M/S ARUN KUMAR KAMAL KUMAR . vs. M/S SELECTED MARBLE HOME .

Case Type: Civil Appeal

Date of Judgment: 01-10-2020

Preview image for M/S ARUN KUMAR KAMAL KUMAR . vs. M/S SELECTED MARBLE HOME .

Full Judgment Text


1
NON­REPORTABLE
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NO. 8980 OF 2017
M/S ARUN KUMAR KAMAL KUMAR & ORS. … APPELLANT(S) 
VERSUS
M/S SELECTED MARBLE HOME & ORS.        … RESPONDENT(S)
J U D G M E N T
S. ABDUL NAZEER, J.
1. In this appeal, the appellants have questioned the legality and
correctness   of   the   final   judgment   and   order   dated   11.02.2010
passed by the High Court of Delhi in FAO(OS)No.450/2009 whereby
the Division Bench of the High Court dismissed the appeal filed
against the judgment of the Learned Single Judge of the High Court
Signature Not Verified
Digitally signed by
GEETA AHUJA
Date: 2020.10.01
15:17:07 IST
Reason:
dated 24.07.2009 passed in C.S.(OS)NO(s).647­A/1998 and 715­
A/1998   whereby   the   Learned   Single   Judge   had   rejected   the

2
objections of the appellants and made the Award dated 16.03.1998
the rule of the court.   However, vide the impugned judgment the
Division Bench reduced the rate of interest from 16% per annum to
9% per annum as applicable to future interest i.e. from the date of
the Award, 16.03.1998, till the date of the judgment. This reduction
was made subject to the appellants paying the complete decretal
amount to the respondents on or before 30.06.2010, failing which
the Award along with interest would stand as it is.
2. The   appellants   are   in   the   business   of   running   of
restaurants/eateries and manufacture & sale of sweets and other
food items.   The appellants are running their business under the
brand name “Nathu’s Sweets”.   In the year 1990, the appellants
entered into two separate licence agreements with the respondents
whereunder it was agreed that the appellants will operate and run a
restaurant   cum   sweets   shop   at   the   respondents’   premises   and
make payment to the respondents on commission basis.  The first
licence   agreement   dated   27.08.1990   was   executed   between
appellant no. 1­M/s. Arun Kumar Kamal Kumar through appellant
no.2­Arun Kumar Gupta and respondent no.1 M/s. Selected Marble

3
Home  through   respondent   no.2­Anil   Kumar   Jain   and   two   other
partners   of   the   said   respondent   no.   1   firm   and   the   second
agreement of the same date was executed between appellant no. 1­
M/s.   Arun   Kumar   Kamal   Kumar   through   appellant   No.2­Arun
Kumar Gupta and respondent no.3­Bhim Sain Jain.
3.   According to the appellants, the respondents started violating
the terms of the agreements after commencement of the business
and raised obstacles in the smooth running of the business. The
premises which were handed over to the appellants had only two
electricity connections – one meter of 1 KV and the other of 0.25 KV
respectively.  Since the sanctioned capacity of the said connections
was less than required, the appellants allege that the respondents
had   agreed   to   apply   and   obtain   electricity   connection   with   a
sanction   to   load   of   2.5   KV.   However,   in   order   to   harass   the
appellants,   the   respondents   did   not   make   arrangements   for
sufficient electricity supply. On the other hand, it was due to their
acts of omission and commission that the then Delhi Electricity
Supply Undertaking (DESU) disconnected electricity supply to the
entire building on 22.10.1990.  The business could not be operated

4
and the same was stopped in February 1991.  The shop thereafter
remained closed from March 1991 to October 1995.  
4. On account of the appellants’ non­payment of commission and
failure to handover the vacant possession of the premises to the
respondents, the respondents filed Suit NO.3708­A/1991 before the
Delhi High Court under Section 20 of the Arbitration Act, 1940 (for
short, ‘the  Act’).   Vide Order dated 18.09.1995, the High Court
appointed the Arbitrator to adjudicate upon the dispute between
the parties.
5. During   the   pendency   of   the   arbitration   proceedings,   the
business   was   restarted   from   November   1995   and   continued   in
operation till March 2000 when possession of the same was handed
over by the appellants to the respondents.
6. In the arbitration proceedings, learned Arbitrator framed as
many   as   16   issues.   The   parties   agreed   to   file   their   respective
affidavits   which   were   read   as   examination­in­chief,   after   which
cross­examination   took   place.     After   the   conclusion   of   the
arguments   of   the   appellants   and   during   the   arguments   of   the

5
respondents, learned Arbitrator framed an additional issue No.15­A
which reads as under:
“Whether the claimants are entitled to any damages?
If so, for what period and to what amount.”
7. After the arguments were concluded, the respondents filed a
statement   of   account   calculating   the   commission   that   became
payable   to   the   appellants   after   restarting   of   the   business,   as
directed by learned Arbitrator.  This statement was not objected to
by the respondents and was then taken by the Learned Arbitrator
as the basis for calculating damages for the period during which the
business was closed but the appellants had retained possession of
the respondents’ premises.  It is the case of the appellants that in
this statement of accounts submitted before the Learned Arbitrator,
inadvertent errors had crept in. Firstly, the appellants argue that
the sales tax paid on the sales was inadvertently not deducted to
arrive at the commission payable. Secondly, the expenses incurred
on electricity and water bills were inadvertently deducted from the
sales instead of deducting the same from the amount of commission
payable to the respondents, as the same were their liability as per

6
Clause   14   in   both   of   the   Agreements   entered   into   between   the
parties.  Learned Arbitrator published his award on 16.03.1998.
8. The   appellants   challenged   the   said   award   before   the   High
Court.   The Learned Single Judge vide judgment and order dated
04.11.2004   rejected   the   objections   and   made   the   award   of   the
Arbitrator rule of the court.  As noticed above, the Division Bench of
the   High   Court   has   confirmed   the   judgment   of   learned   Single
Judge,   apart   from   allowing   a   reduction   in   the   rate   of   interest
applicable to post­award interest.
9. We have heard learned counsel for the parties.  Appearing for
the appellants Mr. Rakesh K. Khanna, learned senior counsel, has
submitted that the appellants were not liable to pay any rent.  He
argued that the parties had only agreed to pay commission on the
gross sales and that there was no clause in the Agreement which
contemplated payment of damages for the use and occupation of
the   premises.     Therefore,   the   Arbitrator   was   not   justified   in
declaring   the   Agreements   as   Licence   Agreements   and   awarding
damages on the basis of commission paid prior to the closure of the
premises before March 1991 and the commission payable after re­

7
starting of the business after 1995.   He has further argued that
learned   Single   Judge   erred   in   holding   that   the   appellants   were
liable   to   pay   damages   and   further   holding   that   even   if   the
appellants’   argument   is   accepted   and   they   are   deemed   to   be
tenants, even then would have been liable to pay rent even if the
shop   remained   closed   and   there   were   no   sales.   It   was   further
argued   that   the   Agreements   did   not   contain   any   clause   for
damages.   Therefore,   the   awarding   of   damages   is   not   justified.
Secondly,   it   was   argued   that   in   the   statement   of   accounts
submitted by the appellants, the errors had crept in inadvertently.
The sales­tax paid on the sales was not deducted to arrive at the
commission payable.  Further, the expenses incurred on electricity
and water were deducted from the sales instead of deducting the
same from the commission of the respondents as the same was
their liability.  Thus, it was argued that the courts below have failed
to   consider   this   aspect.   These   were   mathematical   errors   and
apparent on the face of the record.   Had these corrections been
carried   out,   the   compensation   payable   would   have   been
considerably lesser.

8
10. Learned counsel for the respondents submits that there were
no mistakes in the statement of accounts and these contentions
have now been urged as an afterthought. The appellants have not
only themselves filed the statement with which they are bound but
have also deducted at source and paid taxes on the commission
shown to be due in the aforesaid statement.   On the question of
damages, learned counsel submits that by taking into account the
plea of the appellants, learned Single Judge has concluded that
they   are   liable   to   pay   damages   for   use   and   occupation   of   the
premises for the period during which the business was not running
and no commission payments were made.  Thus, it was argued that
the findings of fact recorded by the courts below do not call for
interference in this appeal.  
11. We have carefully considered the submissions of the learned
counsel   made   at   the   Bar   and   perused   the   materials   placed   on
record.
12. As   per   Clause   10   of   both   the   Agreements,   in   case   of   any
dispute, it was incumbent on the appellants to handover vacant
possession of the premises to the respondents. On this issue, it is

9
clear that disputes had arisen between the parties. However, it is an
admitted position that possession of the premises was not handed
over   to   the   respondents   by   the   appellants   until   the   arbitration
proceedings had commenced and has, in fact, only been handed
over on 13 March 2000. Therefore, the Arbitrator framed Issue No.
15­A regarding damages payable to the respondents.  The Learned
Arbitrator has rejected the plea of the appellants that they had to
close the business because of the obstructionist tactics adopted by
the   respondents   and   for   that   reason   the   business   activities
remained closed from April, 1991 to November, 1995.  On a detailed
consideration of the materials on record, the Learned Arbitrator had
come to the conclusion that the appellants are liable to pay the
damages.
13. This   question   was   again   considered   by   the   learned   Single
Judge.  The learned Single Judge noticed the plea of the appellants
that the transaction between the parties was of tenancy and not
licence.   After   dealing   with   this   plea,   the   learned   Single   Judge
upheld   the     award   of   damages   by   the   Learned   Arbitrator.   The

10
finding of the learned Single Judge in this regard is in paragraph 20
which reads as under:
“I find it has been the case of the respondents that
the transaction between the parties was of tenancy
and not of a licence.  It is so pleaded in the objections
also.  Even if the respondents consider themselves to
be tenants at the rent equivalent to commission @
11%   per   month,   the   respondents   would   under
Section   108   of   the   Transfer   of   Property   Act   have
continued   to   remain   liable   for   payment   of   rent,
notwithstanding   not   carrying   on   business   in   the
premises.  It has been held by the Division Bench of
this   Court   in  
State   Bank   of   Patiala   v.
1996 RLR 404 held that a tenant
Chandermohan – 
continues to be liable for rent/damages even if the
premises are destroyed and the only option of the
tenant if desirous to stop the running of rent is to
surrender   the   premises.     Thus   as   per   the
respondents own understanding of the relationship
also, the respondents were liable for payment of rent.

14. We do not find any error in the said finding of the learned
Single Judge.
15. After finding the appellants liable to pay damages, the Learned
Arbitrator   has   arrived   at   the   quantum   of   damages   as   per   the
statement of accounts, furnished by the appellants based on their
audited accounts, that too after deduction of TDS for a period of

11
pre­closure   i.e.   15.08.1990   to   22.02.1991   and   post­closure   i.e.
November 1995 to November 1997.   The payment of damages for
the   closure   period   i.e.   March   1991   to   October   1995   has   been
arrived at as an average of commission actually paid pre­closure
and the commission payable post­closure as per the statement of
accounts of the appellants, after deducting TDS.  
16. There is also no merit in the contention of the learned senior
counsel   for   the   appellants   that   the   appellants’   statement   of
accounts erroneously deducted expenses incurred on electricity and
water   from   the   sales   instead   of   deducting   the   same   from
commission of the respondents.  The admitted position is that there
was no electricity supply and the appellants used generator set for
electricity.   The contention of the appellants is that the expenses
incurred towards generator ought to have been deducted from the
gross commission payable and not from the gross sale amount and
then   the   commission   should   have   been   calculated   at   the
contractually stipulated rates of  6% and 5%.  This plea has been
dealt with by learned Single Judge as under:
“The   other   mistake   pointed   out   of   deduction   of
expenses on diesel generator set from sales rather

12
than   from   commission   payable,   even   if   made   out,
also   cannot   be   permitted   to   be   withdrawn   at   this
stage especially when the respondents have already
deducted   and   paid   taxes   on   the   basis   of   said
statement.   Under the agreement the electricity and
water charges of the premises were to be borne by
the petitioners.   Admittedly, the premises/shop on
reopening   were   without   electricity   and   diesel
generator set arranged.  There is no dispute that the
expenses therefor were to be borne by the petitioners.
The respondents while furnishing the statement to
arbitrator, did direct the same.   The objections now
that   such   deduction   was   wrongly   done   is   not
tenable?”
This contention has been raised on the ground that the statement
filed by the appellants was not correct since the appellants were
only liable to pay commission at 6% and 5% under two agreements
on the gross sales and the responsibility to provide electricity was
on the respondents.  We are of the view that the appellants cannot
be   permitted   to   withdraw   their   own   statement   made   before   the
Learned Arbitrator which is predicated to on a mode of calculation,
the same not being disputed by the respondents and accepted by
the   Arbitrator   as   correct.     We   are   also   of   the   view   that   the
appellants are not justified in raising a contrary plea other than
what   was   their   defence   and   statement   of   counter   claim   in   the
arbitral proceedings.

13
17. We are also of the view that the Learned Arbitrator has rightly
relied   on   the   appellants’   statement   of   accounts   for   awarding
commission for the period when the business was restarted post­
closure between November 1995 and November 1997.  The formula
adopted by the Learned Arbitrator for arriving at this commission
amount as well as the damages has been accepted by learned Single
Judge as also the Division Bench of the High Court.
18. In view of above, we do not find any merit in this appeal which
is accordingly dismissed.  There shall be no order as to costs.
19. The Division Bench of the High Court while dismissing the
appeal has reduced the rate of interest from 16% per annum to 9%
per annum from the date of the Award till the date of its judgment,
subject   to   the   appellants   paying   the   decretal   amount   to   the
respondents on or before 30.06.2010. We are inclined to give a
similar benefit to the appellants herein.   Accordingly, the rate of
interest is reduced from 16% per annum to 9% per annum from the
date of the Award till this date, subject to the appellants paying the
complete   decretal   amount   to   the   respondents   on   or   before

14
31.12.2020 failing which the Award along with interest would stand
as it is.
   
…….……………………………J.
    (N.V. RAMANA)
…….……………………………J.
    (S. ABDUL NAZEER)
…….……………………………J.
    (SURYA KANT)
New Delhi;
October 01, 2020