Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 5
PETITIONER:
V. R. SEJBRAMANYAM
Vs.
RESPONDENT:
B. THAYAPPA AND OTHERS.
DATE OF JUDGMENT:
01/02/1961
BENCH:
SHAH, J.C.
BENCH:
SHAH, J.C.
KAPUR, J.L.
CITATION:
1966 AIR 1034 1961 SCR (3) 663
ACT:
Building contract--Defective work--Additional work not
covered by agreement--Compensation, when can be
allowed--Indian Contract Act, 1872 (9 of 1872), s. 70.
HEADNOTE:
The appellant entered into an agreement with the respondent
who was a building contractor entrusting him with the work
of constructing a house and shops. The respondent undertook
the work but before it could be completed disputes arose
between them and the appellant claimed compensation for
effecting repairs to rectify defective work done by the
respondent, and the respondent claimed compensation at
certain rates set up by him for work for which there was no
express provision in the written agreement. Suits based on
their respective claims were filed by the appellant and the
respondent which were partly decreed by the trial court.
The High Court dismissed the appellant’s suit in its.
entirety and remanded the respondent’s suit directing the
appointment of a qualified engineer for determining,
according to the directions given in the judgment, the
amount payable to the respondent for work done in addition
to the agreed work under the contract. The appellant
contended that the respondent having failed to prove the
oral agreement pleaded the respondents’ suit should have
been dismissed and compensation quantum meruit which was not
claimed should not have been awarded.
Held, that if a party to a contract rendered service to the
other not intending to do so gratuitously and the other
party had obtained some benefit, the former was entitled to
compensation for the value of the services rendered by him.
The respondent not intending to do gratuitous work was
entitled to compensation for additional work not covered by
the written agreement.
Even if the respondent failed to prove his claim for
compensation at the prevailing market rate under an oral
agreement the court had jurisdiction to award compensation
for work done under S. 70 of the Contract Act.
The appellant’s suit having been dismissed by the High Court
and no appeal having been preferred against it, it was not
open to him to reagitate the same question of compensation
in the companion suits in which no equitable set-off was
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 5
claimed.
JUDGMENT:
CIVIL APPELLATE JURISDICTION: Civil Appeals Nos. 321 and 322
of 1956.
Appeals by special leave from the judgment and decree dated
September 21. 1951, of the Mysore High Court in Regular
Appeals Nos. 3,24,13 and 25 of 1948. 49, arising gut of the
judgment and decree dated
85
664
January 9, 1948, of the Principal DistriCt Judge, Bangalore,
in Original Suits Nos. 55 of 1946-47 and 117 of 1945-46
respectively.
S. K. Venkataranga Aiyangar and S. K. Aiyangar, for the
appellant.
B. K. B. Naidu, for the respondents.
1961. February 1. The Judgment of the Court was delivered
by
SHAH, J.-V. R. Subramanyam, the appellant herein is the
owner of plot No. 29, Subedar Chattram Road in the town of
Bangalore. B. Thayappa respondent is a building contractor.
The appellant entrusted the respondent with the work of
constructing a house and shops on the plot, on terms and
conditions set out in a written agreement dated October 1,
1942, which was slightly modified on October 6, 1942. By
the agreement the respondent was to construct for the
appellant on the plot six shops abutting a public road, the
main building at the rear of the shops, an out-house and a
garage according to a site plan. The respondent was to be
remunerated at rates specified in the agreement: for
constructions with R. C. C. roofing, the rate stipulated was
Rs. 4-2-0 per square foot and for " tiled construction " it
was Rs. 3-2-0 per square foot. The Municipality of
Bangalore did not sanction the plan as proposed by the
appellant. The plan was altered and it was sanctioned,
subject to those alterations. By the alterations the shops
were deleted from the plan, the area of the out-house was
increased, and a puja room on the ground floor and an extra
room on the first floor were added to the plan. A compound
wall was also to be constructed. The respondent carried out
a substantial part of the construction work according to
plan and the appellant paid to him diverse sums of money and
delivered building materials. The aggregate amount
accordingly received by the respondent was Rs. 20,200. But
before the work could be completed disputes arose between
the appellant and the respondent about the work done by the
latter. The appellant claimed that the work done was
defective and that he was entitled to compensation for
effecting
665
repairs necessary to rectify the defects. The respondent
claimed compensation at certain rates set up by him for work
done for the appellant for which no express provision was
made in the written agreement. Each party set up an oral
agreement about the remuneration to be paid to the
respondent for the extra work which was not included in the
original agreement.
The appellant filed a suit in the court of the Subordinate
Judge, Bangalore, against the respondent which was later
transferred to the court of the Principal District Judge,
Bangalore, and numbered O. S. 54 of 1946-47, for a decree
for Rs. 8,515-4-0 being the amount of compensation which the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 5
appellant claimed he was entitled to receive from the
respondent for defective work and for delay in completion of
the construction. The respondent filed a suit against the
appellant which was later transferred to the Court of the
Principal District Judge, Bangalore, and numbered 55 of
1946-47. By this suit, the respondent claimed a decree for
Rs. 5,988-12-0 being the remuneration due to him for the
work done in constructing the house less Rs. 20,200 received
from the appellant. The respondent filed another suit No.
117 of 1945-46 for a decree for Rs. 15,001-10-9 with
interest and notice charges being the amount due to him for
the construction of the out-house, godown, first floor room
and flight of steps and the value of some building materials
which the respondent claimed he had left in the premises of
the appellant and which the latter had wrongfully removed.
The trial court granted to the appellant a decree for Rs.
3,000 in suit No. 54 of 1946-47. To the respondent, he
granted a decree for Rs. 2,989-6-0 in suit No. 55 of 1946-47
and in suit No. 117 of 1945-46, he granted a decree for Rs.
13,329-10-9. Both the parties felt themselves aggrieved by
the decrees passed in the three suits and six appeals were
preferred to the High Court of Judicature of Mysore at
Bangalore against those decrees. The High Court reversed
the decree passed in suit No. 54 of 1946-47 and dismissed
the appellant’s claim in its entirety. The decrees
666
passed in suit Nos. 55 of 1946-47 and 117 of 1945-46 were
also set aside and proceedings were remanded to the District
Court with a direction that a qualified engineer be
appointed as Commissioner to determine the amounts payable
to the respondent for work done in addition to the work
agreed to be done under the written contract. The High
Court ordered that the same be determined " in accordance
with the directions " given in the judgment. The appellant
has appealed to this court against the decrees in suits Nos.
55 of 1946-47 and 117 of 1945-46 with special leave under
Art. 136 of the Constitution and he challenges the
directions given in the order of remand.
The dispute between the parties related to the construction
of the out-house, garage, puja room, the room on the first
floor, the stair case ’leading to the upper floor room and
the compound wall. In respect of these constructions
(except for the compound wall) the District Judge awarded
compensation to the respondents at the rate of Rs. 4-2-0 per
square foot and in respect of the compound wall he awarded
compensation at the rate of Rs. 5 per running foot, and
certain additional charges. The High Court held that the
respondent was entitled to receive compensation at the
prevailing market rate for constructions which were not
covered by the agreements dated October 1, 1942 and October
6, 1942. The High Court negatived the plea of the
respondent that the appellant had agreed to pay him at "
extra rates for deviations and additions not specifically
contained in the original agreement. " The High Court then
held that for the construction of the out-house,puja room
and the upper floor room, the respondent was entitled to
receive compensation at the rate of Rs. 4-2-0 and for the
out-house he was entitled to receive " some extra amount for
the additional constructions. " In these items, according
to the High Court, there was no material deviation from the
original plan. The High Court further directed that for the
flight of stairs compensation be paid either "by way of a
lump sum or on cubical content whichever was more
practicable or common according to the rates which they
proposed to indicate for such
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 4 of 5
667
additional work. " The High Court however held that there
was substantial variation from the original contract in the
construction of the garage, and therefore the garage could "
not be covered by the contracted rate" and must be paid for
at the rates current at the end of the year 1943. The High
Court also directed that " if the extra items not covered by
Exs. VII and VII(a) have been constructed or supplied by
the defendants as claimed in his bills Exs. XXI, XXII and
XXIII are to be paid for in addition to the flat rate, the
basis on which they should be paid for may.......... be
fixed in accordance with the rates contained in Ex. II. "
Counsel for the appellant submitted that as in the view of
the High Court the respondent failed to prove the oral
agreement pleaded by him, the suit should have been
dismissed, and they should not have awarded compensation
quantum meruit which was not claimed. it was urged that the
respondent must succeed or fail’ on the case pleaded by him,
and not on a cause of action not pleaded. In our view,
there is no substance in this contention. As we have
already observed, in respect of the additional work done by
the respondent, both the parties set up conflicting oral
agreements. These were not accepted by the High Court. If
a party to a contract has rendered service to the other not
intending to do so gratuitously and the other person has
obtained some benefit, the former is entitled :to
compensation for the value of the services rendered by him’
Evidently, the respondent made additional constructions to
the building and they were not done gratuitously. He was
therefore entitled to receive compensation for the work done
which was not covered by the agreement. The respondent
claimed under an oral agreement compensation at prevailing
market rates for work done by him: even if he failed to
prove an express agreement in that behalf, the court may
still award him compensation under s. 70 of the Contract
Act. By awarding a decree for compensation under the
Statute and not under the oral contract pleaded, there was
in the circumstances of this case no
668
substantial departure from the claim made by the respondent.
It was then urged that the High Court was in error in
directing assessment of compensation for the additional work
" in accordance with the rates mentioned in Ex. II. " The
plaintiff’s witness T. S. Narayana Rao had admitted that the
rates in Ex. II were the current market rates for building
construction work similar to the appellant’s building. In
the view of the High Court, the rates set out in that bill
were not excessive. If with a view to restrict the scope of
the enquiry, the learned judges of the High Court gave a
direction to the Commissioner for assessing compensation on
the basis of rates which were approved by the plaintiff’s
witness, it cannot be said that any serious error was
committed in incorporating that direction which would
justify our interference.
Finally it was urged that the appellant was entitled to
claim the loss suffered by him on account of defective work
by way of an equitable set off in the claim made by the
respondent in suits Nos. 55 of 1946-47 and 117 of 1945-46.
But the appellant made a claim in a substantive suit for
compensation for loss suffered by him because of the alleged
defective work done by the respondent. That suit was
dismissed by the High Court and it is not open to the
appellant thereafter to seek to reagitate the same question
in the companion suits when no appeal has been preferred
against the decree in suit No. 54 of 1946-47.- and no plea
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 5 of 5
of equitable set off has been raised in the written
statements in the companion suits.
In our view, there is no substance in any of the contentions
raised. The appeals therefore fail and are dismissed with
costs. One hearing fee.
Appeals dismissed.
669