Full Judgment Text
NON-REPORTABLE
IN THE SUPREME COURT OF INDIA
CIVIL APPELATE JURISDICTION
CIVIL APPEAL No. 8207 of 2012
Arising out of SLP (C) No.33409 of 2009)
Shree Om Enterprises Pvt. Ltd. … Appellant
Versus
BSES Rajdhani Power Ltd. … Respondent
J U D G M E N T
RANJAN GOGOI, J
1. Leave granted.
2. The appellant is aggrieved by the dismissal of
JUDGMENT
its suit by the learned trial court which decree
has been affirmed in First appeal as well as by the
High Court in Second Appeal.
3. The plaintiff is a Private Limited Company
engaged in the business of printing of calendars,
Page 1
2
diaries, stationery items, packing materials since
the year 1983 in premises located in A-98/3, Okhla
Industrial Area, Phase II, New Delhi. The plaintiff
| tered as<br>irectora | a sma<br>te of |
|---|
Administration. According to the plaintiff it is
also holding/held a license from the Municipal
Corporation of Delhi for running the unit of
printing press and has been registered under the
Press and Registration of Books Act, 1867 and with
the Registrar of Newspapers for India. The
plaintiff also claims to have been allotted a code
No. by the Reserve Bank of India for the purposes
of import and export of calendars, diaries,
JUDGMENT
booklets, wedding and greeting cards, printing
books, posters and other material etc. printed in
its unit at the premises described above.
4. According to the plaintiff it had been issued
two separate electrical connections bearing No.K
011 1304067 and K 011 1304075 for running the
Page 2
3
printing press. The plaintiff received a letter
dated 06.11.1991 (Ex.P-14) from the Assistant
Engineer, Delhi Electric Supply Undertaking (DESU)
| nspecti<br>aintiff | on was<br>on 14 |
|---|
of electric connection No. K 011 1304067 in the
course of which the connected load was found to be
beyond the maximum permissible sanctioned load of
100 KW for Small Industrial Power Consumers (SIP).
The same had the effect of placing the plaintiff in
the category of large Industrial Power Consumers
(LIP). Accordingly, in the letter dated 06.11.1991
the plaintiff was given an option to remove the
excess load and it was further informed that till
JUDGMENT
then the plaintiff would be billed at the higher
tariff applicable to LIP consumers along with
surcharge, as applicable, under the terms and
conditions of supply. By the letter dated
06.11.1991 the plaintiff was also informed that in
the inspection carried out on 14.06.1991, the power
factor was found to be below the prescribed limit
Page 3
4
as the shunt capacitor had not been installed or
maintained properly. Accordingly, the plaintiff was
also informed that it was liable to pay surcharge
| rate on | the tot |
|---|
5. In the plaint filed it was further stated that
the plaintiff, who had no knowledge of the
aforesaid inspection, received another letter dated
03.12.1991 enclosing a copy of an Inspection Report
dated 14.06.1991 (Ex.P.10). In the said inspection
report details of the machinery found installed in
the premises of the plaintiff for manufacture of
PVC conduit pipes were mentioned. According to the
plaintiff, on 06.01.1992, a common reply to the
JUDGMENT
letters/notices dated 06.11.1991 and 03.12.1991 was
sent claiming that the business of the plaintiff
was printing of calendars, diaries, stationery
items and packing materials; that there was no
manufacture of PVC conduit pipes in its premises
and further that there was no misuse of electricity
and excess of load beyond the sanctioned load or
Page 4
5
installation of inadequate and improper capacitor
as alleged in the notices under reply. However,
according to the plaintiff, despite its reply dated
| 1) a bil<br>for th | l for<br>e peri |
|---|
February, 1992 threatening disconnection on failure
to make payment of the said bill on or before
06.04.1992. It is in these circumstances that the
plaintiff had filed the suit in question on
06.04.1992 seeking a decree of perpetual injunction
restraining the defendants from enforcing the
disconnection notice and from disconnecting power
supply against Meter No. K 011 1304067 installed in
the premises of the plaintiff at A-98/3, Okhla
JUDGMENT
Industrial Area, Phase II, New Delhi.
6. The defendant, namely, General Manager, DESU
filed a written statement in the case stating that
on 14.06.1991 an inspection was carried out in the
premises of the plaintiff which revealed that the
total connected load in the premises was 190 KW
Page 5
6
which is far in excess of the limit for SIP
consumers, i.e., 100 KW. Accordingly, the notices
dated 06.11.1991 and 03.12.1991 along with the
| dated 1<br>of the | 4.06.19<br>reply |
|---|
submitted by the plaintiff, the bill for
Rs.3,38,378.02 was served and disconnection of
electric power to the plaintiff’s premises was
contemplated in the event the plaintiff failed to
pay the bill on or before the due date. In the
written statement filed by defendants it was
categorically stated that machineries for
manufacture of PVC conduit pipes were found
installed in the premises of the plaintiff in the
JUDGMENT
course of inspection held on 14.06.1991. It was
further stated that such inspection was carried out
in the presence of the representative of the
plaintiff – Company.
7. The parties had gone to trial on the aforesaid
pleadings on the basis of which several specific
Page 6
7
issues were framed. The plaintiff’s suit having
been dismissed by all the courts, the present
appeal has been filed contending that the dismissal
| along,<br>dence o | is plai<br>n reco |
|---|
dismissal, ex facie, discloses errors apparent on
the face of the record.
8. We have heard Shri CS Vaidyanathan, learned
senior counsel for the appellant and Shri K.Datta,
learned counsel for the respondent.
9. Learned counsel for the appellant has
elaborately taken us through the pleadings of the
JUDGMENT
parties and the evidence of PW 1- Shri Gobind Ram
Bafna and DW 1- Shri S.S. Gupta. Learned counsel
has submitted that from the evidence of PW 1 it is
clear that no inspection was carried out in the
premises of the plaintiff on 14.06.1991 as claimed
which fact finds support from the evidence of DW 1
who had admitted that he is not aware of the
Page 7
8
identity and status of the person who was present
on behalf of the plaintiff at the time of
inspection. Learned counsel, by referring to the
| by t<br>mitted | he Sal<br>that in |
|---|
certificate the plaintiff was entitled to purchase
raw materials for the purpose of manufacture of,
inter-alia, PVC pipes. The said certificate only
entitled the plaintiff to claim exemption from
sales tax on such purchases and by no means could
be understood to be proof of the fact that the
plaintiff was actually manufacturing PVC pipes in
its premises. Learned counsel has also drawn the
attention of the court to the Balance-sheet and
JUDGMENT
Profit & Loss Account of the plaintiff – Company
enclosed in the Income-tax Return for the year
st
ending 31 March, 1992 to show that no where in the
said documents there is any mention of PVC conduit
pipes which fact would have, in the normal course,
found a mention had the plaintiff Company been
engaged in the business of manufacture of such PVC
Page 8
9
pipes. Learned counsel has also drawn the attention
of the court to the telegram dated 01.04.1992
(Ex.P-12) issued on its behalf whereby the findings
| repor<br>gard to | t of<br>manufa |
|---|
had been categorically denied.
10. Learned counsel for the respondent, on the
other hand, has submitted that the response of the
appellant to the letters/notices dated 6.11.1991
and 3.12.1991 issued by the competent authority of
the DESU are absolutely vague and ambiguous. Apart
from asserting that it was engaged in the business
of manufacture of calendars, diaries, stationery
JUDGMENT
items etc. and denying any misuse of electricity
or exceeding the sanctioned load, the plaintiff in
its reply dated 06.01.1992 had not taken any
specific stand with regard to the findings of the
inspection dated 14.06.1991. The said reply dated
06.01.1992 does not contain any specific reference
to the findings of the inspection regarding
Page 9
10
installation of machineries which are normally used
for manufacture of PVC conduit pipes. The stand
taken on behalf of the plaintiff in the telegram
| Ex.P-12)<br>r as the | was,<br>oral |
|---|
concerned it is submitted that the said witness had
been inconsistent inasmuch as while denying that
any inspection was carried out on 14.06.1991 in his
examination-in-chief, the said witness in cross-
examination had admitted that such an inspection
had taken place. In this regard learned counsel has
pointed out that in the evidence of DW 1 there is a
clear reference to the fact that the representative
of the plaintiff, though present at the time of
JUDGMENT
inspection, had refused to sign the inspection
report. Merely because DW 1 was not aware of the
status of the person representing the plaintiff
Company at the time of inspection, will not cast
any doubt with regard to the holding of the
inspection itself. Lastly, it is submitted that the
plaintiff having exceeded the maximum permissible
Page 10
11
load for SIP consumers was liable for payment of
surcharge and higher tariff in accordance with the
terms and conditions of supply of electric power by
| y, the a<br>ite cap | ppellan<br>acitor |
|---|
pay surcharge as contemplated by the said terms and
conditions of supply. It is on the aforesaid basis
and in accordance with the terms and conditions of
supply that the bill for Rs.3,38.378.02 for the
period 06.06.1991 to February, 1992 was issued with
the contemplation that if the same remained unpaid
on or before 06.04.1992, electric supply to the
premises of the plaintiff would be disconnected.
JUDGMENT
11. We have considered the submissions advanced
before us. We have also perused the pleadings of
the parties and the evidence of PW 1 and also DW 1
as well as the several documents brought on record
including the notices dated 06.11.1991 and
03.12.1991 and the inspection report dated
14.6.1991 sent by the defendant to the plaintiff as
Page 11
12
well as the reply of the plaintiff dated 06.12.91
and the telegram dated 01.04.1992 in this regard.
| tion wh<br>aises w | at we<br>hat i |
|---|
question of fact, namely, whether the Plaintiff had
exceeded the sanctioned load as permissible for SIP
consumers and whether the Plaintiff was responsible
for low load factor as it had not installed the
requisite capacitor. In a situation where three
Courts have already dealt with the aforesaid
question and have recorded concurrent opinions on
the issue, it would be wholly inappropriate for
this Court to go into the same unless an apparent
JUDGMENT
perversity can be, ex-facie, found in the
conclusions reached. It is from the aforesaid
limited perspective that we had persuaded ourselves
to go into the matter. On such consideration we
find that the plaintiff in its reply dated 6.1.1992
submitted in response to the notices issued by the
Defendant on 6.11.1991 and 3.12.1991 had only
Page 12
13
asserted that it is engaged in the manufacture and
printing of calendars etc. and that it had not
exceeded the sanctioned load. There is no positive
| regard<br>ntioned | to th<br>in |
|---|
14.06.1991. Neither any evidence had been led by
the plaintiff to establish that the machinery
mentioned in the inspection note to have been found
installed in its premises were not so installed or
that such machinery was not used or utilized by the
plaintiff for manufacture of PVC conduit pipes. It
was incumbent on the part of the plaintiff, who had
claimed in the suit that the report of inspection
was incorrect, to prove the said facts by means of
JUDGMENT
legally acceptable evidence. No such evidence was
forthcoming, perhaps, because the plaintiff had
taken the stand that no inspection at all was
carried out. Though the plaintiff tried to prove
the said fact i.e. that no inspection took place
through PW 1, the evidence of the said witness on
the aforesaid score is wholly inconsistent. The
Page 13
14
reliance placed on the evidence of DW 1 in this
regard is also somewhat misplaced in as much as DW
1 had clearly stated that he was a member of the
| team wh<br>6.1991 | ich ha<br>and th |
|---|
inspection prepared was refused to be signed by the
plaintiff’s representative though he was present at
the time of inspection. The mere inability of the
DW 1 to specify the status of the plaintiff’s
representative present at the site would not, in
any way, affect the credibility of the fact that an
inspection was, infact, carried out. It has also
to be noticed that the specific denial with regard
to the business of manufacture of PVC conduit pipes
JUDGMENT
in the premises of the plaintiff had come only in
the telegram dated 01.04.1992 sent by the advocate
representing the plaintiff. In the absence of any
clear stand to the above effect in the reply of the
plaintiff dated 6.12.1991, the subsequent plea put
forth in the telegram dated 01.04.1992 must be
understood to be an after thought on the part of
Page 14
15
the plaintiff and the result of an attempt to
improve its case through its counsel.
| scussio<br>the pr | ns comp<br>esent c |
|---|
was given an option to remove the excess load
failing which it was made clear it will be charged
at the higher rate of tariff. We have also found
that the bill for Rs.3,38.378.02 for the period
06.06.1991 to February 1992 was prepared and
submitted for payment by the plaintiff in
accordance with the terms and conditions of supply
in force in the DESU and that the said bill was
prepared after consideration of the stand taken by
JUDGMENT
the plaintiff in its reply dated 06.01.1992. No
infirmity or illegality is disclosed in any of the
actions of the defendant infringing any known right
of the plaintiff so as to entitle it to a decree of
perpetual injunction as prayed for.
Page 15
16
13. For all the aforesaid reasons we find no merit
whatsoever in this appeal. It is accordingly
dismissed and the judgment and order dated
| High Cou | rt of D |
|---|
................J.
[P.SATHASIVAM]
................J.
[RANJAN GOGOI]
New Delhi,
November 22,2012
JUDGMENT
Page 16