RADHIKA PROPERTY DEVELOPERS PVT. LTD. vs. AHUNA T. P. Z.A. COOPERATIVE HOUSING SOCIETY LTD. AND ORS.

Case Type: NaN

Date of Judgment: 21-04-2010

Preview image for RADHIKA PROPERTY DEVELOPERS PVT. LTD.  vs.  AHUNA T. P. Z.A. COOPERATIVE HOUSING SOCIETY LTD. AND ORS.

Full Judgment Text

2010:BHC-AS:8737
1
IN THE  HIGH COURT OF JUDICATURE AT BOMBAY
APPELLATE SIDE CIVIL JURISDICTION
WRIT PETITION NO. 1170 OF 2010  
Radhika Property Developers Pvt. Ltd.
A company incorporated under The
Companies Act, 1956, having office at
Soham House, Rammaruti Road,
Thane (W)­400 602.  ....   Petitioner
vs
1  Ahuna T. P.Z.A. Cooperative Housing Ltd.,
    a Society registered under the Maharashtra
    Cooperative Societies Act, 1960, having its
    office at Divecha Complex, B, Edulji Road,
    Charai, Thane (W) 400 601
2  The Municipal Corporation of the City of
    Thane, a Body corporate incorporated under
    The Bombay Provincial Municipal Corporation
    Act, 1949, having its office at Palika Bhavan,
    Dr.Almeida Road, Chandan Wadi,
     Thane 400 602
3  The Thane Parsi Zoroastrian Anjuman
     The Society registered under the
     Societies Registration Act, 1960 and
     Bombay Public Trust Act, 1950, having
     its office at Divecha Complex, B, Edulji Road,
     Charai, Thane (W)­400 601
4   The State of Maharashtra,
     the summons to be served on
     The Collector, Thane
5  Cawasji Beharamji Divecha Trust, registered
    under Bombay Public Trust Act, Darya Chambers,
    Hutatma Chowk, Fort, Bombay 400023,
    Represented by its trustees:
1. Behram K. Divecha
2. Yezdi K. Divecha; and
3. Sir Jamshedji Jeejeebhoy Burronett ....    Respondents
Mr. P. K. Dhakephalkar, Sr. Counsel with Mr. Sanjay Borkar i/by Mr. Kailas Dewal 
::: Downloaded on - 01/04/2024 15:40:12 :::

2
for the petitioner.
Mr. E. P. Bharucha, Sr.Counsel i/by Mr. V .P. Sawant for respondent no.1.
Mr. S.S. Kanetkar for respondent no.3. 
Mr. A. P. Vanarse, AGP for respondent no.4. 
CORAM: ANOOP V. MOHTA, J.
st
  DATE  :  21   April,  2010
ORAL JUDGMENT:
1 Rule,  returnable forthwith.  Heard finally by consent.
2 The Petitioner has invoked Article 227 of the Constitution of India and 
thereby challenged the impugned judgment and order dated 07.01.2010 passed 
by the learned Principal District Judge, Thane in Misc. Civil Appeal No.66 of 2009 
in   Regular   Civil   Suit   No.733/2008,   whereby   granted     an   ad­interim 
relief/injunction in the following words:
“  Appeal is hereby allowed.
Order dt.25.3.2009 rejecting Exh. 5 in RCS No.733/08 by Jt. 
Civil Judge, S.D., Thane is hereby set aside.
Exh. 5 is hereby allowed and respondent no.1/defendant no.1 
is hereby injuncted temporarily, or for that matter, pending hearing 
and   disposal   of   the   suit   from   proceeding   with   construction   of 
proposed building in remaining portion of plot over CTS Nos.57A 
and 85B.
In   the   peculiar   circumstances   of   this   matter,   parties   are, 
however, left to bear their own costs.”
3  Cawasji Beharamji Divecha Trust, (respondent no.5) (the Trust) is owner 
of 8593.28 sq.mt. Of land out of City Survey No.57­A, 85­B, 88, 89 and 90, Tikka 
No.11, situated at Charai, Panchpakhadi, Thane (the property).  
::: Downloaded on - 01/04/2024 15:40:12 :::

3
4 By an Agreement dated 02.02.1988, the petitioner/developer agreed with 
the   Trust   (respondent   no.5)   to   develop   the   larger   property   and   accordingly, 
entered into an Agreement after obtaining the requisite permission from the 
Charity Commissioner.    The same was challenged in Writ Petition No.1041/1989 
by respondent no.3­The Thane Parsi Zoroastrian Anjuman.  However, the parties 
settled the matter  by Consent Terms (the Consent terms) on 30.04.1991.   The 
petitioner/developer agreed to provide/construct a building of 33,000 sq.ft. On 
City Survey Nos. 57­A and 85B (the suit property) for the Zoroastrian community. 
The plan was submitted by the petitioner/developer was approved on 20.04.1992. 
Various separate Agreements entered into with the members of the community for 
sale of flats in the building to be constructed in the year 1992 itself.  The building 
named   as   “Ahuna”­respondent   no.1(original   plaintiff).       The   respective 
members/persons formed the plaintiff/society and occupied their respective flats 
and enjoying all the facilities and the area as per the Agreements accordingly. 
The petitioner is under obligation to execute Conveyance, subject to cooperation 
from all members, as per the Consent Terms and the Agreements as claimed after 
completion of the construction on the property.       The petitioner, as permitted, 
submitted and got the Plan   sanctioned in the year 1992 of the proposed suit 
building to the west of the Ahuna building.   As per the Consent Terms, Ahuna 
building was to be constructed on 20,000 sq.ft. Of land demarcated and it was 
constructed accordingly.   All the parties have full knowledge of the area, flat and 
their respective rights to use and utilise the flats and the surrounding area.  
5 Respondent no.2­The Municipal Corporation supported the fact that the 
Plans as approved are legal and valid.       Respondent no.3 (defendant no.3) 
::: Downloaded on - 01/04/2024 15:40:12 :::

4
supported   the   original   plaintiff.     Mr.   S.S.   Kanetkar,   the   learned   counsel   for 
respondent no.3  and adopted the same line of arguments of Mr. Bharucha, the 
learned senior counsel for respondent no.1.
6 Admittedly,   based   upon   the   Consent   Terms,   the   parties   proceeded   to 
develop the particular plot/area.   The Consent Terms provide various clauses 
giving various rights and obligations of the respective parties.    Those includes to 
develop and construct building on other remaining portion of the land.    There is 
no   dispute   that   the   subject   matter   of   the   Consent   Terms   refers   to   total 
admeasuring   area   of   about   8593.28   sq.mts.   together   with  the  buildings  and 
structures standing therein.   
7 There is no dispute that based upon the said Consent Terms, after getting 
the approval and commencement certificate in the year   1992 constructed two 
buildings viz. “Sheetal” on Survey No.88 and “Gautam Sagar” on Survey Nos.89 
and 90, based upon the Sanction dated 22.09.1987 and 09.08.1994.       It was 
never agreed that development should be made on the plot at one phase.  It was 
the petitioner’s choice and right to construct and develop rest of the property.  
8 For the plaintiff’s society,   a plan was sanctioned some time in the 
year 2001 and the construction was completed in the year 2004.   Hence, 
there   is   no   dispute   that     apart   from   the   Consent   Terms,   individual 
Agreements have been entered into by the plaintiffs members with the 
petitioner/builder in the year 1992 itself, which also refers and provides 
various clauses of the Consent Terms.    The rights of the builder as well as 
member of the plaintiff/society have been clearly demarcated and defined 
along with the obligations.     Even otherwise, while entering into such 
::: Downloaded on - 01/04/2024 15:40:12 :::

5
contract, it is always necessary to define and describe the property, area 
and all other respective rights referring to the surrounding area.  Any such 
agreement without providing the detail and description of the property just 
cannot be acted upon.    Therefore, both the parties have full knowledge of 
the   nature   of   the   property,   proposed   construction/development   by   the 
petitioner/promoter and all related aspects.  
10 The plaintiff has filed the Suit on 06.11.2008 and prayed as under:
“a) The Defendant No.1 may be ordered and decreed 
to execute the conveyance of the suit plot bearing City Survey 
No.57­A and 85­B of Tikka No.11, situate at Charai, Thane, 
Taluka and District Thane, in favour of the plaintiff Society by 
joining   the   Defendant   No.5   Trust   as   the   party   to   such 
conveyance.
b) It may be declared that the plan approved by the 
Defendant   No.2   vide   V.P.   No.2005/26,   submitted   by   the 
Defendant No.1 with respect to the proposed building in City 
Survey No.57­A and 85­B is illegal, null and void.
c) The said plan V.P. No.2005/26 may be cancelled 
and   revoked   by   and   under   the   order   and   decree   of   this 
Honourable Court.
d) The Defendant No.1 its agents servants, assignees, 
transferees and person or persons claiming through it may be 
restrained   by   the   order   of   permanent   injunction   from 
::: Downloaded on - 01/04/2024 15:40:12 :::

6
constructing any building or structure in the land bearing City 
Survey No.57­A and 85­B of Tika No.11. 
e) The Defendant No.1 may be directed to dismantle 
and remove the building partly constructed in the open space 
in   City   Survey   No.85­B   and   deliver   vacant   and   peaceful 
possession of the suit plot t the plaintiff Society along with the 
execution  of conveyance in favour of the plaintiff Society.
f) It may be declared that the D.P. Reservation of the 
portion   of   land   admeasuring   about   688   sq.meters   in   City 
Survey No.85­B as a playground declared by the Defendant 
no.2 and 4 is illegal, null and void.
g) The   portion   of   land     admeasuring   about   688 
sq.meters, in City Survey No.85­B of Tika No.11, earmarked as 
a   play   ground   in   the   impugned   D.P.   Reservation   of   the 
Defendant No.2 Corporation may be set aside, cancelled and 
revoked by and under the order and decree of this Honourable 
Court   and   after   its   de­reservation   earlier   user   thereof   as 
recreation garden may be ordered to be resumed.
h) Pending the hearing and final disposal of this Suit, 
the Defendant No.1, its agents servants, assignees, transferees 
and person or persons claiming through it may be restrained 
by the order of ad­interim injunction from carrying out any 
construction in the suit land bearing City Survey No.57­A and 
::: Downloaded on - 01/04/2024 15:40:12 :::

7
85­B.
i ) Pending the hearing and final disposal of this Suit 
the Defendant No.1 may be restrained   by the order of ad­
interim injunction from creating third party interest in the suit 
plot or the building proposed to be constructed thereon.
j) The Defendant No.1, 2 and 4 may be ordered and 
decreed to pay costs of this suit to the plaintiff Society.
k) Any   other   and   further   relief   this   Honourable 
Court deems just and property may be awarded to the plaintiff 
Society.”
9 An Application for interim injunction was also moved along with the 
same.    After hearing both the parties, by giving detailed reasoning the trial 
Judge rejected the said injunction application .   The plaintiff thereafter 
preferred   Misc.   Appeal   No.66/2009   on   11.06.2009.     Finally,   by   the 
impugned order, the learned Appellate Court on 07.01.2010 has granted 
injunction as referred above.  
10 There is no serious dispute that in view of the prayers so raised and 
as there are  questions of interpretation of the Consent Terms/decree read 
with the provisions of the Maharashtra Ownership  Flats (Regulations of the 
Promotion of Construction, Sale, Management and Transfer) Act, 1963 (for 
short,   “the   MOFA   Act”),   specially   Sections   7,   7A   and   the   respective 
Agreements including the rights of developer/petitioner to proceed with the 
::: Downloaded on - 01/04/2024 15:40:12 :::

8
construction/development of the property are involved.   The learned Judge 
has also, therefore, observed that there are triable issues raised in the 
matter.  
11 The reversal order,  therefore,  so passed and whereby  the injunction 
has been granted for the first time, if case is made out,  can be interfered 
with even in such private dispute, though contended otherwise, by the 
learned Senior Counsel appearing for the respondent no.1, based upon the 
judgments of the Apex Court in Radhey Shyam and anr. vs. Chhabi Nath 
and others,  (2009) 5 SCC 616  and   Mohan Pandey & anr. vs. Usha Rani 
Rajgaria (Smt) and others,  (1992) 4 SCC 61.  The aggrieved  party  just 
cannot be rendered remedy­less in such situation. 
12 The High Court, therefore, in a Writ Petition under Article 227 of the 
Constitution of India, in its supervisory jurisdiction, if case is made out, is 
empowered to entertain such Petition and may pass appropriate order in 
the interest of justice. 
13 All the aspects which are necessary to grant interim injunction as 
contemplated under Order 39, Rules 1 & 2 of Code of Civil Procedure 
(CPC),   in   such   circumstances,   need   consideration.     The   balance   of 
convenience, irreparable injury, equity and the requisite compensation and 
such other  factors are also relevant even though there are arguable points 
raised. 
14 The   submission   revolving   around    Jayantilal   Investments   vs. 
Madhuvihar Coop. Housing Society & ors.,  (2007) 9 SCC 220 , referring to 
::: Downloaded on - 01/04/2024 15:40:12 :::

9
Sections 7 and 7­A of the MOFA  Act itself provides that “the Promoter 
is   also   required   to   declare   that   no   part   of   that   FSI   has   been   utilised 
elsewhere, and if it is utilised, the promoter has to give particulars of such 
utilisation to the flat takers.  Further, under the proforma agreement, the 
promoter has to further declare utilisation of FSI of any other land for the 
purposes   of   developing   the   land   in   question   which   is   covered   by   the 
agreement.”. 
14­A There is no doubt that the activities of the promoter/developers need 
to   be   regulated   and   checked.     The   full   &   proper   disclosure   by   the 
builder/promoter as contemplated under the MOFA Act is a must to avoid 
various   complications.     If   allegations   are   so   raised/made,   it   is   always 
subject to proof and material on record.  Mere averments are not sufficient 
to pass such interim orders.    
15 Once acted upon the Consent Terms/Decree of the year 1991, both 
the parties proceeded further.  The total area of the land in question and the 
respective terms  of the Consent Terms, respective Agreements are not in 
dispute.  There was no objection of any kind raised at the earliest point of 
time   though,   based   upon   the   same   Agreement   on   the   same   land   in 
question, two buildings were constructed as referred above i.e. In the years 
1987 and 1994.  The plan of the plaintiffs’ building was sanctioned in the 
year 2001.  The construction based upon the same was completed in 2004. 
The   submission   which   they   are   now   making,   merely   because   the 
petitioner/developer started construction  on the remaining portion of the 
::: Downloaded on - 01/04/2024 15:40:12 :::

10
land by raising vague pleas of collusion between defendants 1 to 4 and also 
of fraud  referring to generation of additional FSI and the aspect of sub­
division of the land is afterthought.     The allegations of collusion and the 
conspiracy     so  raised cannot  be   accepted   unless  are  supported   by  the 
material and related evidence.   The development plan reservation (D.P. 
Reservation) at the relevant time was duly sanctioned after following the 
procedure under the respective Rules.   To say now that the D.P. Reservation 
is illegal, null and void is also a matter which just cannot be accepted  at 
this late stage only at the instance of the plaintiff.    Apart from the Consent 
Terms and the Agreements and the development so made by the petitioner, 
based   upon   the   same   and   as   other   societies   members   including   the 
plaintiffs’ members have been enjoying the construction and all the facilities 
as provided by the petitioner/developer.    All in all the issues or the pleas 
so   raised   by   the   plaintiffs     are   intermixed   and   cannot   be   decided   in 
isolation.  The trial is a must.  
16 Even if a case is made out as contended and  the triable issues are 
raised, as contended, still that itself is not sufficient to grant ad­interim 
relief/injunction as prayed by overlooking the other basic elements of grant 
of  injunction,  like  balance  of convenience,  equity,    the  conduct  of the 
parties,  delay  in  taking  steps  and   moving  injunction  applications  and 
entitlement of damages or monetary compensation. 
17 If there are   breaches committed by the petitioner, based upon the 
Consent Terms/Decree/Agreements and even of the provisions of the MOFA 
::: Downloaded on - 01/04/2024 15:40:12 :::

11
Act,  unless those are proved and/or substantiated,  at this prima facie stage 
it is difficult to accept the case merely because the averments are made by 
the plaintiffs revolving around the same.  
18 The prayers so raised by the plaintiffs as reproduced above are of 
multiple in nature ranging from direction against the petitioner/builder to 
execute   the   Conveyance   of   the   suit   plot;   the   plan   approved   by   the 
defendant no.2 vide V.P. No.2005/26, with respect to the proposed building 
in City Survey No.57­A and 85­B is illegal, null and void; the plan be 
cancelled and revoked;   the reservation on the development plan of the 
portion of the land with regard to the playground is illegal, null and void, 
portion   of   the   land   earmarked   for   the   play   ground   be   set   aside   and 
cancelled and even ask for the de­reservation now.   Based upon this, the 
prayer is also made to dismantle and remove the construction already 
commenced on the open space in City Survey No.85­B and deliver the 
vacant possession of the land to the plaintiff/society.   Unless all other 
prayers are not granted and/or decided, in my view, there is no case of 
granting the prayer of dismantling and/or removing of the building already 
constructed,  specially at the instance of plaintiffs/society alone, specially 
when there is no dispute that based upon the said Consent Terms/Decree 
and individual Agreements, the parties have acted upon and are enjoying 
the peaceful possession and facilities of the constructed building as well as 
of the area.  All things are interlinked and interconnected.  It is difficult to 
accept the case of the learned counsel for the original plaintiffs that no 
::: Downloaded on - 01/04/2024 15:40:12 :::

12
further construction can be made on any vacant portion of the land referred 
in the Consent Terms by overlooking the Agreements entered into by the 
respective members of the respective societies.    I am not deciding all those 
issues at this prima facie stage as agitated and those averments itself, in my 
view, just cannot be the reason to grant interim injunction as ordered by the 
Appellate Court for the first time to frustrate the project and the scheme.
19 The aspect of delay and the conduct are also relevant in the present 
case.     As   noted   above,   except   after   the   construction   commenced, 
respondent no.1 has filed the Suit with above prayer clauses and with 
specific prayer to dismantle the construction already commenced.   There 
was no ad­interim relief/injunction in favour of the plaintiff at any point of 
time.     Though Suit was filed in the year 2008, even after rejection of 
Injunction Application, except filing the Miscellaneous Appeal, no further 
steps   were   taken   by   the   plaintiff   for   interim   protection   or   injunction. 
During this period,  the construction was going on.  Now a statement is also 
made   and   which   is   not   in   dispute   that   the   basic   building   has   been 
constructed as per the sanctioned plan.   The aspect of investment and 
construction so made in such type of matter just cannot be overlooked 
specially   when   it   is   based   upon   the     Consent   Terms/Decree   and   the 
Agreements of the year 1991/1992.      The submission that they moved 
immediately for interim relief after having knowledge of the sanctioned 
plan   dated   11.02.2008   by   the   petitioner   and/or   immediately   from   the 
knowledge of commencement of th construction in question and, therefore, 
::: Downloaded on - 01/04/2024 15:40:12 :::

13
the construction so made inspite of pendency of the present Suit, just 
cannot be the reason not to grant equitable relief, in my view, in the present 
facts and circumstances of the case, is unacceptable.   Heavy burden lies 
upon the plaintiff by putting material to substantiate other  prayer clauses 
first  to get the  order of dismantling and/or removal of such construction 
so raised and even of injunction so prayed.     Therefore, the conduct read 
with delay, in my view, goes against the plaintiffs.  
20 The irreparable injury, the balance of convenience   and equity, in 
view of above, in my view, lies in favour of the petitioner/defendant no.1. 
The respondent no.1/plaintiffs, in view of above, failed to prove the case for 
interim   injunction.     There   is   no   prima   facie   a   case;   no   balance   of 
convenience, no equity and on the contrary, the petitioner/defendant no.1 
who proceeded on the basis of Consent Terms/individual Agreements of the 
year 1991 and 1992  and now has  started/commenced the construction on 
the  remaining portion of the land,  which they are entitled to do so, subject 
to terms and conditions, just cannot be prevented on the grounds so raised 
in the plaint which requires detailed inquiry, evidence and interpretation of 
the clauses itself.     Even otherwise, unless those are answered in their 
favour merely   because substantial grounds are raised and the case as 
alleged to be arguable, in my view, just cannot be the reason to grant the 
injunction for the first time as is done by the Appellate Court in the Appeal. 
The   petitioner/promoter/developer   is   not   constructing   or   making   any 
alteration in the exclusive demarcated area and the constructed building of 
::: Downloaded on - 01/04/2024 15:40:12 :::

14
the plaintiff.     The parties have full knowledge of the areas, plans and their 
respective obligations and rights.   Having once obtained the benefits, the 
plaintiff at this stage cannot be permitted to deny the benefits/rights of the 
petitioner/developer, specially when they themselves cannot restore the 
condition and the position of the original area/land.  
21 The Petitioner has made out a case.  Therefore, I am interfering with 
the order passed by the Appellate Judge/Court, who by reversing the order 
passed by the trial Judge/Court,  has granted the Interim injunction.      In 
my view, the reasoning given by the trial Judge just cannot be said to be 
perverse, unjust or contrary to law.      The trial Court referred to various 
clauses of the Consent Terms/individual Agreements and dealt with the 
subject and, the discretion so exercised by the trial Court is  well within the 
frame work, based upon various relevant authorities  and the record.  The 
interference  of the Appellate Court in the present case, in my view, is not 
correct.   There is no perversity, illegality in the order of the trial Judge. 
Therefore, the petitioner has made out the case for interference under 
Article 227 of the Constitution of India in the interest of justice. 
22 The   submission   with   regard   to   the   aspect   of   prior   consent   from 
members of the society as contemplated under Section 7 and 7­A of the 
MOFA Act, though disputed, still that itself means the petitioner/developer 
can construct but subject to consent, therefore, any loss of land, will be 
subject to decision in favour of the plaintiffs &   in a given case, can be 
compensated in terms of money.    The parties can waive their rights also 
::: Downloaded on - 01/04/2024 15:40:12 :::

15
and settle the matter.  
23  It is made clear that the petitioner/developer is not prevented from 
performing   his   part   of   obligation   as   per   the   Consent   Terms   and   the 
Agreements and the law.  The petitioner/developer is bound to perform his 
part of the obligation as per the Consent Terms/agreements.
24 Resultantly, the impugned order passed by the Appellate Court dated 
07.01.2010 is quashed and set aside.  The order passed by the trial Court 
dated 25.03.2009 is maintained.   The Injunction Application as filed is 
rejected.   However, it is made clear that any construction made by the 
petitioner/original defendant no.1 and any transfer of property  in question 
by any means will be subject to the decision of the present Suit.    The Suit 
is expedited.  The issues of jurisdiction & the maintainability are kept open. 
25 The Petition is accordingly allowed in terms of prayer (a).   
26 Rule is made absolute in the above terms.  No order as to costs.
27 The learned counsel for the respondent no.1 seeks stay of this order. 
The learned counsel for the petitioner oppose the same.  The statement is 
made that apart from the construction of the building, the constructed, 
unfinished   flats   have   been   sold   and   respective   Agreements   have   been 
entered into with the third person also.   In view of this and as already 
observed, that any transactions and the transfer,   will be subject to the 
decision of the Suit.  I am not inclined to grant any stay of this order. The 
oral application is rejected. 
(ANOOP V. MOHTA, J.)
::: Downloaded on - 01/04/2024 15:40:12 :::