Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 7
CASE NO.:
Appeal (civil) 1309 of 2001
PETITIONER:
SANSHIN CHEMICALS INDUSTRY
RESPONDENT:
ORIENTALS CARBONS AND CHEMICALS LTD. AND ORS.
DATE OF JUDGMENT: 16/02/2001
BENCH:
G.B. PATTANAIK & K.G. BALAKRISHNAN & B.N. AGRAWAL
JUDGMENT:
JUDGMENT
2001 (1) SCR 1101
The Judgment of the Court was delivered by PATTANAIK, J. Leave granted.
This appeal by grant of special leave is directed against the judgment of
Delhi High Court dated 8th of August, 2000, The question for consideration
is whether a decision regarding the venue of the Arbitration proceedings
could be assailed in appeal under Section 34 of the Arbitration and
Conciliation Act, 1996. The Division Bench of the High Court by the
impugned judgment agreed with the conclusion of the learned Single Judge
and came to hold on examining the arbitration clause in the agreement that
the decision with regard to the venue of the arbitration sitting cannot be
held to be an interim award and as such Section 34 of the Act cannot be
invoked.
The appellant and respondent No. 1 entered into a technical collaboration
agreement called ’Insoluble Sulphur Technical Collaboration Agreement’ on
1st of August, 1989. Under the agreement, respondent No. 1 was required to
provide technical information for production of insoluble sulphur in India.
Appellant discharged its obligation under the agreement. The said
respondent No. 1 in May, 1996, wrote a letter to the Indian Council of
Arbitration, making a claim against the appellant on the basis of certain
disputes between the parties. But the Indian Council of Arbitration
returned the papers to respondent No. 1 on 15.5.96. On the very same day,
the said respondent No. 1 filed a statement of claim before respondent No.
2, which was registered as Arbitration Case No. FTA/137. Said respondent
No. 2, by its letter dated 25th of June, 1996 called upon the appellant to
appoint aft arbitrator. On 9.7.96, the appellant wrote to the respondent
No. 2 bringing to its attention clause 8.4 of the agreement and stated that
the appellant has not received any demand for arbitration from OCCL and as
such the respondent No. 2 has no jurisdiction in the matter. Respondent No.
2 however by its order dated 17th of July, 1996, called upon the appellant
to Submit the agreement regarding the venue of arbitration with reasons
within 30 days. Appellant immediately answered the aforesaid letter of the
respondent No. 2 by letter dated 22.7.96, questioning the jurisdiction of
the respondent No. 2 and also seeking clarification as to whether FICCI had
accepted the statement of claim of respondent No. 1. At this point of time,
the appellant was assured that respondent No. 2 will not proceed with the
matter till the issues regarding the venue are sorted out. On 9.8.1996,
respondent No. 1’s lawyer intimated respondent no. 2 that they had already
appointed an arbitrator and it was for the arbitral tribunal to decide the
venue under Section 20 of the Arbitration and Conciliation Act, 1996.
Respondent No. 2 was called upon to nominate the appellant’s arbitrator.
Appellant by his letter dated 9th of August, 1996, intimated the respondent
No. 2 that the requirement of Article 8.4 not having been complied with,
there is no question of nominating arbitrator on behalf of the appellant.
Appellant also wrote a letter to the respondent No. 1 on 6th of September,
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 7
1996, indicating therein that the Registrar of FICCI had no jurisdiction
and that there had been no proper demand for arbitration. It was also
stated that in any event, Japan was the designated place of arbitration. On
16th of October, 1996, respondent No. 2 sent a communication to the
Manager, Arbitration Department, Japan Commercial Arbitration Association,
stating therein that since parties had not been able to agree on the place
of arbitration within 30 days of the notice calling upon them to submit the
agreement, the JCAA may nominate a member on the Joint Arbitration
Committee. In that letter it had been stated that respondent No, 2 had
already nominated one Umesh Kumar Khaitan as its Member on the Joint
Arbitration Committee. Pursuant to the aforesaid letter from respondent No.
2, the JCAA appointed respondent No. 5 as its Member by letter dated 25th
of October, 1996. Appellant had made some correspondence and queries
regarding the proceedings of the joint Arbitration \007Committee. Mr. Umesh
Khaitan resigned as Member of JAC on 12th of January, 1998 and he was,
therefore, substituted by respondent No. 3. The aforesaid JAC met in Delhi
on 15th of July, 1998 and decided the venue for the sittings of the
arbitral tribunal The appellant filed an application before a learned
Single Judge of Delhi High Court, assailing the decision of the Joint
Arbitration Committee dated 15th July, 1998 on various grounds under
Section 34 of the Arbitration and Conciliation Act, 1996. The learned
Single Judge by his Judgment dated 7th of April, 2000, dismissed the said
application of the appellant on a finding that the impugned decision of the
Joint Arbitration Committee dated 15th of July, 1998 is not an award and as
such is not amenable to appeal under Section 34 of the Arbitration and
Conciliation Act, 1996. Against the said judgment of the learned Single
Judge, the appellant preferred an appeal and the Division Bench having
dismissed the appeal by its Judgment dated 8th of August, 2000, the present
appeals has been preferred to this Court.
Mr. Ashok H. Desai, the learned senior counsel, appearing for the appellant
contended that on a plain reading of clause 8.4 of the Technical
Collaboration Agreement, would indicate that there is no agreed venue where
the arbitral proceedings could be conducted and on the other hand, the
procedure in the arbitral proceedings would be governed by the decision of
the venue inasmuch as if it is to be held in India, then it shall be
conducted in accordance with the rules applicable in India and if it is to
be conducted in Japan, then the rules of Japan Commercial Arbitration
Association would apply. According to Mr. Desai, since the procedure and
the rules to be applicable for resolving the dispute would depend upon the
very decision of the venue, Such a decision amounts to a vital right of the
party being decided by the Joint Arbitration Committee and as such the same
partakes the character of an interim award and consequently Section 34 of
the Arbitration and Conciliation Act, 1996 would apply to such a decision
and aggrieved party against such decision cannot be held to be remedy-less.
Mr. Desai further urged that on an analysis of the agreement, itself would
indicate that it contains two arbitration clauses, one nomenclatured as
Joint Arbitration Committee and the other is the Arbitral Tribunal. While
the former decides the dispute in relation to the venue, the latter decides
the dispute on merits of the claim. Under such circumstances to hold that
the decision of the Joint Arbitration Committee on the dispute relating to
the venue even does not amount to an interim award, is un-sustainable in
law and the learned Single judge as well as the Division Bench committed
serious error in recording a finding that the said decision does not amount
to an award. Mr. Desai also urged that in case of an International
Commercial Arbitration, the seat of the arbitral proceeding is of paramount
importance and the parties to the agreement being conscious of the same,
provided such an elaborate mechanism for resolution of a dispute in the
event no agreement is arrived at on the question of venue. Adjudged from
this stand point, the impugned judgment illegally excludes such a decision
from the purview of a judicial review by way of filing an appeal under
Section 34 of the Act and the same must be interfered with. Mr. Desai also
urged that in view of the definition of "Award" in the Act in Section 2(c)
which includes an interim award, and an award being a final determination
of a particular issue or claim in the arbitration and the issue regarding
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 7
venue being of seminal importance for adjudication of the rights of the:
parties, the conclusion is irresistible that such decision by the Joint
Committee of Arbitrators, must be held to be an interim award and as such
amenable to be reviewed under Section 34 of the Act and consequently, the
High Court committed Serious error in holding to the contrary.
Mr. D.A. Dave, the learned senior counsel, appearing for the respondents on
the other hand submitted that though the expression ’award’ has been
defined to include an interim award under Section 2(c) of the Act, but a
decision to become an award must be a final determination of a particular
issue or claim in the arbitration. The decision on the question of venue by
a forum under the agreement termed as Joint Arbitration Committee is at an
earlier stage of initiation of the proceedings of the arbitral tribunal
and, therefore, the same cannot be termed as an interim award, The High
Court, therefore, was justified in not entertaining an appeal against the
same under Section 34 of the Act. With regard to the different clauses of
the agreement, Mr. Dave contends that the parties themselves agreed that
the place of arbitration shall be determined by the Joint Arbitration
Committee and such determination shall be binding and final, whereas the
arbitration clause stipulates that any claim or dispute arising out of or
relating to the agreement shall be settled by arbitration. The very fact
that the parties agreed that the question of venue will be determined by a
Joint Arbitration Committee in the event parties do not designate the place
of arbitration or are unable to agree within 30 days of the demand,
indicates that the parties never intended the said decision to partake the
character of an award to be assailed in appeal and on the other hand the
agreement not having authorised the arbitral tribunal to determine the
place of arbitration, clearly establishes that such a determination by a
separate forum is not an award and, therefore, is not appealable under
Section 34 of the Arbitration and Conciliation Act. Mr. Dave
also contended that the argument advanced on behalf of the appellant that
the decision with regard to the venue of the arbitral proceeding is an
adjudication of a vital right of the parties inasmuch as the procedure to
be adopted in the arbitral proceedings would be the law which governs the
venue of the proceedings, is devoid of any force in view of Clause 9(1) of
the agreement which categorically indicates that the agreement shall be
interpreted in accordance with and governed by the laws of India. According
to Mr. Dave, this provision in the arbitration agreement is conclusive of
the fact as to which law will govern and consequently, the decision of the
Joint Arbitration Committee with regard to the venue looses its
significance. It is next contended by the learned senior counsel for the
respondents that the arbitration clause providing resolution of any dispute
or claim arising out of the agreement by arbitration can obviously relate
to a claim or dispute in relation to the contract and a decision or
determination by the Joint Arbitration Committee on the question of venue,
which power the Committee gets under the agreement itself, cannot be held
to be a decision in course of the arbitral proceedings nor can it be said
to be an adjudication of claim arising put of the agreement and, therefore,
is not an award. Mr. Dave also after referring to the different
provisions in the Arbitration and Conciliation Act contended that making of
an arbitral award and termination of proceedings occurs in Chapter VI and
starts from Section 28, whereas place of arbitration occurs in Chapter V
dealing with the conduct of arbitral proceedings. The commencement of
arbitral proceedings contemplated under Section 21 is the date when a
particular dispute is referred to the arbitration. In this view of the
matter a decision on the question of venue will not be an award or interim
award against which a party can take recourse to a Court under Section 34
and as such the impugned judgment of the learned Single Judge as well as
the Division Bench remain unassailable.
Before we examine the rival submissions made, it would be appropriate for
us to notice the relevant clauses of the agreement, which ultimately would
help us to decide the question as to whether the decisions of the Joint
Arbitration Committee dated 15.7.1998 can be held to be an interim award.
Clause 8.4 is in fact the most crucial clause that requires consideration,
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 4 of 7
which is quoted herein-below in extenso.
’’Clause 8.4.-Any dispute or claim arising out of or relating to this
Agreement shall be settled by arbitration. If the arbitration is to be held
in India, the dispute shall be submitted to the Arbitration Tribunal of the
Federation of Indian Chambers of Commerce and Industry and shall be
conducted in accordance with the Rules of that Tribunal. If the arbitration
is to be held in Japan, it shall be conducted in accordance with the Rules
of the Japan Commercial Arbitration Association.
In the event that the parties have not designated the place of arbitration
or are unable to agree thereon within thirty (30) days after the demand for
arbitration has been made, the place of arbitration shall be determined by
a Joint Arbitration Committee of three members, one to be appointed by the
Arbitration sub-committee of the Federation, another by the Japan
Commercial Arbitration Association and the third of a nationality other
than that of any one of the parties to act as Chairman to be chosen by the
other two members. In deciding the place of arbitration, the Joint
Arbitration Committee shall consider among others the principle that, if
only the quality of the good is in dispute and/or inspection of the goods
is necessary, arbitration of such case shall take place at the place where
the merchandise is located. The party demanding arbitration according as it
is resident in India or Japan shall give notice to the Arbitration Tribunal
of the Federation or the Japan Commercial Arbitration association, as the
case may be. The Arbitration Tribunal of the Federation or the Japan
Commercial Arbitration Association, as the case may be, shall request both
the parties to submit their agreement and reasons within thirty (30) days
for preference regarding the place of arbitration. The determination of the
place by the Joint Arbitration Committee shall be final and binding."
Clause 9.1 stipulates that the agreement shall be interpreted in accordance
with and governed by the laws of India. Clause 9.7 is extracted herein-
below in extenso:
"9.7. The terms and conditions herein contained constitute the entire
agreement between the parties and shall supersede all previous
communication, either oral or written, between the parties with respect to
the subject matter hereof, and no agreement or understanding varying or
extending the same shall be binding upon either party unless in writing
signed by a duly authorised representative thereof in which writing this
Agreement is expressly referred to."
Apart from the aforesaid relevant clauses, it would be appropriate to
notice a few sections of the Arbitration and Conciliation Act, 1996.
Section 2(6) is extracted herein-below in extenso :
"Sec.2(6)’ : Where this Part, except section 28, leaves the parties free to
determine a certain issue, that freedom shall include the right of the
parties to authorise any person including an institution, to determine that
issue."
Section 20 is the provision for deciding the place of arbitration, which is
extracted herein-below in extenso :
"Sec.20 Place of arbitration- (1) The parties are free to agree on the
place of arbitration.
(2) Failing any agreement referred to in sub-section (1), the place of
arbitration shall be determined by the arbitral tribunal having regard to
the circumstances of the case, including the convenience of the parties.
(3) Notwithstanding sub-section (1) or sub-section (2), the arbitral
tribunal may, unless otherwise agreed by the parties, meet at any place it
considers appropriate for consultation among its members, for hearing
witnesses, experts or the parties, or for inspection of documents, goods or
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 5 of 7
other property."
On a construction of Clause 8.4 of the Agreement, it is apparent that the
parties themselves have maintained a distinction between submission of
dispute to the arbitration tribunal and decisions as to the place of
arbitration to be determined by a Joint Arbitration Committee of three
members. In the first part of the Clause, parties have agreed for referring
any dispute or claim arising out of, or relating to the agreement to be
settled by arbitration of an arbitration tribunal. The second part of the
agreement relates to a decision as to the venue of arbitration which in the
event of lack of agreement between the patties, is required to be
determined by a Joint Arbitration Committee of three members. Such
decisions of the Committee with regard to the venue is not a decision of a
dispute or claim arising out of, or relating to the agreement and,
therefore, cannot partake the character of an award or an interim award.
Under Section 2(6) of the Arbitration and Conciliation Act, 1996, excepting
Section 28, parties are free to determine certain issues and that freedom
would include the right of the parties to authorised any person including
an institution to determine that issue. Section 20 is the provision which
sees that the parties are free to agree on the place of arbitration and
failing upon any agreement, then under sub-section (2), it has to be
determined depending upon the circumstances of the case and convenience of
the parties. A conjoint reading of Section 2(6) and Section 20, therefore
leads to the conclusion that in the event, parties do not agree with regard
to the place of arbitration, though they were free to determine the same,
then they had the right to authorise any person including an institution
and in the case in hand, the Joint Committee is such an institution for
deciding the Venue of the arbitration and such decision of the Committee
will not partake the character of adjudication of a dispute arising out of
the agreement, so as to clothe it the character of an award. Chapter V of
the Act contains Section 18 to 27 and chapter VI deals with making of
arbiter award and termination of proceedings which starts with Section 28.
The decision on the question of venue under Section 20 would not come
within making of an arbitral award starting from Section 28 and on this
view of the matter also, the said decision on the question of venue will
not be either an award or an interim award so as to be appealable under
Section 34 of the Act. The decision of the Joint Committee on the question
of the venue under Clause 8.4 is not a decision, deciding legal rights of
the parties under the contract; There is no mutuality and the said
Committee is merely a machinery for deciding the question of venue. Such a
decision does not have the characteristics of an arbitration award nor even
can it beheld to be an interim award. The conclusion of the Joint Committee
is a conclusion on the guidelines contained in second pan of Clause 8.4 of
the agreement and is not a judicial determination and as such the said
conclusion would not amount to an award. In K.K. Modi v. K.N. Modi & Ors.,
[1998] SCC 573, this court considered the question as to whether Clause (9)
of the Memorandum of understanding would constitute an arbitration
agreement. The Court answered the question in the negative after
considering as to what would be the attributes to be present for an
agreement to be considered as an arbitration agreement. Paragraph (17) of
the aforesaid judgment is quoted herein-below in extenso :
"17. Among the attributes which must be present for an agreement to be
considered as an arbitration agreement are :
(1) The arbitration agreement must contemplate that the decision of the
tribunal will be binding on the parties to the agreement,
(2) that the jurisdiction of the tribunal to decide the right of parties
must derive either from the consent of the parties or from an order of the
court or from a statute, the terms of which make it clear that the process
is to be an arbitration,
(3) the agreement must contemplate that substantive right of parties will
be determined by the agreed tribunal,
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 6 of 7
(4) that the tribunal will determine the rights of the parties in an
impartial and judicial manner with the tribunal owing an equal obligation
of fairness towards both sides,
(5) that the agreement of the parties to refer their disputes to the
decision of the tribunal must be intended to been forceable in-law and
lastly,
(6) the agreement must contemplate that the tribunal will make a decision
upon a dispute which is already formulated at the time when a reference is
made to the tribunal."
The second part of clause 8.4 conferring powers on a Joint committee to
decide the question of venue of the arbitration does not satisfy the
aforesaid test laid down in Modi’s case and, therefore would not be an
arbitration agreement. Necessarily, therefore, the ultimate decision of the
said Committee on the question of venue cannot be held to be an award, so
as to confer a right of appeal to an aggrieved person under Section 34 of
the Act. Russel on Arbitration in paragraph 2.098 deals with the question
of venue of arbitration and the same is quoted herein-below in extenso :
"Ascertaining the seat. The place of arbitration is often specified in the
arbitration agreement, by the selection of a particular place or country in
which the arbitration is to be held. If the seat is not agreed on by the
parties, the matter may be resolved by the arbitration institution or
person the parties have agreed should have the power to designate the seat,
or by the arbitral tribunal if the parties have authorised the tribunal to
do so. The rules of various arbitration institutions contain a means of
establishing the place of arbitration in the absence of express agreement
by the parties. In all other cases, it is necessary to look at the parties’
agreement and all the relevant circumstances. A reference to arbitration
under the English Arbitration Acts would be construed as implying that
English would be the place of arbitration. Similarly, provisions in an
arbitration agreement stipulating for arbitration by a local tribunal or
institution may indicate the appropriate place of arbitration."
In the present case, the second part of Clause 8.4 of the agreement
conceived of the institution of Joint Committee which institution had the
power to decide with regard to the venue and such decision of the said
Joint Committee cannot be held to be an award of a arbitral tribunal. In
view of our analysis on the different provisions of the agreement as well
as the provisions of the Act itself, we are unable to accept Mr. Desai’s
argument that the agreement conceived of two arbitral proceedings, one in
relation to any dispute for the venue and the other in relation to the
dispute arising out of the agreement.
It would be appropriate for us to notice at this stage that respondent No.
2 had intimated the Manager, Arbitration Department, Japan Commercial
Arbitration Association that the parties had not been able to agree on the
place of arbitration within 30 days of the notice, calling upon them to
submit the agreement and, therefore, the said Japan Commercial Arbitration
Association could nominate a Member to the Joint Arbitration Committee and
pursuant to the said communication from respondent No. 2 the Japan
Commercial Arbitration Association, appointed respondent No. 5 as its
Member in the Joint Arbitration Committee by letter dated 25th of October,
1996. The aforesaid conduct of the Japan Commercial Arbitration Association
and the unanimous decision of the Joint Arbitration Committee about the
venue, is also quite significant in the context of the dispute.
Besides, bearing in mind the object behind the Arbitration and Conciliation
Act, 1996, as has been indicted by this Court in the ease of Konkan Railway
Corpn. Ltd. & Ors. v. Mehual Construction Co., [2000] 7 SCC 201, which is
in consonance with the UNCITRA model law, it would not be conducive to
interpret the decision of the Joint Arbitration Committee with regard to
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 7 of 7
the venue to be an interim award, conferring a right of challenge to an
aggrieved person under Section 34 of the Act.
Mr. Desai’s contention that the question of venue is of utmost importance,
since the arbitral proceeding will be conducted in accordance with the
rules applicable to the place where the arbitration proceeding is conducted
and consequently, denial of a right to appeal against the same is never
contemplated of, requires consideration. It is undoubtedly true that if the
arbitration is to be held in India, then the proceeding will be conducted
in accordance with the rules applicable in India and if the arbitrations is
to be held in Japan, it has to be conducted in accordance with the rules of
Japan Commercial Arbitration Association and as such the decision on the
question of venue is of utmost importance. But the further contention that
aggrieved party has no right to assail the same, once the said decision is
not assailed at this stage, does not appear to be correct. The ultimate
arbitral award could be assailed on the grounds indicated in sub-section
(2) of Section 34 and an erroneous decision on the question of venue, which
ultimately affected the procedure that has been followed in the arbitral
proceeding could come within the sweep of Section 34 (2) and as such it
cannot be said that an aggrieved party has no remedy at all.
This appeal, accordingly fails and is dismissed.