REPORTABLE
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
Civil Appeal No. 5627 of 2021
(Arising out of SLP (C) No. 4115 of 2019)
Delhi Airport Metro Express Pvt. Ltd.
.... Appellant(s)
Versus
Delhi Metro Rail Corporation Ltd.
…. Respondent (s)
W I T H
Civil Appeal No. 5628 of 2021
(Arising out of SLP (C) No. 8311 of 2019)
J U D G M E N T
L. NAGESWARA RAO, J.
Leave granted.
1. Whether in exercise of its power under Section 37 of
the Arbitration and Conciliation Act, 1996 (hereinafter, ‘the
1996 Act’), the Division Bench of the Delhi High Court was
right in interfering with the award dated 11.05.2017 passed
by the Arbitral Tribunal in favour of the Appellant - Delhi
1 | P a g e
Airport Metro Express Pvt. Ltd. (hereinafter, ‘DAMEPL’ or the
‘Concessionaire’), is the question that arises for
consideration in these Appeals.
2. Delhi Metro Rail Corporation Ltd. (hereinafter, ‘DMRC’),
a joint venture of the Government of India and the
Government of National Capital Territory of Delhi, proposed
implementation of the Airport Metro Express Line project in
New Delhi, from New Delhi Railway Station to Dwarka Sector
21 via Indira Gandhi International Airport, New Delhi
(hereinafter, ‘AMEL’). The approximate length of the project
was 22.7 kilometers. It was decided to develop the project
by engaging a concessionaire for financing, design,
procurement, installation of all systems (including but not
limited to rolling stock, overhead electrification, track,
signaling and telecommunication, ventilation and air
conditioning, automatic fare collection, baggage check-in and
handling, depot and other facilities). DMRC had to
undertake design and construction of basic civil structure for
the project, which was in the nature of a public private
partnership.
3. The bid of a consortium comprising Reliance Energy
Limited (renamed as Reliance Infrastructure Limited) and M/s
Construcciones y Auxiliar de Ferrocarriles, S.A. was accepted
2 | P a g e
by DMRC, by issuing a letter of acceptance on 21.01.2008.
Thereafter, on 25.08.2008, a Concession Agreement was
entered into between DMRC and DAMEPL for design,
installation, commissioning, operation and maintenance of
the AMEL. It was agreed between the parties that all civil
works as well as appointment of consultants, land acquisition
and other clearances from the Government and other
authorities have to be obtained by DMRC and the design,
supply, installation, testing and commissioning of various
systems like rolling stock, power supply, overhead
equipment, signalling, track system, platform, screen doors,
ventilation, architectural finishing etc. were to be provided by
DAMEPL. As the work could not be completed in time,
extensions were granted and finally, safety clearances were
obtained from the Commissioner of Metro Railway Safety
(hereinafter, the ‘CMRS’ or ‘Commissioner’) on 10.01.2011.
The date of commercial operation was achieved on
23.02.2011.
4. On 22.03.2012, DAMEPL requested DMRC for a joint
inspection of viaduct and its bearings before expiry of the
defect liability period of the civil contractors. Another letter
was written by DAMEPL on 23.05.2012, complaining of issues
relating to the design and quality in the installation of viaduct
3 | P a g e
bearings. It was mentioned in the said letter that there were
signs of girders having sunk at some locations as a result of
deformations/cracks. DMRC responded to the said letter of
DAMEPL on 08.06.2012 by which DAMEPL was informed that
inspections were carried out at the locations pointed out by
DAMEPL and no bearings were found damaged. However,
DMRC admitted that grouting material filled above/below the
bearings was damaged/loosened for which action would be
taken to repair them on priority. Due to the said defects,
DMRC advised DAMEPL to impose speed restrictions as
deemed necessary in the interest of safety.
5. The Ministry of Urban Development, Government of
India convened a meeting of all the stakeholders on
02.07.2012. The views of all the parties relating to the
defects were obtained and a Joint Inspection Committee was
formed. An interim report was submitted by the Joint
th th
Inspection Committee after inspection on 4 & 5 July, 2012.
Subsequently, DAMEPL stopped operations of the Line on
08.07.2012.
6. A notice was issued by DAMEPL on 09.07.2012, asking
DMRC to cure the defects in DMRC’s works within a period of
90 days from the date of the notice, failing which it shall be
treated as a breach having Material Adverse Effect on the
4 | P a g e
Concessionaire under the Concession Agreement. In the said
notice dated 09.07.2012, ‘a non-exhaustive list of defects’
was set out by DAMEPL. Thereafter, a number of meetings
were conducted between the parties which were attended by
SYSTRA, the original design consultant for the viaduct
sections. It appears from the record that DMRC had also
engaged some other agencies for carrying out the repair
work.
7. DAMEPL issued a notice dated 08.10.2012 terminating
the Concession Agreement as, according to it, the defects
that were pointed out in the notice dated 09.07.2012 were
not cured within a period of 90 days, resulting in an Event of
Default under the Concession Agreement. DMRC invoked
arbitration under Article 36.2 of the Concession Agreement
on 23.10.2012. On 22.01.2013, the Line was restarted with
reduced speed after a certificate sanctioning resumption was
issued by the Commissioner on 18.01.2013. According to
DAMEPL, it agreed to operate the Line only as an agent in
public interest and on instructions of DMRC, although
DAMEPL’s stance was not accepted by DMRC. DAMEPL
stopped its operations on 30.06.2013 and handed over the
Line to DMRC on the next day.
5 | P a g e
8. At this stage, it is relevant to refer to Article 36 of the
Concession Agreement which refers to dispute resolution.
Article 36.2.2, read with Article 36.2.3, provides that all
disputes, whatsoever arising between the parties, out of,
touching upon or relating to construction, measuring,
operation or effect of the Concession Agreement or the
breach thereof, shall be settled through arbitration by
reference to a sole arbitrator, where the total value of claims
do not exceed Rs.1,500,000/-. Beyond this limit, the dispute
shall be referred to three arbitrators who will be selected
from a panel of engineers with requisite qualifications and
professional experience relevant in the field to which the
Concession Agreement relates. The panel shall be from
serving or retired engineers of government departments or of
public sector.
9. The main issue that arose for determination before the
Arbitral Tribunal constituted under the Concession Agreement
is the validity of the termination notice dated 08.10.2012.
DMRC claimed that the termination notice issued by DAMEPL
is illegal, as DMRC had taken various steps honouring its
obligations under the Concession Agreement. A direction
was sought from the Arbitral Tribunal to DAMEPL to take over
operations of the AMEL under the Concession Agreement,
6 | P a g e
and in the alternative, to grant compensation of Rs.3,173
crore with interest of 18% per annum. Further monetary
reliefs were sought by DMRC. The claim of compensation
sought by DMRC was dependent on the determination of the
main issue, i.e., the validity of the termination notice dated
08.10.2012. DMRC also raised an issue on the real motive of
DAMEPL to terminate the Concession Agreement. DAMEPL
justified the termination as being in conformity with the
Concession Agreement and consequently, filed a counter
claim seeking an amount of Rs.3,470 crore as termination
payment along with interest and further amounts as detailed
in the counter claim, on the ground that DMRC did not cure
the defects in the civil structure in terms of the cure notice
dated 09.07.2012. As DMRC did not comply with its
obligations under Article 29.5.1(i), DAMEPL justified the
termination notice dated 08.10.2012 and the consequent
claim of termination payment from DMRC under Article
29.5.2.
10. The Arbitral Tribunal formulated the following primary
issues for consideration in relation to the termination notice
dated 08.10.2012: -
“i) Were there any defects in the civil structure of the
airport metro line?
7 | P a g e
(ii) If there were defects, did such defects have a
material adverse effect on the performance of the
obligation of DAMEPL under CA?
(iii) If there were defects in the civil structure, which
had a material adverse effect on the performance of
the obligations under the CA by DAMEPL, have such
defects been cured by DMRC and / or have any
effective steps been taken within a period of 90 days
from the date of notice by DAMEPL to cure the defects
by DMRC and thus were DMRC in breach of the CA as
per 29.5.1 (i)?”
11. In assessing whether the defects pointed out by
DAMEPL were cured and/or effective steps to cure them were
taken by DMRC within the time stipulated in the notice dated
09.07.2012, the Arbitral Tribunal undertook an in-depth
analysis of the defects in the civil structure and steps taken
for their repair/rectification. Insofar as the existence of
defects is concerned, the Arbitral Tribunal concluded that
there were as many as 1551 cracks in 367 girders, i.e., 72 %
of the girders were affected by such cracks. Reports of
inspections conducted at the behest of DMRC, giving
mapping data of the cracks, were relied upon by the Tribunal
to hold that such cracks were spread in a large number of
8 | P a g e
girders. The Tribunal referred to the meeting dated
02.07.2012 conducted by the Ministry of Urban Development
during which the Managing Director, DMRC expressed his
views that the cracks occurred during “lowering” and not
during operations. The evidence of Mr. Muls of Systra was
considered by the Arbitral Tribunal to hold that they were not
sure of the cause of the cracks. On account of such large
numbers of cracks in the base slab of the pre-stressed
concrete girders in about a year of train operation, coupled
with unreliable measurement of crack depth and non-serious
inspection of the repairs by an agency appointed by DMRC,
the Arbitral Tribunal was of the opinion that these defects
adversely impacted the integrity of the structure. As
effective steps were not taken within the cure period of 90
days, the Tribunal held that DMRC was in breach of the
Concession Agreement, resulting in Material Adverse Effect
on the Concessionaire.
12. As far as twist in the girders were concerned, the
Arbitral Tribunal found that there were about 80 girders with
twists varying between 10 to 20 mm which had not been
rectified and no effective steps were taken to cure the
defects in such girders. The defects pointed out by DAMEPL
regarding gaps between the shear key and the girder being
9 | P a g e
more than 25 mm and between 10 mm to 25 mm were not
addressed and only gaps below 10 mm were addressed by
some grinding, detailed methodology for which was not
brought out by DMRC in its evidence, as per the findings of
the Arbitral Tribunal. Therefore, the Tribunal concluded that
these defects were neither cured nor effective steps taken by
DMRC within the cure period up to 08.10.2012, constituting a
material breach on the part of DMRC. On the basis of the
above findings and findings in relation to other defects,
deficiencies and constraints in the civil structure of the AMEL
which are not referred to herein, the Arbitral Tribunal
concluded that the defects had not been cured within the
cure period of 90 days from 09.07.2012 nor had effective
steps been taken to cure such defects. Ergo, the termination
notice issued by DAMEPL on 08.10.2012 was valid.
13. Having decided on the validity of the termination
notice, the Tribunal went on to consider certain legal issues
so as to determine questions around specific performance of
the contract, or alternatively, the award of damages and the
outcome of the counter claim filed by DAMEPL. One such
issue considered by the Arbitral Tribunal was whether the
issue of certificate by the Commissioner on 18.01.2013,
giving clearance for resuming operations of the AMEL,
10 | P a g e
showed that the defects were duly cured. After examining
the certificate issued by the Commissioner, the Arbitral
Tribunal held that while the Commissioner had sanctioned
resumption of services, certain conditions were imposed,
essentially relating to the restriction of speed up to 50 km
per hour, which had a material bearing on the prime purpose
of the AMEL intended to serve as a high-speed connectivity
line. Moreover, the Commissioner himself recognized that the
operation of the Line had to be regularly monitored. The
subsequent operation of the Line by DMRC was found to be
not relevant for determining the validity of the termination
notice dated 09.07.2012. The Arbitral Tribunal answered this
issue in favour of DAMEPL. On consideration of the counter
claim of DAMEPL, the principal issue that came up before the
Arbitral Tribunal was on determination of the amount of
Termination Payment payable by DMRC under the Concession
Agreement. In this regard, the Tribunal had to determine the
quantum payable under each component of Termination
Payment, one of which was ‘Adjusted Equity’. DAMEPL
sought payment of an amount of Rs.3,470 crore as
Termination Payment. In this total, an amount of Rs.685
crore, which had been infused by DAMEPL’s promoter, was
factored in by DAMEPL for the purposes of calculating
11 | P a g e
‘Adjusted Equity’. Relying on the relevant clauses of the
Concession Agreement, the Tribunal first sought to determine
the portion of funds that would qualify as ‘Equity’ under the
Concession Agreement, which would then be used for
arriving at the figure of ‘Adjusted Equity’. Out of Rs.685 crore
which was sought to be slotted under the head ‘Equity’ by
DAMEPL, an amount of Rs.611.95 crore was determined to be
‘Equity’ by the Tribunal, on the basis of the evidence
produced and the construction of the relevant provisions of
the Concession Agreement. Thereafter, the Tribunal worked
out ‘Adjusted Equity’ at Rs.983.02 crore and awarded a total
amount of Rs.2782.33 crore, along with further interest, as
Termination Payment to be made to DAMEPL.
14. DMRC filed a petition under Section 34 of the 1996 Act
for setting aside the award of the Arbitral Tribunal dated
11.05.2017 in the Delhi High Court, which was dismissed by
the learned Single Judge of the High Court by a judgement
dated 06.03.2018 observing that grounds for interference
had not been made out by DMRC. The learned Single Judge
held that the findings recorded by the Arbitral Tribunal on
facts, law and interpretation of the Concession Agreement
were all within the realm of the Arbitral Tribunal and they
needed no intervention by the Court exercising its power
12 | P a g e
under Section 34 of the 1996 Act. He was also of the view
that the Court cannot substitute its view when there are two
views possible and the view taken by the Arbitral Tribunal is a
plausible one.
15. DMRC filed an appeal under Section 37 of the 1996 Act
read with Section 13 of the Commercial Courts, Commercial
Division and Commercial Appellate Division of High Courts
Act, 2015 (the title since amended to Commercial Courts Act,
2015), challenging the correctness of the judgment passed
by the learned Single Judge on 06.03.2018 dismissing the
objections filed by DMRC under Section 34 of the 1996 Act.
The Division Bench reversed the judgement of the learned
Single Judge and allowed the appeal filed by DMRC. The
award passed by the Arbitral Tribunal was partly set aside.
The parties were left to invoke the arbitration clause for
adjudication of the issues that were not decided by the
Division Bench. The judgement of the Division Bench dated
15.01.2019 is assailed in these Appeals.
16. DMRC has also filed SLP (C) No.8311 of 2019
challenging the correctness of the aforesaid judgement of the
Division Bench in relation to the issues of grant of interest,
waiver of the termination notice due to DAMEPL’s conduct of
operating the project for more than five months from
13 | P a g e
22.01.2013, refusal by the Division Bench to grant relief of
specific performance of the Concession Agreement and non-
consideration of the issue pertaining to the real reason for
the termination of the Concession Agreement by DAMEPL.
Reasons given by the Division Bench for setting aside
the award
17. The Division Bench of the High Court held that the
award of the Arbitral Tribunal had recorded two different
termination dates. As the Tribunal had based its reasoning on
the validity of the termination notice on two different dates
leading to confusion and ambivalence as to the termination
notice and the date of termination, the award was found to
be suffering from the vices of perversity, irrationality and
patent illegality. The High Court observed that in deciding
the question on defects in the civil structure and whether
effective steps were taken to cure the defects, the Arbitral
Tribunal had committed serious error by holding, without
‘reason’, that the vital evidence of the sanction granted by
the CMRS for resumption of commercial operations of the
AMEL and the fact that DMRC had successfully operated the
AMEL from 30.06.2013 till the date of the award without any
adverse incident were inconsequential. The High Court found
14 | P a g e
fault with the Arbitral Tribunal in virtually negating the
certificate issued by the CMRS under the Delhi Metro Railway
(Operation and Maintenance) Act, 2002 (hereinafter, ‘the
Delhi Metro Act’) and held that the cumulative effect of the
findings of the award on this issue ‘shocked the conscience
of the court’.
18. On the issue of Adjusted Equity, while considering the
approach taken by the Arbitral Tribunal for computation of
the amounts payable under Article 29.5.2, the High Court
was of the opinion that the Tribunal’s reasoning was
completely flawed and perverse. The High Court ruled that
the reasoning adopted by the Tribunal was patently illegal
and the conclusion reached after doing so, was one which no
reasonable person would have come to. According to the
High Court, the treatment of Rs.611.95 crore as ‘Equity’ by
the Tribunal, on the ground that such a project could not
have been executed with only Rs.1 lakh as equity funded by
DAMEPL’s promoter (in terms of share capital), was based on
an assumption that the debt-to-equity ratio is commonly
60:40 or 80:20, contrary to the evidence on record. This was
held to be an egregious mistake committed by the Tribunal.
The High Court also found fault with the award which ignored
the resolution passed by the board of directors of DAMEPL on
15 | P a g e
16.03.2011, by which the amount of Rs. 611.95 crore was
converted to subordinated debt. The High Court held that
‘Adjusted Equity’ under the Concession Agreement does not
contemplate funds recognized as subordinated debt to be
treated as ‘Equity’. With respect to the interpretation of
the various provisions of the Concession Agreement and the
resultant conclusions on ‘Adjusted Equity’, the High Court
held that the findings of the Tribunal on this issue were in
violation of Sections 28(1)(a) and 28(3) of the 1996 Act, as
elaborated in Associate Builders v. Delhi Development
1
Authority , as contractual provisions had been interpreted
in a way no fair-minded and reasonable person would.
19. In light of the reasons mentioned, the High Court set
aside the conclusions of the Arbitral Tribunal on the validity
of the termination notice and that Rs.611.95 crore was
‘Equity’ for the purpose of Article 29.5.2 of the Concession
Agreement. Consequently, the award of Rs.2,782.33 crore to
DAMEPL was set aside. In view of the above findings, the
High Court considered the direction for payment of interest
to have become infructuous. The High Court felt that it
would be inappropriate to hear the parties on the issue of
restitution at that stage and granted liberty to the parties to
1 (2015) 3 SCC 49
16 | P a g e
move appropriate applications under the 1996 Act to seek
remedies available to them.
Contours of the Court’s power to review arbitral
awards
20. The 1996 Act was enacted to consolidate and amend
the law relating to domestic arbitration, international
commercial arbitration and enforcement of foreign arbitral
awards and also to define the law relating to conciliation and
for matters connected therewith, by taking into account the
United Nations Commission on International Trade Law
(UNCITRAL) Model Law on International Commercial
Arbitration and the UNCITRAL Conciliation Rules. One of the
principal objectives of the 1996 Act is to minimize the
supervisory role of courts in the arbitral process. With
respect to Part I of the 1996 Act, Section 5 imposes a bar on
intervention by a judicial authority except where provided
for, notwithstanding anything contained in any other law for
the time being in force. An application for setting aside an
arbitral award can only be made in accordance with
provisions of Section 34 of the 1996 Act. Relevant
provisions of Section 34 (as they were prior to the Arbitration
and Conciliation (Amendment) Act, 2015) read as under:-
17 | P a g e
“ 34. Application for setting aside arbitral award.
— (1) Recourse to a Court against an arbitral award
may be made only by an application for setting aside
such award in accordance with sub-section (2) and sub-
section (3).
(2) An arbitral award may be set aside by the Court
only if—
(a) the party making the application furnishes proof
that—
(i) a party was under some incapacity, or
(ii) the arbitration agreement is not valid under
the law to which the parties have subjected it or,
failing any indication thereon, under the law for
the time being in force; or
(iii) the party making the application was not
given proper notice of the appointment of an
arbitrator or of the arbitral proceedings or was
otherwise unable to present his case; or
(iv) the arbitral award deals with a dispute not
contemplated by or not falling within the terms of
the submission to arbitration, or it contains
decisions on matters beyond the scope of the
submission to arbitration:
Provided that, if the decisions on matters
submitted to arbitration can be separated from
those not so submitted, only that part of the
arbitral award which contains decisions on
matters not submitted to arbitration may be set
aside; or
(v) the composition of the arbitral tribunal or the
arbitral procedure was not in accordance with the
agreement of the parties, unless such agreement
18 | P a g e
was in conflict with a provision of this Part from
which the parties cannot derogate, or, failing such
agreement, was not in accordance with this Part;
or
(b) the Court finds that—
(i) the subject-matter of the dispute is not capable
of settlement by arbitration under the law for the
time being in force, or
(ii) the arbitral award is in conflict with the public
policy of India.
Explanation.—Without prejudice to the generality
of sub-clause (ii), it is hereby declared, for the
avoidance of any doubt, that an award is in conflict
with the public policy of India if the making of the
award was induced or affected by fraud or corruption
or was in violation of section 75 or section 81.
…”
21. An amendment was made to Section 34 of the 1996 Act
by the Arbitration and Conciliation (Amendment) Act, 2015
(hereinafter, ‘the 2015 Amendment Act’). A perusal of the
statement of objects and reasons of the 2015 Amendment
Act would disclose that the amendment to the 1996 Act
became necessary in view of the interpretation of the
provisions of the 1996 Act by courts in certain cases which
had resulted in delay of disposal of arbitration proceedings
and increase in interference by courts in arbitration matters,
which had the tendency to defeat the object of the 1996 Act.
19 | P a g e
Initially, the matter was referred to the Law Commission of
India to review the shortcomings in the 1996 Act in detail.
th
The Law Commission of India submitted its 176 Report,
recommending various amendments to the 1996 Act.
However, the Justice Saraf Committee on Arbitration
constituted by the Government, was of the view that the
proposed amendments gave room for substantial
intervention by the court and were also contentious.
Thereafter, on reference, the Law Commission undertook a
comprehensive study of the amendments proposed by the
Government, keeping in mind the views of the Justice Saraf
th
Committee and other stakeholders. The 246 Report of the
Law Commission was submitted on 05.08.2014. Acting on
the recommendations made by the Law Commission in its
th
246 Report, amendments by way of the 2015 Amendment
Act were made to several provisions of the 1996 Act,
including Section 34. The amended Section 34 reads as
under: -
“ 34. Application for setting aside arbitral award.
— (1) Recourse to a Court against an arbitral award
may be made only by an application for setting aside
such award in accordance with sub-section (2) and sub-
section (3).
20 | P a g e
(2) An arbitral award may be set aside by the Court
only if—
(a) the party making the application furnishes proof
that—
(i) a party was under some incapacity, or
(ii) the arbitration agreement is not valid under
the law to which the parties have subjected it or,
failing any indication thereon, under the law for
the time being in force; or
(iii) the party making the application was not
given proper notice of the appointment of an
arbitrator or of the arbitral proceedings or was
otherwise unable to present his case; or
(iv) the arbitral award deals with a dispute not
contemplated by or not falling within the terms of
the submission to arbitration, or it contains
decisions on matters beyond the scope of the
submission to arbitration:
Provided that, if the decisions on matters
submitted to arbitration can be separated from
those not so submitted, only that part of the
arbitral award which contains decisions on
matters not submitted to arbitration may be set
aside; or
(v) the composition of the arbitral tribunal or the
arbitral procedure was not in accordance with the
agreement of the parties, unless such agreement
was in conflict with a provision of this Part from
which the parties cannot derogate, or, failing such
agreement, was not in accordance with this Part;
or
(b) the Court finds that—
21 | P a g e
(i) the subject-matter of the dispute is not capable
of settlement by arbitration under the law for the
time being in force, or
(ii) the arbitral award is in conflict with the public
policy of India.
Explanation 1. —For the avoidance of any doubt, it is
clarified that an award is in conflict with the public
policy of India, only if,—
(i) the making of the award was induced or
affected by fraud or corruption or was in violation
of section 75 or section 81; or
(ii) it is in contravention with the fundamental
policy of Indian law; or
(iii) it is in conflict with the most basic notions of
morality or justice.
Explanation 2. —For the avoidance of doubt, the test
as to whether there is a contravention with the
fundamental policy of Indian law shall not entail a
review on the merits of the dispute.
(2-A) An arbitral award arising out of arbitrations other
than international commercial arbitrations, may also be
set aside by the Court, if the Court finds that the award
is vitiated by patent illegality appearing on the face of
the award:
Provided that an award shall not be set aside
merely on the ground of an erroneous application of the
law or by re-appreciation of evidence.
…”
22. A cumulative reading of the UNCITRAL Model Law and
Rules, the legislative intent with which the 1996 Act is made,
Section 5 and Section 34 of the 1996 Act would make it clear
22 | P a g e
that judicial interference with the arbitral awards is limited to
the grounds in Section 34. While deciding applications filed
under Section 34 of the Act, courts are mandated to strictly
act in accordance with and within the confines of Section 34,
refraining from appreciation or re-appreciation of matters of
fact as well as law. (See: Uttarakhand Purv Sainik Kalyan
2
Nigam Limited. v. Northern Coal Field Limited. ,
Bhaven Construction Through Authorised Signatory
Premjibhai K. Shah v. Executive Engineer Sardar
3
Sarovar Narmada Nigam Ltd. and Another and
Rashtriya Ispat Nigam Limited v. Dewan Chand Ram
4
Saran ).
23. For a better understanding of the role ascribed to courts
in reviewing arbitral awards while considering applications
filed under Section 34 of the 1996 Act, it would be relevant to
refer to a judgment of this Court in Ssangyong
Engineering and Construction Company Limited v.
5
National Highways Authority of India (NHAI) wherein
R.F. Nariman, J. has in clear terms delineated the limited area
for judicial interference, taking into account the amendments
brought about by the 2015 Amendment Act. The relevant
2 (2020) 2 SCC 455
3 2021 SCC OnLine SC 8
4 (2012) 5 SCC 306
5 (2019) 15 SCC 131
23 | P a g e
passages of the judgment in Ssangyong (supra) are noted
as under: -
| “ | 34. | | What is clear, therefore, is that the expression |
|---|
“public policy of India”, whether contained in
Section 34 or in Section 48, would now mean the
“fundamental policy of Indian law” as explained in
| paras 18 and 27 of | | Associate Builders | | [Associate |
|---|
| Builders | | v. | | DDA, (2015) 3 SCC 49: (2015) 2 SCC |
|---|
(Civ) 204] i.e. the fundamental policy of Indian law
would be relegated to “Renusagar” understanding
of this expression. This would necessarily mean
| that | | Western Geco | | [ONGC | | v. | | Western Geco |
|---|
International Ltd., (2014) 9 SCC 263 : (2014) 5 SCC
(Civ) 12] expansion has been done away with. In
| short | , | Western Geco | | [ONGC | | v | . | Western Geco |
|---|
International Ltd., (2014) 9 SCC 263 : (2014) 5 SCC
(Civ) 12] ,as explained in paras 28 and 29
| of | | Associate Builders | | [Associate Builders | | v. | | DDA, |
|---|
(2015) 3 SCC 49 : (2015) 2 SCC (Civ) 204] , would
no longer obtain, as under the guise of interfering
with an award on the ground that the arbitrator has
not adopted a judicial approach, the Court's
intervention would be on the merits of the award,
which cannot be permitted post amendment.
However, insofar as principles of natural justice are
concerned, as contained in Sections 18 and 34(2)
(a)(iii) of the 1996 Act, these continue to be
grounds of challenge of an award, as is contained
| in para 30 of | | Associate Builders | | [Associate |
|---|
24 | P a g e
| Builders | | v. | | DDA, (2015) 3 SCC 49 : (2015) 2 SCC |
|---|
(Civ) 204] .
| 35. | | It is important to notice that the ground for |
|---|
interference insofar as it concerns “interest of
India” has since been deleted, and therefore, no
longer obtains. Equally, the ground for interference
on the basis that the award is in conflict with
justice or morality is now to be understood as a
conflict with the “most basic notions of morality or
justice”. This again would be in line with paras 36
| to 39 of | | Associate Builders | | [Associate |
|---|
| Builders | | v. | | DDA, (2015) 3 SCC 49 : (2015) 2 SCC |
|---|
(Civ) 204] , as it is only such arbitral awards that
shock the conscience of the court that can be set
aside on this ground.
| 36. | | Thus, it is clear that public policy of India is |
|---|
now constricted to mean firstly, that a domestic
award is contrary to the fundamental policy of
Indian law, as understood in paras 18 and 27
| of | | Associate Builders | | [Associate Builders | | v. | | DDA, |
|---|
(2015) 3 SCC 49: (2015) 2 SCC (Civ) 204], or
secondly, that such award is against basic notions
of justice or morality as understood in paras 36 to
| 39 of | | Associate Builders | | [Associate Builders | | v. | | DDA, |
|---|
(2015) 3 SCC 49 : (2015) 2 SCC (Civ) 204] .
Explanation 2 to Section 34(2)(b)(ii) and
Explanation 2 to Section 48(2)(b)(ii) was added by
| the Amendment Act only so that | | Western |
|---|
| Geco | | [ONGC | | v. | | Western Geco International Ltd., |
|---|
25 | P a g e
(2014) 9 SCC 263 : (2014) 5 SCC (Civ) 12] ,as
| understood in | | Associate Builders | | [Associate |
|---|
| Builders | | v. | | DDA, (2015) 3 SCC 49 : (2015) 2 SCC |
|---|
(Civ) 204] , and paras 28 and 29 in particular, is
now done away with.
| 37. | | Insofar as domestic awards made in India are |
|---|
concerned, an additional ground is now available
under sub-section (2-A), added by the Amendment
Act, 2015, to Section 34. Here, there must be
patent illegality appearing on the face of the
award, which refers to such illegality as goes to the
root of the matter but which does not amount to
mere erroneous application of the law. In short,
what is not subsumed within “the fundamental
policy of Indian law”, namely, the contravention of
a statute not linked to public policy or public
interest, cannot be brought in by the backdoor
when it comes to setting aside an award on the
ground of patent illegality.
| 38. | | Secondly, it is also made clear that |
|---|
reappreciation of evidence, which is what an
appellate court is permitted to do, cannot be
permitted under the ground of patent illegality
appearing on the face of the award.
| 39. | | To elucidate, para 42.1 of | | Associate |
|---|
| Builders | | [Associate Builders | | v. | | DDA, (2015) 3 SCC |
|---|
49 : (2015) 2 SCC (Civ) 204] , namely, a mere
contravention of the substantive law of India, by
itself, is no longer a ground available to set aside
26 | P a g e
| an arbitral award. Para 42.2 of | | Associate |
|---|
| Builders | | [Associate Builders | | v. | | DDA, (2015) 3 SCC |
|---|
49 : (2015) 2 SCC (Civ) 204] , however, would
remain, for if an arbitrator gives no reasons for an
award and contravenes Section 31(3) of the 1996
Act, that would certainly amount to a patent
illegality on the face of the award.
| 40. | | The change made in Section 28(3) by the |
|---|
Amendment Act really follows what is stated in
| paras 42.3 to 45 in | | Associate Builders | | [Associate |
|---|
| Builders | | v. | | DDA, (2015) 3 SCC 49 : (2015) 2 SCC |
|---|
(Civ) 204] , namely, that the construction of the
terms of a contract is primarily for an arbitrator to
decide, unless the arbitrator construes the contract
in a manner that no fair-minded or reasonable
person would; in short, that the arbitrator's view is
not even a possible view to take. Also, if the
arbitrator wanders outside the contract and deals
with matters not allotted to him, he commits an
error of jurisdiction. This ground of challenge will
now fall within the new ground added under
Section 34(2-A).
| 41. | | What is important to note is that a decision |
|---|
which is perverse, as understood in paras 31 and
| 32 of | | Associate Builders | | [Associate Builders | | v. | | DDA, |
|---|
(2015) 3 SCC 49 : (2015) 2 SCC (Civ) 204] , while
no longer being a ground for challenge under
“public policy of India”, would certainly amount to a
patent illegality appearing on the face of the
27 | P a g e
award. Thus, a finding based on no evidence at all
or an award which ignores vital evidence in arriving
at its decision would be perverse and liable to be
set aside on the ground of patent illegality.
Additionally, a finding based on documents taken
behind the back of the parties by the arbitrator
would also qualify as a decision based on no
evidence inasmuch as such decision is not based
on evidence led by the parties, and therefore,
| would also have to be characterised as perverse. | ” |
|---|
24. This Court has in several other judgments interpreted
Section 34 of the 1996 Act to stress on the restraint to be
shown by courts while examining the validity of the arbitral
awards. The limited grounds available to courts for
annulment of arbitral awards are well known to legally
trained minds. However, the difficulty arises in applying the
well-established principles for interference to the facts of
each case that come up before the courts. There is a
disturbing tendency of courts setting aside arbitral awards,
after dissecting and reassessing factual aspects of the cases
to come to a conclusion that the award needs intervention
and thereafter, dubbing the award to be vitiated by either
perversity or patent illegality, apart from the other grounds
available for annulment of the award. This approach would
lead to corrosion of the object of the 1996 Act and the
28 | P a g e
endeavours made to preserve this object, which is minimal
judicial interference with arbitral awards. That apart, several
judicial pronouncements of this Court would become a dead
letter if arbitral awards are set aside by categorising them as
perverse or patently illegal without appreciating the contours
of the said expressions.
25. Patent illegality should be illegality which goes to the
root of the matter. In other words, every error of law
committed by the Arbitral Tribunal would not fall within the
expression ‘patent illegality’. Likewise, erroneous application
of law cannot be categorised as patent illegality. In addition,
contravention of law not linked to public policy or public
interest is beyond the scope of the expression ‘patent
illegality’. What is prohibited is for courts to re-appreciate
evidence to conclude that the award suffers from patent
illegality appearing on the face of the award, as courts do not
sit in appeal against the arbitral award. The permissible
grounds for interference with a domestic award under
Section 34(2-A) on the ground of patent illegality is when the
arbitrator takes a view which is not even a possible one, or
interprets a clause in the contract in such a manner which no
fair-minded or reasonable person would, or if the arbitrator
commits an error of jurisdiction by wandering outside the
29 | P a g e
contract and dealing with matters not allotted to them. An
arbitral award stating no reasons for its findings would make
itself susceptible to challenge on this account. The
conclusions of the arbitrator which are based on no evidence
or have been arrived at by ignoring vital evidence are
perverse and can be set aside on the ground of patent
illegality. Also, consideration of documents which are not
supplied to the other party is a facet of perversity falling
within the expression ‘patent illegality’.
26. Section 34 (2) (b) refers to the other grounds on which
a court can set aside an arbitral award. If a dispute which is
not capable of settlement by arbitration is the subject-matter
of the award or if the award is in conflict with public policy of
India, the award is liable to be set aside. Explanation (1),
amended by the 2015 Amendment Act, clarified the
expression ‘public policy of India’ and its connotations for the
purposes of reviewing arbitral awards. It has been made
clear that an award would be in conflict with public policy of
India only when it is induced or affected by fraud or
corruption or is in violation of Section 75 or Section 81 of the
1996 Act, if it is in contravention with the fundamental
policy of Indian law or if it is in conflict with the most basic
notions of morality or justice. In Ssangyong (supra), this
30 | P a g e
Court held that the meaning of the expression ‘fundamental
policy of Indian law’ would be in accordance with the
understanding of this Court in Renusagar Power Co. Ltd.
6
v. General Electric Co. In Renusagar (supra), this Court
observed that violation of the Foreign Exchange Regulation
Act, 1973, a statute enacted for the ‘national economic
interest’, and disregarding the superior courts in India would
be antithetical to the fundamental policy of Indian law.
Contravention of a statute not linked to public policy or
public interest cannot be a ground to set at naught an
arbitral award as being discordant with the fundamental
policy of Indian law and neither can it be brought within the
confines of ‘patent illegality’ as discussed above. In other
words, contravention of a statute only if it is linked to public
policy or public interest is cause for setting aside the award
as being at odds with the fundamental policy of Indian law. If
an arbitral award shocks the conscience of the court, it can
be set aside as being in conflict with the most basic notions
of justice. The ground of morality in this context has been
interpreted by this Court to encompass awards involving
elements of sexual morality, such as prostitution, or awards
6 1994 Supp (1) SCC 644
31 | P a g e
seeking to validate agreements which are not illegal but
7
would not be enforced given the prevailing mores of the day.
27. In light of the principles elucidated herein for
interference with an arbitral award by a court in exercise of
its jurisdiction under Section 34 of the 1996 Act, we proceed
to consider the questions that arise in these Appeals as to
whether the Division Bench of the High Court was right in
setting aside the award of the Arbitral Tribunal dated
11.05.2017.
Validity of the termination notice and consequences of
the CMRS sanction
28. Mr. Harish Salve, learned Senior Counsel appearing for
the Appellant (DAMEPL), submitted that the High Court
committed an error in setting aside the award of the Arbitral
Tribunal by deviating from the well-settled principles for
interference under Sections 34 and 37 of the 1996 Act. The
findings recorded by the Arbitral Tribunal in relation to the
existence of defects in the civil structure and failure on the
part of DMRC in curing those defects/not taking effective
steps to cure the defects are findings of fact which cannot be
made subject to review by the court exercising its jurisdiction
under Section 34. He asserted that interpretation of the
7 Ssangyong (supra)
32 | P a g e
provisions of the Concession Agreement is within the domain
of the Arbitral Tribunal and even if such interpretation is not
the most accurate interpretation in the opinion of the court,
the award cannot be set aside if the Arbitral Tribunal has
taken a possible view. He contended that the certificate
issued by the CMRS, which was relied upon by DMRC, was
considered by the Tribunal to rightly conclude that the
conditions imposed for restarting the AMEL showed that the
defects were not cured. He further submitted that the cure
notice was issued on 09.07.2012 demanding the rectification
of defects within a period of 90 days from the date of the
notice, as per the Concession Agreement. After the expiry of
90 days, the termination notice dated 08.10.2012 had been
issued. He stated that there cannot be any doubt that the
defects had to be cured within 90 days from the date of the
cure notice. He emphasized that the observations of the High
Court as regards confusion in the mind of the Arbitral Tribunal
regarding the date of the termination notice are unfounded.
The relevant portions of the award were shown to the Court
to argue that the Arbitral Tribunal was clear in its mind that
the defects had to be cured within 90 days from the date of
cure notice dated 09.07.2012. On the defects not being
cured within the 90-day period, the termination notice was
33 | P a g e
issued on 08.10.2012, with the effective date of termination
as 07.01.2013. The further submission made on behalf of
DAMEPL is that the subsequent successful operation of the
AMEL for nearly four years is not relevant for adjudication of
the disputes between the parties by the Arbitral Tribunal.
Finally, according to Mr. Salve, the High Court committed a
palpable error in setting aside the award.
29. Mr. P.S. Narasimha and Mr. Parag Tripathi, learned
Senior Counsel appearing for DMRC, on the other hand,
supported the judgment of the Division Bench of the High
Court by arguing that the award is contrary to public policy.
Mr. Narasimha relied upon the Delhi Metro Act and the Rules
made thereunder to submit that the CMRS is the sole
authority to determine the safety of the Metro Railway and
the certificate issued by the Commissioner on 18.01.2013 is
conclusive proof of the fact that the defects pointed out by
DAMEPL had been rectified. It was contended on behalf of
DMRC that the period for curing the defects did not lapse on
expiry of 90 days from the initial notice dated 09.07.2012 but
extended for another 90 days from the termination notice
dated 08.10.2012. According to the Respondent, a serious
error was committed by the Arbitral Tribunal in its
interpretation of Article 29.5.1 of the Concession Agreement.
34 | P a g e
Abundant material placed by DMRC to show effective steps
were taken to cure the defects was not considered by the
Arbitral Tribunal. The Commissioner in exercise of his powers
conferred by the Delhi Metro Act permitted the opening of
the AMEL on 18.01.2013 after considering all safety aspects
and the AMEL has been in operation since then without any
adverse event. The subsequent smooth functioning of the
AMEL is a relevant consideration which was ignored by the
Arbitral Tribunal. DAMEPL’s participation in several meetings
that were conducted which led to inspections and steps
taken to address the defects as well as the AMEL being run
by DAMEPL from 22.01.2013 to 30.06.2013 would show that
even DAMEPL was aware that effective steps had been taken
to cure the defects.
30. Termination by DAMEPL for DMRC Event of Default is
dealt with in Article 29.5.1 which reads as under: -
“ 29.5 Termination for DMRC Event of Default
29.5.1 The Concessionaire may after giving 90
(ninety) days notice in writing to DMRC terminate this
Agreement upon the occurrence and continuation of any
of the following events (each a "DMRC Event of
Default"), unless any such DMRC Event of Default has
35 | P a g e
occurred as a result of Concessionaire Event of Default
or due to a Force Majeure Event.
(i) DMRC is in breach of this Agreement and such
breach has a Material Adverse Effect on the
Concessionaire and DMRC has failed to cure such
breach or take effective steps for curing such
breach within 90 (ninety) days of receipt of notice
in this behalf from the Concessionaire;
(ii) DMRC repudiates this Agreement or otherwise
evidences an irrevocable intention not to be
bound by this Agreement;
(iii) GoI or GNCTD or any Governmental Agency have
by an act of commission or omission created
circumstances that have a Material Adverse Effect
on the performance of its obligations by the
Concessionaire and have failed to cure the same
within 90 (ninety) days of receipt of notice by
DMRC in this behalf from the Concessionaire;
(iv) DMRC has delayed any payment that has fallen
due under this Agreement if such delay exceeds
90 (ninety) days.”
36 | P a g e
31. By referring to certain paragraphs of the award, the
Division Bench of the High Court held that there was
confusion in the mind of the Arbitral Tribunal relating to the
actual date of termination, which would have a material
bearing on the exegesis of Article 29.5.1. The confusion
around the date of termination is highlighted by the High
Court by referring to the award of the Arbitral Tribunal in
which it was held that the defects were not cured within the
90-day period from the date of the cure notice dated
09.07.2012. However, in paragraphs 128, 130 and 131, the
Arbitral Tribunal, while considering the counter claim,
referred to 07.01.2013 as the date of termination of the
Concession Agreement. It is clear from a careful examination
of the award that the Arbitral Tribunal had in precise terms
held that the defects had to be cured within 90 days from the
date of the cure notice dated 09.07.2012. Further, the
Arbitral Tribunal held that the termination notice dated
08.10.2012 was issued as defects were not cured. The
Tribunal expressed its view that consequently, the effective
date of termination was 07.01.2013, which is 90 days from
the termination notice. As there is no ambiguity in the
findings of the Arbitral Tribunal regarding the time given for
curing the defects and the effective date of termination of
37 | P a g e
the Concession Agreement, we are not in agreement with the
findings of the Division Bench that there is an ambivalence in
the award concerning the date of termination, having a
bearing on the final outcome of the award. The ancillary
issue that arises for consideration is whether the period for
curing the defects is 180 days or 90 days under Article 29.5.1
of the Concession Agreement. The Arbitral Tribunal in its
award has clearly held that DMRC failed to cure the defects
before the expiry of 90 days from the initial notice laying
down the non-exhaustive list of defects issued on
09.07.2012. The said conclusion is the outcome of
interpretation of Article 29.5.1 of the Concession Agreement
by the Tribunal. An attempt was made by the learned Senior
Counsel appearing for the Respondent to impress upon this
Court that as the termination notice would become effective
only after 90 days from the date of its issue, i.e., 08.10.2012,
DMRC could avail this period as well to address the defects
and if the defects stood cured or effective steps were taken
within this additional 90-day period, the termination notice
became defunct and should not be effectuated.
Construction of a provision of the Concession Agreement is
within the domain of the Arbitral Tribunal. The view taken by
the Arbitral Tribunal that the defects have to be cured within
38 | P a g e
90 days from the date of the cure notice, failing which
DAMEPL is entitled to terminate the Concession Agreement,
is a possible interpretation of Article 29.5.1. We refuse to
interfere with the findings of the Arbitral Tribunal on this
point, even assuming a different view can be taken on a
reading of the said Article.
32. The High Court was of the view that the Tribunal
committed a grave error in ignoring the CMRS certificate, as
the Tribunal lost sight of the binding nature of the certificate.
According to the Division Bench, the Arbitral Tribunal went
wrong in considering the issue of the CMRS certificate as a
separate issue, distinct from the questions pertaining to the
termination of the Concession Agreement. The Delhi Metro
Act was promulgated for the operation, maintenance and
regulation of the working of the metro railway in the National
Capital Region, metropolitan city and metropolitan area. The
Commissioner of Metro Railway Safety, appointed under
Section 7 of the said Act, has the duty to inspect the metro
railway with a view to determine whether it is fit to be
opened for the public carriage of passengers and report
thereon to the Central Government as required thereunder.
Section 15 of the Delhi Metro Act provides that before
granting sanction to the opening of the metro railway by the
39 | P a g e
Central Government under Section 14, a report has to be
obtained from the Commissioner certifying fitness of the
metro railway so as not to be of any danger to the public.
Rule 11 of the Opening of Delhi Metro Railway for Public
Carriage of Passengers Rules, 2002 imposes a duty on the
Commissioner to inquire into all relevant matters concerning
safety before coming to a conclusion that the metro railway
should be opened. Sanction to open the metro railway line
for public carriage of passengers is granted by the Central
Government after considering the report of the
Commissioner on the fitness and safety aspects. The
contention on behalf of DMRC is that the certificate issued by
the Commissioner is binding on the Arbitral Tribunal and the
Tribunal could not have taken a different view. In addition
thereto, the certificate is conclusive of the fact that there
were no defects in the civil structure, as otherwise, the
Commissioner would not have permitted the AMEL to be
opened. On the basis of the certificate issued by the
Commissioner, the Respondent has argued that all defects
pointed out by DAMEPL had been cured. In any event,
effective steps had been taken to cure the defects by
periodical meetings and inspections being held.
40 | P a g e
33. The Arbitral Tribunal was called upon by the parties to
decide whether there was a breach of the Concession
Agreement due to the fault of DMRC and whether the defects
pointed out by DAMEPL were cured within the period
specified in the notice dated 09.07.2012. Safety of the
AMEL was not an issue that fell for determination by the
Arbitral Tribunal, though DAMEPL had insisted on not
continuing operations of the Line citing safety concerns
arising from the defects in its structural integrity. It is no
doubt true that the Commissioner is the competent authority
to determine the safety of the AMEL. It is also beyond cavil
that the Commissioner would not have granted permission to
restart the AMEL unless it was of the opinion that restarting
of commercial operations would not pose a danger to the
public. However, the certificate by itself cannot come to the
rescue of DMRC to show that the defects pointed out by
DAMEPL were cured within the expiry of 90 days from
09.07.2012. The finding of the Arbitral Tribunal that the
defects were not cured is one of fact which cannot be
interfered with by the court.
34. The CMRS certificate dated 18.01.2013 was relied upon
by DMRC before the Arbitral Tribunal as a strong piece of
evidence to support its case that the defects were cured.
41 | P a g e
DMRC did not contend before the Tribunal that the CMRS
certificate is binding and is conclusive of the defects being
cured/effective steps taken to cure the defects. The
conditions imposed by the Commissioner relating to speed
restrictions and close monitoring of the Line, according to the
Tribunal, support the contention of DAMEPL that the defects
were not fully cured. The issue before the Tribunal was
whether the defects were cured within 90 days from the
notice dated 09.07.2012 and the certificate dated
18.01.2013 is relevant for deciding the said issue. We are not
in agreement with the High Court’s view that the issue of the
CMRS certificate being dealt with separately has a bearing on
the Tribunal’s determination of the validity of the termination
notice. The members of the Arbitral Tribunal, nominated in
accordance with the agreed procedure between the parties,
are engineers and their award is not meant to be scrutinised
in the same manner as one prepared by legally trained
minds. In any event, it cannot be said that the view of the
Tribunal is perverse. Therefore, we do not concur with the
High Court’s opinion that the award of the Tribunal on the
legality of the termination notice is vitiated due to the vice of
perversity.
42 | P a g e
35. The Division Bench referred to various factors leading
to the termination notice, to conclude that the award shocks
the conscience of the court. The discussion in paragraph 97
of the impugned judgement amounts to appreciation or re-
appreciation of the facts which is not permissible under
Section 34 of the 1996 Act. The Division Bench further held
that the fact of the AMEL being operated without any adverse
event for a period of more than four years since the date of
issuance of the CMRS certificate, was not given due
importance by the Arbitral Tribunal. As the arbitrator is the
sole judge of the quality as well as the quantity of the
evidence, the task of being a judge on the evidence before
the Tribunal does not fall upon the court in exercise of its
8
jurisdiction under Section 34. On the basis of the issues
submitted by the parties, the Arbitral Tribunal framed issues
for consideration and answered the said issues. Subsequent
events need not be taken into account.
36. For the aforementioned reasons, the conclusion of the
Division Bench that the award of the Arbitral Tribunal suffers
from patent illegality and shocks the conscience of the court
is held to be erroneous.
Adjusted Equity
8 State of Rajasthan v. Puri Construction Co. Ltd. and Another (1994) 6 SCC
485
43 | P a g e
37. Article 29.5.2 of the Concession Agreement which deals
with Termination Payment is as follows:-
“ 29.5.2 Upon termination by the Concessionaire on
account of DMRC Event of Default, DMRC shall pay to the
Concessionaire, by way of Termination Payment, an
amount equal to
a) Debt Due;
b) 130 % of the Adjusted Equity;
c) Depreciated Value of the Project Assets, if any,
th
acquired and installed on the Project after the 10
anniversary of the COD.”
38. It is relevant to note the definitions of ‘Adjusted Equity’,
‘Concessionaire’s Capital Costs’, ‘Debt Due’, ‘Equity’, and
‘Subordinate debt’ as provided in the Concession Agreement,
which read as follows: -
“Adjusted Equity” means the Equity funded in Indian
Rupees and adjusted on the first day of the current month
(the “Reference Date”), in the manner set forth below, to
reflect the change in its value on account of depreciation
and variations in WPI, and for any Reference Date
occurring:
a) on or before COD, the Adjusted Equity shall be a sum
equal to the Equity funded in Indian Rupees and
expended on the Project, revised to the extent of one
half of the variation in WPI occurring between the first
day of the month of Appointed Date and the Reference
Date;
44 | P a g e
th
b)
from COD and until the 4 (fourth) anniversary thereof,
an amount equal to the Adjusted Equity as on COD shall
be deemed to be the base (the “Base Adjusted Equity”)
and the Adjusted Equity hereunder shall be a sum equal
to the Base Adjusted Equity, revised at the
commencement of each month following COD to the
extent of variation in WPI occurring between COD and
the Reference Date;
th
c) after the 4 (fourth) anniversary of COD, the Adjusted
Equity hereunder shall be a sum equal to the Base
Adjusted Equity, reduced by 0.42% (zero point four two
per cent) (This number shall be substituted in each
case by the product of 100 divided by the number of
months comprising the Concession Period. For
example, the figure for a 20 year Concession Period
shall be 100/240 = 0.416 rounded off to decimal points
i.e. 0.42) thereof at the commencement of each month
th
following the 4 (fourth) anniversary of the Project
Completion Date and the amount so arrived at shall be
revised to the extent of variation in WPI occurring
between COD and the Reference Date; and the
aforesaid shall apply, mutatis mutandis, to the Equity
funded in Indian Rupees. For the avoidance of doubt,
the Adjusted Equity shall, in the event of Termination,
be computed as on the Reference Date immediately
preceding the Termination Date; provided that no
reduction in the Base Adjusted Equity shall be made for
a period equal to the duration, if any, for which the
Concession Period is extended, but the revision on
account of WPI shall continue to be made.”
45 | P a g e
“Concessionaire’s Capital Costs” means following:
• Prior to COD, the cost of the Concessionaire’s Works
as set forth in the Financing Documents plus any
further additional capital cost for any Change of Scope
instructed since the finalisation of the Financing
Documents; and
• After COD, the actual capital cost of the
Concessionaire’s Works upon Project Completion as
certified by the Statutory Auditors.”
“Debt Due” means the aggregate of the following sums
expressed in Indian Rupees outstanding on the Transfer
Date:
a) the principal amount of the debt provided by the Senior
Lenders under the Financing Agreements for financing
the Total Project Cost (the “principal”) but excluding any
part of the principal that had fallen due for repayment
two years prior to the Termination Date;
b) all accrued interest, financing fees and charges payable
under the Financing Agreements on, or in respect of,
the debt referred to in Sub-clause (a) above until the
Transfer Date but excluding (i) any interest, fees or
charges that had fallen due one year prior to the
Transfer Date, (ii) any penal interest or charges payable
under the Financing Agreements to any Senior Lender,
and (iii) any pre-payment chares in relation to
accelerated repayment of debt except where such
charges have arisen due to Authority Default; and
46 | P a g e
c) any Subordinated Debt which is included in the
Financial Package and disbursed by lenders for
financing the Total Project Cost.”
“Equity” means the sum expressed in Indian Rupees
representing the equity share capital of the
Concessionaire and shall include the funds advanced by
any Member of the Consortium or by any of its
shareholders to the Concessionaire for meeting the equity
component of the Concessionaire’s Capital Costs.”
“Subordinated Debt” means the aggregate of the
following sums expressed in Indian Rupees or in the
currency of debt, as the case may be, outstanding as on
the date of termination:
a) the principal amount of debt provided by lenders or the
Concessionaire for meeting the Concessionaire’s Capital
Cost and subordinated to the financial assistance
provided by the Senior Lenders; and
b) all accrued interest on the debt referred to in Sub-
clause (a) above but restricted to the lesser of actual
interest rate and a rate equal to 5% (five per cent)
above the Bank Rate in case of loans expressed in
Indian Rupees and lesser of the actual interest rate and
six-month LIBOR (London Inter Bank Offer Rate) plus
2% (two per cent) in case of loans expressed in foreign
currency, but does not include any interest that had
fallen due one year prior to the Termination Date;
47 | P a g e
provided that if all or any part of the Subordinated Debt
is convertible into Equity at the option of the lenders and/
or the Concessionaire, it shall for the purposes of this
Agreement be deemed to be Subordinated Debt even
after such conversion and the principal thereof shall be
dealt with as if such conversion had not been
undertaken.”
39. The Tribunal focused on two components of Termination
Payment, which are (i) ‘Debt Due’, and (ii) 130 % of the
‘Adjusted Equity’. According to the Appellant, the Division
Bench committed an error in concluding that the expression
‘Adjusted Equity’ in the Concession Agreement should be
calculated by taking into account only the share capital of
DAMEPL. The Appellant contended that the Tribunal had
rightly held that the expression ‘Adjusted Equity’ should
include the money brought in by DAMEPL’s promoter and had
fairly concluded that the amount of Rs.611.95 crore was used
as expenses, thereby qualifying as ‘Concessionaire’s Capital
Costs’ under the Concession Agreement. The Tribunal was
correct in holding that the amount of Rs.611.95 crore
advanced by DAMEPL’s promoter would qualify for inclusion
under the definition of ‘Equity’ on a plain reading of the said
definition. Construction of the contract is within the
jurisdiction of the Tribunal and merely because another view
48 | P a g e
is possible, the court cannot interfere with such construction
and substitute its own view.
40. On the other hand, it was contended by DMRC that the
amount of Rs.611.95 crore was recorded as ‘share
application money’ in the balance sheet of DAMEPL as on
31.03.2010. However, the said amount was shown as
subordinated debt in the balance sheet as on 31.03.2011.
The Respondent referred to the resolution passed by the
board of directors of DAMEPL on 16.03.2011, in which a
decision was taken to convert the share application money
into subordinated debt. DMRC urged that the conversion of
the share application money as subordinated debt was a
calculated move on the part of DAMEPL. If the share
application money had been allowed to retain the nature of
equity, DAMEPL would have lost the entire amount in the
event of termination of the Concession Agreement by DMRC
for Concessionaire Event of Default in terms of Article 29.1.1.
After electing to convert the share application money into
subordinated debt, DAMEPL should not be permitted to claim
that for the purposes of computation of ‘Adjusted Equity’, the
said amount be treated as ‘Equity’. It was further argued on
behalf of the Respondent that no material was produced by
DAMEPL to show that the amount of Rs. 611.95 crore was
49 | P a g e
actually used for ‘Concessionaire’s Capital Costs’. Reference
was also made to the testimony of one of the witnesses
produced by DAMEPL to contend that the amount of
Rs.611.95 crore cannot be treated as equity in accordance
with the provisions of the Companies Act, 2013. DMRC
contended that the High Court aptly set aside the findings
recorded by the Tribunal in respect of computation of
‘Adjusted Equity’.
41. We do not intend to re-examine the entire material on
record for the purpose of deciding whether the High Court
was right in reversing the conclusion of the Tribunal in
relation to computation of the amount under Article 29.5.2 of
the Concession Agreement. The opinion of the Tribunal is
that the amount of Rs.611.95 crore was an amount advanced
by DAMEPL’s promoter which was not disputed by DMRC. The
contention advanced by DMRC, that it was only the equity
share capital as is understood within the meaning of the
Companies Act, 2013 which is liable to be paid by DMRC
under Article 29.5.2, was rejected by the Tribunal. The view
taken by the Tribunal that the amount contributed by a
member of the consortium or by shareholders to meet the
‘Concessionaire’s Capital Costs’ in any form, including where
such funds are classified as subordinated debt, cannot be
50 | P a g e
treated as ‘Subordinated Debt’ in terms of its definition in the
Concession Agreement, is a reasonable and possible view.
On the other hand, the Division Bench of the High Court
relied upon the board resolution dated 16.03.2011 and held
that the Tribunal ought not to have treated the said amount
as ‘Equity’ after the share application money was converted
into subordinated debt. After a detailed consideration of the
relevant clauses of the Concession Agreement, the High
Court held that the Tribunal had committed a serious error in
its tabulation of ‘Adjusted Equity’ by completely ignoring the
evidence on record.
42. Even assuming the view taken by the High Court is not
incorrect, we are afraid that a possible view expressed by the
Tribunal on construction of the terms of the Concession
Agreement cannot be substituted by the High Court. This
view is in line with the understanding of Section 28(3) of the
1996 Act as a ground for setting aside the arbitral award, as
held in Associate Builders (supra) and thereafter upheld in
Ssangyong (supra). No case has been made out by the High
Court to establish violation of Section 28(3). Having carefully
examined the Concession Agreement, the findings recorded
by the Tribunal and the findings recorded by the Division
Bench, we are not in a position to hold that the opinion of the
51 | P a g e
Tribunal on inclusion of Rs.611.95 crore under ‘Equity’ is a
perverse view. It cannot be said that the Tribunal did not
consider the evidence on record, especially the resolution
dated 16.03.2011 passed by DAMEPL’s board of directors.
We also do not find fault with the approach of the Tribunal
that the understanding of the term equity as per the
Companies Act, 2013 is not relevant for the purposes of
determining ‘Adjusted Equity’ in light of the express
definition of the term in the Concession Agreement. As has
been held in Ssangyong (supra), mere contravention of
substantive law as elucidated in Associate Builders (supra)
is no longer a ground available to set aside an arbitral award.
The support placed by the Division Bench on the
interpretation of Section 28(1)(a) of the 1996 Act as adopted
in Associate Builders (supra) is, therefore, no longer good
law. In view of the foregoing, we set aside the findings of the
High Court and uphold the award by the Tribunal in respect of
the computation of Termination Payment under Clause
29.5.2.
Grounds of challenge in SLP (C) No. 8311 of 2019 filed
by DMRC
43. One of the legal issues considered by the Tribunal is
whether DAMEPL waived their rights to terminate after
52 | P a g e
participating in the reconciliation process and after operating
the AMEL for more than five months from 22.01.2013 to
30.06.2013. As the participation of DAMEPL in several
meetings held after issuance of the termination notice dated
09.07.2012 and its decision to continue operating the AMEL
was without prejudice, the Tribunal rejected the submission
of DMRC that the doctrine of waiver applied and that DAMEPL
was estopped from terminating the Concession Agreement
after having actively participated in the process of rectifying
the defects pointed out. The Division Bench of the High
Court approved the said finding on the ground that the
decision of the Tribunal could not be held to be flawed within
the limited scrutiny afforded to courts under Section 34 of
the 1996 Act. In our view, the Division Bench of the High
Court rightly refrained from interfering with the findings on
waiver by the Tribunal.
44. The prayer for a direction to DAMEPL for specific
performance of its obligations under the Concession
Agreement to operate the AMEL was refused by the Tribunal.
The Division Bench of the High Court in its judgment
observed that the said findings had not been challenged
before the High Court. Therefore, there is no reason for this
53 | P a g e
Court to adjudicate on the point of specific performance of
the Concession Agreement.
45. The Tribunal awarded interest in accordance with the
terms of the Concession Agreement on termination payment.
DMRC contended before the High Court that the award in
respect of interest had to be set aside on the ground that it
would result in unjust enrichment. After a thorough
consideration of Article 29.8 and Article 36.2.6.1 of the
Concession Agreement, the High Court has rightly refused to
interfere with the findings by the Tribunal relating to interest
and we see no cause for interference.
46. For the aforementioned reasons, the Appeal filed by
DAMEPL is allowed and the judgment of the Division Bench of
the High Court is set aside. The Appeal arising out of SLP(C)
No. 8311 of 2019 filed by DMRC is dismissed.
.....................................J.
[ L. NAGESWARA RAO ]
.....................................J.
[ S. RAVINDRA BHAT ]
New Delhi,
September 09, 2021.
54 | P a g e