Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 3
PETITIONER:
DELHI DEVELOPMENT AUTHORITY
Vs.
RESPONDENT:
MR. RAVINDRA MOHAN AGGARWAL & ANR. ..
DATE OF JUDGMENT: 19/03/1999
BENCH:
Sujata V.Manohar, R C Lahoti
JUDGMENT:
R.C. Lahoti, J.
A plot bearing number 13 of site no.58 on Kalkaji
Road, Delhi admeasuring 162 sq.mtrs. with two sides open
was put to auction on 5.2.1985 holding it out to be a
developed plot by Delhi Development Authority. The
respondents made a bid of Rs.3,25,000/- which was the
highest. The officer conducting the sale knocked down the
bid in favour of the respondents. With the fall of hammer,
the respondents deposited an amount of Rs.81,250/- being 25
per cent of the bid amount.
The authority competent to accept or not the bid was
the Vice-Chairman of the DDA before whom the papers were
placed. It appears that a public interest litigation was
filed by a third party laying challenge to the auction
complaining that the plot was situated in green-belt and
therefore could neither have been treated as a developed
plot nor put to auction for any purpose other than use as a
green-belt. The High Court had issued an ad-interim writ
staying the auction. The interim order though passed
earlier was brought to the knowledge of the Vice-Chairman,
DDA after the authority had signed its approval of the bid
on the file. The authority then stayed its hands in view of
the High Court’s order.
The respondents filed a writ petition before the High
Court of Delhi seeking a direction to the DDA to conclude
the auction sale proceedings and handover possession of the
plot to the respondents. The High Court found that the plot
being situated in the green-belt, could not have been put to
auction at all. The High Court by its order dated 1.8.1991
refused to grant any relief to the respondents so far as
plot number 13 is concerned. However, it held that the
respondents could not be faulted for having made a bid at
the auction and inasmuch as an expectation has been built up
in their favour of having a plot in face of acute shortage
of land in Delhi, the DDA was directed to give a plot to the
respondents of equivalent measurement at the same price in
the same area adjoining the area in question, i.e., Kalkaji
within a period of two months from the date of the order.
Aggrieved by the abovesaid direction of the High
Court, the DDA has filed this petition for special leave to
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 3
appeal before this Court. Leave granted. The facts
relevant and material for the disposal of this appeal are :-
(i) that the plot on the date of the auction was situated
within the green-belt and hence could not have been put to
auction by the DDA; (ii) that the sale was not finalised
inasmuch as the same was stayed by the High Court in a
public interest litigation; (iii) that the authority
competent to accept the bid recorded its acceptance at a
point of time when the High Court had already stayed the
same though the order of the High court was not till that
point of time brought to the notice of the authority; (iv)
that the acceptance of the bid was never communicated by the
DDA to the respondents; (v) that the tendered amount was 25
per cent only of the bid amount. The balance 75 per cent
was yet to be paid by the respondents to the petitioner;
and (vi) that it was only in the year 1994 that the zonal
plan was modified to alter the use of the plot to
residential purpose.
It is submitted by the learned counsel for the
appellant that the auction never achieved a finality. No
right much less a vested right had accrued in favour of the
respondents. The High Court was therefore not justified in
directing an alternate plot to be given to the respondents.
On the other hand, it is submitted by the learned counsel
for the respondents that a bid having been finalised and
also accepted by the competent authority, a right had
accrued in favour of the respondents. In the year 1994 the
disability attached with the plot has ceased to exist and
therefore on the doctrine of feeding the grant by estoppel
enunciated in Section 43 of the Transfer of Property Act,
the DDA should be compelled to finalise the sale and deliver
possession over the plot to the respondents. Alternatively,
the DDA must compensate the respondents by allotting an
alternate plot as directed by the High Court and they should
not be made to suffer for no fault of theirs. The learned
counsel for the respondents insisted that both in law and
equity the respondents are entitled to some relief.
Having heard the learned counsel for the parties, we
are of the opinion that there is merit in the appeal and the
same deserves to be allowed. On the date of the auction the
plot being in the green-belt, could not and should not have
been put to auction. There is no estoppel against statute
and when the considerations of public interest are involved.
The acceptance of the bid recorded by the Vice-Chairman, DDA
on the file was bad for two reasons. Firstly, it was so
recorded after the passing of the interim order of stay by
the High Court though it was in the process of being
communicated. Secondly, the acceptance was not communicated
by the DDA to the respondents and therefore the acceptance
was not complete. Merely because the respondents gathered
knowledge of the acceptance having been recorded on the file
would not make any difference. Reliance on Section 43 of
the Transfer of Property Act is entirely misconceived
inasmuch as there was no transfer or grant ever made by the
DDA in favour of the respondents. Acceptance of bid at a
public auction and deposit of 25% of bid amount do not
constitute a transfer of property. The respondents have no
basis in law to support their claim. Even the equitable
considerations would not justify a public authority like DDA
being directed today to provide an alternate plot to the
respondents in the same locality and at the same price after
a lapse of 14 years from the date of the auction.
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 3
We may place on record that according to the
appellant, the auction having been stayed by the High Court,
the amount of Rs.81,250/- was sent by cheque to respondents,
but they did not accept the same. The amount has remained
with the DDA for all these 14 years.
The appeal is allowed, the impugned order of the High
Court directing the DDA to allot an alternate plot to the
respondents is set aside. The writ petition filed by the
respondents is directed to be dismissed. However, in the
facts and circumstances of this case the amount of
Rs.81,250/- which has remained with the DDA is directed to
be returned to the respondents with interest calculated at
the rate of 9 per cent per annum from 5.2.1985 till the date
of return. No order as to the costs.