Full Judgment Text
REPORTABLE
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NO. 9115 OF 2022
(@ SLP (C) No. 23141 of 2022)
(@ Diary No. 22292 of 2022)
Delhi Development Authority …Appellant(s)
Versus
Chandermal & Ors. …Respondent(s)
WITH
CIVIL APPEAL NO. 9123 OF 2022
(@ SLP (C) No. 23184 of 2022)
(@ Diary No. 2650 of 2022)
Govt. of NCT of Delhi & Anr. …Appellant(s)
Versus
Chandermal & Ors. …Respondent(s)
J U D G M E N T
M.R. SHAH, J.
Signature Not Verified
Digitally signed by R
Natarajan
Date: 2022.12.15
18:15:15 IST
Reason:
1. Feeling aggrieved and dissatisfied with the impugned judgment
and order dated 03.10.2018 passed by the High Court of Delhi at New
1
Delhi in Writ Petition (C) No. 2255 of 2016 by which the High Court has
allowed the said writ petition preferred by the respondents herein and
has declared that the acquisition with respect to the lands in question is
deemed to have lapsed under Section 24(2) of the Right to Fair
Compensation and Transparency in Land Acquisition, Rehabilitation and
Resettlement Act, 2013 (hereinafter referred to as “Act, 2013”), the Delhi
Development Authority (DDA) as well as the Government of NCT of
Delhi have preferred the present appeals.
2. By the impugned judgment and order, the High Court has declared
that the acquisition with regard to the subject land is deemed to have
lapsed under Section 24(2) of the Act, 2013 on the ground that the
compensation in respect of the subject land has not been tendered to
the original writ petitioners – respondents herein. However, it is required
to be noted that before the High Court, it was the specific case on behalf
of the appellants, more particularly, the Land Acquisition Collector (LAC)
that the possession of the land in question was taken by the LAC and
was handed over to the DDA. The High Court has also believed the
taking over of the possession by the LAC, but thereafter on the ground
that the compensation has not been tendered to the original writ
petitioners, the High Court has declared that the acquisition is deemed to
have lapsed.
2
3. Referring to the possession certificate dated 26.05.1998 relied
upon on behalf of the appellants (Annexure P/4), learned counsel
appearing on behalf of the original writ petitioners has submitted that in
the said possession certificate, there is no reference of “taking over of
the possession of the subject land” by the LAC from the original writ
petitioners – predecessors. It is submitted that it only mentions “handing
over of possession by the Tehsil staff to the Land and Building
Department”. It is submitted that as per Section 16 of the Land
Acquisition Act, 1894 only the Collector was empowered to take
possession and possession taken by his subordinate cannot be said to
be lawful. It is submitted that therefore the possession so alleged to be
taken on 26.05.1998 cannot be said to be lawful possession. Reliance
is placed on the decision of this Court in the case of E.A. Aboobacker
and Ors. Vs. State of Kerala and Ors., (2018) 18 SCC 560. It is further
submitted that as such the contesting respondents herein disputes the
actual taking over of possession and according to them, they are in
possession of the land in question.
4. We have heard the learned counsel appearing for the respective
parties at length.
5. At the outset, it is required to be noted that before the High Court,
a counter affidavit was filed by LAC as well as DDA and in which it was
3
specifically mentioned that the land in question was handed over to DDA
on 26.05.1998 and therefore, the acquisition is complete and the lands
vest in the Government and free from any encumbrances. Nothing is on
record that any rejoinder affidavit was filed on behalf of the original writ
petitioners to the counter affidavit filed by the LAC or DDA. Nothing is
on record that at any point of time, the original writ petitioners –
predecessors made any grievance that the possession taken over on
26.05.1998 was not lawful. Even the High Court in the impugned
judgment and order has believed the stand taken by the LAC that the
possession of the subject land has been taken over. Under the
circumstances, it is too late and/or not permissible on the part of the
original writ petitioners to now contend that the possession taken over on
26.05.1998 was not lawful.
5.1 As observed and held hereinabove, solely on the ground that the
compensation in respect of the subject land has not been tendered to
the original writ petitioners, the High Court has declared that the
acquisition proceedings with respect to the land in question is deemed to
have been lapsed under Section 24(2) of the Act, 2013. It is required to
be noted that in the present case, a notification under Section 4 of the
Land Acquisition Act, 1894 was issued in 1964 and the award was
declared on 10.12.1997 and the possession was handed over to DDA on
4
26.05.1998. So far as the submission on behalf of the original writ
petitioners that “in the possession certificate dated 26.05.1998, there
was no mention of taking over of possession of the subject lands by the
Land Acquisition Collector from the original writ petitioners –
predecessors” is concerned, mere non-mention of taking over of
possession cannot be a ground not to believe the possession certificate
in which it is specifically mentioned that the possession of the land in
question is handed over to the DDA. What is relevant is handing over of
the possession to the DDA.
5.2 The view taken by the High Court that the acquisition is deemed to
have lapsed under Section 24(2) of the Act, 2013 on the ground that
though the possession of the subject lands has been taken over but the
compensation in respect of the subject lands has not been tendered is
just contrary to the Constitution Bench decision of this Court in the case
of Indore Development Authority Vs. Manoharlal and Ors. (2020) 8
SCC 129 . In paragraph 366, it is observed and held by this Court as
under:-
“ 366. In view of the aforesaid discussion, we answer
the questions as under:
366.1. Under the provisions of Section 24(1)(a) in
case the award is not made as on 1-1-2014, the date of
commencement of the 2013 Act, there is no lapse of
proceedings. Compensation has to be determined under
the provisions of the 2013 Act.
5
366.2. In case the award has been passed within the
window period of five years excluding the period covered
by an interim order of the court, then proceedings shall
continue as provided under Section 24(1)(b) of the 2013
Act under the 1894 Act as if it has not been repealed.
366.3. The word “or” used in Section 24(2) between
possession and compensation has to be read as “nor” or as
“and”. The deemed lapse of land acquisition proceedings
under Section 24(2) of the 2013 Act takes place where due
to inaction of authorities for five years or more prior to
commencement of the said Act, the possession of land has
not been taken nor compensation has been paid. In other
words, in case possession has been taken, compensation
has not been paid then there is no lapse. Similarly, if
compensation has been paid, possession has not been
taken then there is no lapse.
366.4. The expression “paid” in the main part of
Section 24(2) of the 2013 Act does not include a deposit of
compensation in court. The consequence of non-deposit is
provided in the proviso to Section 24(2) in case it has not
been deposited with respect to majority of landholdings
then all beneficiaries (landowners) as on the date of
notification for land acquisition under Section 4 of the 1894
Act shall be entitled to compensation in accordance with
the provisions of the 2013 Act. In case the obligation under
Section 31 of the Land Acquisition Act, 1894 has not been
fulfilled, interest under Section 34 of the said Act can be
granted. Non-deposit of compensation (in court) does not
result in the lapse of land acquisition proceedings. In case
of non-deposit with respect to the majority of holdings for
five years or more, compensation under the 2013 Act has
to be paid to the “landowners” as on the date of notification
for land acquisition under Section 4 of the 1894 Act.
366.5. In case a person has been tendered the
compensation as provided under Section 31(1) of the 1894
6
Act, it is not open to him to claim that acquisition has
lapsed under Section 24(2) due to non-payment or non-
deposit of compensation in court. The obligation to pay is
complete by tendering the amount under Section 31(1).
The landowners who had refused to accept compensation
or who sought reference for higher compensation, cannot
claim that the acquisition proceedings had lapsed under
Section 24(2) of the 2013 Act.
366.6. The proviso to Section 24(2) of the 2013 Act is
to be treated as part of Section 24(2), not part of Section
24(1)(b).
366.7. The mode of taking possession under the
1894 Act and as contemplated under Section 24(2) is by
drawing of inquest report/memorandum. Once award has
been passed on taking possession under Section 16 of the
1894 Act, the land vests in State there is no divesting
provided under Section 24(2) of the 2013 Act, as once
possession has been taken there is no lapse under Section
24(2).
366.8. The provisions of Section 24(2) providing for a
deemed lapse of proceedings are applicable in case
authorities have failed due to their inaction to take
possession and pay compensation for five years or more
before the 2013 Act came into force, in a proceeding for
land acquisition pending with the authority concerned as on
1-1-2014. The period of subsistence of interim orders
passed by court has to be excluded in the computation of
five years.
366.9. Section 24(2) of the 2013 Act does not give
rise to new cause of action to question the legality of
concluded proceedings of land acquisition. Section 24
applies to a proceeding pending on the date of
enforcement of the 2013 Act i.e. 1-1-2014. It does not
revive stale and time-barred claims and does not reopen
concluded proceedings nor allow landowners to question
7
the legality of mode of taking possession to reopen
proceedings or mode of deposit of compensation in the
treasury instead of court to invalidate acquisition.”
6. In view of the above and for the reasons stated above, the
impugned judgment and order passed by the High Court is
unsustainable and the same deserves to be quashed and set aside and
is accordingly quashed and set aside.
Present appeals are accordingly allowed. However, in the facts
and circumstances of the case, there shall be no order as to costs.
Pending applications, if any, also stand disposed of.
………………………………….J.
[M.R. SHAH]
NEW DELHI; ………………………………….J.
DECEMBER 15, 2022. [S. RAVINDRA BHAT]
8