mentioned herein-above (Performance Guarantee). The
Court passed an order directing the status quo to be
maintained on 17.10.1994. Appellant filed arbitration
petition Lodg. No. 240/94 and contended that the Bank
Guarantees have been fraudulently and dishonestly invoked.
Regarding Guarantees in respect of advance and liquidated
damages, it was further alleged that they were invoked after
the date of expiry of the said Guarantees. Vyas,J. rejected
the above pleas and declined to grant the interim relief as
prayed for by the appellant. As agreed to by counsel on both
sides, the interim order was made the order in the main
petition itself. Arbitration Petition Lodg. No. 240/94 was
dismissed. Hence this appeal by special leave.
We heard appellant’s Counsel Mr. B.M. Naik, Senior
Advocate, and Mr. Harish N. Salve, Senior Advocate, who
appeared for the respondents. At the outset we should make
it clear that the Bank Guarantee relating to performance,
item No. 2 mentioned in the preceding paragraph, was not
invoked and is not covered by the subject matter of this
proceeding.
Before we adjudicate the rival pleas urged before us by
Counsel for the parties, it will be useful to bear in mind
the salient principles to be borne in mind by the Court in
the matter of grant of injunction against the enforcement of
a Bank Guarantee/irrevocable Letter of Credit. After survey
of the earlier decisions of this Court in United Commercial
Bank v. Bank of India and ors., 1981 (2) SCC 766, U.P.
Cooperative Federation Ltd. v. Singh Consultants & Engineers
(P) Ltd., 1988 (1) SCC 174, General Electric Technical
Services Company Inc. v. Punj Sons (P) Ltd. and anr., 1991
(4) SCC 230 and the decision of the Court of Appeal in
England in Elian and Rabbath v. Matsas and Matsas, 1966 (2)
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 7
Lloyd’s Report 495 and a few American decisions, this Court
in Svenska Handelsbanken v. M/s. Indian Charge Chrome And
Others, 1994 (1) SCC 502, laid down the law thus :-
"...... in case of confirmed bank
guarantes/irrevocable letters of credit,
it cannot be interfered with unless
there is fraud and irretrievable
injustice involved in the case and fraud
has to be an established fraud. ......"
(p.523)
"....... irretrievable injustice which
was made the basis for grant of
injunction really was on the ground that
the guarantee was not encashable on its
terms......." (p.524)
"...... there should be prima facie case
of fraud and special equities in the
form of preventing irretrievable
injustice between the parties. Mere
irretrievable injustice without prima
facie case of established fraud is of no
consequence in restraining the
encashment of bank guarantee." (pp.526-
527)
In the order appealed against the learned Judge has
referred to the decisions aforesaid and has held thus:-
"...... only in the event of fraud or
irretrievable injustice, the Court would
be entitled to interfere in a
transaction involving a bank guarantee
and under no other circumstances. The
petitioners have failed on both these
counts."
(Paper Book - Vol.I p. 7)
Appellant’s Counsel contended that the Bank Guarantees
have been fraudulently and dishonestly invoked by the first
respondent. It was submitted that so far as the Bank
Guarantee towards advance was concerned, no amount remains
as balance towards advance and in fact a sum of Rs. 27,000/-
is recoverable from the first respondent. With regard to the
two Bank Guarantees, dealing with retention money (Item Nos.
3 and 5) it was contended that the trial was taken by the
first respondent after which performance test was also done
and thereafter the take-over was completed and so, on the
basis of the contract, the first respondent was bound to
return the Retention Guarantees. Regarding liquidated
damages (Item No. 4) it was contended that the first
respondent should prove that they suffered damages and
quantify the same before invoking the Guarantee. It was also
contended that the invocation of the Guarantees relating to
advance and liquidated damages was after the expiry of the
period. The learned Judge found that no fraud or
irretrievable injustice has been made out. The Court also
held that the appellant will be able to claim relief before
the Arbitrators by way of damages, for amounts wrongly
recovered, and so no irretrievable injustice can be said to
exist. The learned Judge also held that the first respondent
by separate letters dated 14.9.1994 and 10.5.1994 addressed
to the Bank of Baroda and Standard Chartered Bank
respectively, while requesting to extend the Bank Guarantee,
specifically stated that, if it was not so done, the
communication should be treated as notice for encashment of
the Bank Guarantee and these communications addressed to the
respective banks prior to the Guarantees would serve the
purpose of notice to the banks and so it cannot be held that
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 4 of 7
the invocation was after the date of expiry of the said
Guarantees.
Having heard Counsel and on perusing the relevant
records, we are of the view that the order of the Court
below regarding Item No. 3 - Partial relase of retention
money in the sum of Rs. 2,72,39,850/-, Guarantee given by
the Citi Bank alone requires modification. We will deal with
the various items in seriatim :
ITEM NO. 1: Security against advance payment
(Advance Bank Guarantee).
The Guarantee given on this count by the Standard
Chartered Bank for a sum of Rs. 5,50,30,000 is contained in
paper book Volume II at pages 109 to 113. It was agreed at
the bar that the Bank Guarantee has not been invoked for the
entire sum of Rs. 5.50 crores but is limited to a sum of Rs.
8 lakhs only. We find that dispute exists with regard to the
said subject matter, as is evident from the relevant papers
-- (Volume II pages 312 and 316). It is seen from the
communication dated 10.5.1994 addressed by the first
respondent to the appellant, with an endorsement to the
Standard Chartered Bank, that a request was made to extend
the validity of the Bank Guarantee for a further period of 6
months, i.e., 30.11.1994 and in case the extension is not
received before that date, the communication be treated as
notice for encashment (Vol.II pages 33 to 34 of the paper
book). We are of the view that the invocation of the
Guarantee is in time. We hold that in the light of the
dispute pending before the Arbitrator, the Court below was
justified in declining to grant an injunction against the
invocation of the Bank Guarantee on this count.
Item Nos. 3 & 5 : Partial release of retention money :
Items 3 and 5, though come under the same category, are
not similar in content and scope. Item 3, relates to Bank
Guarantee furnished by the Citi Bank, N.A. in the sum of Rs.
2.72 cores. It is a conditional Guarantee. Copy of the
document is available in paper book Volume II at pages 122
to 126. The relevant portions in the Guarantee in Volume II
at pages 124 and 125 of the paperbook, are as follows:
"AND WHEREAS at the request of the
contractors, we, CITI BANK N.A.
(hereinafter referred to as "The Bank"
has agreed to guarantee 2,72,39,850
(Rupees Two crores, Seventy Two lakhs,
Thirty Nine thousand, Eight hundred
fifty only) covering the amount of the
said payments till successful completion
of trial operations.
In pursuance of the said agreement and
in consideration of the board making the
said payment to the contractors, the
Bank hereby agree with the Board as
follows:
1. The Bank hereby agree unequivocally
and uncondition to guarantee the said
amount released by the Board till
successful completion of trial
operations in due performance of the
contract and undertakes to at Bombay
within 48 hrs. on demand in writnig from
MSEB, or any officer authorised by it in
this behalf of any amount upto and not
exceeding Rs. 2,72,39,850/- (Rupees Two
crores, Seventy two lakhs, Thirtynine
thousand, Eight hundred fifty only) to
the Maharashtra State Electricity Board
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 5 of 7
on behalf of the contractors..........
2. That the guarantee hereby given
shall be continuing guarantee upto 19
May, 1990. The validity of this Bank
Guarantee will be extended one month
prior to its present validity at the
request of the Board for suitable
period(s) till successful completion of
trial operations."
(emphasis supplied)
Volume II, pages 46 to 108, contains a copy of the
Agreement executed between the appellant and the first
respondent Board. The following clauses therein at
paragraphs 70.1, 70.2, 70.3 and 70.4.01, appearing at pages
92 to 95, are relevant in this connection. They are as
follows :
"70.1 i)..........
ii)..........
iii) After the precommissioning tests
are satisfactorily completed equipment
shall be considered ready for initial
operation. During initial operation, the
complete equipment shall be operated
integral with sub-system and supporting
equipment as a complete plant.
70.2 TRIAL OPERATION:
i) After satisfactory initial
operation, the Plant shall then be put
on trial operation. The period of trial
operation shall be 30 days from the date
of completion of initial operation.
During the period of trial operation,
all the necessary adjustments in the
plant/equipments shall be made by the
Contractor and make ready the same in
all respects for performance and
guarantee test. Out of the total period
of 30 days of trial operation, the plant
shall run for atleast a period of 100
hours at the rated capacity. Out of
these 100 hrs. a minimum of 20 hours of
operation at the rated load shall be
established for the mode of operation
from wagon tippler to the bunker.
70.3 PERFORMANCE TESTS AT SITES:
i) The performance test shall be
conducted at site by the Contractor,
after successful completion of trial
operation. The duration of the
performance test of the plant at the
rated capacity shall be of 2 hours.
Performance Guarantee test shall in any
case be conducted within 45 days of
successful completion of trial operation
or within the extended period as can be
mutually agreed. In case the performance
test cannot be conducted within a period
of 75 days after successful completion
of trial operation due to reasons solely
attributable to owner, the time frame
and method of conductance of the same
shall be discussed mutually and
finalised.
v) Any special equipment, tools and
tackles required for the successful
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 6 of 7
completion of the performance tests
shall be provided by the Contractor free
of cost."
"70.4.01 Upon successful completion of
all the performance tests at site, the
owner shall issue to the Contractor a
"Taking Over Certificate" as a proof of
the final acceptance of the
equipment........"
(emphasis supplied)
The first respondent Board intimated the appellant by
communication dated 10.6.1994 thus:
"After reasonable completion of the Coal
Handling plant works as per the contract
2 M part-A, capacity operation of the
various equipments of C.H.P. were
planned from 15th January, 1994. Rates
as well as design capacity trials also
tried. Certain points for stabilisation
which were pointed to L&T were attended.
Since these trials are generally
satisfactory as per Clause no. 70.2 &
70.3, all the commissioned equipments
under the contract of 2M Part-A are
taken over by MSEB for regular operation
and maintenance from 10th June, 1994 as
per Clause No. 70.4 of Contract
Agreement Vol. I."
(emphasis supplied)
The appellant wrote to the first respondent on 21.2.1994
that the plant was completed and so all Bank Guarantees have
served their contractual requirements. On a perusal of the
relevant clauses in the contract, executed between the
appellant and the first respondent, and the communication of
the first respondent dated 10.6.1994, it is fairly clear
that the stipulations or conditions mentioned as per clauses
70.2, 70.3 and 70.4 have been successfully fulfilled and the
Plant was admittedly taken over by the first respondent. The
Guarantee given by the Citi Bank, N.A. dated 10th of May,
1989 appearing in Volume II at pages 122 to 126 will enure
only till successful completion of the trial operations and
the plant is taken over. That event having ensued, the
invocation of the Guarantee given by the Citi Bank dated
10.5.1985 in the sum of Rs. 2.72 crores is not encashable on
its terms and in order to prevent irretrievable injustice,
an injunction as prayed for, to respondents 1 and 4 deserves
to be issued on that score. The Court below was in error in
not doing so. We hereby restrain respondents 1 and 4 from
invoking the Bank Guarantee aforesaid.
But item No. 5 partial release of retention money, for
which the second respondent, Standard Chartered Bank has
given a Bank Guarantee for Rs. 1,12,00,000 (Rs. 1.12 crores)
stands on a different footing. The relevant Guarantee is
contained in paper book Volume II at pages 134 to 138. The
first respondent made an ad hoc payment of Rs. 1.11 crores
out of the total retention amount for which the Guarantee
was furnished by the Standard Chartered Bank. It is an
unequivocal and unconditional Guarantee. We hold that no
fraud or irretrievable injustice has been made out by the
appellant. The court below was justified in declining to
issue an order of injunction on this count.
The last item is covered by the Guarantee specified as
No. 4 hereinabove. It was furnished by the Bank of Baroda as
a security against ‘liquidated damages’. The Guarantee is
contained in paper book Volume II at pages 129-131.
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 7 of 7
The Bank has given Guarantee for Rs. 6.13 crores
against the liquidated damages recoverable by the first
respondent Board, from the appellant. The relevant clauses
regarding levy of liquidated damages is contained at pages
99 and 100 of the Paper book, (Clause 75.01), to the
following effect :
"75.01 If the Contractor fails to
complete the works as per the clause
72.01 item 1, 2 & 3 within a period of
25 months from the date of letter of
intent or within any extension of time
granted by the owner then the liquidated
damages shall be levied by the Owner on
the Contractor at the rate of 1/2% (one
half of one per cent) per week of delay
of the contract price for the works
limited to 10% (ten percent) of the
contract price of the works."
Appellant’s Counsel argued that before invoking the Bank
Guarantee the first respondent should have levied the
liquidated damages and only for the sum so determined, and
intimated to the appellant, the Bank Guarantee can be
invoked. It was further argued that the Guarantee was due
for expiry on 26.9.1994 and it has been invoked after the
expiry of the said period. There is no force in the above
pleas. It is common ground that the arbitration proceeding
for resolving the dispute between the parties (appellant and
the respondent) is pending before the Arbitrator. The
parties are at issue as to whether the Plant was completed
in time or was delayed. They are blaming each othe for the
delay. That is a matter to be adjudicated in the
proceedings. It is also brought to our notice that the first
respondent has claimed liquidated damages as per clause
75.01 of the contract of more than eight crores -- much more
than the amount of Rs. 6.13 crores guaranteed. Since the
decision in the arbitration proceedings has an impact on
this aspect, we are of the view that no prima facie case of
fraud or irretrievable injustice is made out to restrain
respondents 1 and 5 from invoking the Bank Guarantee.
Perusal of the communication dated 14.9.1994, sent by the
first respondent to the appellant and also to the Bank of
Baroda appearing in paper book Volume I at pages 35 to 36,
will show that a request to extend the validity of the Bank
Guarantee which was to expire on 26.9.1994, was made and if
not so done, the communication was to be treated as notice
for encashment of the Bank Guarantee. The plea that the
invocation was not in proper time is also without substance.
In the result, we hold that the appeal succeeds in
part. The appellant is entitled to an order of injunction,
to a limited extent, against respondent Nos. 1 and 4 (Citi
Bank, N.A.), restraining them from invoking the Bank
Guarantee given by the 4th respondent - Citi Bank, N.A.
dated 1.5.1989 (item No. 3 stated hereinabove) (Volume II at
pages 122 to 126 of the Paper book). Subject to the above
modification, the order passed by the court below dated
20.10.1994 is affirmed. In the circumstances, there shall be
no order as to costs.