Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 3
CASE NO.:
Appeal (civil) 6498 of 1998
PETITIONER:
M/S K. STREETLITE ELECTRIC CORPORATION
Vs.
RESPONDENT:
REGIONAL PROVIDENT FUND COMMISSIONER, HARYANA
DATE OF JUDGMENT: 09/04/2001
BENCH:
S. Rajendra Babu & Shivaraj V. Patil
JUDGMENT:
J U D G M E N T
RAJENDRA BABU, J. :
L...I...T.......T.......T.......T.......T.......T.......T..J
A notice dated December 30, 1986 was served upon the
appellant to show cause why damages under Section 14-B of
the Employees Provident Funds & Misc. Provisions Act, 1952
[hereinafter referred to as the Act] for period from July
1976 to June 1980 be imposed upon the appellant. On March
13, 1987 an order was made by the respondent imposing
damages to the extent of Rs. 88,731.25 on account of
belated deposit of the amount towards the provident fund.
The appellant claimed that delay in depositing the amount in
certain cases is only for a few days; that even so the
respondent had assessed the damages in most of the cases at
100% and that the actual loss suffered by the respondent is
only to the extent of Rs. 664/-. Challenging the order
dated March 13, 1987 the appellant filed a writ petition in
the High Court contending that the order is not in
accordance with the instructions issued on November 3, 1982;
that the order has been passed at a very belated stage
inasmuch as for the period ending in July 1976 the notice
has been issued in the year 1987; that para 32(A) was
inserted into the scheme after the amendment of the Act as
under:
Period of Default
Rate of Damages
[%age of arrears
per annum]
(a) Less than two months
17
(b) Two months and above but less than
four months
22
(c) Four months and above but less than six
months
27
(d) Six months and above
37
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 3
The writ petition was resisted by the respondent by
taking the stand that the damages have been levied in
accordance with law. The Division Bench of the High Court
dismissed the writ petition filed by the appellant. Hence
this appeal by special leave.
In this appeal, it is contended that :
(i) the action has been initiated very late inasmuch as
the proceedings had been initiated from 10 to 6 years later
than the default stated to have been committed by the
appellant; and
(ii) the Central Government had instructed under Section
20 of the Act that the damages at the rate of 25% per annum
can be levied.
These two contentions stood rejected by the High Court.
Firstly, that delay in initiating proceedings under Section
14-B of the Act will not be a ground for setting aside an
order imposing damages unless specific plea of prejudice is
raised before the Provident Fund Commissioner and
established and further that the instructions given by the
Central Government do not have any binding force. The High
Court adverted to the decision of this Court in Hindustan
Times Ltd. vs. Union of India & Ors., 1998(2) SCC 242, to
reach this conclusion. In that case, this Court examined
the scheme of the provisions of the Act in relation to delay
in passing of the order. It was stated that the mere fact
that the proceedings are initiated or demand for damages is
made after several years cannot, by itself, be a ground for
drawing an inference of waiver of that the employer was
lulled into a belief that no proceedings under Section 14-B
would be taken and mere delay in initiating such action
cannot amount to prejudice inasmuch as such delay would
result in allowing the employer to use the monies for his
own purposes or for his business especially when there is no
additional provision for charging interest on such amount.
However, the employer can claim prejudice if there is proof
that between the period of default and the date of
initiation of action under Section 14-B he has altered his
position to his detriment to such an extent that if the
recovery is made after a large number of years, the
prejudice to him is of an irretrievable nature, and such
prejudice can also be established by stating reason of
non-availability of records of the personnel by which
evidence it could be established that there was some basis
for delay in making the payments. Therefore, this Court was
of the opinion that such delay, by itself, would not result
in any prejudice. In the present case, the High Court found
that no such prejudice was either pleaded or proved. Hence
the first contention stands rejected.
The second contention need not be examined in the view
we propose to take in the matter. Even if we hold that the
Central Government instructions issued under Section 20 of
the Act are not binding on the respondent, still in
assessing the damages it will be necessary for us to take
note of the manner in which the amounts of damages have been
levied and appropriately consider as to what would be the
correct rate of damages to be imposed under Section 14-B of
the Act. The statement of calculation prepared by the
respondent regarding delay in payments discloses that the
respondent has imposed damages at different rates, for
example, for the month of July 1976 the rate of damages is
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 3
50% whereas the period of default is over month, while in
case of December 1976 the damages imposed upon the appellant
are at the rate of 20% though the period of delay is over
two months, in the case of delay for April 1988 damages
imposed are at the rate of 30% though the period of delay is
only one month. In certain cases, even for a delay of below
15 days, like October 1977, damages at the rate of 85% have
been imposed, while for another period though the delay is
for six months 65% damages have been levied. Therefore, it
is not possible to discern the rationale adopted by the
respondent in the matter of imposition of penalty. In the
circumstances, therefore, it would have been appropriate for
us to set aside the order and remit the matter to the
respondent, but we do not think that such an exercise is
necessary after such a long period. In this case, the
amount due towards provident fund has already been deposited
and this Court, by order dated December 18, 1998, granted an
interim relief to the extent of 75% of the amount of damages
sought to be recovered, while out of the disputed amount of
damages (that is, Rs. 88,731.25), 25% had already been
directed to be deposited. In that view of the matter, we
think, it is appropriate to confine the damages leviable in
this case on an over all consideration to the extent of 25%
of the total damages imposed.
The appeal is, therefore, partly allowed and the order
made by the Provident Fund Commissioner is modified
accordingly. No costs.