Full Judgment Text
1
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
CIVIL APPEAL No.5712 OF 2002
GARG WOOLLEN PVT.LTD. .......APPELLANT
VERSUS
STATE OF U.P. & ORS ......RESPONDENTS
J U D G M E N T
1. This appeal is directed against order dated 09.09.1997
by which the Division Bench of the Allahabad High Court dismissed
the writ petition filed by the appellant for quashing the
acquisition of its land.
2. The appellant purchased the land comprised in Khasra
No.262 of village Central Hope Town, Tehsil and District Dehradun
by registered sale deed dated 19.10.1984 for setting up an
industrial unit. Its name was mutated in the revenue records on
25.01.1985.
3. The Government of Uttar Pradesh issued notification
dated 8.5.1985 under Section 4(1) read with Section 17(1) of the
JUDGMENT
Land Acquisition Act, 1894 (for short, 'the Act') for the
acquisition of over 250 acres land including the land purchased
by the appellant for planned development of industrial area in
District Dehradun through the agency of Uttar Pradesh State
Industrial Development Corporation (UPSIDC). The declaration
under Section 6 was issued on 09.05.1985. Special Land
Acquisition Collector, Dehradun passed award dated 22.11.1986.
He took cognizance of the fact that industries were existing on
some portions of Khasra Nos. 235 to 238 and 262 of which
possession had not been taken and observed:
Page 1
2
"On the date of possession on dated 17.3.86, the
factories Everest Gas Cylinders Pvt.Ltd. and Garg
Wollen Pvt. Ltd. were found constructed and in
the initial stage of production and located on
Khasra Numbers 235, 236, 237, 238 and 262 area
respectively 0.56 acre, 0.63 acre, 0.38 acre,
0.65 acre and 3.65 acres; that on the land of
Khasra No.262, one tin covered room was found
constructed for the Textile Mill of Babu Lal
Jain. Since, the time and constructions of the
construction of these factories was a matter of
dispute on 17.3.86, an area of 5.47 acre was
reduced from the total area of 251.38 acres and
possession was taken on the reduced area of 245-
91 acres and was handed over to the acquiring
body. Notices were also issued to the factory
owners but they failed to report as to when and
in what circumstances, their factories were
constructed. It appears that the aforesaid
factories were constructed after the issue of
Section 4 notification and in that eventuality,
the compensation for the construction does not
become payable. Because, the construction of the
factories would have been done after proper
sanction and after taking loans etc.; and more so
since heavy machinery has already been installed
and the production is in preliminary stage; and
since in these proceedings the acquiring body has
also the same purpose of developing industrial
plots and leasing the same for establishing
industrial units, it has been discussed with the
acquiring body, such acquired land shall be
leased to the owners of the constructed
factories, absorb the factories in its regulated
area and shall decide the dispute of standing
factories by mutual arrangement at its own level.
Therefore, after leaving aside the constructed
areas, the compensation for the land of the areas
0.56, 0.63, 0.33, 0.25 and 3.65, i.e. total 5.47
acres from Khasra No.235, 236, 237, 238 and 262
respectively, whose possession have not been
handed over to the acquiring department yet, will
be payable to the land-owners."
JUDGMENT
(as contained in the paper book)
4.The appellant challenged the acquisition proceedings in Writ
Petition No. 2500/1988. In paragraphs 4 to 6 and 12 to 17 of the
Page 2
3
writ petition, the appellant averred as under:
“4. That for constructing the said factory and
installing machines therein the petitioner had
taken a loan of Rs. 21.70 lakhs from U.P.
Financial Corporation. The petitioner started the
construction of the aforesaid building in the
year 1984 with the help of the aforesaid loan.
5. That the Superintending Engineer, Dehradun
sanctioned an electrical power connection of 70
horse power to the petitioner on 29.3.1985.
6. That by 26.1.1985 the petitioner had
incurred expenses to the tune of Rs. 2,29,888/-
as is clear from the report of the Chartered
Accountant dated 30-1-1985 a true copy whereof is
being filed herewith as Annexure-III.
12.That the aforesaid acquisition proceedings are
in colourable exercise of power and wholly
illegal as is clear from the facts stated
hereinafter.
13.
That there was no urgency in the matter. There
was nothing to show that acquisition for the
alleged "planned development of Industrial area
in District Dehradun" was of such an urgent nature
that proceedings under section 5-A of the Act
should have been dispensed with.
It may be stated that the proceedings under
Section 5-A are themselves summary in
nature.Merely giving 30 days' time to file
objection to the proposed acquisition would in
any case have not interfered with the proposed
planned development of industrial area. There was
nothing to justify exclusion of inquiry under
Section 5-A of the Act.
JUDGMENT
14.
That there was no material to justify existence
of any urgency for acquisition of the
petitioner's land. The opinion of the Governor
about the existence of urgency mentioned in the
impugned notifications is based on non-existing
materials and consequently the application of
Sections 17(1) and 17(4) of the Act to the case
is illegal.
15.That, while issuing the impugned notifications
the State Government has not at all considered
Page 3
4
that the petitioner was also using the land for
an industrial project which was prestigious for
Dehradun, that the petitioner's factory had
already been constructed, that the petitioner had
been advanced a loan of Rs. 21.70 lakhs by the
U.P. Financial Corporation, that the petitioner
had incurred an expenditure of more than Rs.3.8
lakhs by August 1985 on the construction of the
factory etc.
16.
That the petitioner has reasons to believe
that had the State Government been apprised of
the aforesaid facts by the land acquisition
authorities or had it taken the same into
consideration, it would never have applied the
provisions of Section 17(4) of the Act and would
not have dispensed with the inquiry under section
5-A of the Act.
17. That the Petitioner's factory over plots
no.262 (area 1.92 acre)cannot disturb the alleged
purpose of planned development of industrial area
even if this plot was excluded from acquisition.
Moreover,large patches open land are still lying
vacant in the neighbourhood and are available to
the U.P. State Industrial Development
Corporation. These patches are contiguous to the
land sought to be acquired. Had the petitioner
been given opportunity to file objection under
section 5~A of the Act,it would have brought oil
the aforesaid facts along with other facts to the
.”
notice of the State Government
5.
In the counter affidavit filed on behalf of the respondents,
JUDGMENT
it was not disputed that the appellant had established an
industrial unit on the land purchased by it. However, the
invoking of urgency clause was justified in the following words:
"Planned Development Scheme in the backward hilly
area is urgently needed to be implemented
according to the Government policy. In view cf
the urgency f o r the development in the backward
hill area, the Govt. considered it necessary that
the proceedings under Section 5-A of the Land
Acquisition Act may be dispensed with so that the
land may be acquired without delay and the
development according to the planned scheme may
be implemented in the area. The Deputy General
Page 4
5
Manager of the U.P. State Industrial Development
Corporation Ltd. Kanpur submitted the application
in the proforma prescribed for acquisition of
land at village Central Hope Town Pargana
Pachpadan District Dehradun for planned
development of Industrial area through U.P. State
Industrial Development Corporation Ltd. on
23.10.84. The proposed acquisition was requested
to be made immediately without any delay,
otherwise there would be delay in setting up the
Industries for the planned development of the
backward hill area in the State.”
“The Deputy General Manager, U.P. State
Industrial Development Corporation, Kanpur
prepared the scheme for setting up industries in
the backward hill area of Dehradun for the
planned development according to the policy of
the State Government. The Deputy General Manager
of the Corporation submitted the requisition
application to the State Government through the
Collector for immediate steps so that land be
acquired and industries according to the planned
development in the backward hill may be set up
soon without any delay. He had forwarded
necessary records and details of the plan to the
Government through the Collector. The Collector
endorsed the plea of urgency of the
implementation of the planned Development Scheme
which was duly considered by the State Govt. and
the State Govt. was of the opinion that the
backward hill area of Dehradun should be
developed in planned way without delay according
to the Government policy and it was directed
under Sections 17(1) and 17(4) of the Land
Acquisition Act to dispense with the proceedings
under Section 5-A of the Land Acquisition Act.
The Government decided about the urgency on
material evidence on record. The allegations
contrary in the paragraph under reply are
baseless and imaginary which are denied."
JUDGMENT
6. The Division Bench of the High Court did not consider the
appellant's challenge to the invoking of urgency clause and
dismissed the writ petition only on the ground that the appellant
had made an incorrect statement about the construction of the
Page 5
6
factory prior to the issue of notification under Section 4(1) and
had made an attempt to mislead the Court.
7. At this stage, we may mention that this and the connected
appeal being C.A. No. 5713 of 2002 - Everest Gas Cylinders Pvt.
Ltd. v. State of U.P. and others were disposed of on 15.04.2009 by
taking cognizance of the statement made by learned counsel for
UPSIDC that the Corporation is willing to give the acquired land to
the appellants on lease at the specified rates and statement of the
appellants' counsel that the offer made by the Corporation was
acceptable to their clients. However, in view of some controversy
relating to the price mentioned in the affidavit filed on behalf of
UPSIDC, the order disposing of the appeals was recalled on
15.07.2011. On the same day, interlocutory application filed by
M/s. Tirupati LPG Industries Limited for its impleadment as party-
respondent was allowed.
8. We have heard learned counsel for the parties and perused
the record.
9. The question whether urgency clause embodied in Section
17 can be invoked for the acquisition of land for planned
industrial development was recently considered in Radhy Shyam
(Dead) through L.Rs. and others v. State of U.P. and others (2011)
5 SCC 553. In that case, the Government of Uttar Pradesh had
JUDGMENT
acquired 205.0288 hectares land of village Makaura, Pargana
Dankaur, Tehsil and District Gautam Budh Nagar for planned
industrial development of the District. Radhy Shyam and others
challenged the acquisition on the ground that there was no
justification to invoke the urgency provisions and to dispense with
the application of Section 5A because planned industrial
development of the district was not something which could not wait
for few months' time within which inquiry under Section 5A could
have been held. Their writ petition was dismissed by the High
Court by observing that the averments contained therein were not
sufficient to call upon the respondents to place before the Court
Page 6
7
material to justify the exercise of power under Section 17(1) and
17(4) of the Act. This Court examined the scheme of the Act,
referred to various judicial precedents including the judgments in
Narayan Govind Gavate vs. State of Maharashtra (1977) 1 SCC 133,
Munshi Singh vs. Union of India (1973) 2 SCC 337, State of Punjab
vs. Gurdial Singh (1980) 2 SCC 471, Union of India vs. Mukesh Hans
(2004) 8 SCC 14, Hindustan Petroleum Corporation Ltd. vs. Darius
Shapur Chenai (2005) 7 SCC 627 and Anand Singh vs. State of U.P.
(2010) 11 SCC 242 and laid down the following propositions:
"(i) Eminent domain is a right inherent in every
sovereign to take and appropriate property
belonging to citizens for public use. To put it
differently, the sovereign is entitled to reassert
its dominion over any portion of the soil of the
State including private property without its
owner’s consent provided that such assertion is on
account of public exigency and for public good. –
Dwarkadas Shrinivas v. Sholapur Spg. and Wvg. Co.
Ltd., AIR (1954) SC 119, Chiranjit Lal Chowdhuri
v. Union of India AIR (1951) SC 41 and Jilubhai
Nanbhai Khachar v. State of Gujarat (1995) Supp.
(1) SCC 596.
(ii) The legislations which provide for compulsory
acquisition of private property by the State fall
in the category of expropriatory legislation and
such legislation must be construed strictly – DLF
Qutab Enclave Complex Educational Charitable Trust
v. State of Haryana (2003) 5 SCC 622; State of
Maharashtra v. B.E. Billimoria (2003) 7 SCC 336
and Dev Sharan v. State of U.P. (2011) 4 SCC 769.
JUDGMENT
(iii) Though, in exercise of the power of eminent
domain, the Government can acquire the private
property for public purpose, it must be remembered
that compulsory taking of one’s property is a
serious matter. If the property belongs to
economically disadvantaged segment of the society
or people suffering from other handicaps, then the
Court is not only entitled but is duty bound to
scrutinize the action/decision of the State with
greater vigilance, care and circumspection keeping
in view the fact that the landowner is likely to
Page 7
8
become landless and deprived of the only source of
his livelihood and/or shelter.
(iv) The property of a citizen cannot be acquired
by the State and/or its agencies/instrumentalities
without complying with the mandate of Sections 4,
5-A and 6 of the Act. A public purpose, however,
laudable it may be does not entitle the State to
invoke the urgency provisions because the same
have the effect of depriving the owner of his
right to property without being heard. Only in a
case of real urgency, the State can invoke the
urgency provisions and dispense with the
requirement of hearing the land owner or other
interested persons.
(v) Section 17(1) read with Section 17(4) confers
extraordinary power upon the State to acquire
private property without complying with the
mandate of Section 5-A. These provisions can be
invoked only when the purpose of acquisition
cannot brook the delay of even a few weeks or
months. Therefore, before excluding the
application of Section 5-A, the authority
concerned must be fully satisfied that time of few
weeks or months likely to be taken in conducting
inquiry under Section 5-A will, in all
probability, frustrate the public purpose for
which land is proposed to be acquired.
(vi) The satisfaction of the Government on the
issue of urgency is subjective but is a condition
precedent to the exercise of power under Section
17(1) and the same can be challenged on the ground
that the purpose for which the private property is
sought to be acquired is not a public purpose at
all or that the exercise of power is vitiated due
to mala fides or that the authorities concerned
did not apply their mind to the relevant factors
and the records.
JUDGMENT
(vii) The exercise of power by the Government
under Section 17(1) does not necessarily result in
exclusion of Section 5-A of the Act in terms of
which any person interested in land can file
objection and is entitled to be heard in support
of his objection. The use of word “may” in sub-
section (4) of Section 17 makes it clear that it
merely enables the Government to direct that the
Page 8
9
provisions of Section 5-A would not apply to the
cases covered under sub-section (1) or (2) of
Section 17. In other words, invoking of Section
17(4) is not a necessary concomitant of the
exercise of power under Section 17(1).
(viii) The acquisition of land for residential,
commercial, industrial or institutional purposes
can be treated as an acquisition for public
purposes within the meaning of Section 4 but that,
by itself, does not justify the exercise of power
by the Government under Section 17(1) and/or
17(4). The Court can take judicial notice of the
fact that planning, execution and implementation
of the schemes relating to development of
residential, commercial, industrial or
institutional areas usually take few years.
Therefore, the private property cannot be acquired
for such purpose by invoking the urgency provision
contained in Section 17(1). In any case,
exclusion of the rule of audi alteram partem
embodied in Sections 5-A (1) and (2) is not at all
warranted in such matters.
(ix)If land is acquired for the benefit of private
persons, the Court should view the invoking of
Sections 17(1) and/or 17(4) with suspicion and
carefully scrutinize the relevant record before
adjudicating upon the legality of such
acquisition."
10. In our view, proposition Nos.(v) to (ix) of the judgment
JUDGMENT
in Radhy Shyam's case are squarely attracted in the present case
and the acquisition of the appellant's land is liable to be
quashed because the respondents have not produced any material to
show that the State Government had formed a bonafide opinion on
the issue of invoking of the provisions contained in Section 17(1)
and 17(4) of the Act. Learned counsel for the respondents could
not show as to how this case is different from the case of Radhy
Shyam in which the acquisition made for planned industrial
development of Gautam Budh Nagar was quashed on the ground that
the acquisition of land for industrial purpose does not justify
invoking of the urgency provisions.
Page 9
10
11. In the result, the appeal is allowed, the impugned order
is set aside and the acquisition of the appellant's land is
quashed. It is, however, made clear that this Court has not
expressed any opinion on the rights of the impleaded respondent
and if any other litigation is pending, then the same shall be
adjudicated by the competent Court without being influenced by the
observations contained in this order.
................................J.
(G.S.SINGHVI)
................................J.
(FAKKIR MOHAMED IBRAHIM KALIFULLA)
NEW DELHI;
JULY 19, 2012.
JUDGMENT
Page 10
11
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
CIVIL APPEAL No.5713 OF 2002
EVEREST CYLINDERS PVT.LTD. .......APPELLANT
VERSUS
STATE OF U.P. & ORS ......RESPONDENTS
O R D E R
This appeal is directed against order dated 09.09.1997
passed by the Division Bench of the Allahabad High Court whereby
the writ petition filed by the appellant questioning the
acquisition of its land was dismissed.
Learned counsel for the parties agree that the main issue
raised in this appeal is identical to the one raised in Civil
Appeal No.5712 of 2002.
By a separate judgment passed today, we have allowed Civil
Appeal No.5712 of 2002 and quashed the acquisition proceedings.
For the detailed reasons recorded in the aforesaid judgment,
which shall be read as part of this order, the appeal is allowed,
the order passed by the High Court is set aside and the
acquisition of the appellant's land is quashed.
JUDGMENT
................................J.
(G.S.SINGHVI)
................................J.
(FAKKIR MOHAMED IBRAHIM KALIFULLA)
NEW DELHI;
JULY 19, 2012.
Page 11
12
JUDGMENT
Page 12