Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 6
CASE NO.:
Appeal (civil) 4979 of 2006
PETITIONER:
Sub Divisional Officer (P), UHBVNL
RESPONDENT:
Dharam Pal
DATE OF JUDGMENT: 15/11/2006
BENCH:
ARIJIT PASAYAT & LOKESHWAR SINGH PANTA
JUDGMENT:
JUDGMENT
(Arising Out of S.L.P.(C) No. 20653 of 2004)
ARIJIT PASAYAT, J.
Leave granted.
Challenge in this appeal is to the order passed by the
National Consumer Disputes Redressal Commission, New
Delhi (in short the ’Commission’). By the impugned order, the
Commission dismissed the revision petition filed in terms of
Section 2l of the Consumer Protection Act, 1986 (in short the
’Act’).
Background facts in a nutshell are as follows:
The respondent is a consumer of electricity and a meter
was installed by the appellant at his factory premises. An
inspection was done on 04.07.2000. The Inspecting staff
found that there was tampering with the meter and, therefore,
a demand of Rs.1,07,326/- was made purporting to be
charges payable for actual consumption of energy.
Questioning the demand, a complaint was filed before the
District Consumer Disputes Redressal Forum, Yamuna Nagar,
Jagadhiri, Haryana (in short ’District Forum’).
The basic stand of the respondent as complainant was
that prior to the inspection, on 02.07.2000 there was a
sparking in the C.T. Box installed at his factory premises and
the complainant immediately informed the appellant and
requested for rectification of the defect. The complainant had
also given a letter dated 2.7.2000 to the department in this
behalf and since the meter was defective the appellant should
have rectified the meter. Instead of doing that, the demand
was raised for alleged tampering with the meter. With
reference to the inspection report it was averred that the seals
were found intact and, therefore, there was no question of any
tampering. It was, therefore, prayed that reference should be
made to the Electrical Inspector for action in terms of Section
26(6) of the Indian Electricity Act, 1910 (in short ’the Act’). It
was further submitted that notice was to be given before
raising of demand. This was stated to be in line with principles
of natural justice and statutory prescriptions. The said prayer
was rejected by the present appellant taking the stand that in
case of tampering there was no question of any reference to
the Electrical Inspector. The District Forum found substance
in the complaint filed by the respondent and held that the
demand was illegal and instead reference ought to have been
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 6
made in terms of Section 26(6) of the Act.
An apneal was filed by the appellant herein before the
State Consumer Disputes Redressal Commission, Chandigarh
(in short the ’State Commission’). The appeal under Section 15
of the Act was dismissed by the State Commission holding
that the direction given by the District Forum was in order
and action in terms of Section 26(6) of the Act was required to
be taken. A revision was filed before the Commission which,
as noted above, has been dismissed holding that proper
direction has been given by the District Forum which was
upheld by the State Commission.
In support of the appeal, learned counsel for the
appellant submitted that in case of tampering there was no
scope for reference to the Electrical Inspector in terms of
Section 26(6). Notice is to be given only when there is a default
in payment of the demand raised and in cases of this nature,
no notice is required.
Learned counsel for the respondent on the other hand
submitted that this is not a case of tampering. The respondent
had, two days prior to the inspection, requested the
authorities to verify the meter as the same was defective.
Instead of rectifying the meter, and a reference under Section
26(6) to the Electrical Inspector, arbitrarily the demand has
been raised. Before raising the demand, no notice was issued
to the respondent which is in clear violation of the principles
of natural justice. As the respondent was denied opportunity
of placing his stand before the demand was raised, the same
cannot be maintained being in violation of the principles of
natural justice.
Question as to when action in terms of Section 26(6) of
the Act is to be taken has been considered by this Court in
many cases. (See Bombay Electricity Supply and Transport
Undertaking v. Laffans (India) (P) Ltd. & Anr. (2005 (4) 5CC
327). Section 26(6) of the Act and Rule 57 of Indian Electricity
Rules, 1956 (in short ’Electricity Rules’) read as follows:
"5. The relevant parts of Section 26 of the
Indian Electricity Act, 1910 and Rule 57 of
the Indian Electricity Rules, relevant for the
purpose of this judgment, are reproduced
hereunder:-
The Indian Electricity Act, 1910
"26. Meters.- (1) In the absence of an
agreement to the contrary, the amount of
energy supplied to a consumer or the
electrical quantity contained in the supply
shall be ascertained by means of a correct
meter, and the licensee shall, if required by
the consumer, cause the consumer to be
supplied with such a meter:
Provided that the licensee may require
the consumer to give him security for the
price of a meter and enter into an agreement
for the hire thereof, unless the consumer
elects to purchase a meter.
(2) xxx xxx xxx
(3) xxx xxx xxx
(4) The licensee or any person duly authorized
by the licensee shall, at any reasonable time
and on informing the consumer of his
intention, have access to, and be at liberty to
inspect and test, and for that purpose, if he
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 6
thinks fit, take off and remove, any meter
referred to in sub-section (1); and, except
where the meter is so hired as aforesaid, all
reasonable expenses of, and incidental to,
such inspecting, testing, taking off and
removing shall, if the meter is found to be
otherwise than correct, be recovered from the
consumer; and, where any difference or
dispute arises as to the amount of such
reasonable expenses, the matter shall be
referred to an Electrical Inspector, and the
decision of such Inspector shall be final:
Provided that the licensee shall not be at
liberty to take off or remove any such meter if
any difference or dispute of the nature
described in sub- section (6) has arisen until
the matter has been determined as therein
provided.
(5) xxx xxx xxx
(6) Where any difference or dispute arises as
to whether any meter referred to in sub-
section (1) is or is not correct, the matter shall
be decided, upon the application of either
party, by an Electrical Inspector; and where
the meter has, in the opinion of such
Inspector ceased to be correct, such Inspector
shall estimate the amount of the energy
supplied to the consumer or the electrical
quantity contained in the supply, during such
time, not exceeding six months, as the meter
shall not, in the opinion of such Inspector,
have been correct; but save as aforesaid, the
register of the meter shall, in the absence of
fraud, be conclusive proof of such amount or
quantity:
Provided that before either a licensee or a
consumer applies to the Electrical Inspector
under this sub-section, he shall give to the
other party not less than seven days’ notice of
his intention so to do.
(7) xxx xxx xxx
Explanation - A meter shall be deemed to be
"correct" if it registers the amount of energy
supplied, or the electrical quantity contained
in the supply, within the prescribed limits of
error, and a maximum demand indicator or
other apparatus referred to in sub-section (7)
shall be deemed to be "correct" if it complies
with such conditions as may be prescribed in
the case of any such indicator or other
apparatus."
Indian Electricity Rules, 1956
"57. Meters, maximum demand indicators
and other apparatus on consumer’s premises.
- (1) Any meter or maximum demand
indicator or other apparatus, placed upon a
consumer’s premises in accordance with
Section 26 shall be of appropriate capacity
and shall be deemed to be correct if its limits
of error are within the limits specified in the
relevant Indian Standard Specifications and
where no such specification exits, the limits of
error do not exceed 3 per cent, above or below
absolute accuracy at all loads in excess of
one-tenth of full loads and up to full load:
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 4 of 6
Provided that for extra high voltage
consumers the limit or error shall be 1 1 per
cent.
(2) No meter shall register at no load.
(3) Every supplier shall provide and maintain
in proper condition such suitable apparatus
as may be prescribed or approved by the
Inspector for the examination, testing and
regulation of meters used or intended to be
used in connection with the supply of energy:
Provided that the supplier may with the
approval of the Inspector and shall, if
required by the Inspector, enter into a joint
arrangement with any other supplier for the
purpose aforesaid.
(4) Every supplier shall examine, test and
regulate all meters, maximum demand
indicators and other apparatus for
ascertaining the amount of energy supplied
before their first installation at the
consumer’s premises and at such other
intervals as may be directed by the State
Government in this behalf.
(5) Every supplier shall maintain a register of
meters showing the date of the last test, the
error recorded at the time of the test, the limit
of accuracy after adjustment and final test,
the date of installation, withdrawal, re-
installation, etc. for the examination of the
Inspector or his authorized representative.
(6) Where the supplier has failed to examine,
test and regulate the meters and keep records
thereof as aforesaid, the Inspector may cause
such meters to be tested and sealed at the
cost of the owner of the meters in case these
are found defective."
6. The above-said provisions have been the
subject-matter of consideration by this Court
in three cases which have been brought to
our notice. They are M.P. Electricity Board v.
Basantibai (1988 (1) SCC 23), Belwal
Spinning Mills Ltd. and Ors. v. U.P. State
Electricity Board and Anr. (1997 (6) SCC 740)
and J.M.D. Alloys Ltd. v. Bihar State
Electricity Board (2003 (5) SCC 226). The first
and the last of the cases are decisions by
three learned Judges and the second one is a
decision by two learned Judges. We have
carefully perused the three decisions and we
find ourselves in entire agreement with the
view of the law taken in these cases. In
particular, in Belwal Spinning Mills’s case,
this Court has examined the provisions of
Section 26, specially sub-section (6) thereof,
in very many details, also taking into
consideration the legislative intention and the
object sought to be achieved by substituting
sub-section (6) by Act 32 of 1959 in its
present form over the predecessor provision.
We would be referring to the relevant findings
of law recorded in these cases. However, at
the outset and here itself, we would like to
mention that the applicability of sub-section
(6) of Section 26 is attracted only when the
meter is not correct. Section 26(6) will have
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 5 of 6
no applicability (i) if the consumer is found to
have committed a fraud with the licensee and
thereby illegally extracted the supply of
energy preventing or avoiding its recording, or
(ii) has resorted to a trick or device whereby
also the electricity is consumed by the
consumer without being recorded by the
meter. In effect the latter class of cases would
also be one of fraud. Tampering with the
meter or manipulating the supply line or
breaking the body seal of the meter resulting
in non-registering of the amount of energy
supplied to the consumer or the electrical
quantity contained in the supply - are the
cases which were held to be not covered by
Section 26(6) in the case of Basantibai
(supra), while the provision was held
applicable to any case of meter being faulty
due to some defect and not registering the
actual consumption of electrical energy.
Similar is the view taken in the case of J.M.D.
Alloys Ltd. (supra).
7. What is a correct meter? The language of
sub-section (6) of Section 26 starts with -
"where any difference or dispute arises as to
whether any meter referred to in sub-section
(1) is or is not correct...". The dictionary
meaning of the word "correct" is: Adhering or
conforming to an approved or conventional
standard; Conforming to or agreeing with fact;
Accurate.
8. As to what would be a "correct" meter,
there is sufficient indication in the Act and
the Indian Electricity Rules, 1956 in the
explanation given at the end of sub-section (7)
of Section 26 of the Act and sub-rules (1) and
(2) of Rule 57, quoted hereinabove. Where the
meter is completely non-functional on
account of any fault or having been burnt, it
will not register the supply of energy at all.
Since a burnt meter does not record any
supply of energy, it virtually means "no
meter".
9. What is contemplated by Section 26(6) is a
running meter, but which on account of some
technical defect registers the amount of
energy supplied or the electrical quantity
contained in the supply beyond the
prescribed limits of error. It contemplates a
meter which is either running slow or fast
with the result that it does not register the
correct amount of energy supplied. There is
an additional reason for coming to such a
conclusion. Section 26(6) confers power upon
the Electrical Inspector to estimate the
amount of energy supplied to the consumer or
the electrical quantity contained in the
supply, during such time, not exceeding six
months, as the meter shall not, in the opinion
of such Inspector, have been correct. Where
the meter is running slow or fast, it will be
possible for the Electrical Inspector to
estimate the amount of energy supplied to the
consumer by determining the extent or
percentage of error in recording the supply,
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 6 of 6
whether plus or minus. However, where the
meter is burnt or is completely non-
functional, such an exercise is not at all
possible. Therefore, Section 26(6) can have no
application in a case where a meter has
become completely non-functional on account
of any reason whatsoever."
In State of W.B. and Ors. v. Rupa Ice Factory (P) Ltd. and
Ors. (2004 (10) 5CC 635) it was observed as follows:
"5. As regards the second claim, namely, the
claim for the period from December 1993 to
December 1995, the finding of the High Court
is that the a Vigilance Squad had found that
Respondent 1 had tapped the electric energy
directly from the transformer to the LT
distribution board bypassing the meter
circuit. If that is so, we do not know as to why
the High Court would go on to advert to
Section 26 of the Electricity Act and direct
reference to the Electrical Inspector for
decision under Section 26(6). In two decisions
of this Court in M.P Electricity Board v.
Basaniibai and J.M.D. Alloys Ltd. v. Bihar
SEB it has been held that in cases of
tampering or theft or pilferage of electricity,
the demand raised falls outside the scope of
Section 26 of the Electricity Act. If that is so,
neither the limitation period mentioned in
Section 26 of the Electricity Act nor the
procedure for raising demand for electricity
consumed would arise at all, In this view of
the matter, that part of the order of the
Division Bench of the High Court, directing
that there should be a reference to the
Electrical Inspector, shall stand set aside. In
other respects the order of the High Court
shall remain undisturbed. The appeal is
allowed accordingly."
Though strong reliance was placed by learned counsel for
the respondent on a decision in M.P.E.B. & Ors. v. Smt.
Basantibai (AIR 1988 SC 71) more particularly, paragraph 13
thereof, a bare reading of the decision shows that the same
did not relate to a case of tampering and, therefore, has no
application to the present case.
Above being the position, the District Forum, State
Commission and the Commission were not justified in holding
that a reference in terms of Section 26(6) of the Act was called
for. The orders passed by these authorities are quashed.
The appeal is allowed but without any order as to costs.