Full Judgment Text
IN THE HIGH COURT OF DELHI AT NEW DELHI
W.P.(C) 11247/2009
th
Reserved on: 9 December 2010
st
Decision on: 31 January 2011
BIRLA GTM - ENTERPOSE LTD.
AND ORS. ..... Petitioners
Through Mr. Ramesh Singh with
Mr. Shabyashachi Patra, Advocate
versus
UNION OF INDIA & ANR ..... Respondents
Through : Mr. Sandeep Sethi, Senior Advocate
with Ms. Padma Priya with Ms. Meenakshi Sood,
Advocates for NHAI.
CORAM: JUSTICE S. MURALIDHAR
1. Whether reporters of local paper may be allowed
to see the judgment? No
2. To be referred to the reporter or not? Yes
3. Whether the judgment should be referred in the digest? Yes
JUDGMENT
31.01.2011
1. The Petitioners Birla GTM-Entrepose Limited (`BGEL‟), and its Ex-
Chairman, Ex-Director and Chief Executive Officer have filed this petition
th
challenging an order dated 6 October, 2008 issued by the National
Highways Authority of India (NHAI), Respondent No.2 banning/black
listing BGEL from participating or bidding for projects of/or to be
undertaken by NHAI either by itself or in association with any person or
entity for a period of five years from the date of the order.
Background facts
2. The Petitioners state that BGEL is a joint venture company (JV)
incorporated under the Companies Act, 1956 pursuant to a JV agreement
W.P.(C) No. 11247/2009 Page 1 of 27
th
dated 18 January, 1990 between National Engineering Industries Limited
and GTM Entrepose, France (GTME). The Petitioners state that the said JV
agreement provided that technical assistance of specialist subsidiaries of
GTME would be available to BGEL through technical assistance contracts
to be entered into on a case by case basis. It is stated that BGEL was formed
with 40% equity participation of GTME. It is stated that at the relevant
point of time, Entreprise Jean Lefebvre, France (EJL) was a subsidiary of
GTME and specialized in road construction works.
3. It is stated that the Public Works Department, Rajasthan on behalf of the
Ministry of Road Transport and Highways („MRTH‟), Government of India,
Respondent No. 1 herein, awarded to BGEL the contract of carrying out the
construction of works in a portion of the Delhi-Jaipur National Highway 8
(„NH 8‟) in the year 1992 (hereafter referred to as `the ADB-II contract‟). It
is stated that BGEL bid for the contract as a JV company. The contract
involved construction of additional two lanes and strengthening of the
existing carriageway from KM 162.5 to KM 231 on NH 8. According to the
Petitioners, the ADB-II contract, valued at Rs.80 crores, was performed to
the satisfaction of the NHAI.
4. In 1995, the MRTH, on behalf of the NHAI, invited pre-qualification
applications for a National Highways project under the ADB loan assistance
(hereafter as `the project‟) to be followed by invitation to pre-qualified
bidders for international competitive bidding for execution of the project.
BGEL, on behalf of itself and EJL, submitted the pre-qualification
rd
application dated 3 April, 1995 enclosing a copy of the Memorandum of
W.P.(C) No. 11247/2009 Page 2 of 27
nd
Understanding (MOU) dated 2 April, 1995 between BGEL and EJL.
BGEL claims that while making the application, it had disclosed that BGEL
and EJL proposed to enter into an agreement for forming a separate
company to be called Birla – Jean Lefebvre Construction Ltd (`BJL‟).
However, the said agreement did not materialize.
th
5. By a letter dated 10 July 1995, NHAI informed BGEL that it had pre-
qualified for the project subject to the condition that a proper JV agreement
with EJL should be furnished prior to the bidding.
th
6. BGEL submitted its bid on 5 January, 1996. It bid for only one package,
as against three packages for which it had pre-qualified. It is stated that
th
BGEL and EJL entered into a technical assistance agreement dated 14
December 1995 whereby EJL agreed to provide technical assistance to
BGEL to execute the said contract on the terms and conditions stipulated
therein. According to the BGEL, technical obligations and responsibilities
nd
initially agreed upon to be borne by EJL in the MOU dated 2 April, 1995
continued to be the responsibilities of the EJL in the subsequent technical
th
assistance agreement dated 14 December 1995, a copy of which is stated to
have been enclosed with the bid submitted by BGEL to NHAI.
7. It is stated by NHAI that when the JV agreement enclosed with the bid
was examined, it was noticed that it was not in conformity with Clause 5.2
of the Instructions to Bidders. This was communicated to the JV by NHAI
th th
by a letter dated 17 June 1996. By a letter dated 27 June 1996, the
President and authorised signatory of BGEL submitted a fresh JV agreement
W.P.(C) No. 11247/2009 Page 3 of 27
th
dated 26 June 1996. A further modified power-of-attorney, purportedly
executed jointly by the partners of the JV, was also submitted authorising
st
BGEL to sign the contract on behalf of JV. NHAI issued a letter dated 1
th
July 1996 accepting the bid of BGEL. By a contract agreement dated 19
August 1996, NHAI awarded the contract for the execution and completion
of the works with respect to the said project to BGEL.
th
8. It is stated that a coordination meeting was held on 25 January 1997 at
the office of NHAI to review the progress of the project. This meeting was
attended by the representatives of NHAI, BGEL and EJL. According to
BGEL, during the meeting it was clarified that EJL, a subsidiary of GTME,
had disclosed its intention to provide technical assistance to BGEL and that
the sole responsibility for EJL‟s technical assistance agreement and the
liability arising under the contract rested with BGEL. However, NHAI‟s
th
version is different. According to NHAI, a letter dated 25 January 1997
was written by EJL to Snowy Mountains Engineering Corp. Ltd
(Supervision Consultant), a copy of which was marked to NHAI, stating that
they are not JV partners with BGEL as far as the project was concerned and
that EJL was in fact providing only technical assistance to BGEL under a
th
technical assistance agreement. The letter dated 25 January 1997 of EJL
th
was followed by a letter dated 11 April 1997 by Mr. Bernard Merchant of
EJL confirming that he had never signed, executed or approved any JV
agreement between BGEL and EJL. In the meeting convened by the NHAI
th
on 28 April 1997, the Chairman of BGEL confirmed that EJL was not a
partner in the JV and that they were providing only technical assistance.
W.P.(C) No. 11247/2009 Page 4 of 27
9. According to NHAI, the above disclosure came as a shock to it since it
had awarded the contract to BGEL only on the basis that the bid was
submitted by a JV. On account of the above misrepresentation by BGEL,
th
upon which NHAI had acted in good faith, the NHAI issued a letter dated 9
June, 1997 rescinding the contract. The relevant portions of the said letter
contained in paragraphs 3, 4 and 5 read as under:
th
“3. During the review meeting held on 25 January, 97 at New
Delhi it transpired that the assertion of the BGE-EJL (JV) that it
has a JV Agreement and that both partners are jointly and
severally liable for the execution of the work was incorrect. At
the said meeting EJL had stated that they had undertaken to
provide only technical assistance to BGE and denied existence
of any Joint Venture with BGE. EJL has now furnished an
affidavit to NHAI in which it has been stated that the EJL has
not entered into, signed, executed, ratified or approved whether
in writing, verbally or by any other means any JV agreement
with the BGE relating to bid for Contract-I and they have not
signed any deed or document or done anything or omitted to do
anything to give power or authority to BGE to include any
liability and/or to enter into any Contract or agreement of any
nature on behalf of the EJL in respect of Contract-I. This
position was also confirmed by BGE‟s representative Shri P. C.
Agarwala during the meeting with you taken by Chairman,
NHAI on 23.4.97 at New Delhi.
4. In view of the above it is obvious that you had secured pre-
qualification as also the contract by misrepresentation.
5. In view of the above, the Contract is voidable at the option
of NHAI and NHAI therefore hereby rescinds the same with
immediate effect without prejudice to its or her legal rights and
remedies. NHAI is also accordingly taking over the complete
W.P.(C) No. 11247/2009 Page 5 of 27
possession of the site.”
th
10. According to the BGEL, a meeting was held on 14 June 1997 between
the representatives of BGEL and NHAI. It is stated that at this meeting,
NHAI agreed to issue a suitable clarification that the rescinding of the
contract would not prejudice BGEL from being pre-qualified and for bidding
for future contracts.
th
11. It is stated that on 4 August 1998, the Board of NHAI deliberated and
discussed the whole issue regarding the action to be taken against the BGEL
and ultimately proposed to recover Rs.5.17 crores from the Petitioners
towards damages. It was also decided to drop the proposal for blacklisting
the Petitioner. The Petitioners have placed on record copies of the Agenda
th
and Minutes of the meeting of the Board of NHAI dated 4 August, 1998.
th
Consequent upon the said meeting, a letter dated 28 August 1998 was
written by the NHAI to BGEL as under:
“Sir,
Please refer to this office letter of even No. dated the 9th
June, 1997 wherein you were intimated that your contract with
NHAI for the work mentioned in the subject had been rescinded
with immediate effect and without prejudice to the Authority‟s
other legal rights and remedies.
2. Consequent to the problems created by your firm resulting in
the rescission of the contract and the need to fix up another
agency for completing the same, NHAI has suffered certain
losses and damages which are payable by you. These losses
and damages have been carefully assessed in consultation with
the Engineer for the project, namely, M/s SMEC, Australia and
W.P.(C) No. 11247/2009 Page 6 of 27
the same amount to Rs.5,17,30,230/-
3. It is also noted in this connection that your firm had executed
certain works on the project before rescission of the contract,
measurements of which were taken by the Engineer and
accepted by your representative. The cost of such works
payable to you as intimated by the Engineer amounts to
Rs.2,10,38,266/-.
4. It has, accordingly, been decided that in case you pay to
NHAI the net amount of Rs.3,06,91,964/- (Rupees three crores
six lakhs ninety one thousand nine hundred and sixty four only)
as full and final settlement in respect of the rescinded contract,
NHAI will release your performance security amounting to
Rs.2618 lakhs held by us in the form of Bank Guarantee.
5. It is requested that your unconditional acceptance of the
above proposal for full and final settlement in respect of the
rescinded contract, may be communicated to the Authority
within seven days of the receipt of this letter failing which we
will presume that the proposal is not acceptable to you.
6. In case you propose to convey your acceptance of the above
proposal within seven days, you may simultaneously take
action to pay the said amount of Rs.3,06,91,964/- by a Bank
Draft payable at Delhi or Gurgaon in favour of the project
Director, Project Implementation Unit I, NHAI, Gurgaon.
7. In case either your acceptance of the above proposal is not
received within seven days of the issue of this letter or after
receipt of your acceptance the payment is not received by the
Project Director, PIU, Gurgaon, within 30 days of the issue of
this letter, we shall presume that the proposed settlement is not
acceptable to you and we shall feel free to take recourse to other
W.P.(C) No. 11247/2009 Page 7 of 27
options available to us for recovering the losses and damages
incurred by us which may include encashment of your Bank
Guarantee held by us.
8. In view of the above, an immediate reply is requested.”
rd
12. In response to the above letter, BGEL, on 3 September 1998, conveyed
its “unconditional acceptance” of the proposal made by NHAI and asked to
be furnished the detailed particulars of how the sum of Rs.5,17,30,230/- as
damages had been arrived at. This was provided by NHAI by its letter dated
th th
7 September 1998. On 28 September 1998, BGEL made payment of a
sum of Rs.3,06,964 to the NHAI, which was acknowledged by NHAI by its
th
letter dated 28 September 1998 which reads as under:
“Sir,
Please refer to your letter No. dated 3.09.1998 on the above
subject, wherein you have submitted your unconditional
acceptance of our proposal contained in this office letter
th
No.1105/1/198/Tech/PU dated 28 August, 1998, in full and
final with respect to the rescinded.
th
Further referring to your letter No. HO/19/98-99/295 dated 28
September, 1998 submitting therewith an amount of
Rs.3,06,964/- as net balance payment to NHAI, in compliance
to our above mentioned letter, please find enclosed herewith the
Bank Guarantee No. 83/96-97 amounting to Rs.26,18,05,046/-
(Rupees Twenty Six Crores Eighteen Lakhs Five Thousand and
Forty Six Only) dated 24.07.1996 from UCO Bank, 10
Brabourne Road, Calcutta and amendment thereto dated
31.07.1996, duly discharged submitted by you towards
performance Guarantee for the above contract.”
13. It is stated that thereafter NHAI awarded BGEL the following three
W.P.(C) No. 11247/2009 Page 8 of 27
construction contracts:
W.P.(C) 11247/2009
th
Reserved on: 9 December 2010
st
Decision on: 31 January 2011
BIRLA GTM - ENTERPOSE LTD.
AND ORS. ..... Petitioners
Through Mr. Ramesh Singh with
Mr. Shabyashachi Patra, Advocate
versus
UNION OF INDIA & ANR ..... Respondents
Through : Mr. Sandeep Sethi, Senior Advocate
with Ms. Padma Priya with Ms. Meenakshi Sood,
Advocates for NHAI.
CORAM: JUSTICE S. MURALIDHAR
1. Whether reporters of local paper may be allowed
to see the judgment? No
2. To be referred to the reporter or not? Yes
3. Whether the judgment should be referred in the digest? Yes
JUDGMENT
31.01.2011
1. The Petitioners Birla GTM-Entrepose Limited (`BGEL‟), and its Ex-
Chairman, Ex-Director and Chief Executive Officer have filed this petition
th
challenging an order dated 6 October, 2008 issued by the National
Highways Authority of India (NHAI), Respondent No.2 banning/black
listing BGEL from participating or bidding for projects of/or to be
undertaken by NHAI either by itself or in association with any person or
entity for a period of five years from the date of the order.
Background facts
2. The Petitioners state that BGEL is a joint venture company (JV)
incorporated under the Companies Act, 1956 pursuant to a JV agreement
W.P.(C) No. 11247/2009 Page 1 of 27
th
dated 18 January, 1990 between National Engineering Industries Limited
and GTM Entrepose, France (GTME). The Petitioners state that the said JV
agreement provided that technical assistance of specialist subsidiaries of
GTME would be available to BGEL through technical assistance contracts
to be entered into on a case by case basis. It is stated that BGEL was formed
with 40% equity participation of GTME. It is stated that at the relevant
point of time, Entreprise Jean Lefebvre, France (EJL) was a subsidiary of
GTME and specialized in road construction works.
3. It is stated that the Public Works Department, Rajasthan on behalf of the
Ministry of Road Transport and Highways („MRTH‟), Government of India,
Respondent No. 1 herein, awarded to BGEL the contract of carrying out the
construction of works in a portion of the Delhi-Jaipur National Highway 8
(„NH 8‟) in the year 1992 (hereafter referred to as `the ADB-II contract‟). It
is stated that BGEL bid for the contract as a JV company. The contract
involved construction of additional two lanes and strengthening of the
existing carriageway from KM 162.5 to KM 231 on NH 8. According to the
Petitioners, the ADB-II contract, valued at Rs.80 crores, was performed to
the satisfaction of the NHAI.
4. In 1995, the MRTH, on behalf of the NHAI, invited pre-qualification
applications for a National Highways project under the ADB loan assistance
(hereafter as `the project‟) to be followed by invitation to pre-qualified
bidders for international competitive bidding for execution of the project.
BGEL, on behalf of itself and EJL, submitted the pre-qualification
rd
application dated 3 April, 1995 enclosing a copy of the Memorandum of
W.P.(C) No. 11247/2009 Page 2 of 27
nd
Understanding (MOU) dated 2 April, 1995 between BGEL and EJL.
BGEL claims that while making the application, it had disclosed that BGEL
and EJL proposed to enter into an agreement for forming a separate
company to be called Birla – Jean Lefebvre Construction Ltd (`BJL‟).
However, the said agreement did not materialize.
th
5. By a letter dated 10 July 1995, NHAI informed BGEL that it had pre-
qualified for the project subject to the condition that a proper JV agreement
with EJL should be furnished prior to the bidding.
th
6. BGEL submitted its bid on 5 January, 1996. It bid for only one package,
as against three packages for which it had pre-qualified. It is stated that
th
BGEL and EJL entered into a technical assistance agreement dated 14
December 1995 whereby EJL agreed to provide technical assistance to
BGEL to execute the said contract on the terms and conditions stipulated
therein. According to the BGEL, technical obligations and responsibilities
nd
initially agreed upon to be borne by EJL in the MOU dated 2 April, 1995
continued to be the responsibilities of the EJL in the subsequent technical
th
assistance agreement dated 14 December 1995, a copy of which is stated to
have been enclosed with the bid submitted by BGEL to NHAI.
7. It is stated by NHAI that when the JV agreement enclosed with the bid
was examined, it was noticed that it was not in conformity with Clause 5.2
of the Instructions to Bidders. This was communicated to the JV by NHAI
th th
by a letter dated 17 June 1996. By a letter dated 27 June 1996, the
President and authorised signatory of BGEL submitted a fresh JV agreement
W.P.(C) No. 11247/2009 Page 3 of 27
th
dated 26 June 1996. A further modified power-of-attorney, purportedly
executed jointly by the partners of the JV, was also submitted authorising
st
BGEL to sign the contract on behalf of JV. NHAI issued a letter dated 1
th
July 1996 accepting the bid of BGEL. By a contract agreement dated 19
August 1996, NHAI awarded the contract for the execution and completion
of the works with respect to the said project to BGEL.
th
8. It is stated that a coordination meeting was held on 25 January 1997 at
the office of NHAI to review the progress of the project. This meeting was
attended by the representatives of NHAI, BGEL and EJL. According to
BGEL, during the meeting it was clarified that EJL, a subsidiary of GTME,
had disclosed its intention to provide technical assistance to BGEL and that
the sole responsibility for EJL‟s technical assistance agreement and the
liability arising under the contract rested with BGEL. However, NHAI‟s
th
version is different. According to NHAI, a letter dated 25 January 1997
was written by EJL to Snowy Mountains Engineering Corp. Ltd
(Supervision Consultant), a copy of which was marked to NHAI, stating that
they are not JV partners with BGEL as far as the project was concerned and
that EJL was in fact providing only technical assistance to BGEL under a
th
technical assistance agreement. The letter dated 25 January 1997 of EJL
th
was followed by a letter dated 11 April 1997 by Mr. Bernard Merchant of
EJL confirming that he had never signed, executed or approved any JV
agreement between BGEL and EJL. In the meeting convened by the NHAI
th
on 28 April 1997, the Chairman of BGEL confirmed that EJL was not a
partner in the JV and that they were providing only technical assistance.
W.P.(C) No. 11247/2009 Page 4 of 27
9. According to NHAI, the above disclosure came as a shock to it since it
had awarded the contract to BGEL only on the basis that the bid was
submitted by a JV. On account of the above misrepresentation by BGEL,
th
upon which NHAI had acted in good faith, the NHAI issued a letter dated 9
June, 1997 rescinding the contract. The relevant portions of the said letter
contained in paragraphs 3, 4 and 5 read as under:
th
“3. During the review meeting held on 25 January, 97 at New
Delhi it transpired that the assertion of the BGE-EJL (JV) that it
has a JV Agreement and that both partners are jointly and
severally liable for the execution of the work was incorrect. At
the said meeting EJL had stated that they had undertaken to
provide only technical assistance to BGE and denied existence
of any Joint Venture with BGE. EJL has now furnished an
affidavit to NHAI in which it has been stated that the EJL has
not entered into, signed, executed, ratified or approved whether
in writing, verbally or by any other means any JV agreement
with the BGE relating to bid for Contract-I and they have not
signed any deed or document or done anything or omitted to do
anything to give power or authority to BGE to include any
liability and/or to enter into any Contract or agreement of any
nature on behalf of the EJL in respect of Contract-I. This
position was also confirmed by BGE‟s representative Shri P. C.
Agarwala during the meeting with you taken by Chairman,
NHAI on 23.4.97 at New Delhi.
4. In view of the above it is obvious that you had secured pre-
qualification as also the contract by misrepresentation.
5. In view of the above, the Contract is voidable at the option
of NHAI and NHAI therefore hereby rescinds the same with
immediate effect without prejudice to its or her legal rights and
remedies. NHAI is also accordingly taking over the complete
W.P.(C) No. 11247/2009 Page 5 of 27
possession of the site.”
th
10. According to the BGEL, a meeting was held on 14 June 1997 between
the representatives of BGEL and NHAI. It is stated that at this meeting,
NHAI agreed to issue a suitable clarification that the rescinding of the
contract would not prejudice BGEL from being pre-qualified and for bidding
for future contracts.
th
11. It is stated that on 4 August 1998, the Board of NHAI deliberated and
discussed the whole issue regarding the action to be taken against the BGEL
and ultimately proposed to recover Rs.5.17 crores from the Petitioners
towards damages. It was also decided to drop the proposal for blacklisting
the Petitioner. The Petitioners have placed on record copies of the Agenda
th
and Minutes of the meeting of the Board of NHAI dated 4 August, 1998.
th
Consequent upon the said meeting, a letter dated 28 August 1998 was
written by the NHAI to BGEL as under:
“Sir,
Please refer to this office letter of even No. dated the 9th
June, 1997 wherein you were intimated that your contract with
NHAI for the work mentioned in the subject had been rescinded
with immediate effect and without prejudice to the Authority‟s
other legal rights and remedies.
2. Consequent to the problems created by your firm resulting in
the rescission of the contract and the need to fix up another
agency for completing the same, NHAI has suffered certain
losses and damages which are payable by you. These losses
and damages have been carefully assessed in consultation with
the Engineer for the project, namely, M/s SMEC, Australia and
W.P.(C) No. 11247/2009 Page 6 of 27
the same amount to Rs.5,17,30,230/-
3. It is also noted in this connection that your firm had executed
certain works on the project before rescission of the contract,
measurements of which were taken by the Engineer and
accepted by your representative. The cost of such works
payable to you as intimated by the Engineer amounts to
Rs.2,10,38,266/-.
4. It has, accordingly, been decided that in case you pay to
NHAI the net amount of Rs.3,06,91,964/- (Rupees three crores
six lakhs ninety one thousand nine hundred and sixty four only)
as full and final settlement in respect of the rescinded contract,
NHAI will release your performance security amounting to
Rs.2618 lakhs held by us in the form of Bank Guarantee.
5. It is requested that your unconditional acceptance of the
above proposal for full and final settlement in respect of the
rescinded contract, may be communicated to the Authority
within seven days of the receipt of this letter failing which we
will presume that the proposal is not acceptable to you.
6. In case you propose to convey your acceptance of the above
proposal within seven days, you may simultaneously take
action to pay the said amount of Rs.3,06,91,964/- by a Bank
Draft payable at Delhi or Gurgaon in favour of the project
Director, Project Implementation Unit I, NHAI, Gurgaon.
7. In case either your acceptance of the above proposal is not
received within seven days of the issue of this letter or after
receipt of your acceptance the payment is not received by the
Project Director, PIU, Gurgaon, within 30 days of the issue of
this letter, we shall presume that the proposed settlement is not
acceptable to you and we shall feel free to take recourse to other
W.P.(C) No. 11247/2009 Page 7 of 27
options available to us for recovering the losses and damages
incurred by us which may include encashment of your Bank
Guarantee held by us.
8. In view of the above, an immediate reply is requested.”
rd
12. In response to the above letter, BGEL, on 3 September 1998, conveyed
its “unconditional acceptance” of the proposal made by NHAI and asked to
be furnished the detailed particulars of how the sum of Rs.5,17,30,230/- as
damages had been arrived at. This was provided by NHAI by its letter dated
th th
7 September 1998. On 28 September 1998, BGEL made payment of a
sum of Rs.3,06,964 to the NHAI, which was acknowledged by NHAI by its
th
letter dated 28 September 1998 which reads as under:
“Sir,
Please refer to your letter No. dated 3.09.1998 on the above
subject, wherein you have submitted your unconditional
acceptance of our proposal contained in this office letter
th
No.1105/1/198/Tech/PU dated 28 August, 1998, in full and
final with respect to the rescinded.
th
Further referring to your letter No. HO/19/98-99/295 dated 28
September, 1998 submitting therewith an amount of
Rs.3,06,964/- as net balance payment to NHAI, in compliance
to our above mentioned letter, please find enclosed herewith the
Bank Guarantee No. 83/96-97 amounting to Rs.26,18,05,046/-
(Rupees Twenty Six Crores Eighteen Lakhs Five Thousand and
Forty Six Only) dated 24.07.1996 from UCO Bank, 10
Brabourne Road, Calcutta and amendment thereto dated
31.07.1996, duly discharged submitted by you towards
performance Guarantee for the above contract.”
13. It is stated that thereafter NHAI awarded BGEL the following three
W.P.(C) No. 11247/2009 Page 8 of 27
construction contracts:
| Project | Date of signing<br>of Contract | |
|---|---|---|
| 1. | Jalandhar Bypass (NS-1) KM<br>372.700 to KM 387.100 | 16.06.1999 |
| 2. | Westerly Diversion KM<br>0.000 to KM 34.250 outside<br>Pune City in Maharashtra<br>(NH-4) | 07.04.2000 |
| 3. | Pune Satara (PS-2) to NH-4<br>KM 760.000 to KM 797.000<br>(excluding Km 773 to Km<br>781) | 11.10.2001 |
th
14. On 15 July 2003, NHAI invited bids for a stretch on Jalandhar-Amritsar
Section of NH-1 from KM 387.100 to KM 407.100. BGEL submitted its bid
st th
on 21 August, 2003. Its technical bid was accepted. On 10 November,
2003 NHAI declared the bid of the BGEL to be the lowest. However,
sometime in January, 2004 BGEL was informed by NHAI during discussion
that NHAI was proposing to initiate proceedings for black listing BGEL for
awarding of future contracts on the ground of alleged misrepresentation
th
which led to the rescinding of the contract in question on 9 June, 1997.
th
The Petitioner protested against this move by letters dated 27 January 2004
th
and 17 February 2004 by pointing out that the issue has already been
th
settled by the letter dated 28 August 1998 of the NHAI and the payment by
BGEL of the damages, as declared by NHAI. Nevertheless, NHAI did not
award the Jalandhar– Amritsar Project to BGEL and the bid itself was
cancelled.
th
15. A show cause notice dated 25 February 2004 was issued by NHAI to
BGEL seeking to blacklist it in view of the misrepresentation which led to
rescinding of the contract in question. According to the Petitioners, this was
W.P.(C) No. 11247/2009 Page 9 of 27
th
based on an advice of the Central Vigilance Commission (CVC) dated 30
th
October 2002. A detailed reply was given by BGEL on 18 March, 2004
th
and a personal hearing was granted on 30 June 2004. BGEL also filed its
nd
written submissions on 2 July 2004.
16. At this stage, the Petitioners filed Writ Petition (Civil) No.3377-80/2004
in this Court. This was on account of an apprehension that BGEL may be
th
blacklisted for future contracts. By an interim order dated 10 March 2004,
the learned Single judge of this Court held that BGEL shall not be held
ineligible for award of the Amritsar-Jalandhar contract on account of the
th
pending show cause notice. Subsequently, an order dated 9 February 2005
was passed by a Division Bench of this Court disposing of Writ Appeal No.
651 of 2004 directing that the decision of the Competent Authority of NHAI
pursuant to its inquiry into the matter will be placed in a sealed cover and
produced before the learned Single Judge for directions.
17. The learned Single Judge , who heard the Writ Petition (C) No. 3377-80
th
of 2004, on 30 July 2009, opened the sealed cover which contained the
th
impugned order dated 6 October 2008 and made it available to the counsel
for BGEL upon whose statement that he would like to challenge the said
orders in appropriate proceedings, the writ petition was disposed of as
having become infructuous. The NHAI was directed not to give effect to the
said impugned order for a period of four weeks and not to give it publicity in
the meanwhile.
18. Thereafter the present writ petition was filed challenging the said
W.P.(C) No. 11247/2009 Page 10 of 27
th
impugned order dated 6 October 2008. While directing notice to issue in
th
the writ petition on 28 August 2009, this Court directed that NHAI will not
give publicity to the impugned order. The said interim order has continued.
Submissions of counsel
19. Mr. Ramesh Singh, learned counsel appearing for the Petitioner
submitted that the matter concerning the alleged misrepresentation by the
BGEL which led to the rescinding of the contract by the NHAI by its letter
th
dated 9 June 1997 was fully and finally settled on the terms decided by the
th
Board of NHAI in its meeting of 4 August 1998. The Minutes of the said
meeting showed that the NHAI quantified the precise amount payable by
BGEL to NHAI as damages. This amount was, in fact, paid by BEGL in
th
acceptance of the terms and conditions on 28 September 1998. He further
th
submitted that the Minutes of the meeting of the Board of NHAI held on 4
August 1998 recorded the decision to drop the proposal for blacklisting
BGEL. On its part, BGEL decided not to contest the charge that it
misrepresented facts since it did not want to jeopardize its chances to bid for
future contracts. It is stated that by acting on the above full and final
settlement, the Petitioner gave up whatever defence it may have had against
the charge of misrepresentation, and agreed to accept the terms and
conditions imposed by NHAI. Having altered its position and having given
up its defence on the basis of such full and final settlement offered by the
NHAI, which it accepted, the BGEL cannot now be sought to be blacklisted
by NHAI for a matter that already stood closed. In support of his
submissions, Mr. Singh has relied upon the judgments in Nathani Steel Ltd.
v. Associated Constructions (1995) Supp (3) SCC 324 ; Hira Lal Hari Lal
W.P.(C) No. 11247/2009 Page 11 of 27
Bhagwati v. Central Bureau of Investigation (2003) 5 SCC 257 and
Rashtriya Ispat Nigam Ltd. v. Verma Transport Co. (2006) 7 SCC 275 .
20. Mr. Ramesh Singh next submitted that the intention of NHAI not to
blacklist BGEL was apparent from the fact that at least three contracts were
awarded to BGEL after the full and final settlement of the disputes as
th
evidenced by letter dated 28 August 1998 of NHAI. The NHAI was,
therefore, estopped from blacklisting BGEL thereafter. Thirdly, it is
submitted that after 2003, the NHAI, in any event, stopped awarding
contracts to the Petitioner. A reference is made to para 32 of the counter-
affidavit of NHAI where it is stated that NHAI decided not to award the
Jalandhar-Amritsar contract to BGEL because by then, it proposed to review
its earlier decision of not blacklisting BGEL. Therefore from 2003 onwards,
there was a de facto blacklisting of BGEL by NHAI. If the five-year period
were to be counted from that date, the blacklisting had already come to an
end. Therefore, there was no justification for NHAI to order a further
blacklisting of BGEL for a period of five years from the date of the
th
impugned order dated 6 October 2008. Fourthly, it is submitted that the
th
show cause notice dated 25 February 2004 makes no mention whatsoever
of the fact that there was a full and final settlement of the outstanding issues
th
arising from the rescission of the contract by the NHAI by its letter dated 9
June 1997. The show cause notice also did not mention the fact that the
Petitioner BGEL had, pursuant to such settlement, already paid the damages
as determined by NHAI and further that the proposal to blacklist the BGEL
had been dropped by NHAI. The fact of NHAI having awarded three
contracts thereafter to BGEL was also not mentioned. These were factors
W.P.(C) No. 11247/2009 Page 12 of 27
relevant for deciding whether there was any justification for blacklisting
BGEL. Fifthly, it is submitted that the action initiated by NHAI to blacklist
BGEL was revived in 2004 whereas the full and final settlement took place
in August 1998 itself. To revive a proposal to blacklist BGEL six years
thereafter was clearly unfair, unreasonable and violative of Article 14 of the
Constitution. Reliance is placed on the decisions of the Supreme Court in
State of Madhya Pradesh v. Bani Singh 1990 (Supp) SCC 738 and State of
A.P. v. N. Radhakishan (1998) 4 SCC 154 . It is submitted that severe
prejudice has already been caused to the Petitioner on account of the
unreasonable decision of the NHAI to blacklist the Petitioner.
21. Mr. Sandeep Sethi, learned Senior counsel appearing for the NHAI
submitted that the JV Agreement and the Power-of-Attorney submitted by
BGEL along with its bid for the contract in question turned out to be forged
and fabricated documents. Although, at one stage, NHAI decided not to
pursue the matter, later when there was a thorough audit conducted and the
CVC entered into the picture, it transpired that there was some more
evidence of the extent of fabrication and forgery practised by BGEL. This
had not been noticed in the initial stage. NHAI had to act on the report of the
CVC, which categorically concluded that blacklisting proceedings had to be
initiated against BGEL for the forgery and fabrication of documents. It is
submitted that an FIR has also been registered against BGEL and certain
officials of NHAI were purportedly involved in the transaction under
Sections 420, 468 and 471 IPC.
22. Mr. Sandeep Sethi submitted that an important aspect was that BGEL
W.P.(C) No. 11247/2009 Page 13 of 27
had admitted to having submitted forged and fabricated documents along
with its bid. It is submitted that the JV Agreement was typed out on a stamp
paper showing a date which was earlier than the date on which the stamp
paper was purchased. There had been a clear attempt to mislead NHAI in
awarding a contract on the basis of there being a JV with EJL, when in fact
there was none. Thirdly, it is submitted that at no point in time did NHAI
inform BGEL that it was dropping the proposal to blacklist BGEL. The letter
th
dated 28 August 1998 only talked of the damages having to be paid by
BGEL. It is submitted that any agreement between the parties that there
would be no blacklisting would be opposed to public policy. This would be
no different from an agreement not to prosecute a person who had
committed the offence of forgery punishable under Sections 468, 471 read
with 420 IPC.
23. Mr. Sandeep Sethi referred to certain portions of the impugned order
th
dated 6 October 2008 of the NHAI, which showed that BGEL urged
patently unsustainable pleas before the competent authority of NHAI at the
hearing consequent upon the show cause notice. The conduct of BGEL did
not entitle it to any equitable relief. It is submitted that the delay in
instituting proceedings to blacklist BGEL cannot, by itself, be said to cause
prejudice to BGEL. It is only when a party is unable to effectively present its
defence to the show cause notice, due to the disappearance of evidence on
account of the passage of time, that prejudice can be said to be caused to
such party. In the instant case, since BGEL admitted to have forged and
fabricated documents and had virtually had no defence in the matter, there
was no question of any prejudice being caused to it. Finally, it is submitted
W.P.(C) No. 11247/2009 Page 14 of 27
that in exercise of its powers of judicial review under Article 226 of the
Constitution, this Court would be concerned only with the decision-making
process and not the decision itself. When a party has admittedly used forged
and fabricated documents to secure a bid and later admits to such forgery
and fabrication, then no leniency ought to be shown to such party even on
equity. It is submitted that the NHAI cannot be compelled to continue to
deal with BGEL in the face of such grave acts of misconduct and crime on
the part of BGEL.
Effect of the full and final settlement of disputes
24. The first question that arises is whether the NHAI was precluded from
initiating proceedings for blacklisting BGEL after the `full and final
th
settlement‟ brought about by its letter dated 28 August 1998?
25. A perusal of the Minutes of the meeting of the Board of NHAI held on
th
4 August 1998 is instructive as to the deliberations that took place on that
day. The minutes of the said meeting show that Agenda Item No. 11 related
to the project in question. A noting against this Item reads as under:
“It was seen that in the instant case, there does not appear any
apparent error in the findings of the Engineer. Further, having
regard to the fact that the contractor has actually executed
measurable quantity of work as also the fact that the problem
regarding the joint venture was known to NHAI in January,
1997, it would not appear feasible that anymore delay other
than those considered by the Engineer, while working out the
probable losses and damages incurred by the NHAI, could be
attributed to M/s BGE-EJL (JV).
W.P.(C) No. 11247/2009 Page 15 of 27
In the light of the above, the Board approved the proposal
contained in para 14 of the agenda note.”
26. The detailed Agenda notes are also relevant in this regard. The relevant
paragraphs are 11, 11.1 and 11.2 which read as under:
“11. It may also be brought out that ADB had requested NHAI
to take action to initiate steps to ensure legal consequences of
the fraudulent action of the contractor. This would mean the
process for blacklisting of the Contractor M/s BGE-EJL (JV).
The following facts need to be considered in this regard:
11.1 M/s Swarup & Co. has mentioned that as there is
rescission of the contract and as one of the BGE-EJL (JV)
Partners has in effect stated that it has made misrepresentation,
it may be appropriate for NHAI to initiate proceedings for black
listing of the Contractors. They have, however, drawn our
attention to the fact that the Supreme Court has laid down
certain principles, which have to be followed for blacklisting.
Under it, the principles of natural justice will have to be
complied with. It requires that a show cause notice has to be
given to the contractor and it has to be given adequate
opportunity of being heard including oral hearing if requested
and only after considering the same if NHAI comes to the
conclusion that there was willful misrepresentation by one or
both of the BGE-EJL (JV) partners whether by overt act or
otherwise that it can be black listed, it would be bad in law to
deny them participation in other tenders. Considering ADB‟s
suggestions for action, it is for consideration whether it is in the
best interest of NHAI to initiate the process of black listing of
the Contractors.
11.2 In this connection, it needs to be noted that the Board in
th
its 13 Meeting held on 28.04.97 took note of the fact that M/s
BGE had requested that since they were capable of executing
W.P.(C) No. 11247/2009 Page 16 of 27
this project by themselves and without having a JV with EJL,
they be permitted to continue with the work with the change
that EJL would provide only technical assistance. The then
Chairman had also informed the Board that the matter had been
discussed informally with officers of ADB who had suggested
that if the Authority considered it prudent and necessary in the
interests of the project, it may submit a proposal for change in
the composition of Contractor to the Bank for reconsideration
with additional built in safeguards. The Board Members agreed
that in view of the importance of the project and the need to
ensure its earliest possible completion, NHAI may make one
last attempt to obtain ADB‟s consent accepting the proposed
modifications. It was also mentioned by the Chairman that in
case Bank do not agree, there may be no alternative but to re-
bid the project. The relevant extracts of the minutes of the
Board meeting are enclosed as Annex. „C‟. Having once taken a
lenient view of the lapse on the part of the Contractor, it would
seem illogical if a more strict view is now taken and black
listing process is initiated.”
27. The recommendations in para 14 of the agenda note, which were
approved at the meeting, read as under:
“14. In view of foregone, the following are for
consideration of the Board:
(a) To recover the money from the Contractor M/s
BGE-EJL (JV) amounting to Rs.5,17,30,230/-
(Rs.4,82,80,230/- + Rs.34,50,000/-) in respect of
probable losses and damages incurred by NHAI
consequent on the rescinding of the contract of M/s
BGE-EJL (JV) and for getting the balance work
completed through M/s BSC-RBN – PATI (JV).
(b) Simultaneously to pay a sum amounting to
W.P.(C) No. 11247/2009 Page 17 of 27
Rs.2,10,38,266/- to the Contractor M/s BGE-EJL (JV)
for the work done over the contract period by the.
(c) To demand from M/s BGE the net payment of
Rs.3,06,91,964/- due to NHAI and in case of their
failure to do so within a period of one month from the
date of demand to recover the same from their
performance security board.
(d) Upon receipt of payment from M/s BGE to release
the performance security in the form of Bank
Guarantee amounting to Rs.2618 lakhs duly discharged
by the NHAI which was submitted by the Contractor
M/s BGE-EJL (JV) to NHAI.
(e) To drop the proposal of initiating black-listing of
M/s BGE-EJL (JV).”
28. There can be no manner of doubt that there was a conscious decision
taken by the NHAI approving the recommendations contained in para 14 of
the agenda note. This was to the effect that the damages incurred by NHAI
consequent upon the rescission of the contract with BGEL would be
quantified and recovered from BGEL after adjusting the amount due from
NHAI to BGEL. Secondly, a conscious decision was taken to drop
blacklisting proceedings against BGEL.
29. It is based on the decision taken at the meeting of the Board of NHAI on
th th
4 August 1998 that the letter of 28 August 1998 came to be written by
NHAI to BGEL. Although the letter does not talk of dropping of blacklisting
proceedings and only talks of the recovery of damages, it is plain from the
W.P.(C) No. 11247/2009 Page 18 of 27
th
minutes of the meeting of the Board on 4 August 1998 that the proposal to
blacklist BGEL had been dropped by NHAI. Consequently, there was no
th
mention of such blacklisting in the letter dated 28 August 1998.
30. The Petitioner was justified in thereafter proceeding on the footing that
there was indeed a full and final settlement. This was reinforced by the fact
that after the above decision was communicated to BGEL by NHAI by its
th
letter dated 28 August 1998, and BGEL accepted it and made payment on
th
28 September 1998 of the damages determined by NHAI, BGEL was
awarded three contracts by NHAI. If indeed BGEL was to be blacklisted,
there was no question of NHAI awarding it three contracts in three different
years thereafter, which contracts admittedly BGEL completed to the
satisfaction of NHAI.
31. It was vehemently argued on behalf of the NHAI that there could have
been no agreement between the parties not to blacklist BGEL and that such
an agreement would be opposed to public policy and hit by Section 23 of the
Contract Act. It was argued that subsequently an FIR had been registered in
2003 against certain officials of NHAI as well as BGEL. The settlement
th
communicated by the letter dated 28 August 2008 was in effect an
agreement to compound an offence which could not be compounded and,
therefore, NHAI was justified in reviewing its decision taken at the meeting
th
of the Board on 4 August 1998 not to blacklist the Petitioner. The second
explanation is that the NHAI was bound by the decision of the CVC in the
matter.
W.P.(C) No. 11247/2009 Page 19 of 27
32. In the first place, it must be noted that the full and final settlement of the
disputes was arrived at in the form of a composite agreement between the
th
parties. The sequence of events shows that a meeting took place on 25
th
January 1997 followed by the rescission of the contract on 9 June 1997.
th
This was followed by the meeting on 4 August 1998 of the NHAI Board
where it was decided not to initiate blacklisting proceedings against BGEL.
The very documents on the basis of which such conclusion is sought to be
drawn at the time of issuance of show cause notice in 2004 were already
th
available with the NHAI at the time of the meeting of its Board on 4
August 1998. On the basis of these very documents, it was decided that the
NHAI will recover damages suffered by it on account of the rescission of the
contract and that it will drop the blacklisting proceedings. The said
composite agreement was accepted and acted upon by both the parties.
th
BGEL paid the damages, as demanded by NHAI by its letter dated 28
th
August 1998. The payment made by BGEL on 28 September 1998 was
accepted by NHAI. This brought about a final settlement to the disputes.
Clearly, BGEL altered its position in the sense that it decided not to defend
itself against the charge of having submitted a fabricated document with its
bid and instead decided to pay up the damages. In turn, it was granted
immunity against blacklisting proceedings. Granting immunity to a wrong
doer in return for payment of damages or compensation by such wrong doer
and the wrong doer admitting his mistake and making reparations for it is
not unusual.
33. In Hira Lal Hari Lal Bhagwati v. CBI the Supreme Court was dealing
with the consequences of grant of immunity under the Kar Vivad Samadhan
W.P.(C) No. 11247/2009 Page 20 of 27
Scheme, 1998 (`KVSS‟). Under the KVSS, immunity was granted from
prosecution under the Customs Act, 1962. On that basis, the assessee
withdrew its appeals pending in the Supreme Court and a certificate for full
and final settlement of tax arrears was issued to it. Thereafter an FIR was
sought to be lodged by the CBI for offences under Sections 120-B/420 IPC.
The assessee then initiated proceedings for quashing of the criminal
proceedings. After being unsuccessful in the High Court, the assessee
appealed to the Supreme Court. Allowing the appeals, the Supreme Court
explained that the very purpose of granting immunity under KVSS was to
render the assessee immune from “any criminal proceedings”. The Supreme
Court referred to an earlier decision in Sushila Rani v. CIT (2002) 2 SCC
697 which explained that once the assessee opts for immunity under the
KVSS, “he obtains immediate immunity under any proceeding under any
and all laws in force.” (SCC @ p. 276)
34. In the concurrent judgment, the rationale behind Section 95 of the KVSS
which granted immunity was further explained. Once the assessee was
induced into giving up the proceedings initiated by him against the
Department by withdrawing his appeals, it would be unfair to thereafter
prosecute him under the penal provisions of the IPC. It was observed as
follows (SCC @ p. 282):
“The declarant could not be dragged and chased in criminal
proceedings after closing the other opening making it a dead
end. It is highly unreasonable and arbitrary to do so and
initiation and continuance of such proceedings lack bonafides.”
35. In Nathani Steel Ltd. v. Associated Constructions , the Supreme Court
W.P.(C) No. 11247/2009 Page 21 of 27
pointed out that (SCC @ p. 326-27):
“....once the parties have arrived at a settlement in respect of any
dispute or difference arising under a contract and that dispute or
the difference is amicably settled by way of a final settlement by
and between the parties, unless that settlement is set aside in proper
proceedings, it cannot lie in the mouth of one of the parties to the
settlement to spurn it on the ground that it was a mistake and
proceed to invoke the Arbitration clause. If this is permitted the
sanctity of contract, the settlement also being a contract, would be
wholly lost and it would be open to one party to take the benefit
under the settlement and then to question the same on the ground
of mistake without having the settlement set aside.”
36. There is considerable merit in the submission that the intention of the
NHAI to act on the settlement to drop proceedings to blacklist the BGEL
was evident from its act of awarding contracts on three subsequent occasions
in favour of BGEL. There is no reasonable explanation offered by NHAI for
this. It is plain that BGEL give up its defence towards actions which led to
th
the rescission of the contract dated 9 June 1997 and agreed to make
payment of damages on the assurance that the blacklisting proceedings will
be dropped. In a sense, therefore, by giving up its defence, the BGEL acted
to its detriment and also parted with the amount of damages without demur.
Thereafter to be faced with proceedings for blacklisting cannot but be
termed as an arbitrary action on the part of the NHAI.
37. This Court is not persuaded to hold that the decision by the NHAI not to
blacklist BGEL was opposed to public policy and hit by Section 23 of the
Contract Act. There were cogent reasons discussed at the meeting of the
W.P.(C) No. 11247/2009 Page 22 of 27
th
Board of NHAI at its meeting on 4 August 1998 deciding not to blacklist
BGEL. This was a conscious decision taken after due deliberation. It was
acted upon by both parties. Thereafter, over a period of three years, BGEL
was awarded three contracts by NHAI which were executed to the
satisfaction of NHAI. While, on this aspect, it must be observed that if a
decision had been taken by NHAI not to pursue criminal law remedies, then
it could possibly be argued that it was opposed to public policy. In fact, at a
later stage, an FIR was registered. This court is not called upon to express
any opinion on the proceedings arising out of the said FIR as it is beyond the
scope of the present petition.
CVC’s advice not based on complete facts
38. The justification offered by NHAI that it was only on account of the
report of the CVC that it revived the proceedings for blacklisting is not
th
convincing. A reading of the CVC‟s decision dated 30 October 2002 shows
that the full facts were not in fact placed before the CVC. The relevant
paragraphs of the CVC decision in this regard reads as under:
“D.1 Paras 3.6 and 3.6.2
Those paras are regarding non-recovery of Rs.2,85,18,556/-
from M/s BGE-EJL (JV) who has failed to execute the work.
Neither next lowest tenderer M/s DSC-RBM-PATI has been
negotiated to the level of M/s BGE-EJL (JV) nor recovery has
been made from M/s BGE-EJL (JV). The government has
suffered losses of Rs.2,85,18,556/- and undue favour of this
amount is extended to M/s BGE-EJL (JV).
D.1.3. Comments of the Commission:-
W.P.(C) No. 11247/2009 Page 23 of 27
The basis of the opinion given by the Engineer M/s SMEC is
not given. The NHAI has accepted the views of Engineer to
prevent recoveries of Rs.2,85,18,556/-. This matter was referred
to ADB and ADB advised to the NHAI to initiate steps to
ensure legal consequences of fraudulent action of the
Contractor as the contract was secured in fraudulent manner
(Refer para 3.7 of our report). No legal action has been taken
against BGE-EJL (JV). In spite of failure of M/s BGE-EJL
(JV) to execute the work, the constituent firms are participating
in the tender in NHAI work. Some of the works are executed
by the constituent firms of this JV.
The matter was referred to legal expert of NHAI M/s. Swaroop
and company Advocate also. It was advised to black-list the
joint venture M/s BGE-EJL (JV) but the same has not been
done on flimsy ground that NHAI will be involved in the
litigation. M/s Swaroop & company Advocates in reply to
queries of NHAI has advised the NHAI vide his letter dated
30.05.97 that compensation for losses and damages suffered by
NHAI can be legally recovered from the contractor. Regarding
method of recovery it was advised by M/s Swaroop and
Company Advocates that claim for damages would be for
restoration of NHAI to its original position. It will include…
incurred by NHAI till date to restore NHAI to original
position,… direct increase in the cost of work could also be
claimed. It would have to lodge its claim on M/s BGE-EJL
(JV). If M/s BGE-EJL (JV) disputes the same, reference to
arbitration will have to be made.
From the legal advice of M/s Swaroop & Co. Advocates, it is
clear that direct costs, i.e. difference in tendered cost is
recovered from the contractor BGE-EJL (JV) in order to restore
the NHAI its original position but no recovery has been made.
W.P.(C) No. 11247/2009 Page 24 of 27
The opinion of the Engineer regarding non-recovery of
Rs.2,85,18,556/- is favourable to the contractor and by
accepting… Engineers advice which is contrary to advice of
their legal advice favour has been extended to M/s BGE-EJL
(JV). CVO may identify officials responsible for the above
lapses along with action proposed in addition to the recovery of
Rs.2,85,18,556/- from the contractor M/s Birla GTME.
The constituent partner M/s Birla GMTE is still working as
contractor with NHAI. Jallundur Bye-pass work and some
other works are being executed by the firm. No comments have
been offered on this issue. It may be examined in detail that the
firm which has failed to execute the work and secured the
contract through fraudulent manner is being allowed to
participate in the tender and execute the work and furnish the
considered comments. Officers responsible for the lapse be
identified and responsibility be fixed… Legal action against
M/s BGE-EJL (JV) be also taken for securing the contract in
fraudulent manner and the firm may be black-listed for future
works of NHAI.” (dotted text illegible)
39. The above narration shows that the CVC was not made aware of the full
and final settlement arrived at between the parties or given a copy of the
th
minutes of the meeting of the Board of NHAI held on 4 August 1998. The
CVC was also not told of the fact that acting on such full and final
settlement BGEL had, in fact, paid the quantified damages to NHAI, and
that NHAI had already decided to drop the blacklisting proceedings. NHAI
ought to have drawn the attention of the CVC to the complete facts instead
of making the CVC‟s report as the basis for reviewing its earlier decision
th
dated 4 August 1998. The conduct of the NHAI in this regard cannot be
th
said to be fair or unreasonable. In the show cause notice dated 25 February
W.P.(C) No. 11247/2009 Page 25 of 27
2004 issued to BGEL by NHAI, there is no whisper of the decision taken at
th
the meeting of the Board of Directors on 4 August 1998 which led to the
th
letter dated 28 August 1998 of NHAI.
40. It was sought to be argued by Mr. Sethi that the amount paid by the
BGEL was not towards the losses suffered by NHAI and, therefore, the CVC
was justified in directing revival of the blacklisting proceedings. This Court
th
finds that this was not even the stand of the NHAI in its letter dated 28
August 1998 to BGEL. The intention of the parties clearly was to bring
about a full and final settlement of all disputes. It was impermissible to
revive the demand for costs six years after the settlement.
Delay in initiation of blacklisting proceedings renders it unreasonable
41. No satisfactory explanation has been given by NHAI for initiating
blacklisting proceedings six years after a full and final settlement had been
arrived at. This is further compounded by the fact that after the said
settlement, three contracts were awarded to the BGEL by the NHAI which
BGEL had completed to the satisfaction of NHAI. The cases cited by
learned Senior counsel for the NHAI in the context of disciplinary
proceedings are not apposite. Moreover, in view of the peculiar facts and
circumstances of the present case those decisions are distinguishable. The
argument that no prejudice would be caused on account of the delayed
initiation of the blacklisting proceedings is also not a convincing one. A
blacklisting order severely affects the reputation of a party and by its very
nature is prejudicial to such party. The delay in initiating such proceedings
will certainly be a factor in determining its reasonableness. In the present
W.P.(C) No. 11247/2009 Page 26 of 27
case, the decision of NHAI to blacklist BGEL, six years after the settlement,
cannot be held to be just or fair. It fails to satisfy the test of reasonableness
in light of Article 14 of the Constitution.
42. It was submitted on behalf of the NHAI that even in the proceedings
before the Competent Authority, which led to the impugned order of
blacklisting, BGEL did not deny that it had submitted fabricated documents
with its bid. In the considered view of this Court, BGEL had been consistent
in its stand that it was giving up its defence in respect of the documents
submitted by it together with its bid and this is what had brought about the
full and final settlement. The parties entered into the settlement fully aware
of the legal implications. Neither of them should thereafter be permitted to
resile from such settlement and retract their position in a manner that causes
prejudice to the other party.
43. For the aforementioned reasons, this Court finds the impugned
th
blacklisting order dated 6 January 2008 to be unsustainable in law and it is
hereby set aside.
44. The writ petition is allowed in the above terms with costs of Rs. 10,000/-
which should be paid by the NHAI to the Petitioner within a period of two
weeks from today.
S. MURALIDHAR, J.
JANUARY 31, 2011
RS-akg
W.P.(C) No. 11247/2009 Page 27 of 27