Full Judgment Text
NON-REPORTABLE
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NO.1805/2021
MAHARASHTRA STATE ELECTRICITY
DISTRIBUTION COMPANY LIMITED APPELLANT(S)
VERSUS
RATTAN INDIA POWER LIMITED
& ANR. RESPONDENT(S)
J U D G M E N T
B.R. GAVAI, J.
1. This appeal challenges the order passed by the
Appellate Tribunal for Electricity dated 13.11.2020. The
operative part of the order reads thus:-
“77. In view of the foregoing
conclusions, we set aside the impugned
order passed on 03.04.2018 by the
Maharashtra Electricity Regulatory
Commission in case No.154 of 2013 and
case no.147 of 2014 to the extent thereby
the above-mentioned five issues were
determined and direct that:-
(i) the matter relating to issues of
SGRM GCV and of compensation for
change in law beyond 31.03.2017
be considered afresh in light of
judgment dated 14.09.2020 by this
tribunal in Appeal No.182 of 2019
Signature Not Verified
Digitally signed by
Narendra Prasad
Date: 2023.04.15
14:09:56 IST
Reason:
1
Adani Power Maharashtra Limited
(APML) v. Maharashtra State
Electricity Distribution Company
Limited & Ors., as per decisions
summarized in para 35 above; and
(ii) the full impact of additional
cost actually incurred in
procurement of coal from alternative
sources to the extent of shortfall in
supply of linkage coal and it being
utilized on monthly basis for the
period in question, and the
consequent carrying cost, be given
pass through such that the
appellant is fully compensated and
put in the same economic position
as it would have been but for
change of law, as concluded in
paras 70 and 76 above.
78. The appeal is allowed in above
terms.”
2.
Shri Balbir Singh, learned Additional Solicitor General
of India (‘ASG” for short) appearing on behalf of the
Distribution Company (“DISCOM” for short), submits that
though the respondent gets a specific quantity for a
particular month out of the Annual Contracted Quantity
(ACQ), in the event the same is not utilized for a particular
month, it is not carried forward to the next month, thereby
giving undue benefit to the generator.
2
3. Shri Sajan Poovayya, learned Senior Counsel and Mr.
Vishrov Mukerjee, learned counsel appearing on behalf of the
Generator submit that the said apprehension is totally
misconceived as could be seen from the impugned judgment.
4.
We find that the apprehension is not well merited.
Insofar as direction No.1 is concerned, the same is in tune
with the view taken by us in Maharashtra State
Electricity Distribution Company Ltd. v. Adani Power
1
Maharashtra Limited and Others . Insofar as, direction
No.2 is concerned, the same is also covered by the judgment
of this Court in Adani Power Maharashtra Limited (supra)
following the law laid down in Energy Watchdog v. Central
2
Electricity Regulatory Commission and Others .
5. Insofar as the apprehension with regard to unutilized
coal quantity for a particular month being not carried
forward to the next month is concerned, the same is also
1 2023 SCC Online SC 233
2
(2017) 14 SCC 80
3
without substance. In this respect, it will be relevant to
reproduce paragraph 43 of the impugned judgment, wherein
the learned Tribunal has recorded the submission of the
respondent/generator, which is extracted below:-
“43. The appellant, on the other hand,
argues that MERC has erred in stating
that computation of compensation for
monthly coal quantum variation shall be
on an annual basis. It is submitted that
demand and consequent offtake of coal
changes month to month and is subject
to various factors such as Plant Load
Factor (PLF), demand, actual coal
supplied etc. Thus, it is possible that in
a given month there is no (or low)
demand of coal than the quantity of coal
offered by CIL for offtake. If
compensation is calculated cumulatively
on annual basis, the aforesaid surplus
may get set off against shortfall in coal
in another month, when the demand of
coal was higher than the quantity of
coal supplied. This is illustrated by
example based on date (Considering
capacity of 1000 MW) as tabulated
below:-
| Month | Coal<br>Assured | Coal<br>Delivered | Actual<br>Generation | Shortfall |
|---|---|---|---|---|
| January | 850 MW | 750 MW | 800 MW | 50 MW |
| February | 850 MW | 800 MW | 700 MW | +100<br>MW |
| March | 850 MW | 600 MW | 750 | 50 MW” |
4
6.
The chart itself would show that for the month of
February the coal assured was 850 MW, the coal delivered
was 800 MW and the actual generation was 700 MW. As
such, for the said month the generator had surplus coal for
production of 100 MW energy. The same has been carried
forward for the month of March. It is clear from the chart
that though for the month of March the assured coal was
850 MW, the actual coal delivered was only 600 MW and the
generation was 750 MW. If the apprehension of the learned
ASG was to be of substance, then the generator could have
claimed a shortfall of 150 MW, however, the surplus coal of
100 MW from the month of February has been carried
forward and the shortfall claimed is only 50 MW.
7. If this methodology is adopted by the generator, we do
not find that the apprehension of the learned Additional
Solicitor General of India would be substantiated.
8. The appeal is, accordingly, disposed of.
5
9.
Pending application(s), if any, shall stand disposed of.
..............................J
(B.R. GAVAI)
..............................J
(VIKRAM NATH)
NEW DELHI;
MARCH 27, 2023
6